Hamza 1999
Hamza 1999
Hamza 1999
A b s t r a c t - - T h i s paper pn,.sents an evaluation of the settlement prediction techniques used to estimate the
surface settlements associated with the construction of the Greater Cairo Metro Line 2. The construction of
the Cairo Metro involved I~heconstruction of cut-and-cover underground stations and bored tunneling. A
typical underground station was executed using top-down construction technique. The twenty two meters
excavation was carried inside a watertight box with 50-m-deep diaphragm walls to form the sides and a 7-
m thick groutedplug at the bottom. Tunneling was performed using a slurry shield tunnel boring machine,
TBM, having an internal diameter of 9.48 m. This analysis is the first step in uiew of enhancing the
procedures of settlement prediction and appraising potential damages to overlying structures and utilities
for the future construction of the twin road tunnels in the historical urban environment of AI Azhar area and
If7~an El I~alily market in Cairo. © 1999 Published by Elsevier Science Ltd. All rights reserved.
KETWORDS: bored tunnel; settlement prediction; field monitoring; slurry sh~ld; TBM; cut and cover
www.elsevier.com/locate/tust
Tunnelling and Underground Space Technology,Vol. 14, No. 3, pp. 281-289, 1999
0886-7798/99/$ - see front matter © 1999 Published by Elsevier Science Ltd.
All rights reserved.
~ Pergamon
PII: S0886-7798(99)00044-9
ded wall, subsoil properties, depth of excavation inside the
walls, type and stiffness of supporting system, time period
ofcoustruction, surrounding structures, and surcharge loads.
Layer 1: Fill
p 3.1. Installation of Diaphragm Walls (So-Curve)
i m m G.W.Tablc The vertical settlement at the ground surface due to the
., ~",~'',,, ,. ,,
installation of diaphragm walls (or slurry walls) is gener-
ally represented as a function of the trench depth and the
4.00m Layer 2: Clay horizontal distance from the trench (Peck 1969). It is
generally accepted that in normal conditions, based on
data from case histories, the surface movements are lim-
ited to a small percentage of the excavation depth and
decrease with increasing distance from the wall. In view of
the new construction technologies, m a n y researchers have
contributed to the database of the subject by updating it
Layer 3: Silty sand with field measurements and by specifying patterns of
3.111 m movements in the vicinity of deep excavations [e.g., Clough
and Schmidt (1981), Uriel and Sagesta (1989), and Clough
and O'Rourke (1990)].
Hamza (1993) adopted the following expression to de-
scribe the settlement component due to the installation of
diaphragm walls (S o curve),
So )=s,[1- lm (1)
Layer 4: Sand
where:
S t is the maximum settlement adjacent to the wall,
x is the distance from the wall,
x ois the distance from the wall where the settlement due
to wall installation is equal to zero, and
Figure 1. Soil profile at the Cairo Metro Line 2 (Lot 12 at m is an empirical exponent.
kP 3.358).
Because local experiences are essential for the estimate
of this settlement component, it was decided to use initial
settlement measurements at one of the
Table 1. Measured settlements in the vicinity of Rod El Farag Station. first stations t h a t was constructed for
the Cairo Metro Line 2, namely Rod E1
Distance from D. Wall (m) 5 10 20 40 60 Farag Station. The measured in-situ
settlements are presented in Table 1.
Settlement (mm) 15 11 6 1.5 0.9 In this particular case, for the set of
measurements at the West Side of the
station, the m a x i m u m value of settle-
ment is extrapolated as S t = 20 ram.
This value is approximately 0.041% of
the excavated trench depth, which is
Distance from wall (m) typically in the middle range reported
0 l0 40 6O S0 100 120 by Clough and O'Rourke (1990). Figure
2 presents a plot of the measured values
9 ,,,,,
~82 TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY Volume 14, Number 3, 1999
It is also noted that existing buildings
adjacent to these two locations are ap- ~tal;ft' (m t
proximately 8.0 m away from the in- 0 la 20 30 -;0 50 6O "0
stalled walls. The stiffzless of the build- IIIII
ings affected both the value and the -- •O " ~I- ' ~ ' ' ~ ' ' A I ~
J
:
pattern of movements by reducing the
settlement adjacent ~ the wall and
keeping it constant for some distance
below the building. 0.01
A summary of the results from the
Cairo Metro Line 2 (Phase 1A, 1B and
2A) is presented in Figure 5, where the
data are normalized by the trench depth.
Statistics of the ratio of the maximum "~ 1t.02
settlement to the trench depth are as
follows: .... P r e d i c t e d
Minimum S~depth = 0.014 % • Measured
Maximum S]depth = 0.052 % o~o3 - ..........
Average S/depth = 0.031%
The envelope of the data (S0-curve) Figure 3. Settlement trough at St. Theresa Station.
is also plotted on Figure 5 using the
average value S~= 0.041% D. From Fig- Distance (in)
ure 5, it is clear that the adopted method 0 I0 20 30 40
provides an adequate approximation
for most measurements along the route
of the Cairo Metro Line 2.
and 6b.
The two curves pertain only to settle ~+ o , . 0 ~ , ~'- ....:- .......
ments associated with the excavation, A ~ ~ ~ i • ROD
design and execution stages under nor-
real construction conditions. The pre- " _°~i ~ i • oPntA
0,02
dictions do not account ibr other activi-
ties, such as dewatering, poor work-
manship or external eftbcts that may
cause instability.
The results of the computations for ~..~..................... ~ ............ -.. X LOT-I0
the design of the shafts contain the o.0
deformed line of the diaphragm wall. • NAGUIR
The volume of the soil confined be-
tween the initial and final position of X -t-MAZE
the wall, Vw, and the m ~ m u m value
of the horizontal movem~.nt ofthe wall, ¢jl 0 . 0 6 O MAZ-W
y ~ , are used as the main input data
for the settlement estimate of the A ROBE
ground surface and under the neigh-
boring structures. The volume is calcu- - - - - - Emc|ope
lated by numerical integration of the 0.08
horizontal displacement along the
depth of the wall. Figure 5. Summary of normalized settlement due to installation of the
Cairo Metro D. Walls.
ddlnaiam~
/ Vw L. il ~ il ---,¢ i (8)
II I' Yao cota ~ - 0.606 S m~
and the average slope is:
_ x max (9)
cota ~g S max
20 ~ 10
and at the distance x = 2i measured from 25
the soil surface to wall interface. 15 ....... ; : 4- • • ................
30
3.5. Comparison between Predicted and 35
20 - . ~ 4 ~. . . . . . .
Measured Settlements 40
This section presents actual field 45 s (Measured deflection)
measurements of the ground surface i 25
5O SI (Measured deflection)
settlements and the D. wall deflection at
selected Stations at the Cairo Metro line 0 10 20 30 . . . . . . S (Design)
30 - + - - S! (Design)
2. The actual D. wall deflections were Deflection (mm)
measured by installing inclinometers
inside the D. wall. Elewation reference (a) Deflection of D. Wall (b) G r o u n d Surface Settlement
points were installed at the ground sur-
face on the same line with the inclinom- Figure 8. Predicted a n d measured settlements at E1Behoos Station.
eter and perpendicular to the D. wall
(wherever possible). The results of these
measurements are presented in Figures
7 and 8 and are indicated as "measured,"
The design values of the wall deflection are also shown The measured settlements at the selected stations show
on these figures for comparison. Each figure presents the that they follow, to a reasonable extent, the general pat-
actual measured settlements (solid points) in mm versus tern predicted by either S or S1 curves. However, the
the distance from the D. wall. Two sets of the theoretical S measured settlements at Rod E1 Farag do not exactly
and S1 curves are also shown on these figures where the follow the expected (predicted pattern). It is logical to
designated settlement and volume ratios are R = 1.4 and
• • B
understand that the field measurements can involve sig-
R v = 0.75, respectively. The curves in sohd hnes are the nificant settlements caused by other activities at the site
predictions using the measured deflection of D. walls as such as dewatering, frequent and heavy traffic loads, other
input, while the curves in dashed lines represent the excavation or construction in the vicinity of the reference
predictions using the theoretical design values for the points. However, the main focus in viewing these measure-
deflection of D. walls. For the selected stations the maxi- ments is to justify the general pattern of movements.
mum deflection of the D. wall was similar, if not close, to Furthermore, the calculated wall movements are usually
the design value. higher than the expected ones because the designer some-
point of reflection, 1.
Cording and Hansmire (1975) conducted
a statistical analysis for the case of tunnel-
ing in medium to dense sand and concluded
that it is satisfactory to assume that the
Figure 9. Definition of the settlement curve and variables used in the volume of the settlement trough is equal to
computations. the volume of the soil lost into the tunnel.
This has been also satisfactory in case of
cohesive soils (Hamza 1995). Accordingly
times considers a factor of safety or even makes assump- the volume loss is calculated by
tions regarding the material parameters.
V,=V=WS(x)m= , (16)
4. Settlement D u e to B o r e d T u n n e l l i n g where Vs is the volume of the settlement trough and is equal
The methods currently adopted to predict settlements to the half the width of the settlement trough, W, multiplied
upon bored tunneling are generally categorized as sophisti- by the maximum settlement. Therefore,
cated/numerical and empirical correlation. Many research- V~ (%)= 2.507 i S(X)m / V x 100 (17)
ers [e.g,. Ghaboussi et al. (1983), Finno and Clough (1985),
Row and Lee (1992)] have adopted numerical methods Equations (15) and (17) have three unknowns (i, Vl and
based on simplifying hypotheses with respect to the geom- S(X)m:). Numerous empirical studies have been previously
etry and the soil constitutive behavior. Fang, Lin and Su attempted by different authors to estimate the distance to
(1994) pointed out t h a t although these methods might the point ofirdlection, i. One approach, presented by O'Reilly
provide a rational analysis of the problem, the cost and time and New (1982), is to assume that the distance i is a linear
consumed to perform such analyses are quite substantial. function of the depth of the tunnel. O'Reilly and New gave
The simulation of the variably different tunneling shields the following relationships
used in practice and the level of workmanship provide a i = 0.43z +1.1 for cohesive soils, and (18)
major difficulty, if not a challenge, for implementation in
i = 0.28z - 0.1 for cohesionless soils (19)
sophisticated numerical analyses. Accordingly, the use of
empirical correlation, based on actual field measurements, where i and z are in meters.
is mostly favored by m a n y designers as a more practical Equations (18) and (19) have been used successfully by
prediction method. other researchers to predict the ground surface settlements
Using the empirical prediction method requires the avail- in the case of homogenous soils, where the ground is uni-
ability of a reasonable database of measurements from case form from the surface to the tunnel. Unfortunately, this is
histories of tunneling in similar ground and under similar not the case for the Cairo Metro Tunnel, where the soil
conditions. profile is characterized by different layers.
It is now well established t h a t the shape of the settle- Other empirical studies for estimating the distance i
ment trough at the surface due to tunneling in soft ground have been summarized by H a m z a (1995) in the comprehen-
can be reasonably represented by the error function curve. sive report on Tunnel Monitoring. Most of these studies
Many authors have shown t h a t this approach adequately have shown that the value of i can be estimated with very
models the shape of the settlement trough (e.g. Peck 1969; close approximation from the geometric relationship,
Schmidt 1969; O'Roilly and New 1982; Ata 1996). i_ (20)
4.1. Procedure for Estimating the Settlement Trough where:
a = tunnel radius, and
Underground tunneling results in a state of stress relax-
ation in the surrounding soil. The volume of the soil that is K and n are empirical parameters that depend on the
displaced or relaxed across the perimeter of the tunnel is type of soil above the tunnel axis.
termed as the ground loss. The percentage ground loss, V~ The use of the following values of K and n has been
(%), is conventionally expressed as a percentage of the ratio previously suggested:
of the volume of lost ground to the theoretical volume of the (1) K = 1.00 and n = 0.80 for clays (Schmidt 1969;
tunnel, V. As a result of this volume loss the ground surface Clough and Schmidt 1981)
depresses, forming what is known as the settlement trough. (2) K = 1.00 and n = 1.00 for clays (Attewell 1981)
Many authors have used the normal distribution (or error
u
Lot 42
Lot 40
J
m
*
Lot 42
Lot 42
I i
--
: ...... Lot 46
Lot 46
I
i'i
measured averaged 1.7.2%e predictions
overestimated the measured values by ~/ 2 a 2
approximately 74%. The comparison of
volumes of settlements for Phase 2A
versus those at the begimning of tunnel-
ing (Phase 1) show a clear improvement n
with regard to the application of the
slurry overpressure. o Phase i
The results from the back-analysis
of the settlement data proved t h a t the o 8 I i I | J •
Volume 14, Number 3, 1999 Tubr~hLINO AND UNDERGROUND SPACE TECHNOLOGY 289