T C Procedure For Transformer

The document is a 10-page site testing procedure for a transformer that includes: 1) Visual checks of construction and earth continuity 2) Insulation resistance testing before and after pressure testing 3) Pressure testing between windings and earth 4) Checking temperature indicators, winding resistance, phase sequence and other parameters. The procedure concludes with a transformer site test report form to record the results.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
306 views11 pages

T C Procedure For Transformer

The document is a 10-page site testing procedure for a transformer that includes: 1) Visual checks of construction and earth continuity 2) Insulation resistance testing before and after pressure testing 3) Pressure testing between windings and earth 4) Checking temperature indicators, winding resistance, phase sequence and other parameters. The procedure concludes with a transformer site test report form to record the results.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

MTR CORPORATION / CONTRACTOR

Contract No. 3288.66-02E


Upgrade & Reinforcement of Power Supply System at PRE & ADM

DESIGN APPROVAL REOUEST


DAR NO: DATE FORWARDED TO MTRC:
C3288.66-02E/06/02/01/07/001 10 Sep. 03
CONTRACTOR REF: RELEVANT CLAUSE(S) IN THE PS: N/A
3536-L/03/P041/05/02
SUBJECT Design Submission -

DOCUMENT SUBMITTED:
T & C Procedure for Transformer

DETAILS:

Site testing procedure for transformer (10 pages)

Hill1111111111111
lii IDlI!111111111111
l111111111
MTRC (LL) 0000038500

ANSWER REQUIRED BY INITIATED BY: SIGNED BY: Danny Yuen


(TO AVOID DELAY): 9 Oct 2003 Danny Yuen Project Manager

MTRC USE ONLY:


LEAD DESIGNER DATE RECEIVED BY MTRC:

SIGNATURE:
DATE RETURNED TO CONTRACTOR:

Updated: 9/10/2003 2:12 PM


MTRC CONTRACT NO. C3288.66-02E F LEPEP
Upgrade and Reinforcement of Power Supply System at PRE and ADM
DAR No. C3288.66-02E/06/02/01/07/001 Rev. 0 Date: 9 Sept 2003

Site Testin2 Procedure for Transformer

I. CONSTRUCTION INSPECTION

General inspection for the construction of the transformer shall be carried out as per the
check list in the test form.

2. VISUAL CHECK OF EARTH CONTINUITY

Check the earthing connection of the transformer frame, HV & LV cable box, LV neutral,
control and marshalling cubicle visually.

3. INSULATION RESISTANCE BEFORE PRESSURE TEST

Insulation resistance test (Megger Test) for HV to LV windings, HV & LV windings to


earth shall be tested by 5kV d.c. megger tester before pressure test.

4. PRESSURE TEST

AC high voltage shall be increased gradually to 19.2kV between I IkV to 415V/earth and to
3 .5kV between 415V to 11 kV/earth for I minute.

5. INSULATION RESISTANCE AFTER PRESSURE TEST

Insulation resistance test (Megger Test) for HV to LV windings, HV & LV windings to


earth shall be tested by 5kV d.c. megger tester after pressure test.

6. TRANSFORMER RATIO TEST

Check the transformer ratio by connecting a three-phase, four wire, low voltage supply
(auto-transformer) to the H.V. terminals. Measure and record the data at the L.V. side.

7. VECTOR GROUP CHECK

Measure the phase voltages for HV & LV side (refer to the test form) to check the vector
group of the transformer.

8. FUNCTION TEST ON TEMPERATURE INDICATORS

(A). Check the Winding Temperature Indicator

1. Adjust and calibrate the winding temperature indicators.


Insert a thermometer (as reference) and the winding temperature
indicator in boiling oil.
Record the readings of the thermometer and calibrate the indicator.

FILE NAME: Transformer Page I of 10


ALE'.,1
MTRC CONTRACT NO. C3288.66-02E It LU |P
Upgrade and Reinforcement of Power Supply System at PRE and ADM
DAR No. C3288.66-02E/06/02/01/07/001 Rev. 0 Date: 9 Sept 2003

2. Simulate winding temperature alarm with boiled oil.


The winding temperature alarm contact closes.
Record the switch setting with the reading of thermometer.
(Alarm setting 1050 C)

3. Simulate winding temperature trip with boiled oil.


The winding temperature trip contact closes.
Record the switch setting with the reading of thermometer.
(Trip setting 11 50 C)

(B). Check the Liquid Temperature Indicator

1. Adjust and calibrate the liquid temperature indicators.


Insert a thermometer (as reference) and the liquid temperature
indicator in boiling oil.
Record the readings of the thermometer and calibrate the indicator.

2. Simulate liquid temperature alarm with boiled oil.


The liquid temperature alarm contact closes.
Record the switch setting with the reading of thermometer.
(Alarm setting 85 0 C)

3. Simulate liquid temperature trip with boiled oil.


The liquid temperature trip contact closes.
Record the switch setting with the reading of thermometer.
(Trip setting 950 C )

9. WINDING RESISTANCE MEASUREMENT

Measure the winding resistance for H.V. side and L.V. side.

10. PHASE SOUENCE CHECK & OUTPUT VOLTAGE MEASUREMENT

Check the phase sequence at L.V. side by phase sequence meter.


Measure the output voltage at L.V. side.

11. NOISE LEVEL MEASUREMENT

Check the noise level with the transformer on no load at rated voltage and frequency. The
position of the noise level meter shall be I metre from transformer body.

FILE NAME: Transformer Page 2 of 10


MTRC CONTRACT NO. C3288.66-02E A, Upop
Upgrade and Reinforcement of Power Supply System at PRE and ADM
DAR No. C3288.66-02E/06/02/01/07/001 Rev. 0 Date :9 Sept2003

12. STANDBY EARTH FAULT C.T. TEST

Test the CT magnetisation with a.c. voltage to measure the knee point voltage.

Test the ratio of CT up to 100% rated current by primary injection.

Check insulation resistance and measure resistance of CT.

13. INSULATING OIL SAMPLE TEST

Test the insulating oil sample in compliance with IEC 60156 (Dielectric Test) &
IEC 60814 (Water Content Test) by accredit laboratory.

FILE NAME: Transformer Page 3 of 10


MTRC CONTRACT NO. C3288.66-02E " P UPI
Upgrade and Reinforcement of Power Supply System at PRE and ADM
DAR No. C3288.66-02E/06/02/01/07/001 Rev. 0 Date: 9 Sept2003

Transformer Site Test Report

Date of Testing : Site Location _

Voltage Ratio 11000/433V Serial No. :

Transformer Rating 1500KVA Vector Group Dynll

Place of Manufacture : Cooling Type : ONAN

1. CONSTRUCTION INSPECTION RESULT

- Check Transformer Body


- Check HV & LV Cable Box
- Check Standby Earth CT & Bushing
- Check Cable Terminal Condition
- Check Winding Temperature Indicator
- Check Liquid Temperature Indicator
- Check the Condition of Liquid Level Gauge
- Check Gasket Joints
Transformer Tank Joint
Cable Box Covers
Valve Flanges & Pipe Joints
- Check Liquid Drain Valves are closed
- Check Pressure Relief Valve
- Check Radiator Valves are fully opened

2. VISUAL CHECK OF EARTH CONTINUITY RESULT

- Check Transformer Frame


- Check HV Cable Box
- Check LV Cable Box
- Check LV Neutral
- Check Control and Marshalling Cubicle

3. INSULATION RESISTANCE BEFORE PRESSURE TEST RESULT


(Megger Test)

Using a 5kV Megger


HI.V. Windings (I IkV) to Earth (5kV) 0
LV. Windings (415V) to Earth (IkV) 0
H.V. Windings to L.V. Windings (5kV) 0
Control Circuit to Earth (0.5kV) 0

FILE NAME: Transformer Page 4 of 10


MTRC CONTRACT NO. C3288.66-02E LP MP
Upgrade and Reinforcement of Power Supply System at PRE and ADM
DAR No. C3288.66-02E/06/02/01/07/001 Rev. 0 Date: 9 Sept 2003

4. PRESSURE TEST RESULT

11kV to 415V/earth (19.2kV AC I mins.) mA


415V to I IkV/earth (3.5kV AC I min.) nmA

5. INSULATION RESISTANCE AFTER PRESSURE TEST RESULT


(Megger Test)

Using a 5kV Megger


H.V. Windings (I kV) to Earth (5kV) Q
L.V. Windings (415V) to Earth (IkV) 0
H.V. Windings to L.V. Windings (5kV) 0

6. TRANSFORMER RATIO TEST

Connect a three-phase, four wire, low voltage supply (auto-transformer) to the H.V. terminals, the
following data is recorded:

T APPLIED HV LV LINE VOLTS LV PHASE VOLTS


A LINE VOLTS
P A-B B-C A-C a-b b-ca-c a-n b-n c-n
. . CAL ACT CAL ACT CAL ACT CAL ACT CAL ACT CAL ACT
1 415 415 415 15.52 15.52 15.52 8.96 8.96 8.96
2 415 415 415 15.93 15.93 15.93 9.20 9.20 9.20
3 415 415 415 16.34 16.34 16.34 9.43 9.43 9.43
4 415 415 415 16.75 16.75 16.75 9.67 9.67 9.67
5 415 415 415 17.16 17.16 17.16 9.91 _ 9.91 9.91

FILE NAME: Transformer Page 5 of 10


MTRC CONTRACT NO. C3288.66-02E
Upgrade and Reinforcement of Power Supply System at PRE and ADM
DAR No. C3288.66-02E/06/02/01/07/001 Rev. 0 Date: 9 Sept 2003

7. VECTOR GROUP CHECK (refer to diagram 1)

Theoretical calculation:
AB = 415V
BC = 415V
CA = 415V
ab = 16.34V
bc = 16.34V
ca = 16.34V
Aa = OV
Ab = 16.34V
Ac = 16.34V
Ba = 415V
Bb = ' [AB 2 + ab2 - 2(AB)(ab)cos ZBAb] ZBAb = 300
= I[4152± 16.342- 2(415)(16.34)cos 300]
= 401V

Bc = Bb = 401V
Ca = 415V

Cc = I [AC 2 + Ac2 - 2(AC)(Ac)cos ZAcC] ZAcC = 300


= 1[4152+ 16.342- 2(415)(16.34)cos 30°]
= 401V

Cb = 4 [Cc 2 + bc2 - 2(Cc)(bc)cos


ZbcC] ZbcC = 151.16°
= 4 [4012+ 16.342- 2(401)(16.34)cos 151.160]
= 415.4V

Bc = Ba sin ZBcC (415 4 401)


sin3O0 sin ZAcB 2 2

401 = 415 ZBcC = 62.320


sin3O0 sin ZAcB

ZAcB = 148.840
ZbcB = ZAcB - 600
= 88.840

ZbcC = /bcB + ZBcC


= 151.160

A-B B-C C-A B-b B-c C-b C-c


Calculated 415 415 415 401 401 415.4 401
Volt ___

Measured
Volt ___

*. Phase A at HV side is connected to Phase a at LV side during testing.


*. Neutral terminal at LV side is isolated to earth during testing.

FILE NAME: Transformer Page 6 of 10


MTRC CONTRACT NO. C3288.66-02E ::EPEP
Upgrade and Reinforcement of Power Supply System at PRE and ADM
DAR No. C3288.66-02E/06/02/01/07/001 Rev. 0 Date: 9 Sept 2003

Diagram 1

Aa

FILE NAME: Transformer Page 7 of 10


MTRC CONTRACT NO. C3288.66-02E , LEpIp
Upgrade and Reinforcement of Power Supply System at PRE and ADM
DAR No. C3288.66-02E/06/02/01/07/001 Rev. 0 Date: 9 Sept 2003

8. FUNCTION TEST ON TEMPERATURE INDICATORS RESULT

(A). Check the Winding Temperature Indicator

1. Adjust and calibrate the winding temperature indicators.


Insert a thermometer (as reference) and the winding temperature
indicator in boiling oil.
Record the readings of the thermometer and calibrate the indicator.

2. Simulate winding temperature alarm with boiled oil.


The winding temperature alarm contact closes.
Record the switch setting with the reading of thermometer.
(Alarm setting 105 0C)

3. Simulate winding temperature trip with boiled oil.


The winding temperature trip contact closes.
Record the switch setting with the reading of thermometer.
(Trip setting 11 50 C)

(B). Check the Liquid Temperature Indicator

1. Adjust and calibrate the liquid temperature indicators.


Insert a thermometer (as reference) and the liquid temperature
indicator in boiling oil.
Record the readings of the thermometer and calibrate the indicator.

2. Simulate liquid temperature alarm with boiled oil.


The liquid temperature alarm contact closes.
Record the switch setting with the reading of thermometer.
(Alarm setting 850 C)

3. Simulate liquid temperature trip with boiled oil.


The liquid temperature trip contact closes.
Record the switch setting with the reading of thermometer.
(Trip setting 95 0 C)

9. WINDING RESISTANCE MEASUREMENT

H.V. Side A-B1


B-C
A-C

L.V. Side a-b a-n


b-c b-n
a-c c-n

FILE NAME: Transformer Page 8 of 10


MTRC CONTRACT NO. C3288.66-02E EPE11P
Upgrade and Reinforcement of Power Supply System at PRE and ADM
DAR No. C3288.66-02E/06/02/01/07/001 Rev. 0 Date: 9 Sept 2003

10. PHASE SEQUENCE CHECK & OUTPUT VOLTAGE MEASUREMENT


(Measured after energization)

Phase Sequence Check

Secondary Output Voltage


RY YB RB

RN YN BN

11. NOISE LEVEL MEASUREMENT

Check the noise level with the transformer on no load at rated voltage and frequency. The position
of the noise level meter shall be 1 metre from transformer body.
Ambient Noise Level: _dB

Position of Tester Noise (dB) at 1/2 tank height


East
South
West
North

12. STANDBY EARTH FAULTC.T. TEST

Substation:

Transformer No:

Current Ratio: Rating: Serial No._

I. Inject a.c. voltage to CT coil to measure the knee point voltage

Neutral C.T.
V
A

FILE NAME. Transformer Page 9 of 10


MTRC CONTRACT NO. C3288.66-02E UPUP
Upgrade and Reinforcement of Power Supply System at PRE and ADM
DAR No. C3288.66-02E/06/02/01/07/001 Rev. 0 Date: 9 Sept 2003

2. Inject primary current to test the C.T. accuracy

CT RESISTANCE INJECTED PRIMARY CURRENT (A) MEASURED SECONDARY CURRENT (A)

OHM 25% 50% 75% 100% 25% 50% 75% 100%

3. CT Insulation Test (500V d.c.)

CT to Earth M ohm

13. INSULATING OIL SAMPLE TEST

Referring to the attached test report from accredit laboratory:

Dielectric Test Result:

Water Content Test Result:

Tested by: Signed:

Witnessed by: Signed:


MTRCL Representative

Date

Approved by: Signed:


MTRCL Representative

Date

FILE NAME: Transformer Page 10 of 10