SMR Form
SMR Form
N D
2 QUARTER SELF-MONITORING REPORT 2020
G ENERAL INFORMATION SHEET
Name of the
MS. ROSETTE S. CABAHUG – MINI-SAWMILL
Establishment/Facility
Establishment/Facility Street # & Street Name: Purok 3
Address
(NOT the company of head
Barangay: Tubaran City/Municipality: Tubod
office)
Province: Lanao del Norte
Name of
MS. ROSETTE S. CABAHUG – MINI-SAWMILL
Owner/Company
Street # & Street Name: Purok 3
Address
(if address is not the same as Barangay: Tubaran City/Municipality: Tubod
previous address)
Province: Lanao del Norte
We hereby certify that the above information are true and correct.
It was on 2013 when Mrs. Rosette S. Cabahug started the mini-sawmill business. She
named it D3S Cabahug Enterprises Mini-Sawmill after the couple’s kids nicknames. At first,
only one (1) unit of chainsaw was used in this enterprise. Some of the clients were barangay
locals and paid only part of the lumber as service charge. For months, the lumbers
accumulated and it was then that the mini-sawmill business started. The proponent then
begun to process the necessary permits and it is still doing business for 6 years now.
DENR Permits/Licenses/Clearances
Environmental
Permits Date of Issue Expiry Date
Laws
A/C No. N/A
P.D. 984
PO No. N/A
ECC 1 ECC-R10-1312-0278 DEC. 27, 2013 N/A
PD 1586 ECC 2 N/A
ECC 3 N/A
RA 6969 DENR
M-GR-R10-35-01373 APRIL 14, 2020 N/A
Registry ID
CCO Registry N/A
Importer N/A
Clearance No
Name of Plant:
Permit to
Transport
N/A
RA 8749 PO No. 2016-POA-C-1035-1988 MAR. 9, 2016 FEB. 10, 2021
Operation
Operating hours/day Operating days/week # of shift/day
Average THREE (3) HRS THREE (3)DAYS/WEEK ONE (1)/DAY
Maximum FIVE (5) HRS FIVE (5) DAYS/WEEK ONE (1)/DAY
Operation/Production/Capacity:
Average Daily
300 BOARD FEET Total Output this Quarter 21,600.00 BOARD FEET
Production Output
Total Water Consumption Total Electric
this Quarter (cubic 0.16M³ Consumption this Quarter 915 KwH
meters) (KwH)
Please use additional sheet/s if necessary
Name of Plant:
MODULE 2: RA 6969
Other Information:
Manner of handling storage on-site Treatment on-site
hazardous wastes storage off-site Treatment off-site
Chemical Substitute Yes (please attach copy if not submitted/included in previous report/s or had been revised)
Plan No
HW Generation:
Remaining HW from
HW HW Generated
HW No. HW Class HW Nature Previous Report
Cataloguing
Quantity Unit Quantity Unit
D402 Arsenic & S F Zero - Zero Zero
its
compounds
I101 Used or Lq F Zero - 15 L
waste oil
Waste Storage, Treatment and Disposal:(Please fill-up one table per HW)
HW No,: D402 ___
HW Details Qty of HW Treated: N/A Unit: ___
TSD Location: N/A ___
HW No,: ___
HW Details Qty of HW Treated: Unit: ___
TSD Location: ___
Name: ___
Storage
Method: ___
HW No,: ___
HW Details Qty of HW Treated: Unit: ___
TSD Location: ___
Name: ___
Storage
Method: ___
N/A
N/A
N/A
N/A
N/A
N/A
Summary of APSE/APCF
Process Equipment Location # of hrs of operations
1. Band sawmill machine Sawmill Plant Site 2,500.00 hrs
2.
3.
4.
Fuel Burning Quantity # of hrs of
Location Fuel Used
Equipment Consumed operations
1. N/A
2.
3.
Pollution Control Facility Location # of hrs of operations
1. NOT APPLICABLE
2.
3.
4.
Cost of Treatment
JANUARY FEBRUARY MARCH
Cost of Person employed,
(salary)
Total Consumption of
Water (cubic meters)
Total Cost of chemicals
used (e.g., activated NOT APPLICABLE
carbon, KMnO4)
Total Consumption of
Electricity (KwH)
Administrative and
Overhead Costs
Cost of operating in-
NOT APPLICABLE
house laboratory, if any
Improvement or
modification, if any.
NONE
(Description)
3. Other sectoral That all other pertinent All necessary permits from
requirements mandated by 11 permits shall be secured other government agencies
other agencies to be complied from concerned were secured and hereto
with government agencies prior attached
to project implementation
4. EMP and updates as Complied with the design Details provided under
deemed required of the drainage canals to Detailed EMP Matrix
address the rain water
runoff.
5. Conduct of baseline,
compliance and self-
monitoring
6. Multi-sectoral Monitoring Not applicable since the
(as may be required) project is only medium risk
7. Regular reporting Self-Monitoring Report SMR is submitted to the
DENR-EMB 10 regularly
8. Institutional management Enforcement of The management handles
necessary for the environmental awareness the environment related
implementation of and compliance within all activities of the project
environmental management levels of the organizations
measures
9. Standard DENR That transfer of ownership The same owner/proprietor
requirement on transfer of of this project carries the of D3S Cabahug
ownership same condition in this ECC Enterprises. There is no
for which written transfer of ownership
notification shall be
submitted to DENR-10
within Fifteen (15) days
from such transfer
10. Standard DENR There is no plan for
requirement on abandonment business abandonment
11. Impact Mitigation Plan or
Construction/Contractor’s
Environmental Program
12. Social Development Plan Miscuts are given to Sergio
Brief Description of The establishment is observing and considering waste reduction and
Solid Waste segregation while in operation.
Management Plan (e.g.,
waste reduction,
segregation, recycling)
NONE - - - -
Personnel/Staff Training
# of Personnel
Date Conducted Course/Training Description
Trained
MARCH 2-4, 2020 40HRS POLLUTION CONTROL ONE (1)
OFFICER SEMINAR PERSON
I hereby certify that the above information are true and correct.
Done this 30th day of June 2020, in Tubaran, Tubod, Lanao del Norte.