The document provides an introduction to the Front End Engineering Design for the Cirebon-Semarang Natural Gas Transmission Pipeline project in Central Java, Indonesia. The 238 km pipeline will transport natural gas from the existing Gresem Pipeline in Semarang to the Cirebon region in 3 stages, reaching capacities of 80 MMSCFD in stage 1, 80 MMSCFD in stage 2, and 240-300 MMSCFD in stage 3. The scope of work includes designing the pipeline, Semarang and Cirebon offtake stations, and Kendal and Batang metering stations. The design life is a minimum of 15 years. Relevant codes, standards, abbreviations and definitions are

Uploaded by

Agus Marpaung
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
478 views5 pages

Doc. Eng. Temp. For CISEM

The document provides an introduction to the Front End Engineering Design for the Cirebon-Semarang Natural Gas Transmission Pipeline project in Central Java, Indonesia. The 238 km pipeline will transport natural gas from the existing Gresem Pipeline in Semarang to the Cirebon region in 3 stages, reaching capacities of 80 MMSCFD in stage 1, 80 MMSCFD in stage 2, and 240-300 MMSCFD in stage 3. The scope of work includes designing the pipeline, Semarang and Cirebon offtake stations, and Kendal and Batang metering stations. The design life is a minimum of 15 years. Relevant codes, standards, abbreviations and definitions are

Uploaded by

Agus Marpaung
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 5

BAKRIE AND BROTHERS TBK.

FRONT END ENGINEERING DESIGN

PEMBANGUNAN PIPA RUAS TRANSMISI GAS BUMI


CIREBON-SEMARANG

Jawa Tengah, Indonesia

JUDUL DOKUMEN
Nomor Dokumen

ORIG. CHECK APPR.


REV DATE DESCRIPTION
ESTU BNBR
REVISION LIST : 1 = Re-Issued for Bid (RFB)
0 = Issued for Bid (IFB)
PEMBANGUNAN PIPA RUAS TRANSMISI GAS BUMI
CIREBON-SEMARANG
JUDUL DOKUMEN
Nomor Dokumen

TABLE OF CONTENTS

1.0 INTRODUCTION.............................................................................................................................................3

1.1 PROJECT DESCRIPTION......................................................................................................................... 3


1.2 SCOPE & OBJECTIVE............................................................................................................................. 4
1.3 SYSTEM OF UNITS................................................................................................................................. 4
1.4 SYSTEM OF LANGUAGE.......................................................................................................................... 4
1.5 DESIGN LIFE.......................................................................................................................................... 4
1.6 REFERENCES, CODES AND STANDARDS................................................................................................ 4
1.7 ABBREVIATIONS..................................................................................................................................... 4
1.8 Definitions of Terms....................................................................................................................................5

Page 2 of 5
PEMBANGUNAN PIPA RUAS TRANSMISI GAS BUMI
CIREBON-SEMARANG
JUDUL DOKUMEN
Nomor Dokumen

1.0 INTRODUCTION

1.1 Project Description


Bakrie and Brothers Tbk. (herein referred as COMPANY) has been commissioned to undertake
the operator of Gas Transmission Pipeline from Semarang to Cirebon. The natural gas taken
from Jambaran Tiung Biru Gas Plant at East Java then transported to Semarang using existing
Gresik Semarang Transmission Pipeline (Gresem).

The pipeline system is approximately 238 km, 24-inch onshore pipeline, starting from existing
Gresem Pipeline near Tambak Lorok Semarang to Cirebon Region.

The Project will be implemented in 3 stages:

1. Stage 1, feed gas supplied from Gresem will be transported to Kendal and Batang area with
approximately 40 MMSCFD;

2. Stage 2, feed gas supplied from Gresem will be transported to Kendal and Batang area with
additional approximately 40 MMSCFD (Total 80 MMSCFD);

3. Stage 3, feed gas supplied from Gresem Pipeline will be transported to Jawa Barat Region.
Gas supplied increment in stage 3 are as follows:

Year Period Total Gas Volume


Year 5 to 10 115 - 200 MMSCFD
Year 11 to 15 205 - 240 MMSCFD
Year 15 to 25 240 - 300 MMSCFD

The scope of this project includes the design of:

 Approximately 230 km of natural gas pipeline


 Semarang Offtake Station
 Cirebon Offtake Station
 Kendal and Batang Metering Station

Page 3 of 5
PEMBANGUNAN PIPA RUAS TRANSMISI GAS BUMI
CIREBON-SEMARANG
JUDUL DOKUMEN
Nomor Dokumen

Figure 1.1 – Cirebon Semarang Natural Gas Transportation Pipeline

1.2 Scope & Objective

The scope and objective of this document ……….

1.3 System of Units

All units in this document shall use the International System of Units (SI) unless otherwise noted.

1.4 System of Language

All project documents, drawings, instructions, specifications, manuals shall be written in English.

1.5 Design Life

The design life of the FACILITIES and all associated equipment, components and systems is a
minimum 15 years, unless otherwise specified. The design life shall be achievable with minimum
onsite maintenance and maximum availability.

All components which for practical, safety or cost-efficiency reasons are unable to meet the
required design life shall be identified as soon as possible. Their expected service life shall be
informed to COMPANY and provision made in the system design for maintenance to extend
component life or routine change-out.

1.6 References, Codes and Standards

- Codes and Standards

API RP 14C Recommended Practice for Analysis, Design, Installation and Testing
of Basic Surface System on Offshore Production Platforms
API RP 14E Recommended Practice for Design and Installation of Offshore
Production Platform Piping Systems
API RP 14J Recommended Practice for the Design and Hazard Analysis for

Page 4 of 5
PEMBANGUNAN PIPA RUAS TRANSMISI GAS BUMI
CIREBON-SEMARANG
JUDUL DOKUMEN
Nomor Dokumen

Offshore Production Facilities

1.7 Abbreviations

API American Petroleum Institute


ASME American Society of Mechanical Engineers
ASTM American Society for Testing Materials
GRESEM Gresik Semarang Gas Transportation Pipeline

1.8 Definitions of Terms

The definitions of terms to be used in this document are as follow

COMPANY Bakrie and Brothers Tbk. or its successor or assignees who are
the end user of the facilities.

CONTRACTOR The party specifying / purchasing the equipment for and on


behalf of the COMPANY

VENDOR/SUBCONTRACTO The party, which manufactures or supplies the equipment and


R services to perform the duties specified by the CONTRACTOR

SUB-VENDOR Sub-contractor to the Vendor

CERTIFICATION AGENCY “Third Party Inspection Agency” appointed by COMPANY to


ensure conformity by the VENDOR with all requirements
necessary to obtain certification of the goods and/or services
described herein so as to get the total facilities certified by them

Page 5 of 5