Time Schedule

The document appears to be a project schedule that outlines the planned percentage of work and timeline for several jobs over a 6 month period. It includes 4 main jobs: 1) replacement of pumps and headers for AC chillers, 2) installation of air curtains, 3) construction of a ground water tank for hydrants, and 4) testing and commissioning. It shows the planned percentage of each job completed each week, with cumulative totals. It will also track the actual completion percentages and any deviations from the planned schedule.

Uploaded by

sigitbambang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
114 views2 pages

Time Schedule

The document appears to be a project schedule that outlines the planned percentage of work and timeline for several jobs over a 6 month period. It includes 4 main jobs: 1) replacement of pumps and headers for AC chillers, 2) installation of air curtains, 3) construction of a ground water tank for hydrants, and 4) testing and commissioning. It shows the planned percentage of each job completed each week, with cumulative totals. It will also track the actual completion percentages and any deviations from the planned schedule.

Uploaded by

sigitbambang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

BULAN KE.1 BULAN KE.2 BULAN KE.3 BULAN KE.4 BULAN KE.5 BULAN KE.

MINGGU KE-
No. JENIS PEKERJAAN BOBOT (%) KET.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

A PEKERJAAN PENGGANTIAN POMPA DAN PIPA HEADER A/C CHILLER 100

1 Pekerjaan persiapan 4.477 0.589 1.296 1.296 1.296

2 Pekerjaan ruang pompa chiller 9.216 2.304 2.304 2.304 2.304

3 Pekerjaan lantai 1 25.204 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100

4 Pekerjaan lantai 1 s/d 9 19.499 1.773 1.773 1.773 1.773 1.773 1.773 1.773 1.773 1.773 1.773 1.773

V Pekerjaan sistem bak pancingan air chiller 5.325 1.775 1.775 1.775

B PEKERJAAN PENGADAAN AIR CURTAIN 4.673 1.558 1.558 1.558

C PEKERJAAN PEMBANGUNAN GROUND WATER TANK UNTUK HYDRANT

1 Pekerjaan persiapan 1.732 0.577 0.577 0.577

2 Pekerjaan tanah 28.220 0.816 0.816 0.816 1.422 1.422 1.693 1.693 2.358 2.358 2.358 2.358 2.358 2.358 1.798 1.798 1.798

D PEKERJAAN TESTING DAN COMMISSIONING 1.653 0.827 0.827

100.000

RENCANA % TIAP MINGGU 1.166 1.873 4.464 3.887 4.691 3.522 3.522 3.794 5.566 6.231 6.231 6.231 6.231 6.231 6.231 5.671 5.874 5.874 4.077 3.862 1.558 1.558 0.827 0.827

KUMULATIF - 1.166 3.040 7.504 11.391 16.083 19.604 23.126 26.920 32.486 38.717 44.949 51.180 57.412 63.643 69.874 75.545 81.419 87.293 91.370 95.232 96.789 98.347 99.173 100.000

REALISASI % TIAP MINGGU

KUMULATIF

DEVIASI %
BULAN KE.1 BULAN KE.2 BULAN KE.3 BULAN KE.4 BULAN KE.5 BULAN KE.6

MINGGU KE-
No. JENIS PEKERJAAN BOBOT (%) KET.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

A PEKERJAAN PENGGANTIAN POMPA DAN PIPA HEADER A/C CHILLER 100

1 Pekerjaan persiapan 4.477 0.589 0.972 0.972 0.972 0.972

2 Pekerjaan ruang pompa chiller 9.216 2.304 2.304 2.304 2.304

3 Pekerjaan lantai 1 25.204 1.800 1.800 1.800 1.800 1.800 1.800 1.800 1.800 1.800 1.800 1.800 1.800 1.800 1.800

4 Pekerjaan lantai 1 s/d 9 19.499 1.393 1.393 1.393 1.393 1.393 1.393 1.393 1.393 1.393 1.393 1.393 1.393 1.393 1.393

V Pekerjaan sistem bak pancingan air chiller 5.325 1.065 1.065 1.065 1.065 1.065

B PEKERJAAN PENGADAAN AIR CURTAIN 4.673 1.558 1.558 1.558

C PEKERJAAN PEMBANGUNAN GROUND WATER TANK UNTUK HYDRANT

1 Pekerjaan persiapan 1.732 0.433 0.433 0.433 0.433

2 Pekerjaan tanah 28.220 0.816 0.816 0.816 1.422 1.422 1.693 1.693 2.358 2.358 2.358 2.358 2.358 2.358 1.798 1.798 1.798

D PEKERJAAN TESTING DAN COMMISSIONING 1.653 0.827 0.827

100.000

RENCANA % TIAP MINGGU 1.022 1.405 1.405 1.405 2.853 3.681 3.681 4.287 5.680 4.886 4.886 5.551 5.551 5.551 5.551 5.551 5.551 4.991 7.295 7.052 5.254 5.254 0.827 0.827

KUMULATIF - 1.022 2.427 3.832 5.237 8.090 11.772 15.453 19.740 25.419 30.306 35.192 40.743 46.295 51.846 57.398 62.949 68.501 73.491 80.786 87.838 93.092 98.347 99.173 100.000

REALISASI % TIAP MINGGU

KUMULATIF

DEVIASI %