Highway Engineering
Highway Engineering
College of Engineering
2 | HIGHWAY AND RAILROAD ENGINEERING
PREFACE
The main purpose of this module is to provide the student with a clear and detailed
presentation of the theory and application of Highway and Railroad Engineering. This
course presents the methods and underlying principles for the design and control of
the elements of road and railroad infrastructure. The course will also discuss
transportation system terminology, flow analysis, driver, vehicle and road
characteristics, and aspects of road geometrics, road construction, drainage,
pavements and maintenance.
To achieve this objective despite of this pandemic due to COVID-19, this work has
been shaped by the comments and suggestions of the peer reviewer in the teaching
profession, as well as the other faculty members who will ensure quality of the
modules that will be distributed to the LGU.
1
2 | HIGHWAY ENGINEERING
3.1 Introduction
Geometric design for highways and railways is essential in the specified field
of engineering which is transportation engineering. Geometric designs matters
depending of the locations of both highways and railways. In addition, it is
important to determine the different parameters to determine the appropriate
geometric design for highways and railways. In making a design, it needs to
take in consideration the different aspects of highway and railways such as:
highway drainage, types of alignments, elevations or slope, and earthworks.
3.2 Topics
Design Exemptions
Design Waivers
Design Variances
Design Exemptions
A design exemption is required whenever the criteria for certain
controlling criteria specified for the different categories of construction
projects are not met. The determination of whether a design exemption
exists rest with the district, unless the project is subject to federal
oversight or review. A design exemption is not required when values
exceed the guidelines for the controlling criteria.
Final approval of a roadway design exception must be signed by the
district engineer and this signature authority cannot be delegated. For
flexibility and efficiency in meeting project design schedules, the review
of design exceptions and recommendations for approval/non-approval
may be established individually by each district. For example, a four-
person review committee might be established which includes:
Director of Transportation Planning and Development,
Director of Construction,
Director of Operations/Traffic, and
Area Engineer (not responsible for project management).
The reviews of any three of the four-member committee would
constitute a quorum for recommending signature action. The
complete documentation for a roadway exception should be retained
permanently in the district project files and a copy furnished to the
Design Division. Since the construction plans are sealed, the design
exception documentation does not require an engineer’s seal.
Design Waivers
When the criteria are not met in a non-controlling category, a design
exception is not required. However, variations from the criteria in these
cases will be handled by design waivers at the district level. Design
waivers will be granted as the district authorizes. The complete
documentation should be retained permanently in the district project
files and a copy furnished to the Design Division.
Design Variances
A design variance is required whenever the design guidelines specified
in the Americans with Disabilities Act Accessibility Guidelines (ADAAG) and
the Texas Accessibility Standards are not met. Design variances should
be sent to the Design Division for forwarding to the Texas Department
of Licensing and Regulation for approval.
The need for proper geometric design of a track arises because of the
following considerations:
(a) To ensure the smooth and safe running of trains
(b) To achieve maximum speeds
(c) To carry heavy axle loads
(d) To avoid accidents and derailments due to a defective permanent
way
(e) To ensure that the track requires least maintenance
(f) For good aesthetics
The geometric design of the track deals with various aspects, which are
as follows:
Alignment of Railway track
Curves
Gradients
Gradients
Gradients are provided to negotiate the rise or fall in the level of the
railway track. A rising gradient is one in which the track rises in the
direction of movement of traffic and in a down or falling gradient the
track loses elevation the direction of movement of traffic.
A gradient is normally represented by the distance travelled for a rise
or fall of one unit. Sometimes the gradient is indicated as per cent rise or
fall. For example, if there is a rise of 1 m in 400 m, the gradient is 1 in 400
or 0.25 per cent, as shown in Fig. 12.1.
5
2 | HIGHWAY ENGINEERING
Ruling Gradient
P = W sin 8
= W tan 8 (approximately, as 8 is very small)
= W x gradient
Indian Railways does not specify any fixed ruling gradient owing to
enormous variations in the topography of the country, the traffic plying
on various routes, and the speed and type of locomotive in use on
various sections. Generally, the following ruling gradients are adopted
by Indian Railways when there is only one locomotive pulling the train.
In plain terrain: 1 in 150 to 1 in 250
In hilly terrain: 1 in 100 to 1 in 150
Once a ruling gradient has been specified for a section, all other
gradients provided in that section should be flatter than the ruling
gradient after making due compensation for curvature.
In hilly areas, the rate of rise of the terrain becomes very important when
trying to reduce the length of the railway line and, therefore, sometimes,
gradients steeper than the ruling gradient are provided to reduce the
overall cost. In such situations, one locomotive is not adequate to pull
the entire load, and an extra locomotive is required.
6
2 | HIGHWAY ENGINEERING
Momentum Gradient
The momentum gradient is also steeper than the ruling gradient and can
be overcome by a train because of the momentum it gathers while
running on the section. In valleys, a falling gradient is sometimes
followed by a rising gradient. In such a situation, a train coming down a
falling gradient acquires good speed and momentum, which gives
additional kinetic energy to the train and allows it to negotiate gradients
steeper than the ruling gradient. In sections with momentum gradients
there are no obstacles provided in the form of signals, etc., which may
bring the train to a critical juncture.
The gradients in station yards are quite flat due to the following reasons:
The basic principle for locating highways is that roadway elements such as
curvature and grade must blend with each other to produce a system that
provides for the easy flow of traffic at the design capacity, while meeting design
criteria and safety standards. The highway should also cause a minimal
disruption to historic and archeological sites and to other land-use activities.
Environmental impact studies are therefore required in most cases before a
highway location is finally agreed upon.
The highway location process involves four phases:
• Office study of existing information
• Reconnaissance survey
• Preliminary location survey
• Final location survey
The first phase in any highway location study is the examination of all available
data of the area in which the road is to be constructed. This phase is usually
carried out in the office prior to any field or photogrammetric investigation. All
of the available data are collected and examined. These data can be obtained
from existing engineering reports, maps, aerial photographs, and charts, which
are usually available at one or more of the state’s departments of
transportation, agriculture, geology, hydrology, and mining. The type and
amount of data collected and examined depend on the type of highway being
considered, but in general, data should be obtained on the following
characteristics of the area:
The object of this phase of the study is to identify several feasible routes, each
within a band of a limited width of a few hundred feet. When rural roads are
being considered, there is often little information available on maps or
photographs, and therefore aerial photography is widely used to obtain the
required information. Feasible routes are identified by a stereoscopic
examination of the aerial photographs, taking into consideration factors such
as:
• Terrain and soil conditions
• Serviceability of route to industrial and population areas
• Crossing of other transportation facilities, such as rivers, railroads, and
highways
• Directness of route
During this phase of the study, the positions of the feasible routes are set as
closely as possible by establishing all the control points and determining
preliminary vertical and horizontal alignments for each. Preliminary
alignments are used to evaluate the economic and environmental feasibility of
the alternative routes.
Economic Evaluation
The evaluation methods are used for this decision process. Factors usually
taken into consideration include road user costs, construction costs,
maintenance costs, road user benefits, and any disbenefits, which may include
adverse impacts due to dislocation of families, businesses, and so forth. The
results obtained from the economic evaluation of the feasible routes provide
valuable information to the decision maker. For example, these results will
provide information on the economic resources that will be gained or lost if a
particular location is selected. This information is also used to aid the policy
maker in determining whether the highway should be built, and if so, what
type of highway it should be.
Environmental Evaluation
The final location survey is a detailed layout of the selected route. The
horizontal and vertical alignments are determined, and the positions of
structures and drainage channels are located. The method used is to set out the
points of intersections (PI) of the straight portions of the highway and fit a
suitable horizontal curve between these. This is usually a trial-and-error
process until, in the designer’s opinion, the best alignment is obtained, taking
both engineering and aesthetic factors into consideration.
The location process of recreational and scenic routes follows the same steps as
discussed earlier, but the designer of these types of roads must be aware of
their primary purpose. Three additional factors should be considered in the
location of recreational and scenic routes:
1. Design speeds are usually low, and therefore special provisions should
be made to discourage fast driving, for example, by providing a
narrower lane width.
2. Location should be such that the conflict between the driver’s attention
on the road and the need to enjoy the scenic view is minimized. This can
be achieved by providing turn-outs with wide shoulders and adequate
10
2 | HIGHWAY ENGINEERING
The basic principle for locating highway bridges is that the highway location
should determine the bridge location, not the reverse. When the bridge is
located first, in most cases the resulting highway alignment is not the best. The
general procedure for most highways, therefore, is to first determine the best
highway location and then determine the bridge site. In some cases, this will
result in skewed bridges, which are more expensive to construct, or in locations
where foundation problems exist.
• Ground surveys
• Remote sensing
• Computer graphics
3.2.4.1 Drainage
cuts and fill, should likewise be avoided for it will contribute to the
problems of erosion.
l. Hydraulic design that deals with estimating the highest rate of run-off
to be handled.
2. Hydraulic Design deals with the selection of the kinds and sizes
of the drainage facilities that is most economical to accommodate the
estimated water flow.
3. Erosion Control is to ascertain the design will not create erosion
or other unacceptable environmental conditions.
3.2.4.2 Hydrology
that differ in sizes and length including the flow characteristics from the
previous one.
2. Construction operations may disturb the ground cover, and
loosen the soil creating muddy stream as a result of erosion.
3. Erosions create debris that are carried downstream, and
deposited at points where the velocity slackens. Record shows that,
almost every drainage installation disturbed the ecological balance of
nature.
4. Any changes in the land use may alter the historical runoff or
ungauged rural water shed that could be disastrous on wide scale basis.
For instance, if the drainage loss from any flood exceeding the design
flow is P200,000 and according to hydraulic computations such floods
will occur once in every 5 years, then the annual loss of flood damage is
P200,000 divided by 5 years or P40,000 per year.
1. Water flowing across the roadway down the road slope must be
thin enough in a sheet form like so that the erosion on the shoulder will
be minimized.
2. Unprotected slope could be badly washed out if irregularity in
the pavement or shoulder accumulates water into small streams.
Another point of water accumulation that endangers the shoulder is the
low portion of sagged vertical curves.
3. One way of preventing washout of the side slope is to retain the
water at the outer edge of the shoulder.
4. A crown ditch or intercepting channel maybe employed at the top
of the cut slope. This will prevent erosion of the cut slope by surface
runoff from the hillside above.
5. The surface should not be disturbed in any manner where the
natural ground is already covered with grass or other ground cover.
6. The channel or canal should be formed making the original
ground as its bed and a small dike of topsoil or imported materials to
serve as its bank.
7. Scouring must be controlled. If possible, the water flow must be
limited to a safer amount by diverting the flow at intervals. Water should
be dropped down to the road side ditch by means of specially designed
conduit or channels.
Manhole, inlets and catch basins are classified under Item 502 of the
DPWP standard specifications which includes construction,
reconstruction or adjustment of manholes inlets and catch basin. Read
from the manual.
AASHTO defines design speed as “the maximum safe speed that can be
maintained over a specified section of highway when conditions are so
favorable that the design features of the highway govern”.
• Curve radius
• Super elevations
• Side Friction
• Assumed Vehicle Speed
Roadway drainage determines the minimum rate of cross slope for the
traveled way. Acceptable minimum cross slope values range from 1.5 to
2.0 percent (with 2.0 typically used for paved, uncurbed pavements)
depending on the roadway type and weather conditions.
Controls for Maximum Superelevation:
The minimum radius for horizontal curves is a limiting value for design
speeds based on the maximum superelevation and maximum side
friction factor. Actual design values were developed from the laws of
mechanics and depend on practical limits and factors that were
determined empirically. Sharper radii would require superelevation
above the limits for comfortable operation. The minimum radius values
maintain a margin of safety against vehicle rollover and skidding. The
“basic curve equation” governs vehicle operation on a horizontal curve.
3.2.5.6 Grades
When a vehicle takes a curve, external forces act on the front wheels of the
vehicle. These forces have components that retard the forward motion of the
vehicle. This resistance depends on the radius of curvature and the speed of the
vehicle. This curve resistance can give as:
1000 2
(3600 𝑣) 𝑚
𝑅𝑐 = 0.5
𝑅
Where:
Rc – Curve Resistance
Radius of Curvature
Centrifugal Force
The minimum radius of circular curve (R) for a vehicle travelling at kph can
be found by considering the equilibrium of a vehicle with respect to moving
up or down the incline. Let alpha (a) be the angle of incline, the components
of weight down the incline is W*sin (a), the frictional force acting down the
incline is W*f*cos (a). The Centrifugal force, Fc is,
𝑊𝑎𝑐
𝐹𝑐 =
𝑔
Where:
W – weight of the vehicle
Equilibrium of forces
When the vehicle is in equilibrium with respect to the incline, the forces may
be equated as follows:
𝑚𝑣 2 𝑊𝑣 2
=
𝑅 𝑔𝑅
𝑊 𝑠𝑖𝑛 𝑎 + 𝑊𝑓𝑠 𝑐𝑜𝑠 𝑎 = 0
Where:
fs – coefficient of side friction
3.2.6 Earthworks
The final element in the location process is to establish the horizontal and
vertical alignments of the highway project and to prepare highway plans and
specifications for estimating project costs and preparation of bids by
contractors. The following sections explain how the terrain influences the cost
to transport earthen materials that will be used to construct the roadbed and
25
2 | HIGHWAY ENGINEERING
how to estimate payment. The final result of the location process is a highway
plan used in estimating quantities and computing the overall project cost.
These cross sections are obtained by plotting the natural ground levels and
proposed grade profile of the highway along a line perpendicular to the grade
line to indicate areas of excavation and areas of fill. Figure 14.16 shows three
types of cross sections.
𝐿
𝑉= ( 𝐴 + 𝐴2 )
54 1
Where:
V – volume (yd3)
3.3 ASSESSMENT
SCORE
Name: __________________________________Year & Section: _________________
Instructor: ______________________________ Date Finished: __________________
General Instructions: Answer all the items of this assessment by following the set of guidelines
indicated for each item. Use another sheet/s of paper for your answer. Avoid erasures. Do not
mutilate this paper.
Direction: Answer the following questions given below. For problems that needs solution, you
are required to indicate the solution. Problems are 5 pts each.
Evaluation Criteria: Cleanliness – 10%; Timeliness – 10%; Content – 80%
1. The highway is classified into two categories in terms of the service provided by the roadway and
roadway systems. This are the Accessibility and Mobility. Define and describe each classification.
(2 pts each.)
2. There are six distinct travel movements that may be present in a typical trip. Namely as the
following: Describe each of the travel movement. (2 pts each.)
• Main movement
• Transition
• Distribution
• Collection
• Access
• Termination
3. The three main elements that define the geometry of a highway section are Horizontal Alignment,
Vertical Alignment and Cross-sectional Alignment. Describe each element. (2 pts each.)
4. The cross section includes the following features: Discuss each feature of the cross section. (2 pts each.)
• Travel Lanes
• Shoulders
• Side Slopes
• Curbs
• Median and Median Barriers
• Guardrails
• Drainage Channel
5. The point of intersection (P.I.) of two tangent lines is Station 11,500+66. The radius
of curvature is 1,000 feet, and the angle of deflection is 60˚. Find the length of the
curve, stations for the P.C. and P.T., and all other relevant characteristics of the
curve (LC, M, E).
6. A 3.5˚ curve is to be designed on a highway with a design speed of 60 mi/h. Spiral
transition curves are to be used. Determine the length of the spiral and the
appropriate stations for the T.S., S.C., and S.T. The angle of deflection for the
original tangents is 40˚, and the P.I. is at station 15,100+26. The segment consists of
two 12-ft lanes.
28
2 | HIGHWAY ENGINEERING
7. A 5˚ curve (measured at the centerline of the inside lane) is being designed for a
highway with a design speed of 65 mi/h. The curve is on a 2% upgrade, and driver
reaction time may be taken as 2.5 seconds. What is the closest any roadside object
may be placed to the centerline of the inside lane of the roadway while maintaining
adequate stopping sight distance?
8. What is the appropriate superelevation rate for a curve with a 1,200-ft radius on
highway with a design speed of 60 mi/h? The maximum design superelevation is
6% for this highway.
10. Find the maximum allowable grade and critical length of grade for each of the
following facilities: a) A rural freeway in mountainous terrain with a design speed
of 60 mi/h b) A rural arterial in rolling terrain with a design speed of 45 mi/h c)
An urban arterial in level terrain with a design speed of 40 mi/h
11. A vertical curve of 1,000-ft is designed to connect a grade of +4% to a grade of -5%.
The V.P.I, is located at station 1,500 + 55 and has a known elevation of 500 ft. Find
the following:
a) The station of the V.P.C. and the V.P.T.
b) The elevation of the VP.C. and the VPT:
c) The elevation of points along the vertical curve at 100-ft intervals
d) "The location and elevation of the high point on the curve
12. Find the minimum length of curve for the following scenarios.
13. A vertical curve is to be designed to connect a -4% grade to a +1% grade on a facility
with a design speed of 70 mi/h. For economic reasons, a minimum-length curve
will be provided. A driver-reaction time of 2.5 seconds may be used in sight
distance determinations. The V.P.I. of the curve is at station 5,100 + 22 and has an
elevation of 1,285 ft. find the station and elevation of the V.P.C. and V.P.T., the high
point of the curve, and at 100-ft intervals along the curve.
3.4 References:
3.5 Acknowledgement
The images, tables, figures and information contained in this module were taken from
the references cited above.
30
2 | HIGHWAY ENGINEERING
4.1 Introduction
4.2 Topics
1. Drivers Characteristics
a. Visual Reception
The ability of the human eye to differentiate between objects is
fundamental to this phenomenon. The principal characteristics of
31
2 | HIGHWAY ENGINEERING
the eye are visual acuity, peripheral vision, color vision, glare
vision and recovery, and depth perception.
b. Hearing Perception
The ear receives sound stimuli, which is important to drivers only
when warning sounds, usually given out by emergency vehicles,
are to be detected. Loss of some hearing ability is not a serious
problem, since it normally can be corrected by a hearing aid.
Solution:
2. Pedestrian characteristics
While the force of gravity pulls the vehicle down, the force
of friction resists that movement. The forces acting this
vehicle can be simplified to:
𝐹 = 𝑤 (sin 𝜃 − 𝑓𝑐𝑜𝑠 𝜃)
Where:
𝑊 = 𝑚𝑔 = 𝑜𝑏𝑗𝑒𝑐𝑡𝑠 𝑤𝑒𝑖𝑔ℎ𝑡
𝑓 = 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑜𝑓 𝑓𝑟𝑖𝑐𝑡𝑖𝑜𝑛
𝑎 = 𝑔(sin 𝜃 − 𝑓 cos 𝜃)
𝑣𝑖 2 − 𝑣𝑒 2
𝑑𝑏 =
2𝑔(𝑓 cos 𝜃 − sin 𝜃 )
𝑣𝑖 2 − 𝑣𝑒 2
𝑑𝑏 =
2𝑔(𝑓 ± 𝐺)
𝑑𝑟 = 𝑣𝑡𝑟
𝒅𝒔 = 𝒅 𝒓 + 𝒅𝒃
(𝟎. 𝟐𝟕𝟖𝒗𝒊 )𝟐
𝒅𝒔 = 𝟎. 𝟐𝟕𝟖𝒕𝒓 𝒗𝒊 +
𝟏𝟗. 𝟔(𝒇 ± 𝑮)
𝑎𝑡1
𝑑1 = 1000𝑡1 (𝑢 − 𝑚 + )
2
Where:
𝑡1 = 𝑡𝑖𝑚𝑒 𝑓𝑜𝑟 𝑖𝑛𝑖𝑡𝑖𝑎𝑙 𝑚𝑎𝑛𝑒𝑢𝑣𝑒𝑟
𝑎 = 𝑎𝑐𝑐𝑒𝑙𝑒𝑟𝑎𝑡𝑖𝑜𝑛 (𝑘𝑚/ℎ𝑟/𝑠𝑒𝑐)
𝑢 = 𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑠𝑝𝑒𝑒𝑑 𝑜𝑓 𝑝𝑎𝑠𝑠𝑖𝑛𝑔 𝑣𝑒ℎ𝑖𝑐𝑙𝑒 (𝑘𝑚/ℎ𝑟)
𝑚 = 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 𝑖𝑛 𝑠𝑝𝑒𝑒𝑑𝑠 𝑜𝑓 𝑝𝑎𝑠𝑠𝑖𝑛𝑔
𝑎𝑛𝑑 𝑖𝑚𝑝𝑒𝑛𝑑𝑒𝑟 𝑣𝑒ℎ𝑖𝑐𝑙𝑒𝑠 (𝑘𝑚/ℎ𝑟)
𝑑2 = 1000𝑢𝑡2
Where:
𝑡2 = 𝑡𝑖𝑚𝑒 𝑝𝑎𝑠𝑠𝑖𝑛𝑔 𝑣𝑒ℎ𝑖𝑐𝑙𝑒 𝑖𝑠 𝑡𝑟𝑎𝑣𝑒𝑙𝑙𝑖𝑛𝑔 𝑖𝑛 𝑜𝑝𝑝𝑜𝑠𝑖𝑛𝑔 𝑙𝑎𝑛𝑒
𝑢 = 𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑠𝑝𝑒𝑒𝑑 𝑜𝑓 𝑝𝑎𝑠𝑠𝑖𝑛𝑔 𝑣𝑒ℎ𝑖𝑐𝑙𝑒 (𝑘𝑚/ℎ𝑟)
𝒅𝒑 = 𝒅𝟏 + 𝒅𝟐 + 𝒅𝟑
37
2 | HIGHWAY ENGINEERING
Solution:
1000 2
(66𝑥 3600) − 02
𝑑𝑏 = = 𝟔𝟑. 𝟓𝒎
2(9.8)(0.3 − 0.03)
1000 2
(150𝑥 3600) − 02
𝑑𝑏 = = 200𝑚
2(9.8)(𝑓 − 0.03)
1000 2
(150𝑥 3600) − 02
= (𝑓 − 0.03)
2(9.8)(200)
𝒇 = 𝟎. 𝟒𝟕
c. You are shown a crash scene with a vehicle and a light pole. The vehicle was estimated to
hit the light pole at 50 km/hr. The skid marks are measured to be 210, 205, 190, and 195 meters. A
trial run that is conducted to help measure the coefficient of friction reveals that a car traveling at
60 km/hr. can stop in 100 meters under conditions present at the time of the accident. How fast
was the vehicle traveling to begin with?
Solution:
(210+205+190+195)/4=200 m
1000 2 1000 2
(𝑣 x ) − (50 x )
3600 3600 = 200
𝑑𝑏 =
2(9.8)(0.14 − 0)
𝑣 = 98 𝑘𝑚/ℎ𝑟
38
2 | HIGHWAY ENGINEERING
∑ 𝑓𝑖 𝑢𝑖
𝑢̅ =
∑ 𝑓𝑖
Where:
𝑢 = 𝑎𝑟𝑖𝑡ℎ𝑚𝑒𝑡𝑖𝑐 𝑚𝑒𝑎𝑛
𝑓𝑖 = 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑏𝑠𝑒𝑟𝑣𝑎𝑡𝑖𝑜𝑛𝑠 𝑖𝑛 𝑒𝑎𝑐ℎ 𝑠𝑝𝑒𝑒𝑑 𝑔𝑟𝑜𝑢𝑝
𝑢𝑖 = 𝑚𝑖𝑑𝑣𝑎𝑙𝑢𝑒 𝑓𝑜𝑟 𝑡ℎ𝑒 𝑖𝑡ℎ 𝑠𝑝𝑒𝑒𝑑 𝑔𝑟𝑜𝑢𝑝
𝑁 = 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑏𝑠𝑒𝑟𝑣𝑒𝑑 𝑣𝑎𝑙𝑢𝑒𝑠
39
2 | HIGHWAY ENGINEERING
Where:
𝑢𝑖 = 𝑚𝑖𝑑𝑣𝑎𝑙𝑢𝑒 𝑜𝑓 𝑠𝑝𝑒𝑒𝑑 𝑐𝑙𝑎𝑠𝑠 𝑖
𝑓𝑖 = 𝑓𝑟𝑒𝑞𝑢𝑒𝑛𝑐𝑦 𝑜𝑓 𝑠𝑝𝑒𝑒𝑑 𝑐𝑙𝑎𝑠𝑠 𝑖
𝑆𝑑
Where:
𝑛1 = 𝑠𝑎𝑚𝑝𝑙𝑒 𝑠𝑖𝑧𝑒 𝑓𝑜𝑟 𝑡ℎ𝑒 𝑠𝑡𝑢𝑑𝑦 1
𝑛2 = 𝑠𝑎𝑚𝑝𝑙𝑒 𝑠𝑖𝑧𝑒 𝑓𝑜𝑟 𝑡ℎ𝑒 𝑠𝑡𝑢𝑑𝑦 2
𝑆𝑑 = 𝑠𝑞𝑢𝑎𝑟𝑒 𝑟𝑜𝑜𝑡 𝑜𝑓 𝑡ℎ𝑒 𝑣𝑎𝑟𝑖𝑎𝑛𝑐𝑒 𝑖𝑛 𝑡ℎ𝑒
𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 𝑖𝑛 𝑚𝑒𝑎𝑛𝑠
𝑆12 = 𝑣𝑎𝑟𝑖𝑎𝑛𝑐𝑒 𝑎𝑏𝑜𝑢𝑡 𝑡ℎ𝑒 𝑚𝑒𝑎𝑛 𝑓𝑜𝑟 𝑠𝑡𝑢𝑑𝑦 1
𝑆22 = 𝑣𝑎𝑟𝑖𝑎𝑛𝑐𝑒 𝑎𝑏𝑜𝑢𝑡 𝑡ℎ𝑒 𝑚𝑒𝑎𝑛 𝑓𝑜𝑟 𝑠𝑡𝑢𝑑𝑦 1
2
𝑡 2 𝛼/2,𝑁−1 (𝑆 ⁄ 2 )
𝑛= 𝑑
2
1 + (1/𝑁)(𝑡 𝛼/2,𝑁−1 ) (𝑆 ⁄𝑑 2 )
2
Where:
n = minimum number of count locations required
t = value of the student’s t distribution with (1 − 𝛼⁄2)
confidence level (N − 1) degrees of freedom)
N = total number of links (population)from which a
sample is to be selected
α = significance level
S = estimate of the spatial standard deviation of the
link volumes
d = allowable range of error
43
2 | HIGHWAY ENGINEERING
𝐴𝐴𝐷𝑇
𝑀𝐸𝐹 =
𝐴𝐴𝐷𝑇 𝑓𝑜𝑟 𝑎 𝑝𝑎𝑟𝑡𝑖𝑐𝑢𝑙𝑎𝑟 𝑚𝑜𝑛𝑡ℎ
44
2 | HIGHWAY ENGINEERING
The AADT for a given year may be obtained from the ADT
for a given month by multiplying this volume by the MEF.
But it is more probable that the test car will not be traveling
at the average speed, thus the second term in the equation
is provided to correct for the difference between the
number of vehicles that overtake the test car and the
number of vehicles that are overtaken by the test car.
𝐷 = ∑(𝑛𝑖 𝑡1 )
𝑖=1
Where:
𝐷 = 𝑠𝑝𝑎𝑐𝑒 𝑣𝑒ℎ𝑖𝑐𝑙𝑒 − ℎ𝑜𝑢𝑟𝑠 𝑑𝑒𝑚𝑎𝑛𝑑 𝑓𝑜𝑟 𝑎 𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑝𝑒𝑟𝑖𝑜𝑑
𝑜𝑓 𝑡𝑖𝑚𝑒
𝑁 = 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑐𝑙𝑎𝑠𝑠𝑒𝑠 𝑜𝑓 𝑝𝑎𝑟𝑘𝑖𝑛𝑔 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛 𝑟𝑎𝑛𝑔𝑒𝑠
𝑡𝑖 = 𝑚𝑖𝑑𝑝𝑎𝑟𝑘𝑖𝑛𝑔 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝑡ℎ𝑒 𝑖𝑡ℎ 𝑐𝑙𝑎𝑠𝑠
𝑛𝑖 = 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑣𝑒ℎ𝑖𝑐𝑙𝑒𝑠 𝑝𝑎𝑟𝑘𝑒𝑑 𝑓𝑜𝑟 𝑡ℎ𝑒 𝑖𝑡ℎ 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛 𝑟𝑎𝑛𝑔𝑒
𝑆 = 𝑓 ∑(𝑡1 )
𝑖=1
51
2 | HIGHWAY ENGINEERING
where:
𝑆 = 𝑝𝑟𝑎𝑐𝑡𝑖𝑐𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑠𝑝𝑎𝑐𝑒 − ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑠𝑢𝑝𝑝𝑙𝑦
𝑓𝑜𝑟 𝑎 𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑝𝑒𝑟𝑖𝑜𝑑 𝑜𝑓 𝑡𝑖𝑚𝑒
𝑁 = 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑝𝑎𝑟𝑘𝑖𝑛𝑔 𝑠𝑝𝑎𝑐𝑒𝑠 𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒
𝑡𝑖 = 𝑡𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡𝑖𝑚𝑒 𝑖𝑛 ℎ𝑜𝑢𝑟𝑠 𝑤ℎ𝑒𝑛 𝑡ℎ𝑒 𝑖𝑡ℎ 𝑠𝑝𝑎𝑐𝑒
𝑐𝑎𝑛 𝑏𝑒 𝑙𝑒𝑔𝑎𝑙𝑙𝑦 𝑝𝑎𝑟𝑘𝑒𝑑 𝑜𝑛 𝑑𝑢𝑟𝑖𝑛𝑔 𝑡ℎ𝑒 𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑝𝑒𝑟𝑖𝑜𝑑
𝑓 = 𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 𝑓𝑎𝑐𝑡𝑜𝑟
1. Basic Capacity:
Basic capacity is the maximum number of vehicles that can pass a
given point on a lane or a roadway during one hour, under the ideal
roadway and traffic conditions that can possibly be attained.
2. Possible Capacity:
Possible capacity is the maximum number of vehicles that can pass a
given point on a lane or roadway during one hour, under the prevailing
roadway and traffic conditions.
3. Practical Capacity:
Practical capacity is the maximum number of vehicles that can pass a
given point in a lane or roadway during one hour, when traffic density
is not so great as to cause unreasonable delay, hazard or restriction to
the driver’s freedom to maneuver under prevailing roadway and traffic
conditions. This is usually considered to be the ‘design capacity’.
The ‘basic capacity’ of the original Highway Manual (1950) has been
replaced with ‘capacity under ideal conditions’. The original ‘practical
capacity’ has been replaced by several ‘service volumes’ related to a
group of desirable operating conditions collectively termed as ‘level of
service’.
100 𝑉
𝐶=
𝑆
Where:
C = Capacity Volume (vehicles/h/lane)
V = Speed (km/hr.)
S = Average spacing of moving vehicles or space headway (meters)
53
2 | HIGHWAY ENGINEERING
The factors affecting capacity and level of service fall under two heads:
The latest IRC recommendations for design service volumes are given
below:
55
2 | HIGHWAY ENGINEERING
For four-lane divided roads, the design service volumes range from
47,000 to 1, 05,000 PCU/day depending upon the terrain, shoulder
type and the level of service (B or C).
(These are for no frontage access, no standing vehicles, and very little
cross traffic; for other restrictive conditions, the capacity values will be
reduced significantly.)
The mass of the traffic laws, rules and regulations have their source in
laws, Presidential Decrees (P.D.’s), Executive Orders (E.O.’s), Letters of
Instructions (L.O.I’s), Administrative Orders and Implementing
56
2 | HIGHWAY ENGINEERING
Republic Acts
Presidential Decrees
• P.D No. 96. Regulating the use of sirens, bells, horns, etc., by
prohibiting the attachment of any siren, horn bell, etc. on motor
vehicles which produce unusual or startling sounds as well as
blinkers and other similar devices unless the vehicle belongs to
the AFP, NBI, LTO, PNP, BJMP, hospitals and Fire Departments
and are specifically intended for use in emergencies.
• P.D No. 101. Expediting the methods of prescribing, redefining or
modifying the lines and modes of operations of public utility
motor vehicles in the Philippines.
• P.D No. 207. Declaring as part of the laws of the Philippines the
Vienna Convention on Road Traffic, Signs and Signals.
• P.D No.612. Requiring compulsory insurance for all types of
vehicles against third party liability as an additional pre-requisite
for registration by the LTO.
• P.D 1686. Imposing a tax on every motor vehicle equipped with
air conditioner.
57
2 | HIGHWAY ENGINEERING
• P.D 1181. Providing for the abatement of air pollution from motor
vehicles and for other purposes.
• P.D 1605. Granting the Metropolitan Manila Commission certain
powers related to traffic management and control in
Metropolitan Manila providing penalties, and for other purposes.
• P.D 98. Regulating the insurance of license plates of all motor
vehicles. P.D 109. Modifying P.D 98.
• P.D 1729. Authorizing the Bureau of Land Transportation to
dispose of impounded motor vehicles unclaimed by owners for a
certain period of time.
• P.D 1730. Declaring the syndicated printing, manufacture,
distribution, possession or use of fake official Bureau of Land
Transportation forms, documents, plates and stickers as offenses
involving economic sabotage
Letter of Instructions
Department Orders
Memorandum Circular
vehicles the authorized fare matrix for the specific route granted
them to avoid conflict.
• M.C. 93-011. Enjoining all public utility operators to use garage
instead of public places or side streets in parking their vehicles.
• M.C 94-002. Sanctions on operators arising from the violations of
their drivers.
• M.C. 94-209. Clarificatory guidelines for the
registration/operation of new private vehicles particularly in the
use of conduction sticker.
Executive Orders
• Batas Pambansa Blg. 344 (B.P. 344). Act to enhance the mobility
of disabled persons by requiring certain buildings, institutions,
establishments and public utilities to install facilities and other
devices. Memorandum Unnumbered Dated July 13, 1992. Early
Warning Device (EWD) not a requirement for registration.
• SC Bars Lawmen from Removing Car Plates (187 SCRA 432).
At the broadest level, road traffic control includes the layout of streets to
serve a variety of travel needs in a region. Highways or expressways
carry through traffic at high speed; arterial streets carry traffic within
and across urban areas; and local streets provide low-speed travel but
access to many local destinations. The hierarchy of streets that perform
at different levels of speed and provide different levels of access form
the foundation upon which traffic control problems evolve. Long delays
and frequent accidents are common outcomes of inadequate road
planning, which results in an insufficient number of roads to meet travel
needs. While traffic control may help, it is not a substitute for adequate
provision of transportation supply.
60
2 | HIGHWAY ENGINEERING
4.2.3.2.1 History
traffic and between pedestrians and turning vehicles. At the same time,
it is necessary to provide for the smooth flow of traffic across the
intersection. The design should therefore incorporate the operating
characteristics of both vehicles and pedestrians using the intersection.
For example, the corner radius of an intersection pavement or surfacing
should not be less than either the turning radius of the design vehicle or
the radius required for design velocity of the turning roadway under
consideration. The design should also ensure adequate pavement
widths of turning roadways and approach sight distances. This suggests
that at-grade intersections should not be located at or just beyond sharp
crest vertical curves or at sharp horizontal curves.
• The assurance that the sight distances are adequate for the type
of control at the intersection.
more judgement time and second, in case of an impact the total relative
energy to be absorbed are less and hence, the damage is less. In addition,
when relative speed is low, the average motorist will accept a smaller
time gap space between successive vehicles to complete his move. This
condition increases roadway capacity.
• Underpass
• Overpass
• Trumpet Interchange
• Diamond Interchange
• Cloverleaf Interchange
• Partial Cloverleaf Interchange
• Directional Interchange
• Bridged Rotary
Design Components:
1. Acceleration Lane
An acceleration lane is defined as extra pavement, of constant or variable
width, placed parallel or nearly so, to a merging maneuver area to
encourage merging at low relative speed. The major difference in
opinion concerning acceleration design stems from lack of information
on driver performance. Field observations have indicated that drivers
desire to follow the direct path even though extra width or tapered
section is provided. The length of acceleration lanes is determined by
two factors: (1) Time required for drivers to accelerate to the speed of the
preferential flow from the speed of entry into the acceleration lane and
(2) Maneuvering time required as a supplement to the sight distance
which is provided in advance of the acceleration lane. Taper distances
are based upon a lateral transition time of about 1/3 sec/ft of
displacement.
65
2 | HIGHWAY ENGINEERING
2. Deceleration Lane
4.3 ASSESSMENT
SCORE
Name: __________________________________Year & Section: _________________
Instructor: ______________________________ Date Finished: __________________
General Instructions: Answer all the items of this assessment by following the set of
guidelines indicated for each item. Use another sheet/s of paper for your answer. Avoid
erasures. Do not mutilate this paper.
5. Data collected at a parking lot indicate that a total of 300 cars park between 8 a.m.
and 6 p.m. 10% of these cars are parked for an average of 2 hr., 30% for an average
of 4 hr., and the remaining cars are parked for an average of 10 hr. Determine the
space hours of demand at the lot. 8 pts
6. Define the following terms and cite examples of how they are used. 3pts each
68
2 | HIGHWAY ENGINEERING
8. Choose at least two traffic operation regulation and describe each by your own
words. 10 pts
4.4 References:
Maricar Lavayna (July 7, 2015). Traffic Rules, Laws and Regulation. SlideShare.
https://www.slideshare.net/akingmister/traffic-laws-rules-and-regulations-and
Prof. Tom V. Mathew (Jan 10, 2019). Grade Separated Intersection (Lecture Notes in
Transportation Systems Engineering.
https://www.civil.iitb.ac.in/tvm/nptel/567_Grade/web/web.html
Nicholas J. Garber, Lester A. Hoel (2009). Traffic & Highway Engineering, Fourth Edition.
Cengage Learning.
http://civilcafe.weebly.com/uploads/2/8/9/8/28985467/traffic_and_highway_en
gineering_4th_edition.pdf
4.5 Acknowledgement
The images, tables, figures and information contained in this module were taken from
the references cited above.
70
2 | HIGHWAY ENGINEERING
70
2 | HIGHWAY AND RAILROAD ENGINEERING
6700