Dispute Resolution and Litigation in PPP Road Projects: Evidence From Select Cases
Dispute Resolution and Litigation in PPP Road Projects: Evidence From Select Cases
Dispute Resolution and Litigation in PPP Road Projects: Evidence From Select Cases
Abstract: Public–private partnership (PPP) projects came to prominence with the launch of the National Highway Development Project in
India in 1998. Since then, the PPP procurement approach to service delivery has permeated the transportation sector and its subsectors of
highways, ports, airports, and railways. Many of these projects have suffered cost and time delays due to disputes over land acquisition, grants
for environmental and forest clearance, and other approval. Concession agreements (CAs) in the road-building sector provide for dispute
resolution clauses, although not in detail; however, it has been observed that dispute resolution is not normally achieved unless all the stages
of litigation have been exhausted. CAs are still evolving, and no PPP-specific legislation yet exists in India, unlike in the UK and Hong Kong,
where individual legislations are enacted for each project. Suitable changes in the land acquisition process and legislation and provision
for strict, time-bound implementations and fair and reasonable compensation can aid in reducing the number of litigation cases. Incentives
and penalties are required to ensure strict compliance with contract provisions. DOI: 10.1061/(ASCE)LA.1943-4170.0000336. © 2019
American Society of Civil Engineers.
Author keywords: Public–private partnerships (PPPs); National Highway Development Project; Disputes; Case study; Arbitration.
Introduction projects are long term and suffer from many unforeseen circum-
stances and pitfalls, often leading to disputes between the public
The development of road infrastructure is crucial to the economic and private partners. These disputes are frequently resolved through
growth of any country. The upgrading of highways in India com- several rounds of dispute resolution, and, when this fails, by liti-
menced with the launch of the National Highways Development gation. The hierarchy of the judicial system in India comprises
Project (NHDP) in 1998. The public–private partnership (PPP) (1) local and district courts, (2) high courts with jurisdiction over
approach to procurement has deeply penetrated the transportation the geographical spread of the respective state(s), and (3) the
sector. In India, the road network comprises (1) national highways, Supreme Court (the apex court).
(2) state highways, (3) major district roads, and (4) rural roads. In Like most contract documents, the PPP concession agreement
general, the upgrading of national highways involves increasing (CA), the most important of all agreements related to a project,
roads from two to four lanes, or from four to six lanes. The pro- invariably includes certain clauses and provisions relating to the
vision of four or six lanes means two or three lanes (where each resolution of disputes. Clauses pertaining to arbitration are integral
lane is approximately 3.5 m wide) for travel in each direction, sep- to all PPP agreements, and this is considered to be the final option
arated by physical dividers. National highways form approximately before litigation is begun. The results of arbitration may be binding
1.5% of the total road network, but handle 40% of the road traffic or otherwise in nature, and in the former case the clauses of the
(MoRTH 2015). The increase in road networks between 2003 and contract should explicitly clarify the method of enforcement. Be-
2013 was around 4%, substantially less than the growth in the cause PPP projects are very complex, occasions may arise in which
number of registered vehicles, which grew at a compound annual disputes are hard to resolve or settle, and these may have an impor-
growth rate of 11% during the same period. The PPP procurement tant bearing on the outcome of the project. However, the arbitration
model has been adopted to improve the road network in India since process has an important advantage over litigation: since disputes
the mid-1990s. The other primary reason for adopting the PPP pro- are very technical and complex in nature, local and subordinate
curement model is the acute shortage of resources that are available courts may not have the relevant expertise to effectively address
to the government of India for financing such investment-intensive the issues involved (Timmermans and Behr 2016). PPP contract
projects. clauses dealing with dispute resolution should mandate the priority
Experience in the implementation of PPP projects has shown of the procedures to be followed, including (1) governance and
that this procurement model is very complex in nature; these contract management, (2) the dispute review board, (3) mediation,
(4) conciliation, (5) testimony of independent experts, (6) arbitration,
1 and finally, (7) litigation (Marques and Berg 2010).
Research Scholar, Dept. of Civil Engineering, Indian Institute of
Technology Delhi, New Delhi, Delhi 110016, India (corresponding In India, the issue of aggressive bidding has on more than one
author). ORCID: https://orcid.org/0000-0002-9597-6238. Email: ajitgaya@ occasion led to either complete or near failure of PPP road projects
rediffmail.com due to time and cost overruns. Insufficient coordination between
2
Professor, Dept. of Civil Engineering, Indian Institute of Technology the different authorities involved in the preparation of tenders
Delhi, New Delhi, Delhi 110016, India. Email: [email protected]
and inadequate preparation and management by the public sector,
Note. This manuscript was submitted on December 20, 2018; approved
on April 30, 2019; published online on October 1, 2019. Discussion period
including poor accountability, are some of the basic reasons for ag-
open until March 1, 2020; separate discussions must be submitted for in- gressive bidding. This is aggravated by a lack of proper regulation
dividual papers. This paper is part of the Journal of Legal Affairs and and contract management. If the concessionaires believe that it may
Dispute Resolution in Engineering and Construction, © ASCE, ISSN not be easy to extract profit by resorting to aggressive bidding, they
1943-4162. will obviously be less inclined to take the risk arising from this
Independent expert for PPPs that are designed to promote investment in infrastructure.
The PPP Act, Mexico (Hodges 2006) and the Partnerships Victoria,
Arbitration
Australia (Abdel Aziz 2007) framework facilitate the efficient,
equitable, and proper distribution of risk between the public and
private partners; these legislations also ensure a framework for
Litigation transparency and accountability, and provide legal certainty to
those involved in the projects. Similarly, the PPP Act of 1994 is a
Fig. 2. Sequential ADR stages leading to litigation. very strong legislative document in Korea that regulates matters
delegated by the act and those that are necessary for its strict
implementation (APEC 2014).
arbitration stage have only recommendatory authority. Dispute res-
olution may also be required at the procurement stage, i.e., prior to Litigation Related to Land Acquisition and
the contract management stage. Disputes may arise over issues such Environmental Clearance
as questions of interpretation and nonfulfillment of contractual ob-
ligations. If these contentious issues remain unresolved following Issues Leading to Conflicts over Land Acquisition
the ADR stage, the matter enters arbitration, and if the disputes In many of the PPP projects in India, several court cases have been
remain unsettled it enters the litigation phase. launched in the course of the acquisition of land and rights of way
Decisions via the first three methods enumerated previously are (RoWs), mostly between landowners and public sector authorities.
typically binding, based on the provisions of the PPP contract. Issues related to land acquisition are not suitable for the arbitration
However, a decision made by an arbitrator may involve the addi- provisions and clauses contained in CAs, and court cases take a
tional application of the arbitrator’s own mandate or judgment, long time to settle or receive a judgment. These cases mostly relate
including on the contract provisions of the project. Thus, the reg- to issues of compensation and resettlement, and include other in-
ulator’s decision also involves the exercise of discretion. tegrally related issues such as livelihoods, places of residence,
ownership of land, and the return of excess acquired land. Such
cases therefore lead to inordinate delays in the acquisition of land.
PPP Laws and Policies in India and Worldwide Lenders and providers of debt do not look kindly on such delays,
In India, there are no specific laws or policies governing PPP proj- and therefore often a financial closure in projects gets overdelayed.
ects, unlike in Belgium, Italy, Poland, Portugal, and Spain, which The Shivpuri-Dewas highway is one example where financial clo-
put into place concession laws very early in the course of develop- sure could not be achieved within the stipulated time and the public
ment of PPP. Until now, issues related to PPP in India have been authorities had to recall tenders after splitting the original project
administered mostly through executive orders. In practice, the ab- work into three smaller packages. This led to a considerable time
sence of PPP legislation has led to changes in and references to delay of 3 years (from 2012 to 2015) and a cost overrun of USD
other binding legislation and regulations. However, the existence 100 million (USD 1 ¼ INR 70). Although land acquisition is gen-
of specific laws is certainly not a mandatory condition for the de- erally the responsibility of the public authorities, the nonavailability
velopment of PPP because the legal framework can also be created of land often results in exchange of reasons for the delay between
by changing existing legal provisions with bearing on the PPP the private partner and the public authority, and has in many cases
compelled concessionaires to abandon PPP projects in the past,
project. The UK has developed its public finance initiative (PFI)
even before construction commences. Lenders foresee increased
model based on specific legislation that confers power to enter into
financing risks in such a situation, and if they are still prepared
a PPP contract (Guash 2004). However, the existence of such laws
to extend debt, they may require the private partner to pay a higher
goes a long way toward establishing the basic principles that are
rate of interest. If the project continues with the original conces-
required in order to ensure transparency and accountability for
sionaire, this may lead to tremendous cost and time overruns, which
PPP arrangements.
in turn may lead to further litigation.
In addition to the provisions contained in the Constitution of
India and the rules and regulations enacted from time to time by Issues Leading to Conflicts in Environmental Clearance
various state bodies, several other laws also have a bearing on The situation is similar when obtaining environmental and forest
PPP arrangements in India, such as the National Highways Author- clearances. This process is time-consuming, and several different
ity of India Act (1988), and laws governing normal commercial authorities may be involved (the federal or state Ministry for For-
transactions such as the Indian Contract Act (1872), the Sale of ests and Environment, the Wildlife Authority of India, the district
Goods Act (1930), and the Negotiable Instruments Act (1881). administration, and the local civic bodies), who often work at cross
In addition, various statutes governing dispute resolution are also purposes. Many of the PPP highway projects that span more than
relevant, for instance, the Code of Civil Procedure (1908), the one state in India face problems with land acquisition due to the
Specific Relief Act (1963), and the Arbitration and Conciliation different policies and rules and regulations of the states concerned,
Act (1996) with their latest amendments. particularly when different political dispensations rule these states.
highways and railways faces delays and time overruns, which also Dispute Resolution Mechanisms
impact cost overruns. The subsectors of ports and airports are less
affected since the land required for these projects is in concentrated Details of the dispute resolution mechanisms provided in CAs are
pockets and is normally subject to favorable, single-state rules. given in Table 2 for several PPP road projects in India. These were
A detailed summary of the reasons for the delays in granting chosen randomly to give an insight into the provisions contained in
environmental clearance and other forms of approval and for the the contracts. The CAs detailed in Table 2 do contain dispute res-
noncompletion of land acquisitions are shown as causes of disputes olution clauses, but these are not elaborate or exhaustive.
and litigation in Fig. 3. From the contract provisions outlined in Table 2, it can be seen
that the dispute resolution procedures are not set out in detail, and
Identifying Factors Affecting Disputes and Litigation this may lead to different interpretations of the process adopted for
in Countries across the World the settlement of disputes, increasing the likelihood of slipping into
The causes of litigation in different countries that have been studied avoidable litigation.
by researchers or authors have several factors in common, such
as changes in the scope of the project, site conditions that are differ-
ent from the information available in the detailed project report, Successful PPP Projects
and differing interpretations of the contract provisions. The most
common causes of claims or counterclaims that lead to disputes, A number of court cases that have been pending in different stages
and then to litigation if not resolved, are changes in the project of litigation over the past 7 or 8 years related to issues of compen-
scope and restricted access to the site (Semple et al. 1994). Sim- sation for land acquisition and changes in alignment, among others,
ilarly, differences in project characteristics, including processes were analyzed with regard to the time duration of this pendency
and other aspects of projects, can contribute to contract disputes leading to delays in completion, and the conclusion was drawn that
(Diekmann and Girard 1995). The most frequent causes within the majority of PPP road projects have encountered problems due
different countries are given in Table 1. to the nonavailability of land. Two successful PPP cases were also
Nearly two decades have passed since India initiated its PPP examined, one in Hong Kong and the other in India. Other PPP
program on a large scale by launching the Golden Quadrilateral road projects that have suffered a time delay of 3 years and cost
Reviewing orders
for award of
compensation
Ownership of
land issues
the high court. The project stands completed. The officer in charge case is pending with the session court at Dhar, which again was
for land acquisition and the concerned lawyer(s) were spoken with filed by the public authority, NHAI, and is related to the mainte-
and they were of the opinion that in a majority of cases the com- nance of the existing road (the stretch between Indore and the
pensation amount was strictly as per the rules. The lawyer opined borders of the Indian states of Gujarat and Maharashtra). The three
that liberal adjournments allowed by the court have resulted in the cases pending with the high court relate to the cutting of trees
dragging on of the cases. Only two authorities in the instant case and maintenance of the existing road. At the time of writing, the
could be contacted over telephone. pleadings were complete and awaiting adjudication. From tele-
phone conversations with representatives of NHAI (the nodal body
Case Study 2: Gwalior Bypass for upgrading roads and highways in India), it appears that the con-
The project was the Gwalior Bypass. The dispute resolution pro- dition of the existing road is poor and that the concessionaire was
cedure for the settlement of conflicts as stipulated in the CA was not heeding requirements for maintenance. All four cases are still
identical to that stated for the previous project, Bhubaneshwar–Puri. pending adjudication. The concerned general manager in charge of
Nine court cases have been filed and are pending adjudication court cases and working with the public authority, when contacted,
by the high court of the state of Madhya Pradesh at Gwalior. The could not express his views regarding delay in adjudication by the
nature of the cases in the high court are as follows: (1) three of the courts. However, he stated that the written pleadings are complete
cases are related to compensation for land acquisition; (2) in one and hearing is still to commence.
case, the petitioner seeks appointment as a stenographer in lieu of
land; (3) two cases relate to the release of excess land acquired; Case Study 4: Surat–Dahisar, NH 8
(4) one case is in the form of public interest litigation (PIL) and The project was upgrading six lanes over 239 km of the Surat–
relates to the issue of illegal mining; and (5) one case alleges con- Dahisar highway (NH 8), to be executed as a BOT (toll) in terms
struction of a road completed on land owned by a private party of its design, build, financing, and operation (DBFO) pattern.
without acquisition by the public authority, i.e., NHAI. Two of In this project, the stages of dispute resolution are as described
these nine cases, one related to land acquisition and the other to in the Case Studies 1 and 2. In all, 10 court cases are pending ad-
arbitration, are pending adjudication with the civil judge at Morena judication. Seven cases are pending with the principal district judge
and the additional district judge at Gwalior, respectively. The in Valsad, and one case with the civil court in Valsad. One further
remaining seven cases are pending adjudication with the court case is pending with the civil judge at Vasai, and the remaining case
commissioner and relate to arbitration. The commissioner is the with the High Court of Judicature at Bombay. Six cases were filed
administrative head of the respective courts, and oversees the tech- simultaneously in September 2009 and two cases each were filed in
nicalities of the petitions filed and ensures that the prerequisites are 2007 and 2013. The respondent in all cases is NHAI. Information
complete before they are put before the judges for hearings. All of regarding the status of these cases was gathered from NHAI by
the cases that are pending with the court commissioner were filed in telephone, and it appears that these cases relate to various aspects
either 2009 or 2010. Similarly, one of the nine cases pending with of land acquisition. Countersuits have already been filed by NHAI.
the high court was filed in 2009, one in 2012, one in 2014, two in The date for the next hearing has not yet been published. It was also
2013, and four in 2010. It has also been clarified that the land par- learned that the project is complete except for a small stretch,
cels acquired are all agricultural land and the owners are subsist- i.e., the last mile remains unfinished. The concerned land acquis-
ence farmers. Although the project is complete, these cases have ition officer could not be contacted despite best efforts. However,
not yet been decided. The registrar of the court at Gwalior could the project manager working in the public authority headquarters
be contacted and he was of the opinion that the cases submitted stated that the project is almost complete except for a particular
were not in proper shape and additional documents were required small stretch.
before the cases could be put before the judge. Similarly, the land
acquisition officer in charge of the case was of the view that the Case Study 5: Farakka–Raiganj, NH 34
cases were mostly filed on frivolous grounds. No other authority The project was upgrading from two lanes to four in the Farakka–
could be contacted. Raiganj section of NH 34 for the length of 103 km in the state of
West Bengal, under NHDP Phase III, using a DBFOT pattern and
Case Study 3: Indore–Dewas, NH 3 on a toll basis.
The project was upgrading from four lanes to six of the 45.05-km The project was awarded on July 19, 2010, and covered the
Indore–Dewas section of NH 3, executed as a BOT project in terms 103 km (approximately) of the highway that was to be upgraded.
of the design, build, finance, operation, and transfer (DBFOT) pat- The dispute resolution procedure in this agreement was identical to
tern. The dispute resolution procedure stipulated under Clause 44 the provisions in the other case studies discussed previously.
and its subclauses (44.1.1–44.4) is identical to the dispute resolu- In all, six cases related to land acquisition have been filed for
tion procedure for the settlement of conflicts in the CA of the afore- this project. Four cases are pending adjudication with the high court
mentioned projects, Bhubaneshwar–Puri and the Gwalior Bypass. of West Bengal at Calcutta and one case is pending with each of the
The project was awarded on May 17, 2010, for a concession civil judges of the courts of the senior and junior divisions at Malda.
period of 25 years. The conditions precedent (i.e., conditions to Three cases were filed in 2015 in the high court, and one in 2010.
be fulfilled by the public authority, NHAI, and the concessionaire The remaining two cases were filed with the civil judge in 2013 and
authorities. This project is still incomplete in some intermediate reach finality. The general manager in charge of the project at the
stretches, where the preceding cases are yet to reach finality and headquarters of the public authority stated that though the perfor-
the land parcels remain to be acquired. Although the primary ob- mance guarantee has been cashed in terms of the provisions of the
jective of upgrading to four lanes serves the purpose of faster trans- contract, the court has unduly interfered and that the ruling by the
portation, the incomplete stretches continue to interrupt the smooth High court of Delhi was being processed.
flow of traffic. The project manager when contacted over telephone
stated that the grounds for the court cases are without any sound
basis and have mostly been filed with a view to obtaining enhanced Discussion
compensation. No representative from the concessionaire could be
contacted. A lack of proper and well-informed framing for CAs by capable
transaction advisors and consultants is a major concern. The pro-
Case Study 6: Raiganj–Dalkhola, NH 34 visions of a concession agreement need to be flexible in terms of
The project was upgrading to four lanes in the Raiganj–Dalkhola the optimal and equitable sharing of risks by the public and private
section of NH 34 (except the Dalkhola bypass) for a length of authorities, and this needs to be supplemented with adequate, time-
54.75 km in the state of West Bengal, under NHDP Phase III using bound, equitable, and justified contract management. Professionals
a DBFOT (toll) pattern. with domain expertise need to be engaged as IEs and professionals
The agreement for this project was executed on June 28, 2010. related to contract management should be employed. The decisions
The dispute resolution mechanism stipulated in the agreement is made by public authorities are required to be strictly merit-
identical to those for the preceding projects. Three cases have been based and exclusively in consonance with the stipulated contract
filed with the high court of West Bengal at Calcutta in 2011, 2013, provisions.
and 2014. The contentions raised by the petitioners are first that the Aspects related to land acquisition, granting of environmental
gazette notification was not proper, and no opportunity was pro- clearance, and approval for the diversion of forest land have proven
vided to the petitioners for lodging objections, if any, and second to be the main hindrances leading to time delays and cost overruns.
that the publication of notice for land acquisition under the provi- Furthermore, most projects also give rise to several court cases that
sions contained in the relevant orders bearing numbers 3A and 3D are primarily related to issues such as the payment of fair compen-
meant for land acquisition were published in Bengali and English, sation in lieu of land acquired. Urgent legislation needs to be
whereas the petitioners were only familiar with Urdu. Bengali is enacted to introduce regulations and legal frameworks for future
spoken in the state of West Bengal and the adjoining areas and PPP projects.
is a language with a completely different script from Urdu. The On perusal of the status of the court cases and interaction with
petitioners pleaded that they did not understand the notice and concerned legal authorities working with the public partner are al-
therefore could not lodge any objections to the proposed land ac- most unanimous in their views that the grounds for filing of cases
quisition. The petitioner in the third case contended that they had are simply baseless and without any legal standing. Further, they
not received a copy of the petition, even a year after having filed it felt that the sole aim for filing the cases was to obtain enhanced
with the court. As such, they were unable to file any objection to the compensation for the acquired land.
acquisition of their land. The representative of the concessionaire A strong legal framework and team are prime requirements for
(engineer) stated that they have been unduly harassed on account PPPs to proceed smoothly. The agreements must be specific, sim-
of the nonavailability of unencumbered land. The project manager ply worded, and unambiguous, leaving no space for alternative in-
expressed his unwillingness to give comments, stating that the terpretations of the intention of the respective clauses or provisions.
cases are sub judice. Once it enters the litigation phase, a dispute needs to be dealt with
by competent personnel, and the cases must be argued strongly in
Case Study 7: Walajahpet–Poonamallee, NH 4 arbitration tribunals and the courts by well-informed lawyers.
The project was upgrading from four lanes to six over 93 km of the Frequent and continuous transparent interaction with landowners
Walajahpet–Poonamallee section of NH 4, for a length of 93 km, in who are basically farmers should be adopted. The landowners
the state of Tamilnadu under NHDP Phase V using a BOT (toll), should be dealt with the authorities who are capable of making
DBFOT pattern. the owners aware of the laws and who are capable of interacting
The date appointed in the concession agreement for construction and creating a congenial atmosphere.
to commence was June 1, 2013, and the period for project comple-
tion was stipulated as 36 months. The project formed part of the
Golden Quadrilateral scheme to connect the four older metropolitan Conclusions
cities of New Delhi, Chennai, Kolkata, and Mumbai.
The project gave rise to seven cases, five of which were filed The government of India has adopted the PPP approach in the trans-
with the high court at Madras and two with the high court of port sector since the mid-1990s. Going by the number of projects,
New Delhi. The latter two cases sought orders from the court the PPP mode of procurement has permeated the road sector more
restraining the respondent (NHAI) from cashing bank guarantees extensively then the other subsectors of ports, railways, and air-
submitted by the concessionaire. Two cases comprised issues ports. In the absence of PPP-specific policies and laws in India,