Steel Bridges Construction
Steel Bridges Construction
46
construction process. An example is a concrete slab of a composite bridge which provides
lateral support to the main beams compression flanges, but which is only in place and effective
after erection of the steelwork and construction of the slab. It is also necessary to check elements
of the steel structure for their resistance to local buckling when subjected to concentrated forces.
The overall stability of the superstructure during its placement (against overturning, uplift, etc.)
must be guaranteed. There may be a lack of stability during erection due to, for example, the
absence of some of the self-weight that has a stabilising effect. It is also important to check that
the various pieces of steelwork can adequately resist the various handling operations to which
they will be subjected (lifting, transportation, assembly) (Lebet & Hirt, 2013).
To ensure that a steel bridge can be safely, economically and reliably executed
(fabricated, assembled and erected), designers should be aware of the processes of fabrication
and erection, the capabilities and limitations of the steelwork contractor and how the design
choices affect those processes. Guidance on design for construction generally follows the
sequence of activities undertaken by the steelwork contractor. The objectives of “design for
construction” are: to maximize the efficiency of the construction process and to minimize the
need for clarification and change. Achieving these objectives will reduce costs, reduce the
construction period, enhance quality and increase the safety of the work. The activities for the
steelwork contractor include planning, ordering, modelling, fabricating, assembling, coating
and erecting (for more details see: SteelConstruction.info).
How the bridge is designed and how it is built are linked. Ensuring that this link is
recognised will have an effect on the safety and quality of the construction. Methods of erecting
steel bridge structures vary considerably from site to site and from project to project. The
subject of erection aspects is therefore a wide and varied subject. This chapter focuses on the
aspects that should be considered during the initial design and detailed design phases.
Construction with a crane means lifting various steelwork elements - lengths of main
beam, cross bracing, horizontal bracing - from the ground using a crane (Fig.2.1). This is an
advantageous means of erecting the steel structure because it requires less equipment on site
and a reduced amount of labour. Erection using cranes is considered the most cost effective
erection method for the majority of structures. However, it does require good accessibility
around the construction site, and is only suitable for bridges which are relatively not very high
(with a deck up to approximately 15 m above the ground). Only crawler cranes and some small
rough terrain mobile cranes are able to traverse the site with a load. The site areas adjacent to
the bridge will affect the position and size of crane that can be used and this will affect capacity
of lift and therefore choice of crane and the piece size. The area for preassembly will also
influence lift size.
The erection of an I-girder is often accomplished with a single construction crane
(Fig.2.2, left). Depending on the size, weight and capacity of the girder, the crane could use
either a single lift point located at the centre of gravity of the member or two lift points located
47
symmetrically towards the centre of gravity utilizing a spreader beam. Depending on the overall
size and complexity associated with the bridge construction, the individual girder erection could
incorporate the use of temporary supports, temporary pier brackets or hold cranes to provide
stability to the member until a sufficient number of girder lines are erected and connected via
permanent cross frames or diaphragms to form a stable system. The erection of a box girder is
often carried out with a pair of construction cranes working in tandem during the lift (Fig.2.2,
right). The cranes are typically rigged with a spreader beam that contains two beam clamps
each. The beam clamps are attached to the top flanges of the box girder near the ends of the
member. Unlike I-girders, an individual box girder may be stable once it is lifted onto its
permanent supports, due to the internal bracing system.
Figure 2.2. Erection of I-girders with a single crane (left) and erection of a box girder with a
pair of cranes working in tandem (right)
The erection may take place either with or without temporary supports. If such supports
(props, falsework) are used, they may be either continuous or discrete. The evolution of heavy
lifting equipment means that when temporary supports are needed, they tend to be a small
number of discrete props rather than continuous falsework. The bending moments that can be
resisted at the bases of the telescopic arms of mobile cranes currently used worldwide can be
as high as 15.000 kNm, which means that, e.g. a weight of 100 tones can be carried at a distance
48
of 15 m. If the spans are sufficiently short, and the size of the individual steelwork pieces allows,
the temporary supports can be avoided. An alternative method may be used if the superstructure
of the bridge is sufficiently strong and stiff in bending, or perhaps it can be supported with
temporary supports. To begin with, the structure is constructed either from the ground or
launched. Once the structure is in place, it serves as a working platform for constructing the
spans. Falsework towers are supported on the deck and allow relatively easy erection of e.g. the
arches. Such a procedure is shown in Figure 2.3.
Figure 2.3. Falsework towers supported on the deck for arch erection: scheme (top) and two
examples (bottom)
49
launches. The superstructure is completely assembled (typically one span or more at a time),
including cross frames and bracing, prior to launching operations.
Launching the steelwork over road or river, involves assembly of steelwork, typically
behind an abutment, on the highway approach. The steelwork is assembled on low resistance
rollers or a sliding system at each pier or temporary support. A haulage and restraint system is
used. The steelwork requires plenty of construction alignment to ensure adequate fit up prior to
launching and needs to have sufficient time in the programme to allow for this. However,
assembly is normally near ground level, with the use of much smaller and less expensive cranes
and minimum work at height.
The method of launching the steelwork is adopted when lifting equipment cannot access
the whole length of the bridge, or when the height of the bridge becomes too big for lifting with
cranes located on the ground. The method can be used to construct a bridge over a wide range
of challenging sites, which feature limited or restricted access, including those with the
following characteristics: deep valleys, deep water crossings, steep slopes or poor soil
conditions making equipment access difficult or environmentally protected species or cultural
resources beneath the bridge. Currently this method is used to launch girder bridges with spans
up to 150 m (Rosignoli, 2002). The launching method has also been applied to tied-arch or truss
spans, although these are fully assembled prior to launching.