PNG LNG Execution Milestones: Forecast
PNG LNG Execution Milestones: Forecast
PNG LNG Execution Milestones: Forecast
EPC5B Roxburgh Airfield aggregate stockpile reaches 1kT Nov-11 Nov-11 0.0 - NA NA NA
C1 Roxburgh Well Pad B Access Available to Drilling Dec-11 Dec-11 0.0 Drilling NA NA NA
C1 Roxburgh Partial Process Area Handover (EPC4) Dec-11 Dec-11 0.0 EPC4 NA NA NA
EPC2 Roxburgh 100% Line-pipe Available (delivered to PNG) Dec-11 Dec-11 0.0 - NA NA NA
EPC4 Roxburgh Complete Main Camp - Phase 2 Dec-11 Mar-12 3.0 - Delay in camp area handover Potential bed constraint Keeping pioneer camp in place longer
EPC5A Roxburgh Omati to Kopi Pipe Mechanical Completion Mar-12 Mar-12 0.0 - NA NA NA
EPC4 Roxburgh Complete Main Camp Construction Apr-12 May-12 2.0 - Delay in camp area handover Potential bed constraint Keeping pioneer camp in place longer
C1 Roxburgh Full Process Area Handover (EPC4) Apr-12 Apr-12 0.0 EPC4 NA NA NA
EPC2 Roxburgh Offshore Pipeline Ready for Hydro test Jun-12 Jun-12 0.0 - NA NA NA
EPC2 Roxburgh Offshore Pipeline Turnover / Omati Tie-in Oct-12 Oct-12 0.0 EPC5A NA NA NA
EPC4 Roxburgh Complete U/G Piping Installation - Process Area Oct-12 Oct-12 0.0 - NA NA NA
EPC5A Roxburgh Kopi to Kutubu Pipeline Mechanical Completion Nov-12 Nov-12 0.0 - NA NA NA
EPC5A Roxburgh Final Handover Omati to Kutubu Dec-12 Dec-12 0.0 EPC3 NA NA NA
EPC4 Roxburgh Feed Gas Available at HGCP Apr-14 Apr-14 0.0 EPC3 NA NA NA