WEEKLY REPORT
MAIN CONTRACT WORKS
NO. 09
6th May –12nd May 2019
CONTENTS
1|PT. SINAR GUNUNG SEJATI
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
1. Executive Summary
( Completed and on-going Major Critical Works )
A. Production Building
1) Completed Work :
Foundation ( F1, F1B ) Zone A
Tie Beam Zone A
Installing Anchor Bolt at F1, and F1B Zone A
2) On-going :
Casting Concrete Zone B
Rebar installation PC1A, and PC2 at Zone A / As Grid R1-Q1
Excavation Boiler area at As Grid N1-M1
Excavation Foundation area F3, and F5 at Zone A
Fabrication Rebar Boiler, F3, F5, F7, and F8
Erection Main Frame ( Rafter R1, Rafter R2, Steel Column SC1, Steel Column
SC2A) at Zone B as grid P-J1
Connecting Steel Beam (SB1) to Steel Column (SC1) Zone A without 100% of
torque at Zone B as grid P-J1
Excavation pit under Daily Bin area
3) On- Schedule :
Excavation Wet Process area in 25th May 2019
Erection Main Frame ( Rafter R1, Rafter R2, Steel Column SC1, Steel Column
SC2A) at Zone C as grid J1-B1 in 20th May 2019
Connecting Steel Beam (SB1) to Steel Column (SC1) Zone A without 100% of
torque at Zone B as grid P-J1 in 20th May 2019
Excavation F5 at grid Q1-P 24th May 2019
Erection Main Frame ( Rafter R1, Rafter R2, Steel Column SC1, Steel Column
SC2A) without 100% of torque at Zone A As grid S1-P1 15th May 2019
Casting Concrete Tie beam at Zone C As Grid 37A B1-E1
Connecting Steel Beam (SB1) to Steel Column (SC1) Zone A without 100% of
torque 15th May 2019
Casting concrete Foundation F5 and F3 at Grid S1-Q1
2) On-going
Fabrication rebar footplate and pedestal
3) On-schedule
Casting Concrete Footplate and Foundation 27th May 2019
Un-install Roof at Grid F1 – F14 depend of FAMSUN tools
Installation Anchor Bolt 26th May 2019
Re-install rear canopy 26th May 2019
C. Intake Building
1) Completed Work :
-
2) On-going
3) On-Schedule
Casting lean concrete at Pit area 25th May 2019
Install Rebar Pit and Foundation 26th May 2019
Excavation Main Pit Area at grid 28 A - 29 A 15th May 2019
Excavation Foundation 15th May 2019
D. Silo
1) Completed work :
Excavation
Backfilling
Form Work S1 & S2 Zone A
Form Work S1 & S2 Zone B
Form Work S1 & S2 Zone C1
Form Work S1 & S2 Zone C2
Rebar installation and Fabrication
Installation Anchor Bolt
Lean Concrete with fc’ 15 Mpa
Ground Slab with fc’ 30 Mpa
2) On- going :
Casting pedestal concrete with fc’ 30 Mpa
Install Form Work pedestal
3) On- Schedule :
Embedded Plate Installation with Chemical Anchor 20th May 2019
E. Office Building
1) Completed work :
-
2) On- going :
-
3) On-Schedule :
Casting Concrete Continues Footing 27th May 2019
Excavation 16th May 2019
Rebar fabrication 16th May 2019
Installing bottom rebar Continues Footing and Footplate at grid 37A - 38 A
19th May 2019
Installing Tie Beam rebar at grid 37A – 38 A 19th May 2019
Casting lean concrete with fc’ 15Mpa 18th May 2019
F. WWTP
1) Completed work :
2) On- going :
Excavation at Zone A W5-W2
3) On-Schedule :
Excavation Zone B-C 22nd May 2019
Anti-termite Zone A W5-W2 20th May 2019
Anti termite Zone B-C 24th May 2019
Filling with imported material ( Sub-Grade ) at Zone A,B,C 25th May 2019
1) Adjustable elevasi pada pedestal diarea Production Building, berkaitan dengan posisi frame
Clading agar sejajar dengan frame lainnya (SGS – STR – BP – 1008 ,1003,1004,1005)
2) Permit Excavation Warehouse, Excavation WWTP, Excavation Intake Building, Excavation
Office area, Installation Rebar Office Still not Ready.
a. Production Building
COMPLETE
ON-GOING
ON-SCHEDULE
SCHEDULE
Q1-P1 Boiler Area
F7F3 Finish Cor F8F5Finish Cor PC 1 & PC2
Finish Cor Casting
Pedestal 2228 Pedestal 28 finish Cor 28
Pedestal 28 Concrete 28
May 2019
May 2019 May 2019 May 2019
May 2019 May 2019
b. Warehouse
COMPLETE
ON-GOING
ON-SCHEDULE
c. Silo
COMPLETE
ON-GOING
d. Intake
COMPLETE
ON-GOING
ON-SCHEDULE
SCHEDULE
Casting Pit Foot Plate
casting LC
Concrete Concrete
25 Mei 2019
28/05/2019 28/05/2019
e. WWTP
SCHEDULE
Excavation
Excavation Filling Sub-
Area Zone A
Zone B-C 24 grade 26
20 May
May 2019 May 2019
2019
SCHEDULE
Casting
Concrete LC
ON-GOING 26/05/2019
ON-SCHEDULE
f. Office
SCHEDULE
Tiebeam
CF Casting
Casting
Concrete 28
Concrete 28
May 2019
May 2019
COMPLETE
ON-GOING
ON-SCHEDULE
COMPLETE
ON-GOING
ON-SCHEDULE
10 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
COMPLETE
ON-SCHEDULE
UJ
11 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
COMPLETE
ON-GOING
ON-SCHEDULE
3.3 SILO
EEE3
ZONA A
COMPLETED
SLAB ZONE A COMPLETE
ON-GOING
SLAB ZONE B
ZONA C1
FINNISH SLAB
ZONE C1
ZONA C2
FINNISH SLAB
ZONE C2
12 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
ON-GOING
ON-SCHEDULE
13 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
3.4 OFFICE
Schedule on
25th May 2019
finish Rebar
COMPLETE
ON-GOING
B. Excavation and LC ( Office Building )
ON-SCHEDULE
Schedule on
16th May 2019
finish
Excavation
14 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
3.5 WWTP
A. Excavation WWTP
On- schedules
17th May 2019
On- Schedule
on 25nd May
2019 On- Schedule
on 22nd May ON-SCHEDULE
2019
On- Schedule
on 25nd May
2019 Finish
15 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
A.Excavation
ON-SCHEDULE
4. PROGRESS PERFORMANCE
28.94 %
Actual Progress
36.08 %
Plan Progress
-7.14 %
Deviation
16 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
17 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
Office Area :
Casting concrete continues footing, tie beam, and fabrication rebar column
Casting concrete Slab 1st floor
Fabrication formwork for column and balk
Intake Building :
WWTP area :
Filling with imported material on the top ground with 500mm layer, compacted CBR
min 80%
Start Casting concrete LC with fc 15 Mpa
Preparation Casting concrete for Backwall with fc 30 Mpa’ (incl. Integral)
Fabrication rebar for foundation and Water Wall
18 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
6. Progress Photo
6.1. Silo
19 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
20 | PCasting
T . Concrete
S I N AFootplate
R GUNUNG SEJATI
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
6.3. WWTP
Excavation WWTP Area Zone 1,2,3 Excavation WWTP Area Zone 1,2,3
Excavation WWTP Area Zone 1,2,3 Excavation WWTP Area Zone 1,2,3
21 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
6.5 FG Warehouse
22 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
7. 3D PROGRESS VIEW
COMPLETE
ON-GOING
ON-SCHEDULE
23 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
24 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
25 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09
26 | P T . S I N A R G U N U N G S E J A T I