New Rice Mill Project PT - Padi Flour Nusantara Mojokerto - Indonesia

This weekly report provides updates on the progress of the New Rice Flour Mill Project in Mojokerto, Indonesia. Key activities completed this week include foundation work and tie beams in Zone A of the production building. Ongoing work includes casting concrete in Zone B of the production building, rebar installation, excavation of several foundation areas, and fabrication of rebar. Major milestones expected to be reached next week include further excavation, erection of steel frames, and concrete work. Overall progress is reported to be on or slightly behind schedule across various areas of the project.

Uploaded by

Dhika Putra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
116 views

New Rice Mill Project PT - Padi Flour Nusantara Mojokerto - Indonesia

This weekly report provides updates on the progress of the New Rice Flour Mill Project in Mojokerto, Indonesia. Key activities completed this week include foundation work and tie beams in Zone A of the production building. Ongoing work includes casting concrete in Zone B of the production building, rebar installation, excavation of several foundation areas, and fabrication of rebar. Major milestones expected to be reached next week include further excavation, erection of steel frames, and concrete work. Overall progress is reported to be on or slightly behind schedule across various areas of the project.

Uploaded by

Dhika Putra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 26

DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.

09

NEW RICE MILL PROJECT PT.PADI FLOUR NUSANTARA


MOJOKERTO – INDONESIA

WEEKLY REPORT
MAIN CONTRACT WORKS
NO. 09
6th May –12nd May 2019

Disetujui oleh : Diperiksa oleh : Disiapkan oleh :


PT. Padi Flour Nusantara PT. TeamworX PT. SINAR GUNUNG SEJATI

Project Manager Construction Manager Project Manager Quantity Survey

CONTENTS
1|PT. SINAR GUNUNG SEJATI
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

1. Executive Summary ……………………………………………………………………………………3


2. Progress of This Week ………………………………………………………………………………..3
3. Area of Concern Engineering……………………………………………………………………….6
4. Summary of Construction & Tracking Performance Progress ……………...6
5. Two Week-Look a Head Schedule ………………………………………………………….19
6. Progress Photo ………………………………………………………………………………..20
7. 3D Progress Review ………………………………………………………………………………..24
8. Equipment Report & Weather Report………………………………………………………..25
9. Man Power Report …………………………………………………………………………………26
10. Summary of Material On-Site ………………………………………………………….27

2|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

1. Executive Summary
( Completed and on-going Major Critical Works )

A. Production Building
1) Completed Work :
 Foundation ( F1, F1B ) Zone A
 Tie Beam Zone A
 Installing Anchor Bolt at F1, and F1B Zone A

2) On-going :
 Casting Concrete Zone B
 Rebar installation PC1A, and PC2 at Zone A / As Grid R1-Q1
 Excavation Boiler area at As Grid N1-M1
 Excavation Foundation area F3, and F5 at Zone A
 Fabrication Rebar Boiler, F3, F5, F7, and F8
 Erection Main Frame ( Rafter R1, Rafter R2, Steel Column SC1, Steel Column
SC2A) at Zone B as grid P-J1
 Connecting Steel Beam (SB1) to Steel Column (SC1) Zone A without 100% of
torque at Zone B as grid P-J1
 Excavation pit under Daily Bin area

3) On- Schedule :
 Excavation Wet Process area in 25th May 2019
 Erection Main Frame ( Rafter R1, Rafter R2, Steel Column SC1, Steel Column
SC2A) at Zone C as grid J1-B1 in 20th May 2019
 Connecting Steel Beam (SB1) to Steel Column (SC1) Zone A without 100% of
torque at Zone B as grid P-J1 in 20th May 2019
 Excavation F5 at grid Q1-P 24th May 2019
 Erection Main Frame ( Rafter R1, Rafter R2, Steel Column SC1, Steel Column
SC2A) without 100% of torque at Zone A As grid S1-P1 15th May 2019
 Casting Concrete Tie beam at Zone C As Grid 37A B1-E1
 Connecting Steel Beam (SB1) to Steel Column (SC1) Zone A without 100% of
torque 15th May 2019
 Casting concrete Foundation F5 and F3 at Grid S1-Q1

B. Finish Good Warehouse


1) Completed Work
 Un-install Wall Cladding Completed
 Excavation Foundation Area

2) On-going
 Fabrication rebar footplate and pedestal

3|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

 Un-install Roof at Grid F14 – F23


 Painting Steel Rafter (Brushing, Cleaning, Coating ) at Grid F14 – F23
 Cleaning FAMSUN Area

3) On-schedule
 Casting Concrete Footplate and Foundation 27th May 2019
 Un-install Roof at Grid F1 – F14 depend of FAMSUN tools
 Installation Anchor Bolt 26th May 2019
 Re-install rear canopy 26th May 2019

C. Intake Building
1) Completed Work :
 -

2) On-going

3) On-Schedule
 Casting lean concrete at Pit area 25th May 2019
 Install Rebar Pit and Foundation 26th May 2019
 Excavation Main Pit Area at grid 28 A - 29 A 15th May 2019
 Excavation Foundation 15th May 2019

D. Silo
1) Completed work :
 Excavation
 Backfilling
 Form Work S1 & S2 Zone A
 Form Work S1 & S2 Zone B
 Form Work S1 & S2 Zone C1
 Form Work S1 & S2 Zone C2
 Rebar installation and Fabrication
 Installation Anchor Bolt
 Lean Concrete with fc’ 15 Mpa
 Ground Slab with fc’ 30 Mpa

2) On- going :
 Casting pedestal concrete with fc’ 30 Mpa
 Install Form Work pedestal

3) On- Schedule :
 Embedded Plate Installation with Chemical Anchor 20th May 2019

4|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

E. Office Building

1) Completed work :
 -
2) On- going :
 -
3) On-Schedule :
 Casting Concrete Continues Footing 27th May 2019
 Excavation 16th May 2019
 Rebar fabrication 16th May 2019
 Installing bottom rebar Continues Footing and Footplate at grid 37A - 38 A
19th May 2019
 Installing Tie Beam rebar at grid 37A – 38 A 19th May 2019
 Casting lean concrete with fc’ 15Mpa 18th May 2019

F. WWTP
1) Completed work :

2) On- going :
 Excavation at Zone A W5-W2

3) On-Schedule :
 Excavation Zone B-C 22nd May 2019
 Anti-termite Zone A W5-W2 20th May 2019
 Anti termite Zone B-C 24th May 2019
 Filling with imported material ( Sub-Grade ) at Zone A,B,C 25th May 2019

5|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

2. Progress of This Week


Recapitulation Progress of This Week :

1. Bill 01 Preliminaries : 5. Bill 06 Silo :


a. Plan of This Week : 1.20 % a. Plan of This Week : 8.26%
b. Actual Progress of This Week : 0.16% b. Actual Progress of This Week : 0.00 %
c. Progress until This Week : 1.80 % c. Progress until This Week : 6.18 %
d. Deviation : 0.60 % d. Deviation : -1.58 %

2. Bill 03 Production Building :


a. Plan of This Week : 19.47 %
b. Actual Progress of This Week : 0.97 %
c. Progress until This Week : 19.07 % *Office Building and WWTP on- Process
d. Deviation : 0.4% Maping
3. Bill 04 Finished Good Ware House :
a. Plan of This Week : 3.15 %
b. Actual Progress of This Week : 0.00 %
c. Progress until This Week : 0.46 %
d. Deviation : -2.57 %

4. Bill 05 Intake Building :


a. Plan of This Week : 1.62 %
b. Actual Progress of This Week : 0.00 %
c. Progress until This Week : 1.65 %
d. Deviation : 0.03 %

6|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

3. Areas of Concern Engineering

1) Adjustable elevasi pada pedestal diarea Production Building, berkaitan dengan posisi frame
Clading agar sejajar dengan frame lainnya (SGS – STR – BP – 1008 ,1003,1004,1005)
2) Permit Excavation Warehouse, Excavation WWTP, Excavation Intake Building, Excavation
Office area, Installation Rebar Office Still not Ready.

4. Summary of Construction Tracking Performance Progress


4.1 Sumarry Progress & Critical Works ( Production Building )

a. Production Building

COMPLETE

ON-GOING

ON-SCHEDULE

SCHEDULE
Q1-P1 Boiler Area
F7F3 Finish Cor F8F5Finish Cor PC 1 & PC2
Finish Cor Casting
Pedestal 2228 Pedestal 28 finish Cor 28
Pedestal 28 Concrete 28
May 2019
May 2019 May 2019 May 2019
May 2019 May 2019

7|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

b. Warehouse

COMPLETE

ON-GOING

ON-SCHEDULE

c. Silo

COMPLETE

ON-GOING

d. Intake

COMPLETE

ON-GOING

ON-SCHEDULE

SCHEDULE
Casting Pit Foot Plate
casting LC
Concrete Concrete
25 Mei 2019
28/05/2019 28/05/2019

8|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

e. WWTP

SCHEDULE
Excavation
Excavation Filling Sub-
Area Zone A
Zone B-C 24 grade 26
20 May
May 2019 May 2019
2019

SCHEDULE
Casting
Concrete LC
ON-GOING 26/05/2019

ON-SCHEDULE

f. Office

SCHEDULE
Tiebeam
CF Casting
Casting
Concrete 28
Concrete 28
May 2019
May 2019

COMPLETE

ON-GOING

ON-SCHEDULE

9|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

3.1 Production Building


A. Tie Beam, and Foundation ( Footplate, and Pilecap )

COMPLETE

ON-GOING

ON-SCHEDULE

*All schedules refer to Executive Summary

10 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

3.2 Ware House

A. Un-Install Roof and Wall Clading ( Warehouse )

COMPLETE

ON-SCHEDULE

UJ

11 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

COMPLETE

ON-GOING

ON-SCHEDULE

3.3 SILO

A. CASTING CONCRETE SLAB WITH FC’ 30MPA

EEE3
ZONA A
COMPLETED
SLAB ZONE A COMPLETE

ON-GOING

ZONA B COMPLETED ON-SCHEDULE

SLAB ZONE B

ZONA C1
FINNISH SLAB
ZONE C1

ZONA C2
FINNISH SLAB
ZONE C2

12 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

B. Casting Concrete and Drilling Embedded Anchor

ON-GOING

ON-SCHEDULE

*On-going install Embedded Plate with Chemical –

Anchor, Planning Finish work in 17th May 2019.

13 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

3.4 OFFICE

A.Rebar Continues Footplate Installation ( Office Building )

Schedule on
25th May 2019
finish Rebar

COMPLETE

ON-GOING
B. Excavation and LC ( Office Building )
ON-SCHEDULE

Schedule on
16th May 2019
finish
Excavation

14 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

3.5 WWTP

A. Excavation WWTP

On- schedules
17th May 2019

On- Schedule
on 25nd May
2019 On- Schedule
on 22nd May ON-SCHEDULE
2019

B. Filling With Imported Material

On- Schedule
on 25nd May
2019 Finish

15 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

3.6 INTAKE BUILDING

A.Excavation

ON-SCHEDULE

On- Schedule On- Schedule


on 16nd May on 16nd May
2019 Finish 2019 Finish

4. PROGRESS PERFORMANCE

28.94 %

Actual Progress

36.08 %

Plan Progress

-7.14 %

Deviation

16 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

17 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

5. Two Week Look A Head Schedules


Work for the next two weeks are follows :
Silo Area :

 Drilling anchor embedded plate


 Installing embedded plate with chemical anchor
Production Building :

 Start foundation work F3 As Grid E1 Zone C, and F1 B As grid 38A


 Start Tie beam As Grid P,J1,E1
 Installation Anchor Bolt F3, PC1A, and PC2
 Erection Steel Column, Rafter 1, Rafter 2, and Steel Beam at Zone A continues to
Zone B
 Continues excavation Pit Rice Cleaning area
Warehouse Area :

 Un-install roof, rear and side canopy


 Excavation foundation area
 Fabrication rebar foot plate
 Installation and Casting concrete footplate

Office Area :

 Casting concrete continues footing, tie beam, and fabrication rebar column
 Casting concrete Slab 1st floor
 Fabrication formwork for column and balk
Intake Building :

 Finishing Excavation at main pit area


 Fabrication rebar for foundation and Water Wall
 Fabrication formwork pit area, footplate, and pedestal column

WWTP area :

 Filling with imported material on the top ground with 500mm layer, compacted CBR
min 80%
 Start Casting concrete LC with fc 15 Mpa
 Preparation Casting concrete for Backwall with fc 30 Mpa’ (incl. Integral)
 Fabrication rebar for foundation and Water Wall

18 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

 Fabrication formwork pit area, footplate, and pedestal column

6. Progress Photo

6.1. Silo

Casting Slab Concrete Zone C1 Un-install formwork pedesdtal Silo

Drilling Process anchor embedded Drilling Process anchor embedded

Install formwork Casting Slab Concrete Zone C1

19 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

6.2 . Production Building

Installation Formwork Pedestal Installation Formwork Pedestal

Casting Concrete pedestal F1 Striping side of tiebeam

20 | PCasting
T . Concrete
S I N AFootplate
R GUNUNG SEJATI
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

6.3. WWTP

Casting Concrete Footplate

Excavation WWTP Area Zone 1,2,3 Excavation WWTP Area Zone 1,2,3

Excavation WWTP Area Zone 1,2,3 Excavation WWTP Area Zone 1,2,3

21 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

6.5 FG Warehouse

22 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

7. 3D PROGRESS VIEW

COMPLETE

ON-GOING

ON-SCHEDULE

23 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

8. Equipment Report & Weather Report

24 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

9. Man-Power Report (terlampir)

25 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.09

10.Summary of Material On-Site

26 | P T . S I N A R G U N U N G S E J A T I