Title of Project Report: Red Zuma Project Management
Title of Project Report: Red Zuma Project Management
Title of Project Report: Red Zuma Project Management
Red Zuma
Project Management
Submitted to – Submitted by –
2. The following holidays are observed: January 1, Martin Luther King Day (third
Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first
Monday in September), Thanksgiving Day (4th Thursday in November), December 25.
3. If a holiday falls on a Saturday, then Friday will be given as an extra day off, and if it
falls on a Sunday, then Monday will be given as a day off. If December 25th falls on a
Friday, then Monday will not be given a day off.
Construct a network schedule for this project and prepare a memo that answers the following
questions:
1. When is the project estimated to be completed? How long will the project take?
The project is estimated to be completed on 1/11/16. It takes 260 days to complete the
project.
This network isn’t much sensitive as it has only one critical path.
A Gantt chart.
A schedule table reporting ES, LS, EF, LF, and slack for each activity.
Part 2
Part A
2. Assume that the project is time constrained and try to resolve any overallocation
problems by leveling within slack. What happens?
When u level all the tasks, the days required to complete the project increases from
260days to 295 days. This resolves the over allocation of all the resources.
3. What is the impact of leveling within slack on the sensitivity of the network?
Detailed Marketing Plan slack has changed from 179 days to 149days. The sensitivity
has reduced as the slack has reduced and the critical path has also changed.
5. How does the new duration compare with the estimated completion date generated
from Part 1? What does this tell you about the impact resources can have on a
schedule?
Once the resources are levelled, the days taken to complete the project is 295 days. After
clearing the leveling, the over allocated resources are sorted and the days required to
complete the project changes to 310days.
Part B
1. What was the impact of introducing Start-to-Start lags to the schedule and budget?
2. Which, if any additional personnel assignments, would you choose to complete the
project before the January 17th deadline? Explain your choices as well as the reasons
for not choosing other options.
We would choose Industrial engineer to complete the project before 17th January
deadline as it is the most optimal option which will remove all over allocation and
maintain cost and schedule.
3. How have these changes affected the sensitivity of the network and the critical
path?
The sensitivity of the resources has increased as now we have 2 critical paths.
1. How much will the project cost? What is the most expensive activity?
The most expensive activity is Detailed Product Design which costs $190,168.27.
2. What does the cash flow statement tell you about how costs are distributed over the
life span of the project?
Part 4
Part A
Submit a professional status report to Robin Lane that addresses the following questions:
Previously, project is taking 260days (ends on 11/1/16) to complete and cost needed to
complete this project is $872,929.81. Now, the project is taking 279days (ends on
27/1/16) and $941,417.69 to complete.
2. What activities have gone well? What activities have not gone well?
Initially there was no over allocation but after the changes, Detailed Marketing Planning
and Build Prototype are over allocated.
46% of the work has been completed. PCIB= EV/BAC = $980,680.53/ $908,926.15 =
1.078
EAC= $980,680.53
5. What is the estimated completion date?
The main priorities of the project are the cost and milestones. The project is still over
budget
and we have achieved both milestones, but as there are still many activities that have yet
to
start, the cost can vary and therefore need to be diligently tracked. The duration has
increased
from the initial estimate of 270 days to 279 days. So the project is not doing well in
terms of time
Part B
1. What is the impact of the revised estimates for Finalized Product Design and
Install Production Equipment on the project schedule and cost?
The project is getting completed in given timeline after revising estimates for Finalized
Product Design and Install Production Equipment.
No. As the project is getting completed before estimated time, it is not needed to
authorize the expenditure of $50,000.
3. What, if any other recommendations, would you make so that the project can
achieve Robin's deadline? Justify your recommendations.
Include a Tracking Gantt chart with variance schedule that depicts your final
recommendations and revised schedule.