6.3.2 Material Receiving Inspection: Ras Markaz Crude Oil Park Project (Phase1)

Download as pdf or txt
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 1

RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE1)

SITE INSPECTION AND TESTING PROCEDURE


Doc No: 9686-6150-PR-000-0029 Rev. 03 Doc. Class 1 /Cat: 2

EPC Contractors QA/QC shall complete his/her inspection prior to Company inspection and provide the
completed signed inspection checklist to Company.

An RFI shall be considered rejected by the Company, if


03
• EPC Contractor's inspector was not present at the time of inspection.

• The stage for which the RFI raised was not ready.

• The inspection was not done by EPC Contractor prior to organizing the inspection and RFI.

Appropriate corrective action shall be taken by EPC Contractor for the rejected RFI.

6.3.2 Material receiving inspection

EPC Contractor QA/QC shall perform the receiving inspection with material controller, Sub-contractor
and Company. EPC Contractor QA/QC shall notify Company 48 hours before material is ready for
03 inspection through a proper RFI.

Where discrepancies are revealed during receiving inspection of equipment and materials,
Nonconformity shall be identified by item number, tag number or material code etc. and will be
separately stored and handled in a segregated area in order to avoid unintended use.

For details refer to Material Handling and Storage Procedure, Doc No. 9686-6120-PR-000-0005 for the
receipt of Goods; handling, storing and maintenance of Goods; issuing and return of Goods.

6.3.3 In-process inspection and test

A construction readiness check supported by an appropriate checklist shall be completed by QA/QC


prior to commencement of any construction activity refer to Attachment 1 checklist for new construction
03
activity. EPC Contractor QC Engineer/Inspector shall organize and perform inspections or tests in
accordance with the approved ITPs and applicable Procedures/Method Statements, after receiving
request for inspection from the relevant Sub-contractors or its Construction team.

If the inspection or test point is designated as Spot Witness, Witness or Hold Point of Company, the
discipline construction department will raise the RFI and EPC QC Engineer shall notify inspection or test
timing to Company prior to 48 hours of the scheduled inspection.

The QC inspector shall prepare the “Inspection and Test Report” after inspection or test and report the
inspection or test results to Site Quality Manager (SQM). SQM shall verify all activities including
inspection or test specified in the ITP, completeness of construction have been satisfactorily completed,
by review of relevant documents and site visits (If required).

Any deviation to the approved Method Statement/ITP shall be requested through a technical deviation
request for Company approval.

Any non-conformity found during construction, installation and erection work will be documented using
the NCR report form and correction/corrective actions with a proper disposition shall be agreed prior to
implementation. Any repair work shall be undertaken only after notifying the Company about the repair,
Page 13 of 24