Proposed Warehouse Cum (G+2) Office For Weathereford (Under Balance) For DCM International
Proposed Warehouse Cum (G+2) Office For Weathereford (Under Balance) For DCM International
Proposed Warehouse Cum (G+2) Office For Weathereford (Under Balance) For DCM International
Bitumen paint
Footing m2 35 2.5 2.5 218.75
Side m2 35 10 0.4 140
8" Solid block in between footings m2 2 169.4 0.4 135.52
8" Solid block in between footings tops to T.B. m2 2 249.4 0.5 249.4
Tie beam m2 2 249.4 0.6 299.28
Total bitumen Quantity 1042.95
Page 1 of 16
Ware house area G S. m3 1 27 12.2 0.25 82.35
Office m3 1 45 12.2 0.25 137.25
Total Roadbase Quantity 626.755
Office Block
100mm thick with BRC Mesh A-142(1-layer) m3 1 45 12.2 0.15 82.35
Total ground slab Quantity 82.35
Page 2 of 16
Decking slab m2 1 45 12.2 549
m2 1 72.2 12.2 880.84
Total decking slab Quantity 1429.84
Parapet
Lift m3 1 18.7 0.2 1 3.74
Escape staircase m3 1 19.8 0.2 1 3.96 7.7
Lift staircase
Landing m3 6 1.4 1.4 0.2 2.352
Waist slab m3 3 7.6 1.4 0.2 6.384
Steps m3 33 1.2 0.3 0.15 1.782
Escape staircase
Landing m3 3 2.5 1.4 0.2 2.1
Waist slab m3 6 4 1.1 0.2 5.28
Steps m3 33 1.1 0.3 0.15 1.6335
Total staircase Quantity 19.5315
Page 3 of 16
Total lintal Quantity 2.384
Ground floor
A/C
Internal wall plaster m2 1 31.84 3 95.52
RUD m2 -1 4 4 -16
FD m2 -1 1 2.1 -2.1 63.52
A/C Storage
Internal wall plaster m2 1 24.9 3 74.7
AD m2 -1 1.8 2.4 -4.32 70.38
Page 4 of 16
I.Wall paint m2 1 70.38
Plant
Internal wall plaster m2 1 14.1 3 42.3
42.3
Etisalat
Internal wall plaster m2 1 12.15 3 36.45
36.45
DEWA
Internal wall plaster m2 1 13 3 39
39
I.Wall paint m2 1 39
Office
Internal wall plaster m2 1 17 3 51
FD m2 -1 1 2.1 -2.1 48.9
Page 5 of 16
D2 m2 -1 1.8 2.4 -4.32 175.11
Toilet,Kitchen,Entrance prayer
Wall C/T m2 1 12.4 3 37.2
m2 1 17.6 3 52.8
m2 1 53.8 3 161.4
m2 1 7.8 3 23.4
m2 1 9.6 3 28.8
m2 1 6.3 3 18.9
m2 -15 0.9 2.1 -28.35 294.15
Locker
Internal wall plaster m2 1 15.8 3 47.4
FD m2 -1 1 2.1 -2.1 45.3
Reception
Internal wall plaster m2 1 27.2 3 81.6
D1 m2 -4 0.9 2.1 -7.56
GD m2 -1 1.8 2.4 -4.32
W1 m2 -2 2.25 0.6 -2.7 67.02
F/C m2 1 45.94
Page 6 of 16
Shaft
Internal wall plaster m2 1 5.7 3 17.1 17.1
Middle wall
Internal wall plaster m2 2 72 4 576 576
Toilet,Kitchen,Entrance prayer
Wall C/T m2 2 30.5 3 183
m2 2 30.5 3 183
m2 2 17.3 3 103.8
m2 -18 0.9 2.1 -34.02 435.78
Meeting room
Internal wall plaster m2 2 21.5 3 129
CW m2 -2 6.4 2.4 -30.72 98.28
Passage
Internal wall plaster m2 2 26.15 3 156.9
CW m2 -8 0.9 2.1 -15.12 141.78
Page 7 of 16
Flooring carpet tiles m2 2 14.85 2.25 66.825 66.825
Shaft
I.Wall plaster m2 2 10.2 3 61.2
D1 m2 -2 0.9 2.1 -3.78 57.42
Escape Staircase
Landing flooring Granite m2 3 2.25 1.4 9.45 9.45
Landing Skirting Granite lm 3 5.05 15.15 15.15
Staircase Steps lm 33 1.1 36.3 36.3
Lift Staircase
Landing flooring Granite m2 6 1.3 1.3 10.14 10.14
Landing Skirting Granite lm 6 2.6 15.6 15.6
Staircase Steps lm 33 1.1 36.3 36.3
External finishing
Alpolic cladding m2 1 27 14 378
Deduction
D2 m2 -1 1.8 2.4 -4.32
GD m2 -1 1.8 2.4 -4.32
W m2 -2 2.25 0.6 -2.7
W2 m2 -2 0.6 0.6 -0.72
CW m2 -1 6.4 2.4 -15.36
CW2 m2 -1 2.25 2.4 -5.4
W3 m2 -1 1.1 1.4 -1.54
Total Alpolic cladding Quantity 343.64
Page 8 of 16
m2 -1 45.85 6.8 -311.78
m2 -1 3.7 15 -55.5
m2 -1 1.8 5.95 -10.71
m2 -1 2 2.8 -5.6
m2 -1 45.85 6.8 -311.78
4860.76
Wooden doors
D1 No. 38 0.9 2.1 2500 95,000.00
Glass door
D2 No. 3 1.8 2.4 4000 12,000.00
D3 No. 10 1 2.1 3000 30,000.00
Ground floor
Aluminium louvers
AD No. 4 1.8 2.4 17.28
Aluminium windows
W No. 4 2.25 0.6 5.4
W2 No. 3 0.6 0.6 1.08
First & second floor
W3 No. 2 1.1 1.4 3.08
W4 No. 2 1.4 0.6 1.68
CW No. 14 6.4 2.4 215.04
CW1 No. 2 4.8 2.4 23.04
CW2 No. 4 2.25 2.4 21.6 288.2
Page 9 of 16
Light weight concrete m2 1 5.1 4.25 21.675 45 975.38
Membrane m2 1 5.1 4.25 21.675 35 758.63
Insulation m2 1 5.1 4.25 21.675 35 758.63
Sepration layer m2 1 5.1 4.25 21.675 5 108.38
30mm cement sand mortar m2 1 5.1 4.25 21.675 30 650.25
White cement tiles m2 1 5.1 4.25 21.675 90 1,950.75
Angle fillit lm 1 18.7 15 280.50
Membrane skirting lm 1 18.7 15 280.50
Tile skirting lm 1 18.7 15 280.50
Flushing lm 1 18.7 40 748.00
Groove & sealent lm 1 18.7 15 280.50
Fire escape staircase:
Light weight concrete m2 1 2.5 7.1 17.75 45 798.75
Membrane m2 1 2.5 7.1 17.75 35 621.25
Insulation m2 1 2.5 7.1 17.75 35 621.25
Sepration layer m2 1 2.5 7.1 17.75 5 88.75
30mm cement sand mortar m2 1 2.5 7.1 17.75 30 532.50
White cement tiles m2 1 2.5 7.1 17.75 90 1,597.50
Angle fillit lm 1 19.2 15 288.00
Membrane skirting lm 1 19.2 15 288.00
Tile skirting lm 1 19.2 15 288.00
Flushing lm 1 19.2 40 768.00
Groove & sealent lm 1 19.2 15 288.00
TOTAL 13,252.00
Steel column cover by gypsum
G.F m2 10 1.2 3 36
F.F. & S.F. m2 40 1.2 3 144 180.00
Page 10 of 16
Decking sheet m2 1 45 12.2 549 1429.23
m2 1 72.15 12.2 880.23
TOTAL
Bitumen paint
Footing m2 34 2 2 136
Side m2 34 8 0.4 108.8
8" Solid block in between footings m2 2 37.3 0.4 29.84
Page 11 of 16
8" Solid block in between footings tops to T.B. m2 2 105.3 0.5 105.3
Tie beam m2 2 105.3 0.6 126.36
Total bitumen Quantity 506.3
Page 12 of 16
PROJECT :WAREHOUSE CUM (G+2) OFFICE ON PLOT NO. S21511
CLIENT :WEATHERFORD(UNDER BALANCE)
CONSULTANT : DCM DESIGN INTERNATIONAL
SUBJECT :BILL OF QUANTITY
DATE :
III SUBSTRUCTURE
A Earth works
1 Excavation for foundation m3 2280 25 57,000.00
2 Back filling & compaction m3 2088 25 52,200.00
3 Cartway surplus material m3 2280 20 45,600.00
154,800.00
B Concrete works
1 PCC m3 35 500 17,500.00
2 RCC Isolated footings m3 89 1200 106,800.00
3 Pedastel m3 10 2100 21,000.00
4 Tie beam m3 31 1600 49,600.00
194,900.00
C Sundries
1 Polythene sheet (Guage-1000) m2 2510 5 12,550.00
2 250mm thick Roadbase below footing and m3 630 90 56,700.00
Ground slab warehouse & office slab
3 Bitumen paint m2 1048 8 8,384.00
4 Antitermite m2 2510 8 20,080.00
5 Expension joint,Sealent ls 10,000.00
107,714.00
D Solid block
1 200mm thick solid block m2 198 95 18,810.00 18,810.00
E Ground slab
1 200mm thick ground slab with fiber m3 325 725 235,625.00 235,625.00
reinforcement polished floor slab with floor
hardner warehouse area
IV SUPERSTRUCTURE
F Concrete works
1 Column m3 2 2100 4,200.00
2 Cooping beam m3 8 1600 12,800.00
3 Encasement column m3 15 2000 30,000.00
47,000.00
G Masonary works
1 150mm thick hollow block up to 1.5m height m2 235 75 17,625.00
2 Internal wall plaster m2 270 34 9,180.00
Page 13 of 16
3 External wall plaster m2 270 38 10,260.00
37,065.00
H Painting works
1 Internal wall fenomastic paints m2 270 15 4,050.00
2 External wall weather tough paints m2 270 45 12,150.00
16,200.00
OFFICE BLOCK
A Concrete works
1 100mm thick ground slab with BRC Mesh A-142 m3 84 500 42,000.00
(1-layer) for office
2 Decking slab 100mm thick with BRC Mesh m2 1430 100 143,000.00
A-142
3 200mm thick RCC lift wall m3 18 1800 32,400.00
4 Lift staircase & Escape staircase Solid slab m3 9 1500 13,500.00
5 Parapet m3 9 1600 14,400.00
6 Lintal m3 4 1600 6,400.00
7 Lift staircase & Escape staircase m3 21 1400 29,400.00
281,100.00
B Masonary works
1 200mm thick insulated block m2 490 110 53,900.00
150mm thick hollow block m2 1525 75 114,375.00
2 100mm thick hollow block m2 485 70 33,950.00
3 Internal wall plaster m2 2420 34 82,280.00
284,505.00
C Flooring works
1 Flooring Composite stone floor finish for m2 48 530 25,440.00
Reception area(PC dhs.380/m2)
2 Flooring Carpet tiles tiles for office area m2 1398 150 209,700.00
(P.C.Dhs.120/m2)
3 Flooring Ceramic tiles(PC Dhs60/m2) m2 162 120 19,440.00
4 Flooring landing granite(PC DHS.400/m2) m2 20 600 12,000.00
5 Staircase step granite(P.C.Dhs.150/lm) lm 74 250 18,500.00
6 Epoxy floor marking in warehouse area ls 10,000.00
295,080.00
D Wall finishes
1 Wall ceramic tiles(P.C.Dhs.60/m2) m2 730 125 91,250.00
2 100mm thick gypsum partition with insulation m2 201 120 24,120.00
3 12mm thick toughened glass partition m2 135 600 81,000.00
4 Wall paper for gypsum partition both side m2 402 40 16,080.00
(PC Dhs.25/m2)
5 Landing Skirting granite(P.C.Dhs.50/lm) lm 32 100 3,200.00
215,650.00
E Painting works
1 Internal wall fenomastic paints m2 2420 15 36,300.00
2 External wall Alpolic cladding m2 345 350 120,750.00
157,050.00
F False ceiling
1 (60x60)cm gypsum tile false ceilling m2 196 65 12,740.00
2 (60x60)cm gypsum tile moisture resistant m2 162 70 11,340.00
false ceiling wet area
3 (60x60)cm modular conceald grid metal false m2 1385 140 193,900.00
Page 14 of 16
ceiling office and plan area
4 Split level gupsum false ceiling reception area m2 50 100 5,000.00
and confrence room 222,980.00
G Roof waterproofing
1 Light weight concrete m2 40 45 1,800.00
2 4mm thick torch applied(one layer) water m2 40 35 1,400.00
proofing membrane including primer
3 50mm thick extruded polystyrene insulation m2 40 35 1,400.00
4 20mm cement sand mortar m2 40 30 1,200.00
5 White cement tiles m2 40 90 3,600.00
6 Angle fillit lm 38 15 570.00
7 Membrane skirting lm 38 15 570.00
8 Tile skirting lm 38 15 570.00
9 Water proofing wet area m2 160 30 4,800.00
15,910.00
H External works
1 Compound wall all sides with railing lm 538 1200 645,600.00
2 80mm thick interlocking m2 4865 80 389,200.00
3 60mm thick interlocking m2 70 70 4,900.00
4 Kerb stone lm 35 75 2,625.00
5 Gaurd room ls 40,000.00
6 Under ground Irrigation tank & Pump room ls 90,000.00
7 Under ground holding tank lm 75,000.00
8 2 Nos.100mm dia conduits crossing each road no 2 1500 3,000.00
9 250mm thick Road base remaining area m3 8635 90 777,150.00
10 Electronic slidding gate no 3 22000 66,000.00
11 Automatic gate barier no 3 10000 30,000.00
12 Provide wall within the boundry lm 161 800 128,800.00
2,252,275.00
Provisional items
1 Internal emergency sinage PS 10,000.00 10,000.00
2 Kitchen cabinets PS 15,000.00 15,000.00
Total PS=25000/-
Page 15 of 16
15% Cordinationcharges 3,750.00 3,750.00
TOTAL 12,147,414.00
Page 16 of 16