Part A: DE3J 35: Preparing Financial Forecasts
Part A: DE3J 35: Preparing Financial Forecasts
Part A: DE3J 35: Preparing Financial Forecasts
Part A
Introduction
I am the advisor of the Tricol plc, I would like to make a flexed budget as well as give
some opinions to evaluate this project for the management.
Flexed budget
Calculation
1. Direct material total variance:
(Standard units of actual production*standard price)- (actual quantity*actual price)
4kg*£10 per kg*1,600 -£61,600=£2,400 (F) (3.75%)
Variance analysis
Direct material total variance:
a) It was a favourable variance. Because the actual price is less than the
standard price and the actual quantity of materials (1600) used is different
from the standard quantity (2,000).
Recommendations
a) All of the rate of significance should be concerned and analyzed by the
management.
b) Some future investigations should be made on the increased price and low labour
efficiency which are the most significance to be considered. It is beneficial in the
long run to find accurate reasons and look for solutions
Part B
Introduction
I am an advisor of the company and I would like to evaluate the financial viability of
the investment proposal to the management and give some recommendations to
improve the project.
Application
I will use two investment appraisal techniques to evaluate the project.
b. NPV
Annual cash Present value Present
Year flow factors at 10% value
£ £ £
0 -1,000,000 1 -1,000,000
1 160,000 0.909 145,440
2 160,000 0.826 132,160
value
Assumptions
Assumptions can be summarised as below:
a) All the cost is happened at year 0.
b) All the cost and revenues for every year are all net cash flows
c) 10% of market rate of return is expected rate of return.
d) The cash flows in each year are evenly spread among 12 months of the year.
e) There is no inflation, no taxation to be considered.
f) Uncertainty does not exist.
g) Unlimited funds can be raised at a competitive rate.
From the result of the calculation of NPV, I found we cannot accept it because it was
negative. In the view of present value, it means the loss of cash and it was not break
even. And in the analysis of expected rate of return, the real rate of rate is lower than
expected rate of return. However, the calculation is unilateral. It only considered the
revenue over the next five years, and the project life is commonly longer than five
years. It may be different when considering the long-term project which may be
turned to be positive. Because the cash flows may increase continually, and the NPV
was not very high in terms of the whole company. Thus, it was not acceptable and the
management should take some other factors into account.