Projectmanagement Plan
Projectmanagement Plan
Projectmanagement Plan
Revision History
3
3.0 Scope Management Planning
This section should provide an explanation for how various inputs are used to determine the
scope of the project. Each scope element should be linked to a project requirement or
deliverable so that all project objectives are met and all project work is attributable to a
meaningful outcome. One pitfall of many projects is allowing extraneous or unnecessary work
to occur which is not directly applicable to an objective or deliverable.
For the NextGen Cable Development Project, the Project Manager is responsible for scope
management. The scope of this project was defined through a formal collection and review of
the project’s objectives and requirements as outlined in the Project Charter, preliminary scope
statement, and all available project documentation. This review was led by the Project Manager
and included the Project Sponsor, Project Team, and all Stakeholders. Based on the
identification and review of all project requirements, the deliverables for the project were agreed
upon and approved by the Project Sponsor.
For the NextGen Cable Development Project, the scope is defined by the Scope Statement,
WBS, and WBS Dictionary. These components will be detailed in the following sections of the
Scope Management Plan in order to provide a common understanding for all project
participants.
4
work is performed in accordance with the project scope. By deconstructing the deliverables into
manageable work packages the scope of the project can be managed much more easily.
The WBS and WBS Dictionary, along with the scope statement, are key components for defining
and managing the project scope. The WBS provides a hierarchical decomposition of the work to
be performed in the project in order to allow the scope to be managed more easily through
clearly understood work packages not exceeding 40 hours of work but not less than 4 hours of
work each. The WBS structure below details the phases and work packages the NextGen Cable
Development Project consists of. All work packages were created and defined with the input
from the groups and individuals who will be performing the work throughout the project.
N e xt G e n C a b le D e v e lo p m e n t P ro je c t
1.3.1 Te s ting Ta s k # 1
1.1.1 C a ble De s ign 1.2.1 P ro c e s s Ta s k
Ta s k # 1 #1
The WBS Dictionary, shown below, provides the necessary detail for the work outlined in the
WBS so the tasks, resources, and deliverables are clearly defined. Every element of the WBS
must be entered in the WBS Dictionary to ensure all work is accounted for, assigned the
appropriate resources, and pertains to the appropriate deliverable(s).
5
6.0 Scope Control
This section should discuss the steps or processes by which the project scope is controlled
throughout the duration of the project. Elements of the project scope must be reviewed on a
regular basis in order to ensure all project work is performed in accordance with the Scope
Management Plan. This section should also describe how changes in scope may be
requested/proposed, reviewed, and approved/denied.
This NextGen Cable Development Project Manager is responsible for continuously monitoring
project work to ensure all work performed is within the project scope outlined in this plan. The
Project Manager may also utilize regularly occurring meetings with the project team to ensure
that all work is performed in accordance with the appropriate work package(s) in support of
project deliverables and objectives.
Project scope change requests (CR) may be submitted by any project participant who determines
that a change in scope is necessary for the project. The individual proposing the change in scope
must submit a CR to the Project Manager outlining the proposed change and why it is necessary.
The Project Manager will review the proposal with the project team to determine if it is
necessary and what impact(s) it will have on the project. The change proposal will then be
presented to all project participants and forwarded to the Project Sponsor for review and
approval. Any scope changes approved by the Project Sponsor will require updates to all project
plans and documentation. This is the responsibility of the Project Manager. The Project
Manager must also communicate the change to all project participants upon its approval.
The NextGen Cable Development Scope Management Plan was created to ensure that all project
work directly supports the scope of the project. As the project progresses, the Project Manager
must verify that interim deliverables correspond to deliverables originally specified in the
project’s scope statement, the WBS and/or the WBS Dictionary. Once the Project Manager
determines that work performed is aligned and in support of the project’s scope, the associated
deliverable may be accepted.
As deliverables are completed, the project team will complete a deliverable acceptance package
which outlines the appropriate WBS level and code, work description, planned completion date,
actual completion date, and any variance in the deliverable. The deliverable acceptance package
will then be submitted to the Project Sponsor for formal acceptance of the deliverable.
8.0 Approvals
All project and management plans must have the approval of the Project Sponsor and Project
Manager. The signatures of these individuals indicate their acknowledgement and
understanding of the Scope Management Plan.
6
The signatures of the people below indicate an understanding in the purpose and content of this
document by those signing it. By signing this document you agree to this as the formal Scope
Management Plan for the NextGen Cable Development Project.
Approver Name Title Signature Date
7
Revision History
8
TABLE OF CONTENTS
1.0 Introduction..............................................................................................................................2
1.1 Purpose..................................................................................................................................................................2
1.2 Scope.....................................................................................................................................................................2
2.0 Cost Management Roles and Responsibilities.........................................................................3
2.1 Project Sponsor.....................................................................................................................................................3
2.2 Project Manager....................................................................................................................................................3
2.3 Project Team.........................................................................................................................................................3
2.4 Contractor Support................................................................................................................................................3
3.0 Cost Management Approach....................................................................................................4
3.1 Cost Planning and Estimating...............................................................................................................................4
3.2 Cost Tracking........................................................................................................................................................4
3.3 Cost Metrics and Reporting..................................................................................................................................5
3.4 Cost Control Measures..........................................................................................................................................6
4.0 Approvals.................................................................................................................................6
1.0 Introduction
1.1 Purpose
The purpose of the cost management plan must be clearly established in order to describe how
project costs will be managed throughout the duration of the project. This section discusses, in
general terms, why the cost management plan is necessary and an important part of overall
project planning.
The purpose of this cost management plan is to define the methodology by which costs
associated with the Building Expansion Project will be managed. This is necessary to ensure
the successful completion of the project within the allotted budget constraints. There are
several cost components associated with this project as well as many metrics, cost variance
considerations, and reporting which this plan will outline. To complete this project
successfully, all key project members and stakeholders must adhere to and work within this
cost management plan and the overall project plan it supports.
1.2 Scope
This section describes what will be included in the cost management plan for this particular
project. Project costs may consist of many internal and external components or unique items
depending on the nature of the project. It is important to define the scope of what will be
included in the cost management plan for a given project.
The cost management plan for the Building Expansion project includes many internal and
external cost components. All metrics and variance analysis must be applied to these cost
components throughout the project lifecycle. These components include:
Internal
Project Management/project team resources
Recruiting and hiring for additional staffing
Capital equipment
Software and licensing
Insurance
External
Construction costs
Insurance
This cost management plan does not include any monthly recurring costs (MRC) which will be
required upon the completion of the project.
10
clear understanding of the roles they and others play in determining project budgets, allocation of
funds, authorization for additional funding, and where the responsibility for each lies.
11
This section should include paragraphs describing cost planning/estimating, cost tracking, cost
reporting/metrics, and cost variance at a minimum. These paragraphs are where cost
management is explained in detail.
12
a function of the value the project has earned (EV), the actual costs of the project to date (AC),
and the planned value the project should have earned to date (PV).
In order to measure project performance, several metrics will be used to capture cost and
schedule performance for the Building Expansion Project. The following metrics will be
compiled and reported by the Project Manager:
Cost Performance Index (CPI) will be reported monthly and is the project’s EV/AC
Schedule Performance Index (SPI) will be reported monthly and is the project’s EV/PV
Control thresholds for CPI and SPI are:
o Yellow: within +/- 20% must be reported to the Project Sponsor. If it is
determined that there is no effect on the project’s cost baseline then there may
be no further action required.
o Red: greater than +/- 20% must be reported to the Project Sponsor. Corrective
measures must be taken to move the project back to an acceptable performance
level (process detail in paragraph 3.3).
Cost Variance (CV) will be reported monthly and is the project’s AC subtracted from
EV
Schedule Variance (SV) will be reported monthly and is the project’s PV subtracted
from EV
One chart will be created for each of the above metrics. The Project Manager will present
these charts to the Project Sponsor at the Monthly Project Status Meeting on the 5th of each
month.
If the Building Expansion Project exceeds its thresholds at any time for its CPI or SPI,
corrective measures will be considered and implemented in order to bring the project back into
an acceptable range of performance. The Project Manager and Team will consider all control
measures which will result in correcting the project performance. A detailed analysis of all
control measures will be presented to the Project Sponsor. The analyses will consist of:
General description of the control measure
Personnel involved
13
Timeline to implement
Issues or concerns regarding implementation
Expected effect on project performance
All control measures will be reviewed by the Project Sponsor. Upon approval from the Project
Sponsor, the Project Manager will lead the implementation of the authorized control measure.
The Project Manager must also complete any change requests required in accordance with the
project’s change control process.
4.0 Approvals
All project and management plans must have the approval of the Project Sponsor and Project
Manager. The signatures of these individuals indicate their acknowledgement and
understanding of the project charter.
The signatures of the people below indicate an understanding in the purpose and content of
this document by those signing it. By signing this document you agree to this as the formal
Cost Management Plan for the Building Expansion Project.
Approver Name Title Signature Date
14
Revision History
15
TABLE OF CONTENTS
1.0 Purpose.....................................................................................................................................2
2.0 Roles and Responsibilities.......................................................................................................2
3.0 Schedule Management Strategy...............................................................................................3
4.0 Schedule Monitoring and Control............................................................................................4
5.0 Schedule Change Process.........................................................................................................4
6.0 Approvals.................................................................................................................................5
1.0 Purpose
Schedule management is an important part of any project. Once project schedules are created,
the must be managed effectively in order to complete project tasks on time, allocate resources
in order to meet deadlines, and provide project progress to all project participants. This
section describes the purpose of the Schedule Management Plan as it relates to this specific
project.
The purpose of this Schedule Management Plan is to establish a formal process by which the
Server Upgrade Project schedule will be created and establishes how schedule management
will be executed. This process includes the tools necessary for schedule creation and
management, the roles and responsibilities of the project participants in creating and managing
the schedule, and the monitoring and control of any proposed schedule changes. In order to
successfully complete this project, it is imperative that formal schedule management
guidelines are created, implemented, and followed.
17
quantifying scheduling impact events. He is responsible for identifying any potential
schedule impacts and submitting the appropriate schedule change request to the Project
Manager for any facility-related project function.
Project Stakeholders: Stakeholders identifying potential schedule impact events will
work with the Project Manager and Team to determine if a schedule change request is
necessary. Schedule status will be communicated to Stakeholders at the monthly
project status meeting.
The schedule for the Server Upgrade project will be based on the Project Charter, requirements
definition, WBS and WBS Dictionary for the Project as outlined in the Scope Management Plan.
The WBS breaks the project work down into manageable work packages with all of the
necessary scheduling detail contained in the WBS Dictionary. This detail includes resources,
time required to complete the task, and any task dependencies. The project team will work
together to determine the correct task definition, sequencing, and estimating for all work detailed
in the WBS. The project schedule will be a result of all required project work in the correct
sequence while accounting for all task dependencies and required resources as defined in the
WBS Dictionary.
Once developed, the Project Sponsor will review the schedule, communicate any necessary
modifications to the Project Manager, and approve the schedule once any required changes are
made.
The Server Upgrade Project Schedule will be created as a Gantt Chart in MS Project. As tasks
are completed, the Project Manager will update the schedule accordingly in order to provide
awareness of the project schedule to all team members.
The creation of the Server Upgrade Project schedule will result in many scheduled tasks and
milestones. However, the following milestones must be included in the schedule as a minimum
and require acceptance by the Project Sponsor:
Project kickoff
Technical design package (TDP) review
Project phase closeout meetings
Project phase kickoff meetings
Acceptance of project deliverables
Project closeout review
18
Project Manager and team to understand and provide the status of the project at any given time.
However, this awareness is also necessary to allow the Project Manager to identify potential
impact events and address these events by adjusting resources, funding, or submitting
appropriate schedule change requests.
The Server Upgrade Project will be monitored and controlled aggressively by the Project
Manager and team. In order to provide constant schedule awareness the Project Manager will
chair bi-weekly project schedule meetings. At these meetings all project team members will be
required to report the status of their assigned work as it relates to the schedule. This will allow
the Project Manager to fully understand the status of the project schedule and provide him with
the opportunity to shift or re-allocate resources, funding, or submit schedule change requests as
necessary.
As each schedule task is completed, the team member responsible for the work will provide an
update to the Project Manager notifying him of such. These notifications must be immediate and
not wait until the next bi-weekly project schedule meeting. This will allow the Project Manager
to track schedule status in real time in order to provide status updates to the Project Sponsor or
Stakeholders as necessary with current information. Additionally, as interim project deliverables
are completed, they will be presented to the Project Sponsor for deliverable acceptance.
For the Server Upgrade Project, proposed schedule changes will follow a formal process which
is agreed to by senior management. Schedule change requests may be submitted by any member
of the project team once it has been determined that a boundary condition may be exceeded. The
change request will be submitted to the Project Manager. The Project Manager will review the
change request with the project team. This review will include an evaluation of the impact of the
change request regarding schedule, cost, resources, or project scope. If it is determined that the
impact falls within the boundary conditions established below, the change request may be
approved or denied by the Project Manager and any changes needed may then be implemented in
accordance with the Change Management Plan. If it is determined that the impact exceeds the
boundary conditions below, then the change request will be forwarded to the Project Sponsor for
review and approval.
19
Once a change request has been approved, the changes will be implemented and the Project
Manager is responsible for updating the project schedule, all project plans/documentation, and
communicating the change(s) to all project participants.
If the impact of the change request requires any changes in the project’s scope then it will follow
the process defined in the Scope Management Plan.
6.0 Approvals
All project and management plans must have the approval of the Project Sponsor and Project
Manager. The signatures of these individuals indicate their acknowledgement and
understanding of the Schedule Management Plan.
The signatures of the people below indicate an understanding in the purpose and content of this
document by those signing it. By signing this document you agree to this as the formal
Schedule Management Plan for the Server Upgrade Project.
Approver Name Title Signature Date
20
Revision History
21
TABLE OF CONTENTS
1.0 Purpose.....................................................................................................................................2
2.0 Procurement Roles and Responsibilities..................................................................................2
3.0 Procurement Requirements......................................................................................................3
4.0 Vendor Identification and Selection.........................................................................................3
5.0 Vendor Management................................................................................................................4
6.0 Contract Requirements.............................................................................................................4
7.0 Approvals.................................................................................................................................4
1.0 Purpose
Many projects require items or services that cannot be provided from within the organization. In
these cases it is necessary for the project team to procure the necessary items or services
required to successfully complete the project. This section should provide a high-level
explanation of purpose of the Procurement Management Plan. Generally, the purpose of the
Procurement Management Plan is to define what items will be procured for the project and how
vendors will be identified, selected, and managed. Additionally, the plan should outline roles
and responsibilities relating to procurement as well as any contract requirements which must be
met.
The purpose of the Procurement Management Plan is to define procurement parameters for the
Software Upgrade Project in order to ensure its successful completion. Procurement is a
deliberate process which involves many internal departments as well as external vendors. This
Procurement Management Plan has been created to provide a framework in which all
procurement actions will be managed across all of the organizations involved.
23
what deliverable the item supports, as well as the date the item is required by to meet the project
schedule.
There are several items which must be procured in order to successfully complete the Software
Upgrade Project. The following list has been created to indicate the necessary items, the
deliverable each item supports, and the date the item is required to meet the deliverable in
accordance with the project schedule:
This section outlines the process through which vendors will be identified and selected to fulfill
the procurement requirements for the Software Upgrade Project. The project team will identify
vendors based on which existing and new vendors are able to meet the procurement requirements
outlined above. Once potential vendors are identified, the project manager will work with the
Contracting Manager to develop RFPs to distribute to vendors to bid on.
Once the contracting group receives all vendor proposals, the Contracting Manager, Project
Manager/Team, IT Director, and Project Sponsor will meet to evaluate proposals. The group
will use the following selection criteria to make their vendor selection:
Vendor most capable of meeting required delivery dates for procurement requirements
Past performance of the vendor (if applicable)
Cost of procurement items
Quality assurance measures
Once the vendor(s) has/have been selected and approved by the Project Sponsor, the Project
Manager will work with the Contracting Department Director, or designated representative, to
draft and finalize the necessary contract(s) with the vendor(s). Once all contracts are complete,
the Project Manager will begin the vendor management phase of the procurement process.
24
vendor which has repeatedly met requirements in a timely manner and with a fair price may
retain the business of an organization for many years. Conversely, vendors which miss deadlines
and fail to meet requirements may no longer be considered in future procurement activities. It is
inherent to the organization to work with the vendor in managing the delivery and fulfillment of
their requirements in order to ensure the successful completion of the project.
The Project Manager is responsible for vendor management and will work with the Contracting
Department Director to oversee vendor performance for the Software Upgrade Project. The
Project Manager will measure the ongoing performance of each selected vendor as it applies to
the requirements stated in their respective contracts. In order to ensure acceptable vendor
performance, service level agreements (SLAs) will be included in the contracts which must be
met by the vendors. SLAs for vendor performance include:
Delivery of item(s) on or before date as agreed upon in the contract
Delivery of item(s) at or below cost as agreed upon in the contract
Acceptable performance/quality of item as agreed upon in the contract
Failure of a vendor to adhere to these SLAs will result in the Contracting Department submitting
a formal dispute as appropriate.
All contracts associated with the Software Upgrade Project will be firm-fixed price. The
Contracting Department Director is responsible for ensuring that each contract complies with
internal corporate guidelines and policies. The Project Manager is responsible for ensuring all
SLAs and performance criteria and expectations are clearly listed in the contract(s) prior to
award. The Project Sponsor will review and approve all contracts prior to award.
7.0 Approvals
All project and management plans must have the approval of the Project Sponsor and Project
Manager. The signatures of these individuals indicate their acknowledgement and
understanding of the Procurement Management Plan.
The signatures of the people below indicate an understanding in the purpose and content of this
document by those signing it. By signing this document you agree to this as the formal
Procurement Management Plan for the Software Upgrade Project.
Approver Name Title Signature Date
25
QUALITY MANAGEMENT PLAN
26
Revision History
27
TABLE OF CONTENTS
1.0 Purpose.....................................................................................................................................2
2.0 Roles and Responsibilities.......................................................................................................2
3.0 Quality Control.........................................................................................................................3
4.0 Quality Assurance....................................................................................................................4
5.0 Quality Control and Assurance Monitoring.............................................................................5
6.0 Approvals.................................................................................................................................5
1.0 Purpose
This section describes the purpose of the Quality Management Plan and how it will be used to
manage quality associated with this particular project. Quality management is an important
aspect of managing a project because it ensures that project objectives and deliverables are met
in accordance with some formally documented standard of acceptable quality. Without this,
there would be no governing document or process by which to measure or assess project
quality.
The purpose of the High Speed Modem Project Quality Management Plan is to establish a
process to ensure that all project goals, objectives, and deliverables are met in compliance with
acceptable and formally approved quality standards. By following this plan we fully intend to
provide our customers with the products they require to meet their business objectives. This
plan defines the roles and responsibilities of project participants as they relate to quality
management and the strategy we will use to achieve acceptable quality standards in the areas
of technical design and documentation, product and process development, and manufacturing.
29
Quality Manager: The Quality Manager is responsible for assisting the Project
Manager in the development and implementation of the Quality Management Plan.
The Quality Manager will make recommendations for processes, tools, methodologies,
and standards of quality which comply with the company’s corporate guidelines on
quality. He will assist the Project Manager in monitoring all project activities in
accordance with the established quality standards. The Quality Manager will also be
responsible for maintaining the Quality Control and Quality Assurance Logs.
Design Engineer: The Design Engineer is responsible for building quality standards
into all product designs required for the High Speed Modem Project. The Design
Engineer will advise and make recommendations to the Project and Quality Managers
regarding acceptable standards of quality associated with their portion of project
activities.
Process Engineer: The Process Engineer is responsible for building quality standards
into all process designs required for the High Speed Modem Project. The Process
Engineer will advise and make recommendations to the Project and Quality Managers
regarding acceptable standards of quality associated with their portion of project
activities.
Project Stakeholders: Stakeholders will be responsible for working with the Project
and Quality Managers to ensure that all established quality standards for the High
Speed Modem Project comply with the acceptable standards of appropriate internal
organizations. Additionally, the Stakeholders will help ensure that all established
quality standards meet the expectations of our customers.
Quality control for the High Speed Modem Project will ensure that all project deliverables
comply with established quality standards. In order to meet customer requirements and
expectations, it is imperative that we implement a formal process in which quality standards
are measured and accepted. For each deliverable the Project Manager will ensure the quality
standards, quality control activities, and frequency of activities outlined below are met. The
Quality Manager and Design Engineer will assist the Project Manager in verifying that all
quality standards are met for each deliverable. It is important to note that as the Project Plan
evolves, more deliverables may be added and the quality standards may change. If any
changes are made, the Project Manager is responsible for communicating the changes to the
project team and updating all project plans and documentation.
30
monthly
Modem Cable <10% attenuation Lab testing Lab tests will be
Field testing conducted weekly
Field tests conducted
monthly
Technical Data Compliant with Document review board TDP will be edited and
Package (TDP) organizational will review and edit approved once product
documentation design is tested and
standards complete
The Project Sponsor is responsible for the formal acceptance of each deliverable meeting the
established quality standards.
Quality assurance efforts for the High Speed Modem Project will ensure that the processes used
in this project product deliverables which meet established quality standards while maximizing
efficiency and minimizing waste. The processes, standards, activities, and frequencies in the
chart below have been developed as a foundation for assuring project quality as it relates to the
various processes involved. For each process the Project Manager will ensure these standards,
activities, and frequencies are met. The Quality Manager and Process Engineer will assist the
Project Manager in verifying that all quality standards are met for each process. It is important
to note that as the Project Plan evolves, more processes may be added and the quality standards
may change. If any changes are made, the Project Manager is responsible for communicating the
changes to the project team and updating all project plans and documentation.
31
and complete
The Project Sponsor is responsible for the formal acceptance of each process meeting the
established quality standards.
For the High Speed Modem Project the Quality Manager will maintain a Quality Control and
Quality Assurance Log. These logs will be reviewed weekly by the Project Manager and also
during bi-weekly project status meetings. These logs will also be provided to the Project
Sponsor at the monthly project status meetings. The purpose of these logs is to itemize and track
quality control and assurance activities until closure or until they are no longer required.
6.0 Approvals
All project and management plans must have the approval of the Project Sponsor and Project
Manager. The signatures of these individuals indicate their acknowledgement and
understanding of the Quality Management Plan.
The signatures of the people below indicate an understanding in the purpose and content of
this document by those signing it. By signing this document you agree to this as the formal
Quality Management Plan for the High Speed Modem Project.
Approver Name Title Signature Date
32
COMMUNICATION MANAGEMENT PLAN
33
Revision History
34
TABLE OF CONTENTS
1.0 Purpose.....................................................................................................................................2
2.0 Roles and Responsibilities.......................................................................................................2
2.1 Project Sponsor.....................................................................................................................................................2
2.2 Project Team.........................................................................................................................................................2
2.3 Project Stakeholders..............................................................................................................................................3
3.0 Communication Matrix............................................................................................................4
4.0 Project Team and Stakeholder Identification...........................................................................4
5.0 Communication Conduct..........................................................................................................5
5.1 Meetings................................................................................................................................................................5
5.2 Electronic Mail (Email)........................................................................................................................................5
5.3 Informal Communication......................................................................................................................................6
6.0 Approvals.................................................................................................................................6
1.0 Purpose
This section should provide a high-level explanation of purpose of the Communication
Management Plan. Generally, the purpose of the Communication Management Plan is to
outline and define the requirements for all communication associated with the project in order
to ensure project success. This section may also include a general description of what is
contained in the plan.
Effective communication is a key to successful project management and project completion.
The purpose of this Communication Management Plan is to define the communication
requirements for the Building Expansion Project throughout the project’s lifecycle. This
Communication Management Plan defines the communication requirements, media,
frequency, and distribution in order to ensure that information is conveyed through proper
channels in a timely and consistent fashion. This plan will serve as a catalyst for successful
project completion by facilitating the information flow required for timely decision-making,
action item tracking, status updates, and overall understanding of the project goals and
deliverables.
Mr. John Doe: The Project Sponsor serves as the Building Expansion Project’s
oversight authority. He is responsible for approving all budget and funding requests as
well as authorizing any change control requests. As a sitting member of the executive
committee, the Project Sponsor is also responsible for providing project status updates
in the monthly executive committee meetings as required.
Project Manager, Mr. Joe Smith: The Project Manager is responsible for day to day
management of the Building Expansion Project. The Project Manager is responsible
for establishing communication requirements for the project, chairing all project
meetings, and submission of all written reports. The Project Manager may delegate
communication tasks to appropriate technical representatives or subject matter experts
36
(SMEs) but is responsible for the timely completion of such tasks. The Project
Manager is responsible for all information dissemination.
Facilities Manager, Ms. Sally Jones: The facilities manager is the SME for all
communications relating to facility management. As such, the facilities manager is
responsible for providing the Project Manager with all facility-related feedback for use
in project communications. The facilities manager will participate in all project team
meetings, monthly status meetings, and will be included on the project’s distribution
list. For project meetings the facilities manager will act as the recorder and take all
notes to be distributed after the meetings.
Technical Representative, Mr. Robert White: The technical representative is the
SME on all information technology (IT) matters as well as capital equipment and
procurement. As such, the technical representative is responsible for providing the
Project Manager with all related feedback for use in project communications. The
technical representative will participate in all project team meetings, monthly status
meetings, and will be included on the project’s distribution list. For project meetings
the technical representative will act as the timekeeper ensuring that the meeting
proceeds in accordance with the agenda.
Contractor Team Lead, Ms. Jane Black: While not a member of our organization,
the contractor team lead is an integral part of the Building Expansion Project. The
contractor team lead is responsible for providing status updates for construction and
any other construction-related details to the Project Manager for use in project
communications. The contractor team lead will participate in all project team
meetings, monthly status meetings, and will be included on the project’s distribution
list.
37
The communication requirements for the Building Expansion Project are listed in the following
matrix. As the project proceeds, it may be necessary to modify the communication requirements.
Any modifications to the communication matrix must be approved by the Project Sponsor.
The following matrix has been created to provide the contact information for all personnel
involved with the Building Expansion Project. Any requests to add to or change this
identification matrix must be submitted to the Project Manager for review and approved by the
Project Sponsor.
38
[email protected]
Bill Johnson Dir. Of Prod. xxx-xxx-xxxx xxx-xxx-xxxx
m
John Green VP of Tech. [email protected] xxx-xxx-xxxx xxx-xxx-xxxx
Joan Blue Director of HR [email protected] xxx-xxx-xxxx xxx-xxx-xxxx
This section provides guidance to all project participants for conduct expected in meetings and
other forms of communication. All participants are expected to adhere to these guidelines at all
times to prevent unnecessary or ineffective communication.
5.1 Meetings
This section discusses expected meeting conduct
The Project Manager will distribute a meeting agenda at least 2 days prior to any scheduled
meeting. All participants are expected to review the agenda prior to the meeting. During
project meetings the timekeeper will ensure that the group adheres to the time allotted for a
given topic and the recorder will take all notes to be distributed to the team upon completion of
the meeting. It is imperative that all participants arrive to each meeting on time and all cell
phones and blackberries should be turned off or set to vibrate mode to minimize distractions.
Meeting minutes will be distributed no later than 24 hours after each meeting is completed.
All email pertaining to the Building Expansion Project should be professional, free of errors,
and provide brief communication. If the email is to provide a status report, it should be
distributed to the correct project participants in accordance with the communication matrix
above. All attachments should be in one of the organization’s standard software suite
programs and adhere to established company formats. If the email is to bring an issue forward
then it should discuss what the issue is, provide a brief background on the issue, and provide a
recommendation to correct the issue. The Project Manager should be included on any email
pertaining to the Building Expansion Project.
Informal communication is a part of every project and is necessary for successful project
completion. However, any issues, concerns, or updates that arise from informal discussion
39
between team members must be communicated to the Project Manager so the appropriate
action may be taken.
6.0 Approvals
All project and management plans must have the approval of the Project Sponsor and Project
Manager. The signatures of these individuals indicate their acknowledgement and
understanding of the Communication Management Plan.
The signatures of the people below indicate an understanding in the purpose and content of
this document by those signing it. By signing this document you agree to this as the formal
Communication Management Plan for the Building Expansion Project.
Approver Name Title Signature Date
40
Revision History
41
TABLE OF CONTENTS
1.0 Purpose.....................................................................................................................................2
2.0 Roles and Responsibilities.......................................................................................................2
2.1 Project Sponsor.....................................................................................................................................................2
2.2 Project Team.........................................................................................................................................................2
2.3 Project Stakeholders..............................................................................................................................................3
3.0 Risk Management Strategy......................................................................................................3
4.0 Risk Management Process.......................................................................................................4
4.1 Risk Identification.................................................................................................................................................4
4.2 Risk Assessment...................................................................................................................................................5
4.3 Risk Control..........................................................................................................................................................6
4.4 Risk Monitoring....................................................................................................................................................6
5.0 Risk Documentation.................................................................................................................7
6.0 Approvals.................................................................................................................................7
1.0 Purpose
Identifying, managing, and mitigating risk is an imperative part of managing projects. If
risks are not identified and steps are not taken to avoid or mitigate those risks, the project
may incur significant delays, additional costs, or reduction in quality. This section
describes why risk management is necessary for successfully managing projects and how
this plan will address risk for this particular project.
The purpose of this Risk Management Plan is to establish a formal process by which risks
will be identified, mitigated or avoided, and managed for the Ameri-car Project. Effective
risk management is a proactive and ongoing process in which we will seek to identify risks
as early in the project as possible and implement controls to mitigate or avoid those risks.
If possible, risks will be identified before they occur so that avoidance and mitigation
efforts can be implemented to avoid any adverse impacts associated with those risks. The
Risk Management Plan will define the processes by which risks and risk owners will be
identified, risks will be evaluated, mitigation and avoidance measures will be evaluated,
and risks will be tracked.
Ms. Jane Doe: The Project Sponsor is the approval authority for the Ameri-car
Project. She is responsible for the approval of the Risk Management Plan as well
as communicating all high-priority risks and mitigation and avoidance strategies to
the Executive Committee.
Project Manager, Mr. Ralph Smith: The Project Manager has overall
responsibility for risk management on the Ameri-car Project. The Project Manager
is responsible for developing and maintaining the Risk Management Plan. He is
also responsible for ensuring the project has adequate resources for implementing
the Risk Management Plan. The Project Manager will review risks and take action
as necessary and communicate all risk-related activities to the project team. He is
responsible for the implementation of risk mitigation and avoidance strategies for all
high-level risks.
Risk Manager, Mr. Bobby White: The Risk Manager is responsible for risk
identification, maintaining the Ameri-car Project risk register, and assisting the
Project Manager in evaluating risk control actions and their impact on cost,
schedule, and quality. Additionally, the Risk Manager will assist the Project
Manager in creating risk assessments, briefings, and reports and he will maintain
day to day responsibility for tracking risks and mitigation/avoidance strategies.
Lead Engineer, Mr. Daniel Black: The Lead Engineer is responsible for risk
identification and providing timely and accurate status on all risks related to
engineering issues. The Lead Engineer is also responsible for assisting the Project
Manager is developing risk mitigation and avoidance strategies.
Operations Lead, Ms. Susan Green: The Operations Lead is responsible for risk
identification and providing timely and accurate status on all risks related to
operational issues. She is also responsible for assisting the Project Manager in
developing risk mitigation and avoidance strategies.
The strategy we will employ on the Ameri-car Project is a proactive approach to risk
management. The goal of this strategy is to identify risks as early as possible in order to
avoid or minimize any adverse impact the risks may have on the project. We will accomplish
this by continuously evaluating critical project areas in order to identify risks, work as a
cohesive team to determine the potential impact of each risk identified, develop and
implement mitigation and avoidance strategies, and monitor the risks. This strategy will be
conducted on the following tenets:
Honest Assessment – It is imperative that all risks are identified and assessed in an
honest manner. Risks cannot be controlled adequately if the full extent of the risk is
not known.
Full Participation – Everyone must participate in the identification of risks. Do not
assume that others will identify all possible risks. Success depends on identifying all
possible risks and in order to accomplish this everyone must participate actively.
Balanced Risk Monitoring – It is key that risks are monitored often enough to
adequately control them but not so often that progress is hindered.
Simplicity – Complex and cumbersome risk tracking and measuring techniques are
not necessary manage risk effectively. We will measure risks with low, medium, and
high designations and spend more time managing risks rather than categorizing them.
The Ameri-car Project will follow a phased risk management process: risk identification, risk
assessment, risk control, and risk monitoring. These phases and activities do not occur one
time, but rather they are ongoing throughout the project’s lifecycle. Once new risks are
identified and assessed, they are controlled and monitored repeatedly until they are resolved
and these actions are no longer required.
Risk assessment is the process of evaluating critical project areas and processes in order to
determine potential risks which may appear at any point during the project. A risk is any
event or threat which may result in some type of adverse impact on the cost, schedule, or
quality/performance of the project. The methods we will use to identify risks are:
Analyze the WBS to determine areas where risk is most likely
Interview subject matter experts (SME) to determine where, in each area, risks may
be most likely
Review project archives and lessons learned to determine where risks have occurred
in similar projects in the past
Review project risk database to determine most likely causes of risk
All project participants will play a key role and be relied upon heavily in identifying risks
their given areas of expertise and knowledge.
Once the Ameri-car Project’s risks have been identified, they will be assessed in order to
determine the priority in which they should be controlled and monitored. Additionally, the
cause of the identified risks must be determined as well as their potential impact on the
project. Each risk will be assessed by the project team in order to determine its probability
of occurring and the impact it may have on the project. In order to quantify these risks,
each will be assigned a score based on the probability and impact and will fall into the high
risk(red), medium risk (yellow), or low risk (green) portion of the probability-impact matrix
below.
10
7
Probability
1 2 3 4 5 6 7 8 9 10
Impact
Risk control is the process in which the team will identify, evaluate, and implement
measures to bring risks down to acceptable levels or avoid them altogether. Risks that
require a mitigation or avoidance strategy will be assigned to a risk owner. The risk owner
is responsible for providing risk status and all documentation associated with such in a
manner consistent with the control strategy guideline below.
Probability Impact
Control Strategy
Score
Risk will be statused on a daily basis. The risk owner will document
all avoidance and mitigation efforts. As mitigation and avoidance
High actions occur the risk will be assessed daily until the risk level is
acceptable or has been avoided altogether
The risk owners for all high and medium risks must consider each of the following options
for controlling risk:
Alternative courses of action or workarounds
Mitigation steps to reduce the probability or impact of the risk
Changing project requirements to eliminate or reduce the probability or impact of the
risk
Risk acknowledgement which accepts the risk without taking any action
Risk monitoring allows us to actively measure the performance of the risk control activities
implemented to mitigate or avoid risks. Risk owners will develop risk control schedules for
each of their assigned high and medium-level risks. Risk owners will provide the status of
their risks and the progress of risk control measures in a frequency as noted in the control
strategy chart above. This status will include anticipated risk control completion date,
assigned resources for risk control activities, and changes in the probability or impact of the
risk occurring.