0% found this document useful (0 votes)
45 views10 pages

Settlement Due To Tunnel Construction: Prepared By: Engr Naqeeb Nawaz

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views10 pages

Settlement Due To Tunnel Construction: Prepared By: Engr Naqeeb Nawaz

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Settlement Due to Tunnel

Construction
Prepared by : Engr Naqeeb Nawaz
INTRODUCTION
Example
Statement of Problem
Tunnel Diameter = 5m
Phreatic surface = 3m below ground surface
MATERIAL PROPERTIES OF SOIL LAYERS IN
TUNNEL
MATERIAL PROPERTIES OF PLATE
CALCULATION PHASES
• 3 calculation phases will be defined
• PHASE-01
• Select plastic analysis, staged construction and click define and activate the
building, anchors and toe plates.
• PHASE =02
• Plastic calculations, reset displacement to zero, staged construction and define
and then activate the tunnel linning.
• Phase-03
• There will be some contraction due to dewatering and tunnel lining
construction.so apply 2% contraction.