PM401 - Final Exam Example - 20140728 - Solutions
PM401 - Final Exam Example - 20140728 - Solutions
PM401 - Final Exam Example - 20140728 - Solutions
Final Exam
Name: ………………………………………………..
Developed by
Simon Gordon-Smith and Ir. Luc De Ceuster, PMP
Page 2 of 12
1. Draw the precedence diagram and calculate project duration, critical path, ES, EF, LS, LF
and slack for all tasks (10 points)
2. Draw the Gantt chart (10 points)
3. Determine the cost per period (time phased budget) and the S-curve (5 points)
4. Verify the utilization of resource "Charlotte" and propose solutions if necessary
(5 points)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A 2 2 2
B 2.5 2.5
D 2 2 2
E 4 4 4
G 2 2
H 1 1 1 1
K 1 1 1 1
Time Phased 6 6 7.5 7.5 7.5 3.5 3.5 3.5 3 3 1 1 1.5 1.5 1.5 1.5 1 1 1 1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
B 0.55 0.55
Charlotte
0.80 0.80 0.70 0.80 0.80 0.50 0.15 0.15 1.15 1.15 0.55 0.55 1.00 1.00 1.00 1.00
Page 6 of 12
Page 7 of 12
There is a resource problem in periods 9 and 10. The task H cannot be moved since it
is on the critical path, so the only solution here is to work with task I. There are basically
three options:
Question 2 – (5 points)
PERT or three-point-estimates (5 points)
Consider the following data for a given task or project related to the duration:
Calculate the expected cost and standard deviation using PERT for a beta distribution
Question 3 – (5 points)
We have 10 stakeholders identified for our project. Suddenly, due to a change 15 more
stakeholders have to be added. (5 points)
n∙ ( n−1 ) 10 ∙ 9
Initial= = =45
2 2
n∙ ( n−1 ) 25 ∙ 24
Initial+15= = =300
2 2
In our project planning we have foreseen that the project team would produce 14 widgets in
period of 10 weeks. We produced 12 widgets and paid 75k.
A. BAC = 21 x 5k = 105k
B. See graph: behind schedule and over budget
C. Approximately 130k
432323??’\k
ji 4ev
Question 5 - (5 points)
Indicate with ‘x’ to which process step the deliverable belongs (according to the Project Management
Process)
Project Review x
Schedule Control x
Question 6 - (5 points)
Explain in short the difference between a project and a process.
A project has a limited duration and creates something unique. The project ends when
all the work is completed
A process is repeating producing similar things. The process will stop when the
economic reality changes. New models that need to guarantee survival of the company.
Question 7 - (5 points)
We have 2 vendors A and B. Vendor A completes the work for 350k and B for 325k. Vendor A
has a probability of 10% to be late 10 days. Vendor B has a probability of 5% to be late 20 days.
A day delay costs 10k.