Operation Management Assignment 2

This document contains two project management examples using Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT). The first example provides a network diagram with activities, durations, and predecessors. It asks to identify the critical path(s) and project duration. The critical paths are A-D-H-I-J-K and A-C-G-J-K, with a total project duration of 32 weeks. The second example provides a PERT table with activity times and asks to calculate expected durations, early/late dates, and variance. It identifies the critical path as A-D-H-I-J-K with an estimated completion of 36.5 weeks
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
586 views4 pages

Operation Management Assignment 2

This document contains two project management examples using Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT). The first example provides a network diagram with activities, durations, and predecessors. It asks to identify the critical path(s) and project duration. The critical paths are A-D-H-I-J-K and A-C-G-J-K, with a total project duration of 32 weeks. The second example provides a PERT table with activity times and asks to calculate expected durations, early/late dates, and variance. It identifies the critical path as A-D-H-I-J-K with an estimated completion of 36.5 weeks
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Chapter 4: Project Management (CPM & PERT TECHNIQUES)

QUESTION 1

Name: Melissa Wong Pau Yu


No matric: BB18110868

A network consists of the following list. Times are given in weeks.

Activity Preceding Duration


A -- 9
B A 2
C A 12
D A 5
E B 6
F B 8
G C, F 3
H D 2
I H 8
J G, I 6
K E, J 2

a. Draw the network diagram.

B E
A K
A
C G J
A A
F
L
D H
A
b. Which activities form the critical path?

Answer: Path A-D-H-I-J-K and A-C-G-J-K are critical


ABEK: 9+2+6+2=19
ABFGJK=9+2+8+3+6+2=30
ACGJK= 9+12+3+6+2=32
ADHIJK=9+5+2+8+6+2=32

c. What is the duration of the project completion?

Answer: 32 week

QUESTION 2
A PERT problem is detailed in the table below. Times are given in weeks.

Probable
Optimistic Time/ Most likely Pessimistic
Activity Preceding Time time Time
A -- 7 9 14
B A 2 2 8
C A 8 12 16
D A 3 5 10
E B 4 6 8
F B 6 8 10
G C, F 2 3 4
H D 2 2 8
I H 6 8 16
J G, I 4 6 14
K E, J 2 2 5

a. Calculate the expected time and ES, EF, LF, and LS of each activity.
Answer:
Expected time Early Early Late Start Late finish
Start Finish
A ( ) 0 9.5 0 9.5
= 9.5
B ( ) 9.5 12.5 23 26
=3
C ( ) 9.5 21.5 12 24
=12

D ( )
= 5.5 9.5 15 9.5 15
E ( )
=6 12.5 18.5 28 34
F ( )
=8 12.5 20.5 26 24
G ( )
=3 21.5 24.5 24 27
H ( ) 15 18 15 18

I ( )
=9 18 27 18 27
J ( )
=7 27 34 27 34
K ( )
=2.5 34 36.5 34 36.5
b. Draw diagram network for this project. E

K
B
F

Start A G J
C

I
D H

c. What are the project variance and the project standard deviation?

A-B-E-K 9.5+3+6+2.5 21 weeks


A-B-F-G-J-K 9.5+3+8+3+7+2.5 33 weeks
A-C-G-J-K 9.5+12+3+7+2.5 34 weeks
A-D-H-I-J-K 9.5+5.5+3+9+7+2.5 36.5 weeks

Critical Path is A-D-H-I-J-K with project completion of 36.5 weeks

Variance ( ) 1.361+1.361+1+2.778+0.25=9.528

Standard deviation √ =3.087

d. What is the estimated completion time?

ANS: Critical Path A-D-H-I-J-K with completion 36.5 weeks

e. What is the probability of completion of the project after week 40?

ANS: The probability of completion of the project x=40

Z= X-Critical Path

Standard Deviation
=40-36.5
3.087
=1.1326
= Probability of completion of the project before week 40=0.8708 or 87.08%