CHAP6 Hydrograph Analysis
CHAP6 Hydrograph Analysis
CHAP6 Hydrograph Analysis
ENGINEERING HYDROLOGY
HYDROGRAPH ANALYSIS
1
WEEK 6 – HYDROGRAPH ANALYSIS
LEARNING OUTCOMES
At the end of the week, students should
be able to:
1) apply unit hydrograph to determine direct runoff hydrograph
2) derive unit hydrograph from a storm hydrograph by principle of
superposition and lagging (CO2);
3) derive unit hydrographs of other durations from a unit
hydrograph (CO2);
4) derive synthetic unit hydrograph for a meteorologically similar
watershed (CO2).
2
Total runoff Direct runoff
hydrograph, TRH - Baseflow = hydrograph, DRH
Q Q Q
t t t
D
1cm RE * Volume of water in UH = RE
Q (m3/s)
* Average Intensity of RE
5
HENCE, UH can be used to predict runoff from a storm event
Effect of Storm Duration, D (hours)
2-hr UH 6-hr UH 12-hr UH
2 hr 1cm RE 6 hr 1cm RE 12 hr 1cm RE
Q Q Q
Unit RE
Unit RE Unit RE
A1 A2 A3
t t t
1cm RE P cm RE
Q Q
t t
tb tb
1cm RE P cm RE
Q Q
t t
tb tb
Q Q
D hr D hr D hr
1 cm 1 cm
1 cm
Total DRH:2 cm
1 cm RE
RE
1 cm RE
1 cm RE
t t
tb tb for 1st rainfall
tb for nd
Total DRH = Sum(DRHi) 2 rainfall
D-hr UH
Q D D D
D Q cm R cm
1cm P cm
Q
= (P+Q+R) DRH
Q-DRH
P-DRH R-DRH
t
tb
tb for P t
Total DRH = DRHi
tb for Q
Time base for Total DRH, tb for R
tb’ = tb + (n-1)D tb’
10
n = number of rainfall
Example: 6.4, pg 207
t(h) Ordinates Ordinates
x RE depth: linear response
6 h-UH DRH
x3.5
0 0 0
x3.5
3 25 87.5
x3.5
6 50 175 3.5 cm DRH
x3.5
9 85 297.5
x3.5
12 125 437.5
6-hr UH
…
x3.5
60 8 28
x3.5
69 0 0 tb
11
Example: A catchment has a constant loss rate of 1.5 cm/h.
In a particular storm event, the catchment receive 6 cm
rainfall in 2 hours and 5 cm rainfall in the next 2 hours.
Determine the resulting runoff hydrograph if the average
baseflow is 20 m3/s and the 2 h UH is given.
13
?????
160
DRH (3cm)
140
DRH (2cm)
120
TOTAL DRH
100 Flood Hydrograph
80
60
40
20
0
0.0 2.0 4.0 6.0 8.0 10.0
14
Example 6.5, pg208
t(h) 6hr-UH DRH2cm
0 0
3 25 x2
Dt = 3h 6 50 0
9 85 50
12 125 100 Dt = 3h Dt = 6h Dt = 9h
15 160 170
18 185 250
24 160 320
Dt = 6h 30 110 370
36 60 320
. . .
. . .
. . .
15
Example 6.5, pg208
t(h) 6hr-UH DRH2cm t(h) UH DRH2
. . .
0 +3 0 . . .
3 +3 25 x2
. . .
6 +3 50 0 x2
48 +6 25 ??
9 +3 85 50 54 +6 16 50
12 125 100 60 +6 8 32
15 +3 160 170 69 +6 0 ??
18 +3 185 250 75 0
21 320
24 +6 160 370
30 +6 110 320 For UH, tb = 69h
36 60 220
. . .
42 36 120 Time base for Total DRH,
. . .
. . . tb’ = tb + (n-1)D
16
17
18
19
DIY:
Example 6.6, pg 210
For 6hr-UH (same ordinates as EX 6.4), where tb = 69 h
20
6
21
WEEK 6 – HYDROGRAPH ANALYSIS
LEARNING OUTCOMES
At the end of the week, students should
be able to:
1) apply unit hydrograph to determine direct runoff hydrograph
2) derive unit hydrograph from a storm hydrograph by principle of
superposition and lagging (CO2);
3) derive unit hydrographs of other durations from a unit
hydrograph (CO2);
4) derive synthetic unit hydrograph for a meteorologically similar
watershed (CO2).
22
DERIVATION OF UH
23
Derivation of UH pg 212
Requires at least five (5) QUALIFIED storm events
with the following characteristics:
• Storm must be isolated/ independent
• Storm must be uniform over entire duration
• Storm must be uniform over entire watershed
• Storm duration must be ±20%D (preferably less)
• Storm duration must be 1/5 to 1/3 of basin lag
• Storm magnitude must be significant, preferably
between 1 to 4cm
24
Limitations of UH
• Storm are rarely uniform over entire catchment,
hence, UH method is only applicable for
2 km2< A < 5000 km2
• Large storage in catchment which will affect the
assumption of linear response is not considered.
• Precipitation must be rainfall only, snow fall
cannot be considered.
• Method invalid if the storm is nonuniform in time.
Accuracy: typically ±20% tb , ±10% Qp
25
Derivation of UH
• 5nos UH from qualified storm events
-Qp are different
Q
- tpk are different
- tb are different
26
Average UH
• determine average Qp, tpk and tb
Qp Average UH
Q
tpk tb t
27
Example
Time UH (m3/s) ≡ DRH (m3/s) UH (avg)
h storm 1 storm 2 storm 3 storm 4 storm 5 (m3/s)
0 0.0 0.0 0.0 0.0 0.0 0.0
2 1.9 1.2 1.5 1.4 1.6 1.5
4 9.4 6.0 8.5 5.5 9.1 7.7
6 9.3 9.9 8.0 10.1 8.5 9.2
8 7.0 8.2 6.1 8.3 6.5 7.2
10 5.2 6.1 4.5 5.9 5.0 5.3
12 3.3 4.3 2.8 4.3 3.5 3.7
14 2.1 2.9 1.8 3.0 2.4 2.5
16 1.2 1.9 0.8 1.9 1.4 1.5
18 0.6 1.0 0.0 1.2 0.6 0.7
20 0.0 0.5 0.6 0.0 0.2
22 0.0 0.0 0.0
2.0
0.0
0 5 10 15 20 25
29
Time UH (avg) UH (avg)
Time, h corrected
h (m3/s)
0 0.0
0 0.0
2 1.5
2 1.5
4 7.7
4 7.7
5 9.4
6 9.2
6 9.2
8 7.2
8 7.2
10 5.3
10 5.3
12 3.7
12 3.7
14 2.5
14 2.5
16 1.5
16 1.5
18 0.7
18 0.7
20 0.2
20 0.0
22 0.0
22 0.0
1.0
1.00
30
10.0
Qp = 9.4 9.0
8.0
Qp average UH = 9.2
7.0 Average
tp average UH = 6 h corrected
6.0
5.0
4.0
3.0
2.0
1.0
0.0
0 5 10 15 20 25
31
Derivation of UH when D is same
DRH for D-hr rain D-hr UH
D hr D hr
Q Q
P units RE
1 unit RE
V=PxA V=1xA
t t
tb tb
33
DERIVATION OF UH FROM
COMPLEX STORM EVENT;
D DIFFERENT SITUATION
34
Analysis
Input Transfer Function Output
Rainfall Data
?
Unit Hydrograph Streamflow Data
Synthesis
Input Transfer Function Output
35
1D 2D 3D
UH of Complex Storm
R1 R2 R3 :different rainfall duration, D
Total DRH due to two D-hr rainfall
Q
R1U4+ R2U3
R1U5+ R2U4
R1U7+ R2U6
DRH due to D-hr effective rain of R2 unit
R1U9+ R2U8
D-hr
36
Convolution Computation
Time Rainfall UH Runoff due to Runoff due to Runoff due to Total direct runoff
(hr) excess Un 1st 2nd 4th Qi
Rm X-hr rain X-hr rain X-hr rain
0 - 0 0 0 0 0
X R1 U1 R1U1 0 0 R1U1
14X 0 0
37
Deconvolution Computation
Q1 = R1U1
Q2 = R2U1 + R1U2
Q3 = R3U1 + R2U2 + R1U3
…
QM = RMU1 + RM-1U2 + … + R1UM
QM+1 = 0 + RMU2 + … + R2UM + R1UM+1
…
QN+M-2 = 0 + 0 + … + RMUN-1 + RM-1UN
QN+M-1 = 0 + 0 +…+ 0 + RMUN
Q=RxU
38
UH of different durations, D
39
Method of Superposition
DRH for 2D-hr rain
D-hr UH
Q
2D hr
D hr
Q 1cm RE 2cm RE
t t
tb
tb
tb
Intensity = 1/D cm/h
Lag time
45
46
S-hydrograph Method
48
S-hydrograph
Q
S-hydrograph, a.k.a S-curve,
hydrograph produced by
continuous ER at constant
D hr
Maximum
rate & is the summation of
infinite series of D-hr UH,
S-hydrograph spaced D-hr apart.
D hr UH
Maximum equilibrium
discharge at a time
equal to the time base of
t the first UH
D hr D hrtb1
tb2 *Approach constant at tb – D
tb3
49
S-hydrograph
Intensity = 1/D cm/h Q T hr
DS
S-hydrograph B
DS DS
T/D cm
DS x D/T
1 cm
t
lagged T hr
tb’ = tb + (T-D)
51
(DRH Ordinate) / RE depth = UH Ordinate
52
Example 6.10 pg:219
Derive S-curve for the 4-hr UH?
Hint: use Eq 6.8; S(t) = U(t) + S(t-D)
t = time, D = rainfall duration
54
55
D -hr Hint: use Eq 6.8; S(t) = U(t) + S(t-D)
Derive 12-h UH from 4-h UH???? t = time, D = rainfall duration
56
Example 6.11; pg221
Approach constant at tb – D = 44 – 4 = 40h For S-curve
Q (m3/s)
0 4 8 12 16 20 24 28 32 36 40 44 t (h)
57
Example 6.11, pg221
Consider two D-h S-curve, displaced by T-h
tb’ = tb + (T-D) = 44 + (12-4) = 52h
Q (m3/s)
S1 S2
DS
0 4 8 12 16 20 24 28 32 36 40 44 48 52 t (h)
58
Example 6.12, pg221
Fairing
59 S(t-D)
Hint: use Eq 6.8; S(t) = U(t) +
Example 6.12, 221
20 20 10 10
0 +4
0 12 42 -4 t (h)
60
Example 6.12, pg221
Fairing
0 12 42 t (h)
61
UH of different durations
Problem solving: 6.18, 6.19
63
Synthetic UH
Gauged Data UH
t ? t
65
tc Storm Hydrograph
D
D = rainfall duration
* Rainfall
L
tpk = time to peak
tb = time base
Q
tc = time of concentration
Point of
inflection/max L = lag time, basin lag
storage
* tr
centre of mass
*t = recession time
r
tpk
Beginning of rainfalltb 66
Components of Hydrograph pg 198
Snyder’s Method – popular method
Snyder adopted a standard duration tr hours of effective rainfall
given by
tr = tp / 5.5
Required UH W75
Qp
Tp
Tb t 69
Snyder’s Method
Qp
W75 /3
0.75Qp
2/3 W75
0.5Qp
W50 /3 2/3 W50
tpk
t
70
Example 6.14, pg227 Snyder’s Method
Step 1: check whether source UH is standard
Step 2: determine regional constants (Ct & Cp) of source UH
Step 3: check whether required UH is standard
Step 4: determine parameters of required UH
Step 5: determine time base of required UH
Step 6: finalizing required UH using S-curve method
Source UH Required UH
Qp
t
? t
71
Snyder’s Method
Step 1: check whether source UH is standard
Assume tr = tR
Source UH
tR tr = tp / 5.5 tp
If tp’ = tp standard
tp’
Qp
If tp’ tp non-standard
Tp = tR/2 + tp’
t 72
If equal, tp is used.
tp
tr
5.5
t p 5.5 t r tr 5.5 2 11h
Recalculate tp 2
3
If equal, tp is used.
Not equal
4
Calculate t’p
73
Snyder’s Method
Step 2: determine regional constants of source UH
If not standard
tp’ = tp + 0.25(tR – tr)
Source UH
tp
tR tp’ = 21tp /22 + 0.25tR
tp = Ct ( L.Lca )0.3 Ct
tp’
Qp
Qp = 2.78 CpA/ tp’ Cp
t 74
Snyder’s Method
Step 3: check whether required UH is standard
If tr tR non-standard
t 75
Snyder’s Method
Step 4: determine parameters of required UH
Qp
tpk = tR/2 + tp’
tpk t 76
Snyder’s Method
Step 4: determine parameters of required UH
W75
Qp W75 = W50 / 1.75
0.75Qp
0.5Qp
W50
t 77
Snyder’s Method
Step 5: determine time base of required UH
Qp
For small catchment:
tb t
tb is always least accurate
78
Example 6.14, pg228
Q (m3/s)
62
Select suitable tb
31
W50 = 44h
t (h)
4 8 11.4 33 48 58
79
Example 6.14, pg228
Q (m3/s)
62 Or use a curve
46.5
W75 = 25 h
31
W50 = 44 h
t (h)
11.4
80
Snyder’s Method
Step 6: Finalising UH using S-curve method
81
SCS Method
SCS = Soil Conservation Service, US
82
t/tpk Q/Qp
0.0 0
0.1
0.2
0.015
0.075
SCS Method
0.3 0.16
0.4 0.28
1
0.5 0.43
0.6 0.6 0.9
0.7 0.77 0.8
0.8 0.89
0.7
0.9 0.97
1.0 1 Q/Qp 0.6
1.1 0.98 0.5
1.2 0.92
0.4
1.3 0.84
1.4 0.75 0.3
1.5 0.66 0.2
1.6 0.56
0.1
1.8 0.42
2.0 0.32 0
2.2 0.24 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0
2.4 0.18 t/tpk
2.6 0.13
2.8 0.098
3.0 0.075
3.5 0.036
4.0 0.018
4.5 0.009
5.0 0.004 Table 6.2 83
6.0 0
SCS Method –Dimensionless UH
• Using Snyder’s method, calc. tpk and Qp
• Multiply t/tpk by tpk =t
• Multiply Q/Qp by Qp =Q
• Plot Q vs t
10
9
8
Example: 7
6
tpk = 20h 5
Qp = 10m3/s 4
3
2
1
0
0 20 40 60 80 100 120
84
SCS Method - SCS Triangular UH
• UH in triangular shape (FIGURE 6.21(b)
• where Tb = 2.67xTp where Tp = time to peak@ lag basin = tr/2 + tp
• Qp = 2.08A/Tp where A in km2
Small watershed
85