A Comprehensive Approach To Integrity of Non-Piggable Pipelines Based On Combined DCVG/CIPS/MTM Survey
A Comprehensive Approach To Integrity of Non-Piggable Pipelines Based On Combined DCVG/CIPS/MTM Survey
Abstract
Widely applicable aboveground survey techniques such as DCVG and CIPS alone,
targeted at evaluation of pipeline coating integrity and CP effectiveness, do not
entirely determine the integrity of non-piggable pipelines. Furthermore, these
methods have limitation – they are not intrinsically sensitive to coating disbondment,
which is considered as one of the significant threats to integrity.
In the meantime, over the last years Magnetic Tomography Method went through
extensive industrial validation. Based on the converse magnetostrictive effect, MTM
defines stress characteristics of pipe sections by registering changes in the magnetic
field of the pipeline. But MTM results in low accuracy for detecting pipe features with
stress level less than 5% of the SMYS (e.g., pitting corrosion).
1 Introduction
The length of Russian gas transmission system (GTS) equals more than 164,7
thousand km [1] where large-diameter pipelines make more than half of it (1020-1420
mm) [2]. Most of the existing system can be characterized by high degree of
equipment and infrastructure wear (e.g. by 2015 the average age of gas pipelines will
exceed 30 years). Stress corrosion cracking, external corrosion, corrosion under
insulation and inadequate levels of cathodic protection are the main threats for
integrity of pipelines in Gazprom. These threats in many ways can be mitigated by
implementation of in-line inspection (ILI) technologies.
Pipeline Technology Conference 2015
However, due to diverse causes ILI cannot be applied for 47% of pipelines. In
addition, for half of those pipelines to run ILI is not economically reasonable (figure
1). These pipelines are primarily branch pipelines, as well as part of transmission
pipelines, which were commissioned more than 30 years ago. These assets have
significant value, since they deliver gas to industrial consumers and population. Thus,
integrity management of non-piggable pipelines up to now remains as an essential
challenge for all Operators, including Gazprom.
36 234 km
22%
87 291 km
53%
Piggable
To run ILI is
unreasonable
To run ILI
41 175 km reconstruction is
25% needed
2 DCVG/CIPS Survey
According to [5] the DCVG signal strength should be adequate to enable the
surveyor to detect small indications distant from the CP current source. Typical
DCVG signal magnitudes measured to remote earth range between 100 and 1,500
mV in soil environments. In DCVG, CP interrupting cycle is set in accordance with
manufacturer’s or operator’s procedures and typically is 0,7 sec ON and 0,3 sec
OFF.
Indication pipe to remote earth DCVG signal magnitudes (P/RE) are calculated using
equation (1):
d x ⋅ ( S1 − S2 )
P / RE = S1 + , (1)
d 2 − d1
Where: P/RE - pipe to remote earth DCVG signal magnitude (mV); S1 - DCVG signal
amplitude to remote earth at Test Station 1 (mV); S2 - DCVG signal amplitude to
remote earth at Test Station 2 (mV); d1 - distance measurement of Test Station 1
(This is zero at the beginning of a survey.) (m); d2 - distance measurement of Test
Station 2 (m); dx - distance measurement of indication from Test Station 1 (m).
Pipeline Technology Conference 2015
Once an indication is located, its severity index (%IR) is estimated by measuring the
potential difference from the indication epicenter to remote earth (OL/RE). This
potential difference is then expressed as a percentage of the total calculated
potential shift on the pipeline at the indication location (P/RE), as shown in equation
(2):
OL / RE ⋅100
% IR = , (2)
P / RE
The following classification of the defects by the severity index was adopted:
Category 1 – the defects with %IR above 35% needed to be repaired;
Category 2 – the defects with %IR in range between 16 and 35% should be
taken into consideration as possibly deserving repair;
Category 3 – the defects with %IR under 15% are small and they do not need
to be repaired.
To add value to the data collected during DCVG survey, attempts have been made to
combine coating-fault location with CP pipe-to-soil potential measurements in
DCVG/CIPS hybrid technique. The close interval potential survey (CIPS) alone is not
classified as a coating assessment tool and rather is a cathodic protection system
assessment tool, but data from CIPS is used in coating condition assessments.
Modern digital data loggers allows to run DCVG and CIPS survey simultaneously
during one pass along the pipeline route, as well as to detect defects/holidays in the
pipeline coating and, most importantly, to measure the “ON” and “OFF” potentials
along pipeline with step approximately 1 m, and at all defects epicentres. Thus, in
addition hybrid DCVG/CIPS survey allows to determine whether the exposed pipeline
wall is effectively protected by CP system.
However, by today in Russia this method has not been widely implemented due to
misthought that DCVG is not efficient for the multiline gas transmission systems.
For the confirmation of DCVG method performance on the multiline gas transmission
systems, during the period between August 4th-15th, 2014 AMT organized a
demonstration DCVG/CIPS survey on “Gazprom transgaz S. Petersburg”
(Gazprom''s gas transmission subsidiary) pipelines. To participate in the project were
invited three companies such as:
Pipeline Technology Conference 2015
Notwithstanding that, both survey teams demonstrated one and the same method,
implemented measurement schemes were distinguished and reflected the specificity
of the equipment which was used by both teams. Figure one shows technological
scheme used by Survey Team #1 and Survey Team #2.
b)
Along with Gazprom VNIIGAZ excavation program was developed to validate the
results of each team. Unfortunately, considering series of restrictions from the
Operator’s side (pipeline is located on the border with Republic of Belarus and
exports gas directly to Western Europe countries, thus gas transport interruption is
not encouraged) there were only 4 excavations executed. Excavation results
demonstrated on figure 3 validated the presence of coating defects, qualitative
parameters (%IR) and position against the centerline as described in reports of both
companies (Geoinvirex and Corrstop). Consequently, it became obvious for Gazprom
that DCVG technique could be effectively applied for surveying multiline gas
pipelines with extensive CP system.
Figure 3: Transmission pipeline excavation results: def. #11, diam. 120 mm (a);
def. #82, 100х90 mm (b); def. #5/8, 1200х600 mm (c)
a) b)
c)
Pipeline Technology Conference 2015
Regardless of successful results of the pilot project, DCVG and DCVG/CIPS hybrid
techniques have number of limitations among which low sensitivity to coating
disbondment, which is considered as one of the significant threats to integrity of
pipelines, operated by Gazprom. In fact, gas pipelines with tape coating make 70-
80% of total length and 95% of large diameter pipelines. Lifetime of such coating
lasts only 8-12 years and most of operating pipelines exceed this age.
3 MTM Survey
Magnetic Tomography Method (MTM) was developed in early 2000s and is patented
in Russia, Malaysia, USA, and Canada. MTM is based on the inverse
magnetostrictive effect (Villari effect) - the change of the magnetic susceptibility of a
material when subjected to a mechanical stress. Method uses “natural”
magnetization of the ferrous pipes by magnetic field of the Earth.
MTM does not measure the dimensions of geometric defects alone but instead it
measures the stress caused by these defects and identifies their character, location
and orientation in accordance with the location and orientation of the stress
concentration area. Linear and angular coordinates of flaws in the metal and coating
are defined within a tolerance of +/-0,25m.
MTM Identifies and analyzes magnetic field anomalies in areas with stress
concentrators due to:
Defects or changes in structural conditions (such as metal loss, cracks, dents,
lamination and inclusions);
Excessive mechanical stress caused by erosion, seismic activity, or third party
damage;
Combination of the above.
The significant advantage of the method is that MTM does not require any
preparation of the pipeline for inspection such as cleaning, opening the pipe, or
interrupting pipeline operation. Magnetic field measurements are performed while
pipeline operating as usual.
F=(F+1)e-ka/S (3)
α=ln(Pop/Pd)/(Тs-Тc) (4)
Wherer Рop - operating pressure by the survey time; Ро - design pressure; Тs - date
of survey; Тc – date of commissioning.
According to [7] MTM anomalies can be classified by three ranks depending on index
F calculations as it is demonstrated in table 2.
Pipeline Technology Conference 2015
Over the last years MTM survey technique went through extensive industrial
validation on more than 17 000 km of Gazprom, Transneft, TNK-ВР and Lukoil
pipelines. Most remarkable were the results of branch pipeline “Kolomna-II” survey in
2014 [8]. This pipeline is operated by “Gazprom transgaz Moscow”. On 2.3 km
pipeline section 563 magnetic anomalies (stress concentration areas) were detected:
11 – 1st rank, 56 – 2nd rank, 496 – 3rd rank. Based on the MTM survey results
operator has done 120 excavations and replaced 670 m of pipeline due to extensive
corrosion damages (more than 50% of wall thickness). Some of the excavations
results are presented on Figure 5.
The most significant limitation is that MTM results in low accuracy for detecting pipe
features with stress level less than 5% of the SMYS (e.g., pitting corrosion). The
same pattern is observed when actual mechanical stress is more than SMYS. In
addition it should be noted, that the method to the date remains as indicative, not
allowing to evaluate absolute values of stresses in pipe wall in defect area, type of a
defect and its dimensions, as well as significantly depend on proficiency of data
interpreter.
К ∙ (5)
Where K∑ - integral parameter – the sum of pipeline integrity factors; Gi(li ) – value of
i-factor; ξi - weight coefficient of i-factor.
Integrity factors and their weights are listed in table 4. The maximum of K∑ responds
to high consequences area, where excavations should be done in the first instance.
Pipeline Technology Conference 2015
Factor Weight
Factor
identifier coefficient ξ
No sufficient
DCVG/CIPS: CP EFFECTIVENESS
70 - 100%
protection
Partially
16 - 69% cathodically
protected
Cathodically
0 - 15%
protected
5 Conclusions
It became the result that AMT has presented on market the combined survey
technique - DCVG/CIPS/MTM - as an effective instrument for comprehensive
integrity assessment of non-piggable pipelines. The results that can be achieved
from this combined technique are to:
Compensate limitations of each method;
Provide a qualified statement on the current condition and integrity;
Identify active degradation mechanisms and assess probable causes of
corrosion;
Recommend appropriate corrosion mitigation and control strategies;
Calculate remaining safe working life;
Define effective integrity management plan (pipeline and/or coating).
For the moment, together with Gazprom the DCVG/CIPS/MTM method has been
actively developed. By 2016, AMT expects that combined survey technique, as an
effective instrument to maintain safety and reliability of assets, will be a part of
integrity management plans of many Operators in Russia.
Pipeline Technology Conference 2015
6 References