Chapter 3 Project Appraisal
Chapter 3 Project Appraisal
Chapter 3 Project Appraisal
Project Appraisal
Although, we are familiar with tools such as Gantt chart,, PERT, CPM, IRR, NPV and
others associated with project management. Yet when it comes to real project scenario, we
find practical problems which could bring deviations. This is not to suggest that the tools
and techniques are inadequate, but assumptions on which the project reports are prepared
are either invalid or unrealistic. A review of the Ministry of Programme Implementation
has shown that about 70% of project time or cost overruns are due to unrealistic
assumptions at the project formulation stage.
stage. It is therefore necessary to pay attention to
this, often overlooked, but vital aspect of project formulation. Project appraisal is the
process of analyzing the technical feasibility and economic viability of a project proposal
with a view to financing their costs. Project appraisal enables to take a decision on
investment with long term effects. During the appraisal stage, measurement of costs and
benefits are difficult as these are spread over a long term with high degree of uncertainty.
uncertainty
The figure below shows types of appraisal generally required for a project
Technical
Economical Social
Project
Appraisal
Financial Legal
Institutional Commercial
66
Meanings of Project Appraisal
Technical Appraisal
Determines whether the technical parameters are soundly conceived, realistic and technically
feasible. Technical feasibility analysis is the systematic gathering and analysis of the data
pertaining to the technical inputs required and formation of conclusion there from. The
availability of the raw materials, equipment, hard/software, power, sanitary and sewerage
services, transportation facility, skilled man power, engineering facilities, maintenance, local
people etc., depending on the type of project are coming under technical analysis. This
feasibility analysis is very important since its significance lies in planning the exercises,
documentation process, risk minimization process and to get approval.
Checklist
- Physical scale
- Technology used & Type of equipments & Suitability conditions
- How realistic is the implementation schedule
- Labour intensive method or others
- Cost estimates of Engineering Data
- Escalation are taken care of or not
- Procurement arrangement
- Cost of operation & Maintenance
- Necessary raw material & Inputs
- Potential impact of project on human & physical Environment
-
Financial Appraisal
To determine whether the financial costs and returns are properly estimated and whether the
project is financially viable. Following minimum details are determined in the financial
appraisal;
1. Total Cost
2. O & M Expenditure
3. Opportunity costs
4. Other costs
5. Returns on Investment over project life
6. NPV
7. CBR
8. IRR
Institutional Appraisal
To determine whether the implementing agencies as identified in the report are capable for
effective implementation, monitoring, and evaluation of the scheme. Managerial competence,
integrity, knowledge of the project, the promoters should have the knowledge and ability to
plan, implement and operate the entire project effectively. The past record of the promoters is
to be appraised to clarify their ability in handling the projects.
Checklist
67
• Whether the entity is properly organised do the job
• Strength to use capability and take initiatives to reach the objectives
• Openness to new ideas and willingness to adopt long term approach to extend over
several projects
•
Commercial Appraisal
The demand and scope of the project among the beneficiaries, customer friendly process and
preferences, future demand of the supply, effectiveness of the selling arrangement, latest
information availability on all areas, government control measures, etc. The appraisal
involves the assessment of the current demand/market scenario, which enables the project to
get adequate demand. Estimation, distribution and advertisement scenario also to be here
considered into.
Environmental Appraisal
To see any detrimental environmental impacts and how to minimise the impacts.
Environmental appraisal concerns with the impact of environment on the project. The factors
include the water, air, land, sound, geographical location etc.
Economic Appraisal
How far the project contributes to the development of the sector, industrial development,
social development, maximizing the growth of employment, etc. are kept in view while
evaluating the economic feasibility of the project.
Legal Appraisal
To determine whether the project satisfies the legal issues related to land acquisition, title
deed, environmental clearance etc.
The cost and returns, estimated after discussions with concerned Engineers, are projected
for its life period of ten to fifteen years for which the loan is taken. The Net Present Value
(NPV) shows the percentage recovery of the capital cost within its project life period. The
Internal Rate of Return (IIR) indicates the percentage returns of the individual projects over
a fixed period for town.
Once the cost estimate is made and the cost of construction is known, the annual returns are
assessed. With the expenditure, construction period and the returns per annum are known,
the financial appraisal of the project-including the annuity of loan repayment is assessed.
Depending on the financial viability of the project.
Appraisal involves a careful checking of the basic data, assumptions and methodology used in
project preparation, an in-depth review of the work plan, cost estimates and proposed
financing, an assessment of the project's organizational and management aspects, and finally
the viability of project. It is mandatory for the Project Authorities to undertake project
68
appraisal or at least give details of financial, economic and social benefits. Projects are
examined for technical, institutional/organizational/managerial, financial and economic point
of view depending on nature of the project. On the basis of such an assessment, a judgment is
reached as to whether the project is technically sound, financially justified and viable from the
point of view of the economy as a whole.
The concerned Technical Section in consultation with other technical sections undertake the
technical appraisal, wherever necessary. This covers engineering, commercial, organizational
and managerial aspects, while the Economic Appraisal Section carries out the pre-sanction
appraisal of the development projects from the financial and economic points of view.
Economic appraisal of a project is concerned with the desirability of carrying out the project
from the standpoint of its contribution to the development of the national economy. Whereas
financial analysis deals with only costs and returns to project participants, economic analysis
deals with costs and returns to society as a whole. The rationale behind the project appraisal is
to provide the decision-makers with financial and economic yardsticks for investment in the
projects.
The techniques of project appraisal includes discounted techniques that takes into account the
time value of money and include (a) Net Present Value (NPV), (b) Benefit Cost Ratio (BCR),
(c) Internal Rate of Return (IRR) (d) Sensitivity Analysis. Economic viability of the project is
invariably judged at 12 percent discount rate/opportunity cost of capital. However, in case of
financial analysis, the actual rate of interest i.e. the rate at which capital is obtained is used.
For the government-funded projects, the discount rate is fixed by the Government. In case the
project is funded by more than one source, the financial analysis is carried out on the
weighted average cost of capital (WACC) for each project. Normally, if the project is
financed through foreign grants, the financial analysis is undertaken at zero discount rate.
However, the economic analysis is undertaken at 12% discount rate.
Many investment projects are addition to existing facilities/activities and thus benefits and
costs relevant to the new project are those that are incremental to what would have occurred if
the new project had not been added. During the operating life of a project, it is very important
to measure all costs and benefits as the difference between what these variables would be if
no project (without project) were undertaken and what they will be should the project be
implemented (with project). It is very common error to assume that all costs and benefits are
incremental to the new project when, in fact, they are not. Hence, considerable care must be
taken in defining a “ base case” which realistically sets out the profile of costs and benefits
expected if no additional investment is undertaken.
69
central levels. In instances when the state is not the owner, the traditional yardstick of
commercial or financial profitability is used for selection of projects. In these cases the
primary criterion is the profit potential for promoter or the owner. But this may not
necessarily result in socially most profitable project. But then can decision makers
overlook this vital aspect of project evaluation, especially in a developing country?
A project has to be formulated and implemented in a social environment. Its impact on the
society in general and to the community in the near vicinity, in particular, is a major
concern to be taken into account at the time of project formulation. This includes land
acquisition, rehabilitation, loss of livelihood, adequate compensation, building up harmony
with the community, through close interaction. All these areas are importance. Yet very
few projects have considered it necessary to take these factors into account. Techno-
economic parameters are only guidelines for project formulation. But then a project cannot
be implemented in a vacuum. It needs an elaborate support system. The Project Manager
has to seek outside intervention for the support system. This where, a manager who is
essentially aware of the multiple dimensions of a project will be better suited to exercise
appropriate control over projects. We may think of the river linking project in India. The
project is yet to reach the pre-feasibility stage, and already there is a public opinion
building against it. Due to this increased social awareness, project formulation
methodology has to take account the social impact of the project. This is a time consuming
process. Often project authorities are made to rush through project preparation stage,
without spending adequate time on project pre-feasibility study, ultimately leading to time
and cost overrun. Projects often face uncertain future, due to intense public opposition and
prolonged litigation. Public servants are often required to face the vagaries of public
opposition, It is well known that a project has both time and cost dimensions. These two
dimensions are interlinked. A time delay often means a cost overrun, and a cost overrun
can also lead to time delay, because of budgetary constraints. Time and cost are the
dimensions in which projects are measured. But then there are web of other interconnected
activities which also impact on the project time and cost flow. Thus the main emphasis on
a project, even at the formulation stage is not the technical parameters alone but on the
control and coordination aspects.
Appraisal Methods
There are appraisal techniques that take into account the variations in the expected
inflows and outflows of the project that the project must inevitably face during its life
cycle. The crux of these methods lies in their consideration of time.
Project Analysis as per Cash Flows
It is common knowledge that projects do not earn the same level of profit every year.
In some years, profits are high; in others they are low. In many years, it can be expected
that the project will earn no profit at all. The question that confronts planners and
administrators is how to examine projects that have different time sequence of costs and
benefits, and therefore of profit/losses. Table 1 can be taken as the starting point for
examining this question.
Table 1 shows the costs and benefits of a hypothetical project over its life cycle of seven
years. In the first year, costs are greater than the benefits; in later years, benefits exceed
costs.
70
Two questions arise with respect to Table 1
Year Difference
Costs Benefits between
benefits and
costs
0 250 0 -250
1. 250 290 40
2 250 290 40
3. 255 300 55
4. 260 335 75
5. 260 335 75
6. 260 335 75
Total 1785 1895 110
1. From the table 1, it is seen that the overall profitability of a project cannot be assessed
on a year-to-year basis. Expected profits of this project as shown in the table vary
between years. Also, if a year-to-year assessment is attempted, it will be a time-
consuming exercise, and may not be able to give any definite conclusion as to its
profitability. So, the task for the planners is to reduce the flows into a single figure
that can indicate the earning capacity or the profitability of the project in question.
How should this be done?
2. How should the “value” of money over time be treated? Should the value of
Rs.75,000 that is likely to be the level of net profits in the fourth year of the project
(see Table 2) be taken at its face value, or be adjusted to take note of the fall in the
value of money from inflation as well as the uncertainty that is implicit in any
consideration of the “future”. What is the method by which the problem of time can
be resolved?
The method of dealing with the flows of costs and benefits over time in project analysis is
called time-discounting. This is a method of reducing to a comparable base the costs and
benefits of a project that accrue at different intervals. The underlying thesis in this
concept is that the value of money is different at different points of time; for instance
Rs.1,000 received today is not of equal worth to a similar amount ten years from now. In
other words, costs which have to be paid in the distant future have, at present, a lower
significance or value than those to be paid now. Similarly, the benefits which accrue
from a project now are of a greater value than those accruing later. Calculation of the
present value of costs and benefits involves the use of a discount factor, which is nothing
but a rate at which the future is to be discounted. Discount rate represents the present
value of the future.
71
To repeat: the crux of time-discounting is that the value of money is different at different
points in time. One thousand rupees received today cannot be equal in worth to Rs.1,000
received in one year’s time. Inflation and uncertainty reduce the value of money over
time.
F = P(1+r)n
Compounding is nothing other than finding out the future worth of the present at a given
rate of interest. Discounting is just reverse of compounding. In discounting, the expected
future values are given and their present values have to be determined at a given discount
rate. This involves using the inverse of the compounding formula:
P = F x 1/(1+r)n
Time-discounting is used for calculating the profitability of the project when cash
flows spread over a medium to long term with differing costs and incomes. It is thus
72
important for practitioners to be acquainted not only with the mechanics of discounting, but
when, and under what conditions, they should use higher or lower discount rates. When the
future carries greater risk and uncertainty, and the fear of inflation or deteriorating
economic situations, a higher discount rate is generally used. Conversely, a lower discount
rate would suffice when the economic and social situations are stable, and no dramatic
changes are expected to take place in the future.
Three methods are discussed here. These are (1) net present value, (2) benefit cost
ratio, and (3) internal rate of return.
The net present value method can be used by taking the following steps
It can be seen from the example in Table 2 below that at a 12 percent rate of discount
the net present values of the project are negative (-15.1). The project, therefore, cannot be
accepted. If, however, a lower discount rate is used, say 8 percent, the net values of the
project would turn positive, and the project may gain acceptability. The net values at 8
percent discount rate are shown in Table 3.
73
Table 3: Computing the Net Present Values (2) (in ` 1000)
Benefit-Cost Ratio
The benefit-cost ratio is a ratio calculated by dividing the sum of discounted benefits by
discounted costs. Steps for calculating the benefit-cost ratio are:
74
The computation of benefit-cost ratio is shown in Table 4.
Y Discounted Values
Costs Discount
e Benefits
(outfl Factor at
a (inflows) Costs Benefits
ows) 8%
r
Step 1 Step 2 Steps 3 and 4
0 250 0 1 250 0
1 250 290 0.93 232.5 269.7
2 250 290 0.86 215 249.4
3 255 300 0.76 193.8 228
4 260 335 0.73 189.8 244.55
5 260 335 0.68 176.8 227.8
6 260 335 0.63 163.8 211.05
The benefit-cost ratio in the above example is greater than 1, indicating that the sum of
the discounted benefits is greater than the sum of the discounted costs. If the ratio has been
less than 1, as indeed it is at 12 percent discount rate, it would not be advisable to accept the
project. Also, as in the case of the NPV, the higher the benefit-cost ratio of a project, the better
it is in terms of profitability.
The internal rate of return is a rate of discount at which the net present values of a project are
zero. Or, expressed differently, it is a rate at which the discounted costs and discounted
benefits become equal. The rate represents the “effective interest earned on the investment in
the project.” In the words of Gittinger. It is the maximum interest that a project could pay for
the resources used if the project is to recover its investment and operating costs and still
breakeven.
Internal Rate of Return = A rate at which the discounted costs are equal to discounted
benefits
Unlike the two other methods discussed earlier where the present values or the benefit-cost
ratios are calculated on the basis of the given discount rates, in the case of the internal rate of
return, a rate at which the discounted costs would become equal to discounted benefits has to
be found out. The higher the IRR, the stronger is the project.
75
The calculation of the internal rate of return involves the following steps.
Step 1. Estimate the cash inflows and cash outflows on a year-to-year basis
Step 2. Work out the net cash flows for individual years.
Step 3. Select any random discount rate and compute the net present values.
Step 4. If the NPV thus arrived at is positive, then select a higher discount
rate at which the NPV may come close to zero. If, however, the NPV
is negative, then select a lower discount rate at which the NPV may
come close to zero.
Step 5. Repeat the exercise until a discount rate that reduces the net present
values to zero is found.
An example using the figures given in Table 5 may once again to be taken to illustrate the
computation of the internal rate of return.
Costs
(Cash Benefits
Net Cash Net Present Values
Year outflow (Cash
Flows Discounted
s) inflows)
In this example, the initial discounting of the net cash flows (Step 3) has been done at 8
percent, which gives a positive net present value of 18.1. Step 4, that is, discounting at 12
percent, turns the net values to a negative figure of 15.1, suggesting that the rate at which the
discounted net values would turn zero must lie somewhere between 8 and 12 percent.
It would thus be noted that the calculation of the internal rate of return requires repetitive
computations and is often taxing. An alternative to the use of repetitive computations is
“interpolation”, which is a technique of finding the intermediate values between any two
76
figures, or any two discount rates in the present context. The equation for interpolation is as
follows:
Difference
Between the Net present value
Discount rates lower discount rate
X -----------------------------
Sum of the net present
Values at the two
Discount Rates (ignore sign)
Or
Internal rate of return = 8+ (12 – 8) 18.1 …………(1)
(18.1)-(-15.1)
= 8+ (4) x 18.1 ……………….. (2)
33.2
= 8 + (4) (.54) ……………….. (3)
= 8 + 2.1
= 10.1 rate of discount
This is the way in which the internal rate of return is calculated. As mentioned earlier,
projects with higher IRRs are considered financially safer and stronger. Evidently, it would be
inadvisable to accept projects whose IRRs are lower than the prevailing lending or borrowing
interest rates in the capital market of the country.
It would be mentioned that the internal rate of return is the most widely used method for
appraising development projects. Most international and bilateral aid agencies rely on this
method as a guide to decisions on projects in question, of course, among several other
considerations. The main advantage of the IRR is that it is less subject to maneuvering than
either the net present value or the benefit-cost ratio methods. In their cases, almost everything
about projects depends on the discount rates: by changing the discount rates, results as desired
by the planners or administrators can be obtained. This is not possible to be done in the case of
the internal rate of return where, if favorable results were to be sought on a particular project,
the entire stream of costs and benefits of the project will need to be changed.
Another example of assessing a water supply project for a town by IRR is illustrated below
77
Key Questions
a) Will the project have a positive cash flow at any time during the project life?
b) In the case of income – generating projects: what is the projected net profit and when
will project break even?
Key Issues
1. To calculate the incremental net benefit because only the net benefits with the project in
excess of those which would have accrued without the project should be taken in to
account. If the project results in cost reductions, they should be considered as incremental
net benefits.
2. To determine the project life. It is usually the economic life of the major investment item
which is shorter than the technical life due to technological obsolescence.
3. To assess the debt-servicing capacity of the project during the entire project life in order
to ensure that the project will be capable of meeting its financial obligations at any time.
Cash flow analysis calculates the expected net cash flow as the differences between
receipts and expenses for each year over the project life. Receipts and expenses for each
year over the project life. Receipts and expenses comprise all monetary transactions (cash
inflows and out flows) irrespective of an impact on real income. A continuous project
implementation and later operation requires a positive net cash flow at any time.
In case of an income – generating project, the commercial profitability of the project has to be
assessed by estimating all revenue and costs. Revenue and costs comprise all transactions that
generate or reduce real income irrespective of cash flows. The commercial profitability is only
given, if a net profit is likely to be achieved at the end of the project life or, in the case of a
continuous operation, after an respected point in time depending on the project type. Funding
assistance is usually required to finance the capital investments needed to get project started
78
Minimum Data
1. PROJECT: Supply of Water to a residents of a town consisting of 10,000 houses
2. Capital Expenditure : Rs. 7 crores
3. Cost of Capital : 10%
4. Operations and maintenance Rs. 25 lakhs per annum
5. Average revenue from each house hold Rs. 150 per month or Rs1.8 crore/year
6. Life of the project: 10 years
With the above data available with us, we can now work out Net Present Values, Benefit Cost
Ratio and IRR based on the incomes and expenditure over the period of 10 years as below
Years
Particular 1 2 3 4 5 6 7 8 9 10 Total
s
Increment 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8
al Revenue
(Rs in
Crores)
Incremental 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25
cost
(Rs in
Crores)
Net cash 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55
flow
(Rs in
Crores)
PVIF at 0.909 0.826 0.751 0.683 0.621 0.564 0.513 0.467 0.424 0.386
10%
PV of cash 1.41 1.28 1.16 1.06 0.96 0.87 0.80 0.72 0.66 0.60 9.62
flows at
10%
PVIF at 0.833 0.694 0.579 0.482 0.402 0.335 0.279 0.233 0.194 0.162
20%
PV of cash 1.29 1.08 0.90 0.75 0.62 0.52 0.43 0.36 0.30 0.25 6.5
flows at
20%
79
BCR at 10%=9.62/7=1.37
IRR-18.40%
The appraisal of a project would provide the project authorities the following information for
taking decision;
Project appraisal leads to overall assessment of the project’s chances for success based on the
findings of the feasibility analysis. It seeks to establish what will occur, who will gain and lose,
when the project’s impacts will occur and the efficiency of the project investments in relation
to the benefits derived. The form of the project appraisal process depends on a variety of
factors, such as the scale and complexity of the given project, the nature of the organization
involved, the availability of professional staff, the importance attached to non-economic
factors and so forth. A project appraisal report should cover the following topics.
Hassan town in Karnataka State is chosen as a model town for taking up such an exercise. This
integrated Infrastructure Plan Programming for Hassan, through its local body i.e., the
municipality, is a well knit package of many programmes-services and remunerative-integrated
into one cohesive unit, instead of disjointed projects planned without any inter relation among
them.
The exercise was taken up to find ways and means of increasing the local body’s internal
resources while at the same time looking to lending agencies for financial assistance towards
schemes for provision of infrastructure facilities and other remunerative schemes designed for
resource augmentation and asset creation. It is now proposed to study the existing service levels
and finances, identifying the gaps, exploring the possibilities of increasing the revenue and
reducing the expenditure to bolster up the savings. The next step would be to estimate the funds
80
required to take up the service and remunerative projects and assess the capability of the
municipality to borrow and finally prioritise the schemes to meet its purpose.
It was followed up with the discussions on the markets, shops, parks and play fields in the town
some of which are remunerative. So with the views expressed on service and remunerative
projects gathered from the public, discussion with the municipal officials, officials of the other
departments, Boards such as Water-Supply and Drainage, Housing, Slum Clearance, were taken
up in two or three informal group meetings to arrive at the possible proposals for meeting the
problems and the needs of the community. This was followed by the spot visits to the places
identified for action.
Estimates were then prepared for the identified projects. In the case of remunerative projects
they were tested for their financial viability. Along with the
Projects costs, the operation and maintenance cost, the resulting annuity payments of loan with
interest were also worked out. The already existing municipal budget with receipt, expenditure,
existing debt service ratio (Ratio of loan repayment to total receipts excluding grant) is projected
for the next five years and to these are added new projects, their income, expenditure with new
debt service ratio of existing and new projects and the net financial status.
Alternative Scenarios:
So different scenarios were tried with various permutation and combinations of the five
principles enunciated above to bring the debt service ratio below 25 percent and at the
same time aim at surplus balances.
81
Checklist :Financial Appraisal of a Infrastructure Development Project-
Corrective Actions-Flow chart
Financial Appraisal
Remunerative Project
Component
Total Costs
Benefits/Returns from
Remunerative
Projects
Incomes over
the next 25
years
Calculation of NPV/IRR/CBR-
Decision to select the project
82
QUIZ
Chapter 3
1. Project appraisal enables
a. To know cost benefits
b. Technical feasibility
c. Economic & Environmental viability
d. All of the above
83
7. In case the project is funded by more than one source, the financial analysis is
carried out using
a. Weighted average cost of capital for each project
b. More than the weighted average
c. Less than the weighted average
d. None of the above
8. Project is acceptable if
a. NPV is positive
b. NPV is negative
c. NPV is Zero
d. None of the above
84
13. The formula for calculation of present value is
PV=FV/ (1+R)n where PV=present value
FV=Future value
R=Rate of Interest
n=Number of years
a. True
b. False
a. True
b. False
85
17. Which is not true in regard of RoI (Return on Investment) for a project?
a. It defines the cumulated net income from an investment at a given point in time or
during a defined period.
b. It includes investment, direct and indirect costs and may include allowances for
capital cost, depreciation, risk of loss, and/or inflation.
c. It is most commonly stated as a percentage of the investment or as a
dimensionless index figure.
d. It is the time when cumulated net income is equal to the investment.
18. A project being evaluated by an agency has a cost of capital of 12%. Initial
investment is Rs 1,00,000 benefits as below
Year Benefit
Year 1 25,000
Year 2 40,000
Year 3 40,000
Year 4 50,000
a. 1.75
b. 1.145
c. 2.3
d. 0.45
20. Assumed is a discount rate of 5% per year. Looking at the present values of the
benefits of these projects in the first 3 years, what is true?
a. Both projects are equally attractive
b. The first project is more attractive by app. 7%.
c. The second project is more attractive by app. 5%.
d. The first project is more attractive by app. 3%
86
TEMPLATE (Indicative)
Project Appraisal
Sl No. Name of the Project
1
Need for the Project
2 project proposal and its objectives; Proposal
Objectives
3 Immediate and long-term benefits? Immediate objectives
Study Area/Location
Environmental Impact
Beneficiaries
Social costs
Legal issues
Demand
Other Constraints
Favourable conditions
Etc.
87
• IRR
88