Time Management: Dr. Saleh Mubarak
Time Management: Dr. Saleh Mubarak
Excavate
Subbase
0, 10 0, 5 0, 3
A B C
10 5 3
0, 10 5, 10 7, 10
Legend
A
Critical
B
Non-critical
C
Float
1 2 3 4 5 6 7 8 9 10 Days
6 1
0, 10 6, 11 7, 10
A B C
10 5 3
0, 10 6, 11 8, 11
C
1 2 3 4 5 6 7 8 9 10 11 Days
0, 10 0, 12 9, 12
A B C
10 12 3
2, 12 0, 12 9, 12
C
1 2 3 4 5 6 7 8 9 10 11 12 Days
0, 10 1, 13 11, 14
A B C
10 12 3
0, 10 1, 13 11, 14
3 1
C
1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days
2 3
0, 10 7, 10 10, 15
A B C
10 3 5
0, 10 7, 10 10, 15
Place 3
Strip Forms
Concrete
Sheathing Shingles
8 days 12 days
1 2 3 4 5 6 7 8 9 10 11 Days
-1
Rafters
Sheathing
Felt
Shingles
1 2 3 4 5 6 7 8 9 10 11 Days
A B
10 8
Actual
At Completion Remaining
Duration
Duration Duration
Design
Construction
Excavation
Foundation
A B
A B
A B
a. Activities A and B must start simultaneously, but B has to finish exactly 2 days
after the finish of A
b. Activity B can start after the start of A but has to finish at least 2 days before
the finish of A
c. Activity B can start before the start of A but has to finish at most 2 days after
the finish of A
d. Activity B can start after the start of A but has to finish at least 2 days after
the finish of A
A -2 B
Time
Time
Ideal,
unrealistic
Time
Leveled,
realistic
Time
39 Constr.
Project
Resource Leveling Example: The
Network
Act ID Activity Description IPA Dur Laborers
A Purchase & Deliver materials - 5 2
B Remove old vinyl tile - 7 4
C Install ceramic tile A 3 3
D Install new vinyl tile A, B 5 3
E Clean up & inspect C, D 2 2
0, 5 5, 8
A C
5 3
0 12, 14
2, 7 9, 12
E
PS 2
0, 7 7, 12
12, 14
0 B D
7 5
0, 7 7, 12
40 Constr.
Project
Bar Chart & Resource Histogram
41 Constr.
Project
Resource Leveling:
Solution, Step 1
42 Constr.
Project
Resource Leveling:
Solution, Step 2
43 Constr.
Project
Site Plan & Logistics
Is space a resource?
If yes, does it have to be leveled?
Things on the ground are changing continuously!
Impact of acceleration (or any increase of
crews) on space
1. Purchase costs
2. Order costs
3. Holding costs
4. Shortage (unavailability) costs
The “two extreme” theories:
Just in time
Inventory buffer
57 Constr.
Project
Procurement
Accounting
CPM
Procurement
Scheduling
Contract
documents
58 Constr.
Project
Materials versus Labor & Equipment
* Taxes differ among the three categories and also depend on local laws and regulations
True or False:
1. When we talk about resource leveling in construction
projects, we mean cash flow leveling.
2. Managing materials is different in principle from managing
labor and equipment in construction projects.
3. Resource leveling is done in construction projects to make
sure each activity obtains the required resource.
4. Resources must not be shared between two different
projects.
5. The GC who performs work by his own forces is more likely
to do resource leveling to his CPM schedule than the GC who
subcontracts all or most of the work.
Schedule Cost
Proj. No. Project Name
As Planned Change No change Change
ABC1200 Washington Street Drainage Improvement, Phase I X X
FGH3211 Road Resurfacing, Main St between 42nd and 52 Ave. X X
LMN4500 Bridge No. 10345, US 41 over Hillsborough River X X
XYZ7812 Traffic Signal at Intersection of Busch Blvd and Florida Ave. X X
PM Signature: Date:
Schedule Signature: Date:
PM: John Doe Project No.: FGH2133 Project Name: Office Building, downtown Tampa
Activity name Start Date A Start Date End Date A End Date Orig Rem %
Change Change Dur Dur Comp
1 NTP 1/3/2003 A 0 0 100%
2 Mobilize 1/6/2003 A 1/8/2003 A 3 0 100%
3 Dewatering 1/9/2003 A 1/19/2003 A 11* 0 100%
4 Excavation - North Side 1/20/2003 A 1/29/2003 A 9 0 100%
5 Excavation - South Side 2/3/2003 A 2/25/2003 A 10 0 100%
6 Drill Piles - North Side 1/30/2003 A 2/28/2003 A 13 0 100%
7 Drill Piles - South Side 3/3/2003 A 3/19/2003 13 3 77%
8 Concrete Piles - NS 3/3/2003 A 3/11/2003 A 7 0 100%
9 Concrete Piles - SS 3/20/2003 3/28/2003 7 7 0%
10 Pile Caps - North Side 3/12/2003 A 3/28/2003 13 10 23%
11 Pile Caps - South Side 3/31/2003 4/16/2003 13 13 0%
12 Footings - North Side 3/24/2003 4/4/2003 10 10 0%
13 Footings - South Side 4/7/2003 4/22/2003 12 12 0%
14 Elevator Pit - NS 3/31/2003 4/9/2003 8 8 0%
15 Elevator Pit - SS 4/14/2003 4/23/2003 8 8 0%
(*) This activity is on a 7-day per week calendar.
14, 22
10 10, 14 34, 37
F
C 8 N
22, 34 3
PC 4
14, 22 I
10, 14 12 34, 37
10
14, 22 22, 34 22, 26
G M
8 4
10, 19 22, 28 30, 34
14, 22
H L
9 6
19, 28 28, 34