Mep BDC Boq: and The Contractor Must Submit and Approve The Hydraulic Calculations Sheets

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 33

Owner: Project:

MEP BDC BOQ

SECTION 14: FIREFIGHTING WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP

14.1 AUTOMATIC DRY POWDER EXTINGUISHER


Supplying and installing of ABKDE cylinder with nozzle type (super matic)
manufactured by "BAVARIA" or similar to be fixed to the R.C. slab.
Rate includes hangers, fixation if required, st/st ring frame and any item deem necessary
to complete the work.

14.1.1 6 kg cylinder UNIT 1.00 3,800.00 3,800.00

14.2 FIRE TRACE FOR ELECTRICAL PANEL


Supplying and installing Automatic Fire Fighting (Suppression) System inside main
panels (fire trace). Complete works including cylinders, CO2 gas UL/FM certified ,
thermal tube,pressure guage & all necesesery accesserioes s according to specs &
drawings and in conformity with panel boards manufacturer standards and
recommendations( 2kg).

6 kg cylinder UNIT 1.00 4,800.00 4,800.00


2 kg cylinder UNIT 5.00 3,100.00 15,500.00

STAINLESS STEEL HOSE REEL Station CABINET


Supplying and installing of wall -recessed or surface mounted St/St Double Cabinet
manufactured by "Bavaria" or similar. The cabinet contains one Mores connection 2.5"
with fabric hose 2.5" with 30m length connected to the dry network and the Siamese
connection in addition to rubber hose reel 1" with 30m length connected to the wet tie-in
from the building network. Complete work including the valve, the necessary steel
substructure whenever required and as per Consultant's instructions.

unit 2.00 29,800.00 59,600.00


14.3 FF. SEAMLESS STEEL PIPES
Supplying and installing of seamless steel pipes UKRAINE origin. Complete work
including valves, connecting to the nearest street water mains, painting with two coats of
undiluted primer, Flushing and three coats of oil paint ..etc.

14.3.1 1" PIPES M 66.00 320.00 21,120.00


14.3.2 1.25" PIPES M 6.00 345.00 2,070.00
14.3.3 1.5" PIPES M 12.00 380.00 4,560.00
14.3.4 2" PIPES M 15.00 410.00 6,150.00
14.3.5 2.5" PIPES M 25.00 600.00 15,000.00

FORWARD 132,600.00

SECTION 14: FIREFIGHTING WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 132,600.00

14.6.2 FM200 SYSTEM ( IT/Control /Archive/Vault/ Safety deposite) Alternative


Furnishing, supplying, installing, testing & commissioning according to the NFPA Code
UL/FM suppression gas of FM200 Gas System for the IT Room, Archive;Vault room or
Security Room manufactured by (Tyco,Siex and LPG ) or similar complete with valves,
nozzles, electric solenoid including connection to the Fire Alarm Panel and system
equipped with all required accessories to close automatically the A/C or/and Motorized
dampers that serve the room that covered by FM200 including:
and The contractor Must submit and approve the Hydraulic calculations sheets

not to be released to any person or organization without the prior written consent of Vision Architects 1/33
Owner: Project:

MEP BDC BOQ

One Fire fighting zone Extinguishing panel (manual and automatic) c/W standby
batteries 8 hours and all related accessories (for FM200 extinguishing system).
gas automatic solenoid release unit.
Gas manual release unit
monitor and control modules.
6" fire alarm bell.
Strobe horn unit with ( flasher )
360 degree nozzle according drawing
Optical smoke detector
Optical Heat detector
Seamless galvanized steel piping table 40 network Lumb sum
The item shall include calculation of the clean agent required quantities in addition to
the system execution
Outlet complete with all required accessories, ((2x1.5mm2) Fire resistant shield Cable
105C , EMT conduits) dedicated for the system and FM200 Cylinder with the hereunder
capacities

not to be released to any person or organization without the prior written consent of Vision Architects 2/33
Owner: Project:

MEP BDC BOQ

The listed capacities below is an indicative capacities and the contractor must
submit the related calculation and hydraulic sheet in this respect in order to get the
Consultant approval prior to starting any works, although no claims will be
accepted for any increasing of the listed capacities.
14.6.2.1 Ditto as above but for 10 kg UNIT 2.00 940,000.00 1,880,000.00
14.6.2.2 Ditto as above but for 15 kg UNIT 2.00 110,000.00 220,000.00
14.6.2.3 Ditto as above but for 22 kg UNIT 1.00 126,000.00 126,000.00
FORWARD 2,358,600.00

SECTION 14: FIREFIGHTING WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 2,358,600.00

14.7 PORTABLE FIRE EXTINGUISHERS


14.7.1 Supplying,installing ,connecting and testing of CO2 manual,portable,hand held ,shall be
compliance with NFPA&UL Listed

14.7.1.1 Ditto as above but for 6 kg UNIT 2.00 3,100.00 6,200.00

14.7.2 Supplying,installing ,connecting and testing of dry powder manual,portable,hand held


,shall be compliance with NFPA&UL Listed
14.7.2.1 Ditto as above but for 6 kg UNIT 1.00 3,200.00 3,200.00
1
14.8 SPRINKLERS
14.8.1 Supplying ,installing ,connecting and testing of 15 mm pendent concelled Quick
response sprinkler fully chrome plated sprinkler heads to be installed UL/FM Approved .
UNIT 35.00 600.00 21,000.00

14.10 VALVES &SWITCHES


14.10.2 Supplying,installing ,connecting&testing of Zone Control Valve O.S&Y gate valves with
tamper switches, swing type check valve, flow switch , Test & Drain to be installed on
zone &all necessary to complete work as per specification ,drawings&NFPA. Size 2.5"

UNIT 1.00 34,000.00 34,000.00


14.10.3 Supplying,installing ,connecting&testing of Zone Control Valve O.S&Y gate valves with
tamper switches, swing type check valve, flow switch , Test & Drain to be installed on
zone &all necessary to complete work as per specification ,drawings&NFPA. Size 2.

UNIT 1.00 32,000.00 32,000.00

FIREFIGHTING WORKS TOTAL 2,455,000.00

SECTION 15: HVAC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP

15.2 CHILLED WATER SYSTEM

15.2.1 FCU

not to be released to any person or organization without the prior written consent of Vision Architects 3/33
Owner: Project:

MEP BDC BOQ

Supplying, installing, and commissioning of chilled water fan coil units, ceiling
concealed as indicate on drawing plans manufactured by "SAIVER, EGAT OR
CARRIER" or approved similar complete with ALL HookUp Accessories&auxilliary
drain pain (2 flexible connection , 3 gate/ball valve, 1 balance valve, 1 strainer, 2way or
3way valve , Die Electric connection if required ) and all needed for operating &all
needed to complete job.

15.2.1.1 TYPE C/W FCU-1 (1 TR) 400 CFM & Ext. St.P 0.25" w.g UNIT 6.00
15.2.1.2 TYPE C/W FCU-2 (1.5 TR) 600 CFM & Ext. St.P 0.25" w.g UNIT 3.00
15.2.1.3 TYPE C/W FCU-3 (2 TR) 800 CFM & Ext. St.P 0.25" w.g UNIT 4.00
15.2.1.4 TYPE C/W FCU-4 (2.5 TR) 1000 CFM & Ext. St.P 0.25" w.g UNIT 4.00

not to be released to any person or organization without the prior written consent of Vision Architects 4/33
Owner: Project:

MEP BDC BOQ

15.2.2 CHILLED WATER SEAMLESS STELL PIPES


Supplying, installing, testing, commissioning, of of Chilled water seamless (schedule
40) pipe UKRAINE origin or similar complete with fitting, elbow, tees, supports and all
needed to complete work. Unit rate to include all main and branch valves, balance
valves, air vents manufactured by CRane or approved similar and connections
according to drawings and specifications.for the following:

15.2.2.1 pipe dia. 3/4" m 93.00


15.2.2.2 pipe dia. 1" m 22.00
15.2.2.3 pipe dia. 1.25" m 72.00
15.2.2.4 pipe dia. 1.5" m 18.00
15.2.2.5 pipe dia. 2" m 8.00
15.2.2.6 pipe dia. 2.5" m 15.00
FORWARD

SECTION 15: HVAC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

15.2.3 CHILLED WATER PIPES INSULATION


Supply, install,test, commissioning of fiber glass pipes isulation thickns 1" densty
96kg/m³ c/w all accessories, labels, aluminum foil& aluminum cladding if needed &all
needed to complete work according to specifiction ,drawings& Codes
IZOCAM OR EQU WITH IT IS ALL ACCESSORIES FOR THE FOLLWING :

15.2.3.1 pipe dia. 3/4" m 93.00


15.2.3.2 pipe dia. 1" m 22.00
15.2.3.3 pipe dia. 1.25" m 72.00
15.2.3.4 pipe dia. 1.5" m 18.00
15.2.3.5 pipe dia. 2" m 8.00
15.2.3.6 pipe dia. 2.5" m 15.00

15.2.6 Water Treatment and chemical cleaning


Water 'Treatment and chemical cleaning systems from specialized company
Supply,Installion,testing,balancing,start up&commissioning of water treatment system
and provision of flushing and chemical cleaning with all accessories&all needed to
complete work including but not limited to ( Dozing pumps, Controllers, Sensors,
Selonide Valves, Water Meters, Softners and chemical materials) in addition to issuing
analysis certificates
L.S 1.00

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 5/33
Owner: Project:

MEP BDC BOQ

SECTION 15: HVAC WORKS


ITEM DESCRIPTION
UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

15.3 Split High wall System

15.3.1 Split High wall Units


Supplying, installation, testing and commissioning of DX. high wall type A/C air
conditioner(HP or CO) produced by " CARRIER" or similar c/w evaporator, condenser
and insulation&all needed to make complete job as herein specified and according to the
drawings with the following capacities:

15.3.1.1 capacity 1 TR UNIT 2.00


15.3.1.2 capacity 1.5 TR UNIT 2.00

15.6.1 Duct Works


Supplying and installing of galvanized steel sheet metal duct work for supply, return
lines complete with hangers, supports, flexible ducts, acoustic lining insulation armflex
6 mm to be 3m from begining of Duct work&End plug of duct, volume , fire&smoke
manual or motorized dampers/splitters, flexible connections, opening on walls and roof
and all needed to complete work as per drawing and specification and SMACNA
standards.

K.G 6200.00
15.7 Thermal Insulation Works
15.7.1
Supply, install of duct thermal insulation fiber glass 24Kg/M³ density,1"thickness.
Complete with vapor barrier and all other accessories, aluminum cladding if needed &all
needed to complete work according to specifiction ,drawings& Codes
IZOCAM , KIMMCO OR EQU.
m2 800.00

15.8 Air Outlets


Supply, installation, testing, commissioning and guarantee air outlest C/w stuffing box
with inner linning and outer insulation and damper including operation, maintenance, as
per the specifications,of EGAT , ZAMZAM OR EQU. for the following items:

15.8.1 Supply, install of Supply Celling Diffuser 24"*24" (S.C.D) No. 27.00
15.8.2 Supply, install of Return Celling Diffuser 24"*24" (R.C.D) No. 26.00
15.8.3 Supply ,install of Supply linear slot Diffuser 2 Slot (S.L.S.D). complete with
plenum box pre internal insulated &connection to main Duct No.
8.00
15.8.4 Supply ,install of Supply linear slot Diffuser 4 Slot (S.L.S.D). complete with
plenum box pre internal insulated &connection to main Duct No.
6.00
15.8.5 Supply ,install of return linear slot Diffuser 2 Slot (R.L.S.D). No. 8.00
15.8.6 Supply, install of Supply Round Celling Diffuser (S.R.C.D) 24 Ø. No. 6.00
15.8.7 Supply, install of Supply Round Celling Diffuser (S.R.C.D) 18" Ø. No. 6.00
15.8.8 Supply, install of Return Round Celling Diffuser (R.R.C.D) 24 Ø. No. 8.00
15.8.9 Supply, install of Supply Celling Diffuser 12"*12" (S.C.D) No. 5.00
15.8.10 Supply, install of Return Celling Diffuser 12"*12" (R.C.D) No. 5.00
HVAC WORKS TOTAL 0.00

SECTION 15: HVAC WORKS

ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP


Before 0.00

15.9 Testing ,Adjusting and Balancing

not to be released to any person or organization without the prior written consent of Vision Architects 6/33
Owner: Project:

MEP BDC BOQ

( Testing ,Adjusting and Balancing) for all hvac works(Air/Water) &Temperature test
during (July, August& September)months from third part Specialized according to
Design requirement.
L.S 1.00

not to be released to any person or organization without the prior written consent of Vision Architects 7/33
Owner: Project:

MEP BDC BOQ

15.10 Fresh Air & EXHAUST FAN

15.10.1 FRESH AIR FAN


fresh air fan manufactured by "S&P" or similar with pre filter C/W all accessories and
galvanized steel sheet metal duct work as per SMACNA slandered C/W exhaust air
outlets grilles ,sandtrap louver, hangers, supports including connecting with fire alarm
system, cables , conduits&all needed to complete work as per specification&Drawings.

15.10.1.1 F.A.F-1( 780 CFM ) & St Pressure 1" UNIT 1.00


15.10.1.2 F.A.F-2( 240 CFM ) & St Pressure 1" UNIT 1.00

15.10.3 Inline Exh. Fan C/W Shutter without filter


Inline Exhaust Fan "S&P" or similar C/W all accessories,supports including connecting
with fire alarm system, cables & conduits &all needed to complete work as per
specification&Drawings.
15.10.3.1 Inline C/W Shutter 375 C.F.M. UNIT 2.00

15.11 Air Curtain


Supply, installation, testing, adjusting, balancing, commissioning and guarantee air
curtain manfactured by Carrier , olifini or approved similar as per the specifications for
the following items:
15.11.2 air curtain 1.20 M UNIT 1.00

15.13 Drainge works


Supplying and installing a drain network from all AC units to the nearest drain point.
Complete work incl. using approved PVC pipes of adequate dia, elbows, bends tees,
hangers, clips, air vents&all needed to complete work as per specification&Drawings.
L.S 1.00
15.14 AC redundancy panel

24 HR redundancy panel for AC units along IT&control room to be over control cables
not power and including ( Timer 24 hr – 3 relay – digital thermostat )
L.S 1.00
HVAC WORKS TOTAL 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 8/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
General Notes
# Consultant forms for documentations (i.e. MRI , RFI, QS ,MS, …, etc. ) are mandatory
for approval
# Submittals shall be submitted for approval for each material item & DWGs

# MRI shall submitted for approval on site for supplied items


# QS shall submitted for approval on site prior to invoice submitting
# Compliance sheets (detailed point by point compliance statement with this
specifications) shall submitted for approval for Equipment , Devices , Lighting fixtures
& Light current
# All required approvals shall be accomplished & enhanced from the client prior to
suppling or executing any item
# Owner Have right to choose any of the specified similar vendor types without giving
reason and without demanding additional cost

16.1 Uninterbuter power supply (UPS)


Supplying, installing, testing and commissioning UPS including Protection, Batteries ,
Inverters, Rectifiers, Static Transfer Switches, DC Circuit Breakers , all related
accessories and ancillary works according to DWG's & Specs
nvr
# UPS Shall be double conversion (unless otherwise indicated) Topology, Unity Output
power factor, 3:1 Crest Factor,<3 % THD,± 20% Voltage tolerance,

# Overload capacity (linear


load) on inverter shall not less than 110% for 60 minutes -125% for 10 minutes - 150%
for 1 minute
# Overall system efficiency shall not less than 95%
# Battery management preferred to be Advanced Battery Management (charger turns off
and “rests” the battery) to increase battery service life

# Battery type shall be VRLA with swappable function


# Manual bypass switch Shall be Included
# UPS shall be applicable for Redundant deployment architectures (Series / Parallel
connection)
#UPS shall be Remotely monitored & communicated
# UPS shall integrated with power management software & Visualization (Automatic
shedding non critical loads to outlast UPS battery capacity)
# contractor shall supplying from suppliers have a Authorized customer service centers

16.1.1 Double conversion UPS 30KVA ,3ph/1ph, 20Min backup time No. 1.00
16.1.2 Online UPS 10KVA ,3ph/1ph,20Min backup time No. 1.00

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 9/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.2 Electrical Distribution Panel Boards


Supplying, installing, testing and commissioning the electrical distribution boards " Type
Tested" including all accessories from glands, insulations, terminals for incoming and
outgoing cables , labels for each component - so that be Irrevocable metal , fixing panels
on dedicated frames according to panel mounting method according to DWG's & Specs ,

**Approved manufactures for DP's ( Schneider or approved similar)


# All MCCB's Shall be adjustable
#Panel Assembler shall arrange components so that each breakers group placing beside
its control devices - Timers, Contactors,…,etc. - according to shop drawing approval

# Contractor shall not supply panels before testing on factory in the presence of
consultant

# Panel Assembler shall attend panel starting up and setting control and metering devices
on site

# Contractor shall require the panel assembler to train the owner staff on the operating
steps instructions , power sources manoeuvring , metering values acquisition and Install
guide boards for operating Steps instructions on the electrical room

# Contractor shall install the load schedule and SLD at each panel internal shutter side so
that it irrevocable

16.2.1 Distribution panel board type (MDB)


No. 1.00
16.2.2 Distribution panel board type(ACPG)
No. 1.00
16.2.3 Distribution panel board type(DPG)
No. 1.00
16.2.4 Distribution panel board type(UPG)
No. 1.00
16.2.5 Distribution panel board type(UDB-LC)
No. 1.00
16.2.6 External bypass panel including manual changeover switch with lock, 3PH, 80A & all
accessories to be used for maintenance of main UPS with no disturbance to the load
according to drawings and specifications
No. 1.00
16.2.7 External bypass panel including manual changeover switch with lock, 1PH, 63A & all
accessories to be used for maintenance of security UPS with no disturbance to the load
according to drawings and specifications
No. 1.00
16.2.8 Load Break Switch 80A, 4p for main UPS No. 1.00
16.2.9 Load Break Switch 40A, 4p for Security UPS No. 1.00

16.5.1.1 Power factor correction panels


# Panel Assembler shall identify and arrange capacitor capacitance so that the steps are
proportional to the actual demand (in the lowest and highest periods) - according to the
actual site operation conditions -even if the number of steps required to be increased -
not less - than those specified by the tender drawings without additional cost , while
maintaining the total rating of the reactive power.

# To reduce line transients on system no stage shall switch more than 120 KVAR and no
capacitor cell shall
#All controls shall be
exceed 25.0 on
mounted KVAR.
enclosure door for easy inspection and service

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 10/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

#A door interlock shall be provided to disconnect control power when enclosure door is
opened.
# A personnel ground fault breaker shall be provided to disconnect control power upon
accidental contact with control power and earth (ground).

# Panel Assembler shall set up power factor meter functions (V,target p.f, steps,
automatic & manual settings) on site according to the actual operation conditions

16.5.1.1.1 Distribution Panel Board Type ( PFC ) No. 0.00

16.5.2 Low Voltage Wires and Cables


16.5.2.1 Multicore Cables
Supplying, installing, testing and commissioning Low Voltage Multicore Cables
XLPE/PVC insulated , Voltage Grade(1/0.6)KV including terminals, Heat Shrinkable
insulation at both ends, Cable raceways from whether run on hot galvanized cable trays -
including covers - with min. thickness 1.5mm or inside conduits EMT-PVC - RGS
according to raceway application and all required ancillary works according to DWG's &
Specs

#Contractor Shall coordinate with electrical utility whether electricity company


,Landlord ,other for cable installation
# Contractor Shall submit short circuit and voltage drop calculation according to the
actual lengths and site status
# Contractor Shall install irrevocable identifications labels for cable destination (From /
TO) and cable code on drawings
# Cable bends radius shall not exceed the coded recommended values
# Emergence Cables shall be segregated on a dedicated raceways
# SLD shop drawing shall be approved prior installation
**Approved manufactures for LV wires and cables are ( Cables - Or Approved Similar)

**Approved manufactures for cable trays are ( EL Sewedy - EgyTray - Emeco)

**Approved manufactures for metal conduits are ( Wheatland - Emeco) with UL


compatible accessories
**Approved manufactures for PVC conduits are (Engineering home - new ega) Heavy
Gauge

16.5.2.1 (3x95+50)mm2,CU/XLPE/PVC Mt 60.00


16.5.2.2 (4x35)mm2,CU/XLPE/PVC Mt 80.00
16.5.2.3 (4x25)mm2,CU/XLPE/PVC Mt 40.00
16.5.2.4 (4x16)mm2,CU/XLPE/PVC Mt 80.00
16.5.2.5 (3x16)mm2,CU/PVC/PVC Mt 70.00

16.5.2.2 Armoured Multicore Cables


16.5.2.1.1 (3x185+95)mm2,CU/XLPE/STA/PVC Mt 1.00 Alternative
16.5.2.1.2 (3x120+70)mm2,CU/XLPE/STA/PVC Mt 1.00 Alternative
16.5.2.1.3 (3x95+50)mm2,CU/XLPE/STA/PVC Mt 1.00 Alternative
FORWARD 0.00

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 11/33
Owner: Project:

MEP BDC BOQ

16.5.2.3 Earthing system wires


Supplying, installing, testing and commissioning Low Voltage Wires CU/PVC
insulated , Voltage Grade (450/750) V , including terminals, Heat Shrinkable insulation
at both ends, Cable raceways from whether run on hot galvanized cable trays - including
covers - with min. thickness 1.5mm or inside conduits EMT- RGS according to raceway
application and all required ancillary works according to DWG's & Specs

# Non-metallic conduits are prohibited for earthing cables

16.5.2.3.5 50mm2,CU/PVC,450/750 Mt 60.00


16.5.2.3.6 35mm2,CU/PVC,450/750 Mt 80.00
16.5.2.3.7 25mm2,CU/PVC,450/750 Mt 40.00
16.5.2.3.8 16mm2,CU/PVC,450/750 Mt 80.00

16.5.4 Outlets& main circuits


**Approved manufactures for LV cables & Wires ( EL Sewedy Cables - Or Approved
Similar )
**Approved manufactures for PVC Conduits (Engineering Home- New Ega) Heavy
Gauge
#Circuits raceways shall be labelled to identify circuit/outlet code
# Conduit installing on wet areas or ground building extremely prohibited
# Conduit specified by the inner diameter
# Contractor shall re-study filling ratio according to the actual Circumstances and
upgrading for high grade - if necessary - without demanding additional cost

# Contractor shall leave sufficient lengths in outlets dedicated for floor boxes, racks or
any non-fixed parts to give flexibility to modify their places during execution in
accordance with the coordinate the length required to be left with specialized
departments

# Contractor shall coordinate with the architecture ceiling, furniture and flooring to
achieve the desired Arch. impression

16.5.4.1 Indoor Lighting Outlets


Supplying, installing, testing and commissioning lighting outlet controlled via lighting
16.5.4.1.1 switches
Lighting ,outlet
occupancy sensors or direct
3x3mm2,CU/PVC from
drawn oncontrol
20mm panel including main & sub main
PVC conduit No. 200.00
circuit from outlet to the other (Max. 8 outlet per circuit) to the switch , battery wire ,
16.5.4.1.2 Lighting
conduits ,outlet 3x3mm2,CU/PVC
junction drawn onworks
boxes , and all ancillary 20mmaccording
EMT conduit for safety
to DWG's rooms
& Specs No. 1.00
16.4.1.3 Lighting outlet 3x4mm2,CU/PVC drawn on 20mm PVC conduit for elevations lighting
No. 12.00

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 12/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.5.4.2 Outdoor Lighting Outlets

Supplying, installing, testing and commissioning outdoor lighting outlet controlled via
lighting switches , sensors or direct from control panel including main & sub main circuit
from outlet to the other, conduits , junction boxes, hand holes , and all ancillary works
according to DWG's & Specs

# Contractor shall fitting out outdoor wiring with water-leakage materials and
accessories and perform the necessary arrangements for prevention of ground leakage by
installing earth leakage devices and grounding lighting units with a earth rod for every 10
outdoor lighting units

16.5.4.2.1 Landscape Lighting outlet 3x3mm2,CU/PVC drawn on 25mm PVC conduit No. 5.00
16.5.4.2.2 Landscape Lighting outlet 3x4mm2,CU/PVC drawn on 25mm PVC conduit No. 5.00

16.5.4.3 Sockets Outlets

Supplying, installing, testing and commissioning single/duplex fed by normal/UPS


system socket outlet installed on walls, ceiling, furniture or floor boxes including main &
sub main circuit from outlet to the other (Max. 6 outlet per circuit) , conduits , junction
boxes , and all ancillary works according to DWG's & Specs

#Duplex and single socket consider as one outlet , group with normal and
emergency/UPS feeding consider as two outlets

16.5.4.3.1 Socket outlet 3x3mm2, CU/PVC drawn on 20mm PVC conduit No. 1.00
16.5.4.3.2 Socket outlet 3x4mm2, CU/PVC drawn on 20mm PVC conduit No. 60.00

16.5.4.4 Power Circuits

Supplying, installing, testing and commissioning power circuit for power sockets
,EWH ,Hand dryers , AC Loads , industrial sockets , Air curtain , rolling shutters , light
current control panels or exhaust / Fresh fans including main & sub main circuit even
plugging on the unit terminals , conduits , junction boxes , and all ancillary works
according to DWG's & Specs

# HVAC Split unit Circuits extends from the control panel to the disconnect switch
beside the internal unit up to the external disconnect beside the outdoor unit
16.5.4.4.1 Power circuit 3x3mm2, CU/PVC drawn on 20mm PVC conduit No. 1.00
16.5.4.4.2 Power circuit 3x4mm2, CU/PVC drawn on 20mm PVC conduit No. 36.00

FORWARD 0.00

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.5.4.4.3 Power circuit 3x6mm2, CU/PVC drawn on 25mm PVC conduit No. 10.00

16.5.5 Wiring devices


Supplying, installing, testing and commissioning sockets and switches wiring devices
including modules , frame , covers , back box for flush/surface mounting , installed on
walls, Furniture, Ceiling or Floor boxes - and all ancillary works according to DWG's &
Specs

**Approved manufactures for wiring devices (Legrand : Arteor)

not to be released to any person or organization without the prior written consent of Vision Architects 13/33
Owner: Project:

MEP BDC BOQ

**Approved manufactures for industrial sockets (Legrand-Schneider)


#Contractor shall coordinate between sockets and its related suitable equipment plugs

#Contractor shall coordinate between power, lighting data socket installation

#Contractor shall label wiring devices with Irrevocable labels indicate outlet and
electrical circuit code
#Contractor shall submit samples for approval for each item and have to be kept on site

16.5.5.1 Single Socket 16A,2P+E, Germany Standard (Sokuo) No. 12.00


16.5.5.2 Flush / Surface mounted -2 module- WP Single Socket 16A,2P+E, Germany Standard
(Sokuo),IP55 No. 1.00
16.5.5.3 Single Socket 16A,2P+E, Germany Standard (Sokuo), Orange Color for UPS No. 1.00
16.5.5.4 Duplex Socket 16A,2P+E, Germany Standard (Sokuo) No. 20.00
16.5.5.5 Duplex Socket 16A,2P+E, Germany Standard (Sokuo), Orange Color for UPS No. 20.00
16.5.5.6 Rocket socket (3p-1ph-25A-220V-50HZ) for IT Rack No. 2.00

16.5.6 Lighting Switches


Supplying, installing, testing and commissioning Lighting Switches including modules ,
frame , covers , back box for flush/surface mounting - and all ancillary works according
to DWG's & Specs
16.5.6.1 Lighting Switch 1way,1gang,10A No. 8.00
16.5.6.2 Flush / Surface mounted -2 module- WP Lighting Switch 1way,1gang,10A,IP55
No. 4.00
16.5.6.3 Lighting Switch 1way,2gang,10A No. 6.00
16.5.6.4 Flush / Surface mounted -2 module- WP Lighting Switch 1way,2gang,10A,IP55
No. 4.00
16.5.6.5 Lighting Switch 1way,3gang,10A No. 1.00
16.5.6.6 Impuls Switch 10A for door bell No. 1.00
16.5.6.7 Rolling shutter switch with 1x3mm2 control circuit No. 2.00

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 14/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.5.6.8 LSP - Lighting switches panel (Grid Switch)


Supplying, installing, testing and commissioning Lighting Switches panel including
modules , frame , covers , back box for flush/surface mounting - blanks and all ancillary
works according to DWG's & Specs
16.5.6.8.1 LSP - 7 gang No. 2.00

16.5.7 Disconnect / Safety switches


Supplying, installing, testing and commissioning Disconnect / Safety switches including
enclosure , indication lambs, handle, back box, Cables entry glands , mounting posts
(according To installation method ) and all ancillary works according to DWG's & Specs

**Approved manufactures for industrial sockets (Legrand- Schneider - Or Approved


Similar)
#Contractor shall coordinate between disconnect breaking capacity , its associated circuit
breaker and the connected rating load, therefore upgrading (if required) without
demanding additional cost
#Contractor shall select the suitable IP grade according to installation method , therefore
upgrading (if required) without demanding additional cost

#Contractor shall label disconnect switches with Irrevocable labels indicate outlet and
electrical circuit code
#Contractor shall submit samples for approval for each item and have to be kept on site

16.5.7.1 Disconnect switch 25A-2P-250V No. 1.00


16.5.7.2 Disconnect switch 25A-2P-250V - equipped with fuse No. 13.00
16.5.7.3 Disconnect switch 32A-2P-250V - IP65 No. 13.00

16.5.8 Floor Boxes


Supplying, installing, testing and commissioning empty floor box but include back box ,
power or datamanufactures
**Approved sockets, installation accessories
for Floor and all ancillary works
boxes (Legrand-Ackerman according Similar
- Or Approved to )
DWG's & Specs
#Contractor shall coordinate between floor box type - in terms of size, capacity ,
16.5.8.1 protection index IP - and For
Floor box 4module,IP67 its associated
washable location
areas and required purpose No. 1.00

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 15/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.5.8.2 Floor box 8module,IP67 For washable areas No. 1.00


16.5.8.3 Floor box 12 module,IP44 For carpeted floor No. 6.00
16.5.8.4 Floor box 18 module,IP44 For carpeted floor No. 1.00
16.5.8.5 Furniture box from Riadco company for CSR desk (Double power& Double data).
No. 6.00

16.5.9 Lighting Fixtures


Supplying, installing, testing and commissioning lighting fixtures including drivers,
supports, cords, mountings, plugs and all ancillary works according to attached lighting
fixture schedule , DWG's & Specs
**Approved manufactures for Lighting Fixture (According to attached lighting fixture
schedule & Vendor list)
#Drivers Shall comply( ta≥50c,of ≥ 50,000 hours with a failure rate of 0.2% per 1,000
hours. ,IP20(Indoor)-IP65(Outdoor),PROTECTION CLASS II
,Low ripple≤10%
,Efficiency≥0.85,UL,SELV,P.F≥0.95)

#Contractor Shall install batteries and drivers inside proper fixed junction boxes and

#Contractor Shall comply with supplying drivers suitable for fixed or dimming operation
according to Specs & DWGs without demanding additional cost

#Contractor Shall comply with providing an warranty certificate for each type of lighting
unit for at least three years

#Contractor Shall comply with supplying at least 10% of drivers and batteries total
amount - as spare parts- to owner under the delivery record
#Contractor shall approve the lighting fixtures in terms of architecture view , lighting
color from the architectural consultant and the owner

#Contractor shall submit samples for approval for each item and have to be kept on site

#Contractor shall comply with suppling non leakage accessories and plugs for weather
proof lighting Fixtures

16.5.9.1 Mounted recessed LED luminaire(60x60cm) with opal diffuser 40w , CRI not less than
0.8 , 4000K, lumen not less than 4000lm

No. 23.00
16.5.9.2 Recessed LED round luminaire 20w (Down light) , CRI not less than 0.8 , 4000K, lumen
not less than 2000lm

No. 105.00
16.5.9.3 Ceiling recessed Linear LED profile with opal louver 100 CM,30w, CRI not less than 0.8
, 4000K, lumen not less than 3000lm

No. 4.00
16.5.9.4 Ceiling Suspended Linear LED profile with opal louver 120 CM,30w, CRI not less than
0.8 , 4000K, lumen not less than 3000lm

No. 22.00
16.5.9.5 Recessed LED Spot luminaire 10w (Down light) , CRI not less than 0.8 , 3000K, lumen
not less than 1000lm, IP44 No. 18.00
16.5.9.6 Ditto 16.5.9.9 but movable No. 1.00
16.5.9.7 Recessed double Spot luminaire 2x16w (adjustable) , CRI not less than 0.8 , 4000K,
lumen not less than 3000lm No. 16.00
16.5.9.8 Decorative suspended fixture (Highbay or cylindar), CRI not less than 0.8 , 4000K, not
less than 2500LM with high efficiency specular aluminum reflector for uniform
symmetrical light distribution.
No. 6.00
16.5.9.9 Chandelier 3 lamps 3000k for VIP area No. 2.00
16.5.9.10 Chandelier 1 lamp 3000k for Manager room No. 1.00
16.5.9.11 Chandelier 1 lamp 3000k for SME area No. 6.00

not to be released to any person or organization without the prior written consent of Vision Architects 16/33
Owner: Project:

MEP BDC BOQ

16.5.9.12 Led Strip 15w per meter 4000k, IP65 Mt. 100.00
16.5.9.13 Ditto 16.5.9.15 but 3000K Mt. 1.00
16.5.9.14 Exit Sign (Ceiling mounted) No. 4.00
16.5.9.15 Ditto 16.5.9.17 but wall mounted No. 1.00
FORWARD

not to be released to any person or organization without the prior written consent of Vision Architects 17/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.5.9.16 Uplight (UL1) No. 4.00


16.5.9.17 Empty Aluminium Led Profile 2.5cmx1.5cm custom length (field cut ability ) CV1
casing complete with Aluminium end cap , PMMA High efficient diffuser ,suspension
kit , ,IP20
Mt. 100.00
16.5.9.18 LED Lighting luminare (Marina) for exposed installation or suspended in concrete
ceiling 1270 X 80 X85mm, 4260 LM output lumen from modules, 38watt, 4000 K
IP=67,prismatic, Long life time, complete with all accessories For generators room,
VRV outdoor rooms,....etc.

No. 2.00

Lighting Fixtures Batteries


16.5.9.1.1 Supplying, installing, testing and commissioning lighting fixtures battery suitable for any
of above mentioned fixture sufficient for 4hr operation including driver, supports,
enclosure and all ancillary works installed in WP box above ceiling.
No. 85.00
16.5.10 Earthing System
Supplying, installing, testing and commissioning earthing system including rods,
earthing pits, standards joints , test links -At electrical rooms-, internal cables between
rods , Cadweld joint for main earthing cable (measured at other item) and all ancillary
works according to standards , DWG's & Specs

**Approved manufactures for earthing system (Furse -wallis or approved similar)

# All system component shall be manufactured by aforesaid brands except earthing pits
and cables permitted to be local
# Contractor shall fitting out system via a specified authorized earthing company

# Contractor shall submit earthing calculation for approval prior based on the
calculations of the value of the soil resistance from a 3rd party specialist - soil works -

# Contractor shall separate the earthing systems from each other to ensure that the fault
currents do not reverse from one system to another, leaving a distance between the rods
not less than twice the length of the rod

# The Contractor shall coordinate with the IT Department of the Owner to comply their
requirements for maximum earthing resistance values ​and required ponding points

# Contractor shall comply with handover the measurement of the resistance of the rods
and system in the presence of the consultant and the Owner after the execution and upon
the initial handover with a valid certificate

16.5.10.1 Earthing System for low voltage system with resistance not less than 2 ohm LS 1.00
16.5.10.2 Earthing System for Light Current system with resistance not less than 0.5 ohm
LS 1.00

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 18/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.6 Light Current Systems


16.6.1 Telecommunication System
# Contractor Shall submit traffic calculation report " TEST FLUKE" for data network
prepared by specialist networks technician
**Approved UTP cables (Panduit - Leviton- or approved similar)
**Approved manufactures for PVC conduits are (Engineering home- new ega) Heavy
Gauge

16.6.1.1 Data system outlets

Supplying, installing, testing and commissioning network run from outlet to associated
data rack or from outlet to its tying destination include conduits, Trunks with covers ,
supports , junction boxes , termination on rack and all ancillary works according to
DWG's & Specs

16.6.1.1.1 Network outlet with pulling thread drawn in PVC conduit 25mm No. 35.00

16.6.2 Fire alarm System

1.6.6.2.1
Supplying, installing, testing and commissioning fire alarm system outlet run from outlet
to other to the FACP including , conduits , junction boxes ,Accessories and all ancillary
works according to Standards , DWG's & Specs

**Approved manufacture for Fire Alarm Cable (Mesc-Belden-Elsewedy) or approved


similar
**Approved manufacture for EMT Conduits (Wheatland-Allied-Emeco)or approved
simila with equivalent UL-Listed accessories
# Contractor shall re-study filling ratio according to the actual Circumstances and
upgrading for high grade - if necessary - without demanding additional cost

# Contractor shall select the types of conduits suitable according to the conditions of
installation in locations exposed to mechanical exposure according to standards without
demanding additional cost
16.6.2.1.1 Fire alarm outlet with shielded cables Shielded 2x1.5mm2 ,Operation temp. 105C drawn
in EMT conduit Dia. 20mm2 - for each cable No. 50.00

Fire alarm Equipment


Supplying, installing, testing and commissioning addressable fire alarm system
according
# Tying withto standards , DWG's
firefighting system& Specs including all required connections and
communications with all building associated works which include BUT NOT LIMITED
#toTying with HVAC, Supply, Fresh , Pressurization and evacuation fans
the following:
# Tying with Access control system , escape doors and fire zone doors

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 19/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

# Tying with elevators, Public address, evacuation system, Audio Visual system , smart
systems , communications system & BMS (If Found)
# Tying with main fire alarm control panels of related buildings (If Found) -Via network
cards - Not including tying cables
# Tying with distribution panel boards to shied HVAC loads in case of fire
# Fault isolator every 10-15 detectors according to the manufacturer's instructions

#Contractor shall coordinate all the specializations associated with the system and
include them in the price
**Approved manufactures for fire alarm system UL/FM (Esser-FireLite-Simplex-
Notifire)
# contractor shall enhance shop drawing by reviewing and approving the security
department of the owner and the Fire Alarm Specialist, as well as providing the
calculations of loss of voltage for cables and calculations of the capacity of batteries -
according to the number of reagents - therefore increasing the Cables CSA or the
capacity of batteries without demanding additional cost

# contractor shall comply with the supplier's presence in the handover committees

# contractor shall supplying from suppliers have round the clock 24/7 customer service
Centre

16.6.2.2 Fire alarm control Panel

Addressable Fire Alarm system including Fire Alarm Control Panel including power
supplies (including spare power supply), batteries sufficient to 24h Normal operation &
30 minute alarm with capacity not less than 7Amp-h, battery charger, interface with
Public Address (if exist), connection to LAN network, Battery charger, Network
Interface Card and auto dialler

16.6.2.2.1 Addressable Fire Alarm Control Panel FACP 2-Loop No. 1.00
16.6.2.2.2 Addressable Fire Alarm Repeater Panel FARP at security desk No. 1.00

16.6.2.3 Fire alarm Devices and detectors


Supplying, installing, testing and commissioning addressable fire alarm devices and
16.6.2.3.1 detectors
Addressableincluding fire rated
Intelligent Pull boxes
Fire Alarm Smoke, indication
Detector lamps
ceiling- mounted
separate in case
with theunit.
base detector
is a composite hidden or enclosed in a mostly closed room - , bases, supports and all
ancillary works according to standards , DWG's & Specs No. 25.00
16.6.2.3.2 Addressable Intelligent Fire Alarm Smoke Detector ceiling mounted with fault isolator
base unit. No. 1.00
16.6.2.3.3 Addressable Intelligent Fire Alarm Heat Detector ceiling mounted with base unit.
No. 1.00

FORWARD 0.00
0.00

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.6.2.3.4 Addressable combined (Heat/smoke) detector No. 3.00


16.6.2.3.6 Indoor strobe UL/FM Siren similar to P2R System sensor with call point No. 4.00
16.6.2.3.7 Outdoor strobe UL/FM Siren similar to P2KR System sensor
No. 1.00
16.6.2.3.8 Addressable Intelligent (Control/Monitor) module No. 3.00
16.6.2.3.9 Addressable Double action UL/FM manual station No. 7.00
16.6.2.3.10 Magnetic lock 1200Ib manufactured be Nordson No. 1.00

not to be released to any person or organization without the prior written consent of Vision Architects 20/33
Owner: Project:

MEP BDC BOQ

16.6.3 Integration and Integrated Security management System (SMS)


Supplying, installing, connecting, programming, operating, testing and commissioning
Integrated Security management System For CCTV, Access Control, Intrusion
Detection, Fire Alarm and firefighting systems to be integrated With the Main Control
room in the HQ including Hardware, Servers, Software, Licenses, Engineering,
Integration, Coordination and all necessary accessories and ancillary works and materials
required for complete installation and operation as per the system manufactures
recommendations and as specified for the following items:

16.6.3.1 ISMS Software and Licenses No. 1.00


16.6.3.2 ISMS Branch server/client
No. 1.00

16.6.4.1 Addressable Intrusion system Outlets


Supplying, installing, testing and commissioning Intrusion system outlet run from outlet
to other to the control Panel including conduits , junction boxes , Accessories and all
ancillary works according to Standards , DWG's & Specs

16.6.4.1.1 Intrusion system outlet with UTP Cat.6 Cable drawn in PVC conduit Dia. 20mm2 - for
each cable No. 80.00
16.6.4.1.2 Intrusion system outlet with UTP Cat.6 Cable drawn in EMT conduit Dia. 20mm2 - for
each cable No. 1.00

Addressable Intrusion System Equipment


Supplying, installing, testing and commissioning Addressable Intrusion alarm system
(the system shall use the ISMS server) according to standards, DWG's & Specs including
Arming keypads, Software, Licesnce, and all required connections and communications
with all building associated works which include BUT NOT LIMITED to the following:

# Tying with escape doors


# Tying with main fire alarm control panels (If Found) -Via network cards - Not
including tying cables
# Tying with Access control , CCTV system , communication , automation & BMS - If
Found
#Contractor shall coordinate all the specializations associated with the system and
include them in the price
**Approved manufactures for Intrusion detection System (Texcom-DSC)
# contractor shall enhance shop drawing by reviewing and approving the security
department
# contractorofshall
the comply
owner and thethe
with system Specialist,
supplier's as well
presence in theashandover
providingcommittees
the calculations
of loss of voltage for cables and calculations of the capacity of batteries - according to
#thecontractor
number of reagents - therefore increasing the Cables CSA or the capacity ofservice
shall supplying from suppliers have round the clock 24/7 customer batteries
Centre
without demanding additional cost

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 21/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.6.4.2 Addressable Intrusion control Panel (ICP)


Intrusion alarm adressable control Panel complete with manufacture enclosure ,
expandable by adding areas & interface cards -IP connection, including batteries
sufficient to 72h Normal operation & 30 minute alarm with capacity not less than
7Amp-h, Battery charger, auto dialler, Network Interface Card and expandable up to 248
harwired and wireless zones.

16.6.4.2.1 Addressable wired Intrusion control panel with suitable capacity and keypad
No. 1.00
16.6.4.2.1 Addressable Intrusion Repeater panel with keypad at security desk No. 1.00
16.6.4.3 Addressable Intrusion system Devices and detectors

Supplying, installing, testing and commissioning Intrusion system devices and detectors
including junction boxes , indication lamps - separate in case the detector is a composite
hidden or enclosed in a mostly closed room - , bases, supports and all ancillary works
according to standards , DWG's & Specs

16.6.4.3.1 Addressable Vibration detector No. 45.00


16.6.4.3.2 Addressable Break glass detector No. 18.00
16.6.4.3.3 Addressable Knee Rails No. 4.00
16.6.4.3.4 Addressable Magnetic door contact (From the same system manufacture) No. 1.00
16.6.4.3.5 Addressable Microwave PIR - Dual Technology Motion Sensor No. 4.00
16.6.4.3.6 Addressable Panic Button ( From the same system manufacture) No. 3.00
16.6.4.3.7 Addressable Internal Siren with Flasher No. 3.00
16.6.4.3.8 Addressable External Weather Proof Siren with Flasher No. 1.00

16.6.5 Access control system


16.6.5.1 Access control system Outlets
Supplying, installing, testing and commissioning Access Control system outlets from
the outlet up to its indicated controller including conduits , junction boxes , Accessories
and all ancillary works according to DWG's & Specs

16.6.5.1.1 Proximity Card Reader outlet - UTP Cat.6 / 20mmPVC conduit No. 4.00
16.6.5.1.2 Push to Exit outlet - UTP Cat.6 / 20mmPVC conduit No. 4.00
16.6.5.1.3 Electro/Magnetic Lock for Single/double/sliding Door outlet - UTP Cat.6 / 20mmPVC
conduit No. 4.00
16.6.5.1.4 Door Contact for Single/double/sliding Door outlet - UTP Cat.6 / 20mmPVC conduit No. 4.00
16.6.5.1.5 Ditto but in EMT conduit No. 1.00

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 22/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.6.5.2 Access control system control panels (ACP)


Supplying, installing, testing and commissioning Expandable Access Control Panel
multi-door controller (By adding cards - UP to 32 I/O) complete(the system shall use
the ISMS server as the access control backend) including Software Licesnce,
manufacture metal enclosures, power supplies, terminations, fittings, battery sufficient
for 24 hours, battery charger, accessories and all ancillary works according to DWG's ,
Specs and manufacture recommendations.

**Approved manufactures for access control system (HID EVO - Lenel - Mercury).

# Tying with main fire alarm control panels (If Found) -Via network cards - Not
including tying cables
16.6.5.2.1 Access Control Panel with suitable capacity. No. 1.00

16.6.5.3 Access control system Devices


Supplying, installing, testing and commissioning Access Control system Devices
including junction boxes , bases, supports and all ancillary works according to DWG's ,
Specs and manufacture recommendations
# Contractor Shall select the Lock and door contact as per Door material and type for
complete installation
• Magnetic Door Lock for Wood doors and as per door weight.
• Magnetic Door Lock for Glass doors and as per door weight.
• Magnetic Door Lock for Metallic doors and as per door weight.

# Size and color of the lock should be acc. To approved by Arch. Provision
16.6.5.3.1 Proximity Card Reader (HID) No. 4.00
16.6.5.3.2 Metal Push to Exit same manufacturer No. 4.00
16.6.5.3.3 Magnetic door Lock for Single/double/sliding door manufactured by same system
supplier or by "Nordson" No. 4.00
16.6.5.3.4 Magnetic Contact for Single/double/sliding door No. 4.00
16.6.5.3.5 Proximity Cards "By HID" No. 50.00

16.6.5.4 Standalone access control

Supplying, installing, testing and commissioning Standalone access control for


individual door including controller , metal enclosure, Lock, Door release push bottom ,
power supply , cables required for tying door component , supports , junction boxes ,
termination on rack and all ancillary works according to DWG's & Specs and supplier
recommendation

**Approved manufactures for access control system


# Standalone system shall tied with the main access control system and other security
system in building

FORWARD 0.00

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

# Standalone system shall be applicable to control access via the employees'


identification cards and with sufficient number of employees

16.6.5.4.1 Standalone access control for individual door No. 1.00 ................. Alternative

16.6.6 CCTV System


16.6.6.1 CCTV System Outlets

not to be released to any person or organization without the prior written consent of Vision Architects 23/33
Owner: Project:

MEP BDC BOQ

Supplying, installing, testing and commissioning CCTV outlet run from outlet to
associated rack or from outlet to its tying destination include conduits, Trunks with
covers , supports , junction boxes , termination on rack and all ancillary works according
to DWG's & Specs

16.6.6.1.1 CCTV outlet with UTP Cat6 cable drawn in PVC conduit 20mm No. 40.00
16.6.6.1.2 CCTV outlet with UTP Cat6 cable drawn in EMT conduit 20mm No. 1.00

16.6.6.2 CCTV System


Supplying, installing, connecting, programming, operating,
testing and commissioning
**Approved IP Video
manufactures for Surveillance
surveillance systemsystem
(Pelco & Axis only)
Main Equipment including servers, cameras, Hardware, Software,
Licenses, Engineering, Integration, Coordination and all
16.6.6.2.1 IP Indooraccessories
necessary fixed domeand
camera (Appendix6)
ancillary works and materials No. 29.00
required for complete installation and operation as per the
system manufactures recommendations and as specified FORWARD 0.00
for the following items:

not to be released to any person or organization without the prior written consent of Vision Architects 24/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.6.6.2.2 IP outdoor fixed dome camera (Appendix7) No. 2.00

16.6.6.2.3 IP outdoor fixed camera weather proof (Appendix8) No. 7.00

16.6.6.2.4 IP outdoor PTZ camera weather proof (Appendix9) No. 1.00

16.6.6.2.5 IP Outdoor/outdoor fish eye Camera 180⁰


• 8 megapixel resolutions & 25fps
• True Day/Night (Automatic)
• Wide Dynamic Range not less than 100 db
• Minimum Illumination 0.2 lux color, 0.05 lux b/w
• Motion detection
• IR-150m
• 3 Streams
• Video Compression H.265 No. 1.00

FORWARD 0.00

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.6.6.3 VMS Server (Appendix1)


Supplying, installing, testing and commissioning server according to DWG's , Specs and
manufacture recommendations
There will be two streams as below:
Monitoring stream: Full HD 25 FPS.
Recording stream on main server and backup server: Full HD 25 FPS.
# Server shall include dual power supply
# Server shall support dual monitor
# Server Shall support 4K resolution
# Server Shall equipped with alarm inputs
Event Trigger: Alarm input, Video loss, Camera event (Sensor, MD, Video analytics

# Server Shall equipped with alarm outputs


Event Action: E-mail, PTZ pre-set, Alarm out, Buzzer, Monitor out
# Server Shall equipped with Internal Raid Support (Raid6)
# Server Shall support External Storage Support (e-SATA/NAS)
# Server Shall include DVD Writer ( For Backup)
# Server Shall equipped with Analogue Video Output (VGA/HDMI)
# Server Shall support Mobile Viewer , Mouse Control , IR Remote Control

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 25/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS

DESCRIPTION
ITEM
UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.6.6.3.1 VMS Software and Licenses with failover (Appendix2) LS. 1.00

16.6.6.3.2 Storage servers for all branch cameras with storage capacity for 90 days continious No. 1.00

16.6.6.3.3 Failover servers for all branch cameras with storage capacity for 2 days continious No. 1.00

Backup Storage servers for 8 Cameras with storage capacity


16.6.6.3.4 No. 1.00
for 2 days continious

CCTV Network Component

16.6.6.4 CCTV system Rack (Appendix3)

16.6.6.4.1 RACK CABINET TYPE A No. 1.00


16.6.6.4.2 RACK CABINET TYPE B No. 1.00
16.6.6.4.3 RACK CABINET TYPE C No. 1.00

16.6.6.5 CCTV system Patching


Supplying, installing, testing and commissioning full loaded Patch panels complete with
organizer and labelled with standard printed label system based on TIA/EIA standards
according to DWG's & Specs

16.6.6.5.1 24 ports Copper Patch Panel complete with Copper patch cord, connector, pigtail and
horizontal organizer. No. 4.00
16.6.6.5.2 12 ports Main Fiber Optic Patch Panel complete with fiber patch cord, Fiber connector,
pigtail and horizontal organizer. No. 1.00
16.6.6.5.3 Media converter for incoming cable (if needed) No. 1.00

16.6.6.6 CCTV system Switches and Active Components


Core Switch
16.6.6.6.1 Supplying, installing, programming, testing and commissioning an Ethernet-Modular-
Multilayer multi-service Core Switch that will be located at IT room and have sufficient
number of 1 Giga modules and ports to serve edge switches of secuirty network. These
ports must occupy max. 80% of the total switch slots leaving 20% of the switch slots for
future expansions. The switche must contain all needed hardware, software elements, 24 No. 2.00
port copper patch panel and licenses to have all functions, protocols and features required
as specified for the following items:

Access Switch
Access Switches, Supplying, Installing, testing, and commissioning of an access Ethernet
switches. The stacks must contain all needed hardware, uplinks ports, software elements,
and licenses to have all functions and features required as specified.

16.6.6.6.2 Supplying, installing, testing, and commissioning an L3 Access Ethernet Switching No. 4.00
Stacks with capacity of (24) 10/100/1000 Base - T ports with POE/POE+ feature. All
access switched must have 10% free ports for future expansions.
16.6.6.7 OPERATOR WORKSTATIONS (Appendix4)

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 26/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.6.6.7.1 CCTV Work Station No. 1.00


16.6.6.7.2 Dell or HP Core i7 -Laptop for manager No. 1.00

16.6.6.8 WALL MOUNTED SURVEILLANCE OPERATOR SCREENS (Appendix5)

16.6.6.8.1 Professional CCTV Display 32" - heavy duty 24/7 No. 3.00

16.6.7 Metal detector gate


Gate contains 33 points for metal detection including sensors, sound alarms, and all
accessories needed for complete installation as CBE instructions European origin
approved as data sheet that will be submitted.

No. 1.00
16.6.8 Telephone Cables
Supplying, installing, testing and commissioning telephone cable include Conduits ,
cable trays, junction boxes, hand holes , terminals of indoor and outdoor (related to
telecommunication authorization) frame and all ancillary works according to standards ,
DWG's & Specs

**Approved manufactures for telephone cable ( El Sewedy)


**Approved manufactures for jelly filed telephone cable (Panduit)
16.6.8.1 PVC Telephone Jelly Filled cable 20Pairs M.L 0.00
16.6.8.2 Empty conduit with pulling thread drawn in PVC & EMT conduit 25mm M.L 150.00

16.6.8.2 Telephone frame


Supplying, installing, testing and commissioning telephone frame including and all
ancillary works according to standards , DWG's & Specs according to standards , DWG's
& Specs
**Approved manufactures for telephone frame ( Comtec)
16.6.8.2.1 Recessed indoor metal screw type 10-Pair Tel. frame No. 0.00
16.6.8.2.2 Exposed Outdoor metal screw type 10-Pair Tel. frame No. 0.00

16.6.9 Queuing System


Queuing System outlets
Supplying, installing, testing and commissioning Queuing system outlet run from outlet
to associated rack or from outlet to its tying destination include conduits, Trunks with
covers , supports , junction boxes , termination on rack and all ancillary works according
to DWG's & Specs

16.6.9.1 Empty Queuing outlet with pulling thread drawn in PVC conduit 20mm No. 15.00
16.6.9.2 Sound outlet with PVC conduit with a diameter of 20mm fire rated heavy gauge (Beit El- No. 6.00
Handasa or similar) and 2*1.5 mm^2 standard wire from outlet (speaker - kiosk) to
amplifier.

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 27/33
Owner: Project:

MEP BDC BOQ

SECTION 16: ELEC WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

16.6.10 MATV
MATV outlets
Supplying, installing, testing and commissioning MATV system outlet run from outlet
to Building roof or from outlet to its tying destination include conduits, Trunks with
covers , supports , junction boxes , termination on rack and all ancillary works according
to DWG's & Specs

16.6.10.1 MATV outlet with RG6 cable drawn in PVC conduit 20mm No. 1.00
16.6.10.2 HDMI outlet with HDMI cable drawn in PVC conduit 29mm No. 1.00

16.6.11 Early warning system


Supplying, installing outlets for auto dialler unit (System Motorola) "supplied by others".
Item includes conduits for the system of 25mm diameter PVC type
from the Control (Security) room to each of
-Branch manager
-Security desk @ the branch control room
-Antenna location
as per client requirement and analogue line cables 2 pairs with all needed accessories.
All specified as per Unit

No. 5.00

16.6.12 Advertising Display Screens


Supplying, installing and testing a commercial display screen "LG" or similar including
all the necessary fixation accessories on the wall for the hereinafter sizes:

16.6.12.1 For 43" No. 2.00


16.6.12.3 For 65"
No. 1.00

16.6.13 Generation set


16.6.13.1 Diesel Generator

Supplying, installing, testing and commissioning a diesel generator


complete with Canopy
**Approved manufactures for diesel generator ( Cummins - caterpiller -
Or Approved Similar)
# Generator electrical rating in KVA or KW at 0.8 power factor
#Power Factor 0.8, Operating voltage 380 V & Operating frequency 50
HZ @ Full load
# Gen. shall eqquiped with electronic Governer.
# Gen. shall equipped with residential silencer.
# Sound pressure levels for Canopy the not exceed 75db@1m
# Gen set shall be a complete package unit mounted on rigid base
suitable for skidding
# Exhaust pipe (Design & constriction) Shall extended from generator
room to the approved outdoor location on top of the roof.

not to be released to any person or organization without the prior written consent of Vision Architects 28/33
Owner: Project:

MEP BDC BOQ

#Gen. shall equipped with built in daily fuel tank


# Bulk storage tank with capacity 1m3 or capacity sufficient for
8hr/7day full load operation - which greater - including control panel,
gear fuel pump, manual pump and piping system
# Monitoring meters indicate all faults, alarms, frequency, volt,…, etc.
# Gen. shall equipped with batteries , charger and accessories.
# Gen. shall equipped with Instrumentation, control panel including
interconnecting control cable, wires & accessories.
# Vibration's mechanical absorber shall be provided.
# Complete set of tools and portable instruments for the operation and
equipment shall be provided, together with suitable means of
identification, storage and securing.
# Generation Set shall couplied by certified the manufature
# Supplier of the diesel engine generator set shall provide a service
contract for a period of five years after guarantee period
# Contactor has to cheek generator dimensions to comply with room
size
# contractor shall supplying from suppliers have a Authorized customer
service centers

16.6.13.1.1 Standby diesel generator 60KVA,3ph No. 0.00


16.6.13.1.2 Standby diesel generator 50KVA,3ph No. 0.00
16.6.13.1.3 Standby diesel generator 30KVA,3ph No. 0.00
0.00
16.6.14 Atuomatic transfer switch - ATS
# ATS shall be 4-Pole to transfer phases & neutral
# ATS shall be electrically and mechanically interlocked to to ensure
only two possible positions, normal or emergency

not to be released to any person or organization without the prior written consent of Vision Architects 29/33
Owner: Project:

MEP BDC BOQ

16.6.14.1 ATS-125A No. 0.00


16.6.14.2 ATS-100A No. 0.00
16.6.14.3 ATS-80A No. 0.00

16.6.15 Automatic Voltage Stabilizer


Type: Servo-Mechanical Voltage Stabilizer with static control, Electrostatic painting&
sholud be made in EU / USA or equivalent.
Input: Voltage: 380VAC 3PH+N
Voltage Tolerance: +/-25%
Frequancy: 50HZ
Output: Voltage: 380VAC 3PH+N
Voltage Tolerance: +/-2%
Frequancy: 50HZ
Efficiency: not less than 97%
Cooling: Natural Air & no need for fans

including:
Manual Bypass
Over/Undere voltage protection at input (Window +/-30%)
Input MCCB & Output MCCB
Stabilizer should has control for each phase & common control rejected

SLP surge protection cl.ll


Digital Multimeter EMM (measure all output parameters)
Installing, Commissioning& Startup
Testing of voltage variation to be performed at no load

16.6.15.1 Rate 80 KVA NO. 0.00


16.6.15.2 Rate 100 KVA NO. 0.00
16.6.15.3 Rate 120 KVA NO. 0.00
16.6.15.4 Rate 150 KVA NO. 0.00
16.6.15.5 Rate 200 KVA NO. 0.00
16.6.15.6 Rate 300 KVA NO. 0.00
ELEC WORKS TOTAL 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 30/33
Owner: Project:

MEP BDC BOQ

SECTION 17 : SANITARY WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP

The following sanitary items of first class quality in approved color. Complete work
including all components complete with all supply, drainage, vent pipes, isolating valve
and all accessories, chromium plated, taps - mixers for cold and hot water - gate valves
produced by "Ideal Standard" or similar, anti-fungus sealant, …etc.

The Works shall include installing crewed and socked poly propylene pipes of adequate
diameter sizes- to the water source- (Hot & cold). To ensure a strong and continuous
water pressure for all pipes, the level of the feeding pipes shall be above the ceramic tiles
level whereas down pipes shall run downwards to the intake of each sanitary fixture
(independent pipe for each fixture). Complete work including elbows, bends, tees,
hangers and all necessary connections, sufficient stopcock valve of adequate diameter,
gate valve diam.3/4" for each individual sanitary fixture, ...etc.

Pipes shall be manufactured by "AQUATHERM", "BANINGER" or similar.


The Works shall also include UPVC pipes manufactured by "Kissel" or similar for
drainage with adequate diameter - to the nearest existing sewage point with sizes to
ensure an efficient drainage system with smooth flow of waste water, Complete work
including elbows, bends, tees, cleaning eyes, floor drain, gully trap, inspection manhole
and all required fixing fastening material. Embedded UPVC sewage/drainage/ventilation
pipes must be covered with 100mm concrete,...etc.

The Works shall include all required works to compete the installation as per BDC / VA
instruction and up to their satisfaction.
17.1 WATER SUPPLY SYSTEM
17.1.1 VALVES
Supplying, installing, bronze gate valves PN20 for cold and hot water piping, including
all fixings and accessories.
Complete as specified, to the approval of the Engineer and according to manufacturer's
recommendations.

17.1.1.1 Supplying and installing 1/2" Valve


ALL SPECIFIED AS PER UNIT UNIT 14.00
17.1.1.4 Supplying and installing 1.5" Valve
ALL SPECIFIED AS PER UNIT UNIT 1.00

17.1.2 WATER DISTRIBUTION PIPING


Supplying, installing and testing cold and hot water Polypropylene pipes with aluminium
ring complete with pipe fittings, supports, accessories and expansion joints.
Complete as specified, to the approval of the Engineer.

17.1.2.1 Supplying and installing 1/2" Pipe


ALL SPECIFIED AS PER METER LENGTH M.L 12.00

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 31/33
Owner: Project:

MEP BDC BOQ

SECTION 17 : SANITARY WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00
17.1.2.2 Supplying and installing 3/4" Pipe
ALL SPECIFIED AS PER METER LENGTH M.L 15.00

17.1.2.3 Supplying and installing 1" Pipe


ALL SPECIFIED AS PER METER LENGTH M.L 10.00

17.1.2.4 Supplying and installing 1.5" Pipe


ALL SPECIFIED AS PER METER LENGTH M.L 3.00

17.2 SEWAGE SYSTEM


17.2.1 SANITARY DRAINAGE AND VENT PIPES
Supplying, installing & testing UPVC pipes mechanical integral joints using the rubber-
sealing rings complete with all required fittings, supports and accessories as specified
and shown on the drawings, to the approval of the Engineer.

17.2.1.1 Supplying and installing 2" Pipe


ALL SPECIFIED AS PER METER LENGTH M.L 12.00

17.2.1.2 Supplying and installing 3" Pipe


ALL SPECIFIED AS PER METER LENGTH M.L 15.00

17.2.1.3 Supplying and installing 4" Pipe


ALL SPECIFIED AS PER METER LENGTH M.L 26.00

17.2.2 FLOOR DRAINS


Supplying, installing, St/St floor drain with a nickel bronze strainer and cover.
Complete as specified, to the approval of the Engineer.

17.2.2.1 Square floor drain 4" UNIT 5.00

17.3 PLUMBING FIXTURES


17.3.1 WASH BASIN (DuraStyle Washbowl )
Supplying and installing 380x600mm washbowl, Durastyle Model-No. 034960 from
Duravit with Sanitary ceramics with the special WonderGliss surface finish.
Including lap hole and chrome waste cover, lava mixer SMART Model: B0460 from
Ideal Standard, with a maximum 5lt/min flow-rate, with 35 mm cartridge, hot water
limiter, flexible hoses SPX G3/8'', Easy-fix, cache aerator M21,5x1 with adjustable flow,
pop-up rod and metal pop-up waste, chrome
Vessel mixer, 5lt/min flowrate
Two 15-mm angle valves, chrome plated similar to Model G4303 from Ideal Standard.
Complete as indicated on drawings and as specified, to the approval of the Engineer and
according to manufacturer's recommendations.

ALL SPECIFIED AS PER UNIT UNIT 4.00

FORWARD 0.00

not to be released to any person or organization without the prior written consent of Vision Architects 32/33
Owner: Project:

MEP BDC BOQ

SECTION 17 : SANITARY WORKS


ITEM DESCRIPTION UNIT QTY RATE EGP AMOUNT EGP
Before 0.00

17.3.2 WATER CLOSET (TONIC Model)


Supplying, installing European type wall mounted bowl with soft close seat and cover,
white colored, similar to TONIC Model G3191 from Ideal Standard with built in douche.
Concealed wall mounted flush valve mechanism (double push button) including the
necessary wall support. 10-mm angle valve with 300-mm long tube, chrome plated..
Complete as indicated on drawings and as specified, to the approval of the Engineer and
according to manufacturer's recommendations.

ALL SPECIFIED AS PER UNIT UNIT 3.00

17.3.4 KITCHEN SINK


Supplying, installing stainless steel, one bowl flush mounted, single drainer, unit shall
include:
- Sink: CENTINOX Model: CEX 210-50/610-50 from Franke, overall size
555x465x200mm with one tap hole, complete with all necessary accessories.
- Single whole mixer SLIMLINE II Model: B0561AA deck mount from Ideal Standard
consists of Mono-block, dual-control, basin mixer with ceramic-disk, 1/4-turn cartridges
and cast brass body. Includes handles and pop-up waste..
- Waste P-trap: 40-mm chrome plated with adjustable inlet.
- Angle valves: Two (2) 15-mm angle valves, chrome plated Model: G4303 from Ideal
Standard.
Complete as indicated on drawings and as specified, to the approval of the Engineer and
according to manufacturer's recommendations.

ALL SPECIFIED AS PER UNIT UNIT 1.00


17.6 Electrical Water Heater
Supplying and installing first class quality electrical water heater
"OLYMPIC"OR "ARISTON" OR similar including all necessary fixing accessories.

17.6.1 Supply & install water heater 50 Liter. No. 3.00


FORWARD 0.00

SANITARY WORKS TOTAL 0.00

SUMMARY
Item Description
No. Amount EGP
14 FIRFIGHTING WORKS
15 HVAC WORKS
16 ELECTRICAL WORKS
17 SANITARY WORKS
FINAL TOTAL

not to be released to any person or organization without the prior written consent of Vision Architects 33/33

You might also like