PROCEDURE MANUAL
REV. : 2
EXECUTION PROCEDURE
DATE : 2013.08.27 PAGE 1 OF 15
SPD0006ERN
PROCEDURE MANUAL
EXECUTION PROCEDURE
REV. : 2
DATE : 2013.08.27
목 차
PAGE
1. SCOPE ------------------------------------------------------------------------------------- 3
2. DEFINITION -------------------------------------------------------------------------------- 3
2.1 Process Design ----------------------------------------------------------------------- 3
2.2 Process Specifications --------------------------------------------------------------- 3
2.3 Basic Design ------------------------------------------------------------------------- 4
3. DOCUMENTS --------------------------------------------------------------------------------- 5
4. ORGANIZATION ------------------------------------------------------------------------------ 5
5. EXECUTION --------------------------------------------------------------------------------- 6
5.1 General ------------------------------------------------------------------------------ 6
5.2 Cooperation with Clients ------------------------------------------------------------- 6
5.3 Handling of Licensed Processes ------------------------------------------------------- 9
8. 작성내력 ----------------------------------------------------------------------------------- 15
1. SCOPE
This manual covers the handling of specifications and other documents in the execution of basic design
in conformance with the basic design manual, the organization of the process engineering department
and the execution of process engineering.
The scope of work for Samsung as contractor on an engineering project can differ considerably from project
to project. This execution procedure considers a “typical” project in which the “Process Design”, a process
design package, has been prepared by a process licensor or the client, and Samsung, as contractor, is
responsible for the “Basic Design”, a basic engineering package. The split of scope between the Process
Design and Basic Design will vary from project to project. In some cases, Samsung as contractor will also
be responsible for the Process Design.
2. DEFINITION
2.1 Process Design
"Process Design" means the following work based on the design basis provided by the client.
- Preparation of process flow diagrams
- Preparation of heat and weight balances
- Preparation of equipment process data sheets
- Calculation of preliminary utility requirements
At this stage, the so called "Conceptual Design" will be executed; namely, the type of reactors,
the type of trays or packings, the most suitable operating conditions, thermal recovery methods,
etc. are studied, based on which the process flow is established. In this case, such factors as
the following must be considered:
- Operating cost
- Investment cost
- Operability
- Flexibility
- Safety
- Operating conditions
- Equipment process data sheet
SPD0006ERN
PROCEDURE MANUAL
REV. : 2
EXECUTION PROCEDURE
DATE : 2013.08.27 PAGE 4 OF 15
The information regarding process design be provided by the client or process Licensor.
The contractor will normally not be required to take responsibility for this information; however, based on the
contract, the contractor is required to clarify the extent to which such information is to be provided by the
client/process licensor. It is deemed that the work not covered by this information is within the scope of the
contractor.
Following the completion of the process specifications mentioned in Section 2.2, the following work must be carr
ied out:
The execution flow within the scope outlined above is as shown in Fig. 2-1.
Regarding contents of basic design package, refer to manual of "Basic Design Package" stipulated
in Section 1-3.
3. DOCUMENTS
Since project specifications or tender documents furnished by the client are to be followed as a
design basis, all engineers assigned to the project must study them.
Especially the key person must pick out all important requirements indicated therein and list up those
pertaining to the basic design.
In usual cases, the project specifications and engineering practice furnished by the client take
precedence over the contractor's design manuals.
However, in many cases, changes and revisions are made in the project specifications and/or
engineering practice in the course of the project work.
Changes and revisions, if made, must be recorded in the form of memorandum or minutes of meetings to
avoid confusion in the future.
Meanwhile, the proposal submitted by the contractor constitutes a part of the contract after award of
contract.
Hence, if any deviations from it are required in individual cases, the client's prior approval must be
obtained as a rule.
4. ORGANIZATION
The process department is responsible to the client and project division for the preparation of specifications.
A Lead Process Engineer is assigned as a key person to each project. The responsibilities of the Lead Pro
cess Engineer and Team Manager are as follows:
5. EXECUTION
5.1 General
Project teams are organized in the respective project divisions and each specialty department
assigns their key persons to the projects, which are executed under the matrix system.
The process engineering group proceeds with the process design under the coordination of the
project manager and engineering manager.
Generally, the execution procedure is as shown on Fig. 2-1.
Value analysis must be carried out to complete P & I diagrams, and the results of the analysis
must be reflected therein.
The basic purposes of value analysis are to eliminate so-called "golden plates" and to check for
conformance to the design philosophy.
SECL design philosophy can be paraphrased as follows:
- The facilities must have high reliability.
- The facilities must be easy to operate.
- Safety of the facilities must be assured.
- Maintenance of the facilities must be easy.
- Environmental and ecological requirements must be fully satisfied.
- Operating costs must be minimal.
- Layout of the facilities must be simple and of good appearance.
- Energy conservation must be considered.
After completion of the value analysis, entries are made in respective data sheets, and drawings
are prepared. Then, the process specifications are issued from the process department. If
necessary, the basic design package must be prepared. Since it is helpful in the following project
engineering, its preparation is recommendable.
[Later]
Case B: In this case, the client prepares a process design package comprising flow sheets,
heat and weight balances and so on. Our view is that this case would be suitable where the
clients' intention can not be fully clarified solely from the design basis or where
modification or finalization of the design basis is required in the process design stage.
Therefore, it is necessary for SECL personnel to be stationed at the client's home office to
participate with the client in the task concerned, from the initial stages of the front end
engineering, to reflect the client's intentions fully in the basic design. SECL has much
experience in this mode of cooperation on jobs performed for major oil companies.
The following are recent cases under this category:
Client Project Completion
[Later]
Case C: Here, the front end engineering is carried out by the clients themselves or by other
engineering companies, and the contractor's task involves only the verification of the front
SPD0006ERN
PROCEDURE MANUAL
REV. : 2
EXECUTION PROCEDURE
DATE : 2013.08.27 PAGE 8 OF 15
[Later]
[Later]
6. DISTRIBUTION OF SPECIFICATIONS
In the case of distribution from process department (PE), documents must be passed through the routes
SPD0006ERN
PROCEDURE MANUAL
REV. : 2
EXECUTION PROCEDURE
DATE : 2013.08.27 PAGE 9 OF 15
Project Division:
After assignment of specification numbers, print copies are distributed and the originals are sent to
the Project Supporting & Administration Division where they are kept in file.
7. FILING SYSTEM
Calculation sheets must be kept in file under the classifications of the categories described in the
Section 1-3 "Basic Design Package".
Since the numbers of calculation sheets are large, it is necessary that calculation sheets should be
prepared in a simple form.
The periods of data storage shall be as shown below.
f. Interoffice
x
correspondence
g. Notes and x
SPD0006ERN
PROCEDURE MANUAL
REV. : 2
EXECUTION PROCEDURE
DATE : 2013.08.27 PAGE 10 OF 15
memorandum
h. Minutes of
x
meetings
i. Letters and
x
telexes
SPD0006ERN
PROCEDURE MANUAL
REV. : 2
EXECUTION PROCEDURE
DATE : 2013.08.27 PAGE 11 OF 15
RECEIVE
RECEIVE
INDEX ISSUE ORIGINAL KEPT IN FILE
PROJECT DIV. EQUIPMENT DESIGN FURNACE DESIGN ELECT. & INSTRU. ROTARY MACHINERY
4.0 EQUIPMENT
6.0 PIPING
RECEIVE
INDEX ISSUE EQUIPMENT FURNACE ELECT. & ROTARY ORIGINAL KEPT IN FILE
PROJECT DIV.
DESIGN DESIGN INSTRU. MACHINERY
7.0 DRAWINGS
WORK CATEGORY
OVERALL PLANT FOR
CONTRACT AWARD ENGINEERING WORK DESIGN BASIS LEGEND : FOR PROCESS
ENGINEERING
ECONOMICAL
STUDY
CONCEPTUAL
DESIGN
PROCESS
CALCULATION &
PROCESS FLOW
DIAGRAM
SAFETY
PROCESS PROCESS CALCULATION
HYDRAULIC CONCEPTUAL PROTECTION &
CALCULATION CALCULATION FOR UTILITY
CALCULATION PLOT PLAN ENVIRONMENTAL
FOR EQUIPMENT FOR INSTRUMENT CONSUMPTION
PROTECTION
PRELIMINARY
P & I DIAGRAM
AND
VALUE ANALYSIS
P & I DIAGRAM
BASIC DESIGN
PACKAGE
DETAIL DESIGN
PROCUREMENT
8. 작성내력
개정번호 개 정 일 자 개정 페이지 개 정 사 유
신규 제정
- 작성부서 : 공정팀
0 98.04.17 전 페이지
- 작성자 : 박종헌 임종은
- 검토자 : 이봉일 조석범 노재철
- 승인자 : 오성국