Sample WBS EPC Project

The document outlines a global work breakdown structure (WBS) for an engineering, procurement, and construction (EPC) project for a client. It details the project scope across 6 levels, with the top level allocated to engineering/design services (15%) and the remaining portions allocated to procurement, construction, and commissioning. The engineering/design services are further broken down into project management (5%) and various engineering design disciplines like process, piping, mechanical, electrical, each containing specifications, drawings, data sheets, and other deliverables.

Uploaded by

Navneet Soni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
4K views7 pages

Sample WBS EPC Project

The document outlines a global work breakdown structure (WBS) for an engineering, procurement, and construction (EPC) project for a client. It details the project scope across 6 levels, with the top level allocated to engineering/design services (15%) and the remaining portions allocated to procurement, construction, and commissioning. The engineering/design services are further broken down into project management (5%) and various engineering design disciplines like process, piping, mechanical, electrical, each containing specifications, drawings, data sheets, and other deliverables.

Uploaded by

Navneet Soni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Global Work Breakdown Structure (WBS) - Doc. No.

xx-xx-xxxx-xx
COMPANY LOGO CLIENT LOGO

EPC Works for XYZ Project


Level 1 Level - 2 Level - 3 Level-4 Level - 0 Level - 1 Level - 2 Level-3 Level-4

EPC WORKS FOR XYZ PROJECT 100.00%

1 ENGINEERING/DESIGN (Home Office Services) 15.00%

1.1 Project Management 5.00%


1.1.1 Common (Project Management)
1.1.1.1 Preliminaries
1.1.1.2 Procedures
1.1.1.3 Statutory Clearances (NOC's, Permit etc)
1.1.1.4 Others (Project Management Level of Effort)
1.2 Engineering & Design Services 70.00%
1.2.1 Common (Engineering Management)
1.2.1.1 Specification/ Procedures / Reports / Calculations / O&M Manual
1.2.1.2 Data Sheets
1.2.1.3 Drawings
1.2.1.4 Material Requisitions
1.2.1.5 Technical Bid Evaluation (TBE)
1.2.1.6 Vendor Documents
1.2.2 Process
1.2.2.1 Specification/ Procedures / Reports / Calculations
1.2.2.2 Data Sheets
1.2.2.3 Drawings
1.2.2.4 Material Requisitions
1.2.2.5 Technical Bid Evaluation (TBE)
1.2.2.6 Vendor Documents
1.2.3 Piping
1.2.3.1 Specification/ Procedures / Reports / Calculations
1.2.3.2 Modelling & Model Reviews
1.2.3.3 Data Sheets

From Deliverables Register as per Man-hours

From Deliverables Register as per Man-hours


1.2.3.4 Drawings
1.2.3.5 Material Requisitions
1.2.3.6 Technical Bid Evaluation (TBE)
1.2.3.7 Vendor Documents
1.2.4 Mechanical - Static
1.2.4.1 Specification/ Procedures / Reports / Calculations
1.2.4.2 Data Sheets
1.2.4.3 Drawings
1.2.4.4 Material Requisitions
1.2.4.5 Technical Bid Evaluation (TBE)
1.2.4.6 Vendor Documents
1.2.5 Mechanical - Rotary
1.2.5.1 Specification/ Procedures / Reports / Calculations
1.2.5.2 Data Sheets
1.2.5.3 Drawings
1.2.5.4 Material Requisitions
1.2.5.5 Technical Bid Evaluation (TBE)
1.2.5.6 Vendor Documents
1.2.6 Mechanical - Package
1.2.6.1 Specification/ Procedures / Reports / Calculations
1.2.6.2 Data Sheets
1.2.6.3 Drawings
1.2.6.4 Material Requisitions
1.2.6.5 Technical Bid Evaluation (TBE)
1.2.6.6 Vendor Documents
1.2.7 Electrical incl. CP
1.2.7.1 Specification/ Procedures / Reports / Calculations
1.2.7.2 Data Sheets
1.2.7.3 Drawings
1.2.7.4 Material Requisitions

Page 1 of 7
Global Work Breakdown Structure (WBS) - Doc. No. xx-xx-xxxx-xx
COMPANY LOGO CLIENT LOGO

EPC Works for XYZ Project


Level 1 Level - 2 Level - 3 Level-4 Level - 0 Level - 1 Level - 2 Level-3 Level-4

EPC WORKS FOR XYZ PROJECT 100.00%

1.2.7.5 Technical Bid Evaluation (TBE)


1.2.7.6 Vendor Documents
1.2.8 Instrumentation & Control
1.2.8.1 Specification/ Procedures / Reports / Calculations
1.2.8.2 Data Sheets
1.2.8.3 Drawings
1.2.8.4 Material Requisitions
1.2.8.5 Technical Bid Evaluation (TBE)
1.2.8.6 Vendor Documents
1.2.9 Telecommunication
1.2.9.1 Specification/ Procedures / Reports / Calculations
1.2.9.2 Data Sheets
1.2.9.3 Drawings
1.2.9.4 Material Requisitions
1.2.9.5 Technical Bid Evaluation (TBE)
1.2.9.6 Vendor Documents

From Deliverables Register as per Man-hours

From Deliverables Register as per Man-hours


1.2.10 Process Safety
1.2.10.1 Specification/ Procedures / Reports / Calculations
1.2.10.2 Data Sheets
1.2.10.3 Drawings
1.2.10.4 Material Requisitions
1.2.10.5 Technical Bid Evaluation (TBE)
1.2.10.6 Vendor Documents
1.2.11 Civil & Structural (incl. Buildings)
1.2.11.1 Specification/ Procedures / Reports / Calculations
1.2.11.2 Data Sheets
1.2.11.3 Drawings
1.2.11.4 Material Requisitions
1.2.11.5 Technical Bid Evaluation (TBE)
1.2.11.6 Vendor Documents
1.2.12 Pipeline

1.2.12.1 Specification/ Procedures / Reports / Calculations


1.2.12.2 Data Sheets
1.2.12.3 Drawings
1.2.12.4 Material Requisitions
1.2.12.5 Technical Bid Evaluation (TBE)
1.2.12.6 Vendor Documents
1.2.13 Corrosion and Materials
1.2.13.1 Specification/ Procedures / Reports / Calculations
1.2.13.2 Data Sheets
1.2.13.3 Drawings
1.2.13.4 Material Requisitions
1.2.13.5 Technical Bid Evaluation (TBE)
1.2.13.6 Vendor Documents
1.3 Procurement Support Services (e.g. Issue RFQ, Receive Bid, P.O./LOA issuance etc.) 20.00%
1.3.1 Pipeline
1.3.1.1 Line pipes
1.3.1.2 Flow lines
1.3.1.3 Valves
1.3.1.4 Fitting
1.3.1.5 Coating
1.3.1.6 Special Items
1.3.2 Piping
1.3.2.1 Pipes
1.3.2.2 Fittings
1.3.2.3 Flanges
1.3.2.4 Valves
1.3.2.5 Others

Page 2 of 7
Global Work Breakdown Structure (WBS) - Doc. No. xx-xx-xxxx-xx
COMPANY LOGO CLIENT LOGO

EPC Works for XYZ Project


Level 1 Level - 2 Level - 3 Level-4 Level - 0 Level - 1 Level - 2 Level-3 Level-4

EPC WORKS FOR XYZ PROJECT 100.00%

1.3.3 Mechanical -Static


1.3.3.1 Tanks
1.3.3.2 Vessels
1.3.3.3 Filters
1.3.3.4 Others
1.3.4 Mechanical-Rotary
1.3.4.1 Multi Phase Pumps
1.3.4.2 Water injection surface pump
1.3.4.3 API Pumps
1.3.4.4 Non API Pumps
1.3.4.5 Others
1.3.5 Mechanical -Packages incl. HVAC
1.3.5.1 Package Equipment

From Deliverables Register as per Man-hours

From Deliverables Register as per Man-hours


1.3.5.2 HVAC
1.3.5.3 Others
1.3.6 Electrical incl. CP
1.3.6.1 Elect. Equipments (Incl. SWGR, Transformers, DG Set, UPS etc.
1.3.6.2 Elect. Cables (HV, MV, LV etc.)
1.3.6.3 Electircal Bulks
1.3.6.4 CP System
1.3.6.5 Others
1.3.7 Instrumentation
1.3.7.1 Instrument Equip. (DCS, ITR, HIPPS etc.)
1.3.7.2 Tag items (PI, TI, MOV, Control Values, other Values etc.)
1.3.7.3 Insrument Control Cables
1.3.7.4 Insturment Bulks
1.3.7.5 Others
1.3.8 Telecom
1.3.8.1 Telecom Equipment
1.3.8.2 Telecom Cables
1.3.8.3 Telecom Bulks
1.3.8.4 Others
1.3.9 HSE
1.3.9.1 Fire Supression & Fire Fighting items
1.3.9.2 Others
1.3.10 Civil and Structural
1.3.10.1 Structural Steel (Incl. all related)
1.3.10.2 Civil incl. Buildings
1.3.10.3 Others
1.4 Subcontracting Support Services (e.g. Issue RFQ, Receive Bid, P.O./LOA issuance etc.) 5.00%
1.4.1 Engineering Services
1.4.1.1 Engineering & HSE Studies
1.4.1.2 Workshops/Third Parties
1.4.2 Construction/Comm. Works
1.4.2.1 Survey Works (Topo/Geo etc.)
1.4.2.2 Temporary Facilities Construction
1.4.2.3 Construction Civil/Structural Works incl. Buildings
1.4.2.4 Construction Mechanical/Piping/NDT Works
1.4.2.5 Construction Pipeline/Flow-lines Works
1.4.2.6 Construction E&I, Telecom Works
1.4.2.7 Construction Painting, Coating, Insulation Works
1.4.2.10 Others

2 PROCUREMENT (Ordering, Manufacturing and Delivery) 45.00%

2.1 Equipment 45.00%


2.1.1 Mechanical -Static
2.1.1.1 Tanks

Page 3 of 7
Global Work Breakdown Structure (WBS) - Doc. No. xx-xx-xxxx-xx
COMPANY LOGO CLIENT LOGO

EPC Works for XYZ Project


Level 1 Level - 2 Level - 3 Level-4 Level - 0 Level - 1 Level - 2 Level-3 Level-4

EPC WORKS FOR XYZ PROJECT 100.00%

2.1.1.2 Vessels
2.1.1.3 Filters
2.1.1.4 Drums
2.1.1.5 Others
2.1.2 Mechanical-Rotary
2.1.2.1 Compressors

From Procurement Register as per Dollar $ Value

From Procurement Register as per Dollar $ Value


2.1.2.2 Water Injection Pumps
2.1.2.3 API Pumps
2.1.2.4 Non-API Pumps
2.1.2.5 Others
2.1.3 Mechanical -Packages incl. HVAC
2.1.3.1 Package Equipment
2.1.3.2 HVAC
2.1.3.3 Others
2.1.4 Electrical incl. CP
2.1.4.1 Elect. Equipments (Incl. SWGR, Transformers, DG Set, UPS etc.
2.1.4.2 Cothdic Protection (CP) System
2.1.4.3 Others
2.1.5 Instrumentation
2.1.5.1 Instrument Equipment (DCS, ITR, HIPPS etc.)
2.1.5.2 Tag items (PI, TI, MOV, Control Values, other Values etc.)
2.1.5.3 Others
2.1.6 Telecom
2.1.6.1 Telecom Equipment
2.1.6.2 Others
2.2 Bulks 35.00%
2.2.1 Piping
2.2.1.1 Pipes
2.2.1.2 Fittings
2.2.1.3 Flanges
2.2.1.4 Valves
2.2.1.5 Others

From Procurement Register as per Dollar $ Value

From Procurement Register as per Dollar $ Value


2.2.2 Electrical
2.2.2.1 Elect. Cables (HV, MV, LV etc.)
2.2.2.2 Electircal Bulks
2.2.2.3 Others
2.2.3 Instrumentation
2.2.3.1 Insrument Control Cables
2.2.3.2 Insturment Bulks
2.2.3.3 Others
2.2.4 Telecom
2.2.4.1 Telecom Cables incl. FOC
2.2.4.2 Telecom Bulks
2.2.4.3 Others
2.2.5 HSE
2.2.5.1 Fire Suppression & Fire Fighting items
2.2.5.2 Others
2.2.6 Civil and Structural
2.2.6.1 Structural Steel (Incl. all related)
2.2.6.2 Civil incl. Buildings
2.2.6.3 Others
2.3 Pipeline / Flow-lines 20.00%
2.3.1 Pipeline / Flow lines
2.3.1.1 Line Pipes
2.3.1.2 Flow-lines
2.3.1.3 Valves
2.3.1.4 Fitting
2.3.1.5 Coating

Page 4 of 7
Global Work Breakdown Structure (WBS) - Doc. No. xx-xx-xxxx-xx
COMPANY LOGO CLIENT LOGO

EPC Works for XYZ Project


Level 1 Level - 2 Level - 3 Level-4 Level - 0 Level - 1 Level - 2 Level-3 Level-4

EPC WORKS FOR XYZ PROJECT 100.00%

2.3.1.6 Speciality Items

3 CONSTRUCTION Incl. Pre-Commissioning/Commissioning/As-Built 40.00%

3.1 Temporary Camp & Site Facilities 6.00%


3.1.1 Camps & Facilities
3.1.1.1 Camps & Facilities for Accomodation
3.1.2 Office Facilities
3.1.2.1 Office Facilities incl. Contractor/Company
3.1.3 Others
3.1.3.1 Warehouse/Yards/Workshops etc.
3.2 Fabrication Drawings & Construction Procedures 3.00%
3.2.1 Procedures & Method Statements
3.2.1.1 Procedures
3.2.1.2 Method Statements
3.2.1.3 Others
3.2.2 Fabrication Drawings
3.2.2.1 Fabrication Drawings
3.2.2.2 Others
3.3 Pre-Fabrication/Fabrication (Piping, Steel Structure) 4.00%
3.3.1 Structural Steel
3.3.1.1 Main Structural Works
3.3.1.2 Pipe Supports
3.3.1.3 Others
3.3.2 Piping
3.3.2.1 U/G Piping
3.3.2.2 A/G Piping
3.4 Construction incl.Mechanical Completion 78.00%
3.4.1 Civil & Structural Works
3.4.1.1 Survey Works (Topo/Geo etc.)
3.4.1.2 Earthwork Cut & Fill (Site Grading)
3.4.1.3 Earthwork (Excavation & Back filling)
3.4.1.4 Concrete Works
3.4.1.5 Asphalt Road
3.4.1.6 Structural Steel Erection
3.4.1.7 Fencing Works
3.4.1.8 Paving & Gravel Works
3.4.1.9 Others

From Control Register as per Man-hours

From Control Register as per Man-hours


3.4.2 Buildings
3.4.2.1 Sub-station Building
3.4.2.2 Control Room & Admin Building
3.4.2.3 Workshop Building
3.4.2.4 Security Building
3.4.2.5 Others
3.4.3 Mechanical Equipment
3.4.3.1 Static Equipment
3.4.3.2 Rotary Equipment
3.4.3.3 Package Equipment
3.4.3.4 Tanks/Vessels/Drums
3.4.3.5 Others
3.4.4 Piping
3.4.4.1 A/G Piping
3.4.4.2 U/G Piping
3.4.4.3 Others
3.4.5 Pipe Line
3.4.5.1 Right of Way - Identifiction and Development
3.4.5.2 Road Crossings

Page 5 of 7
Global Work Breakdown Structure (WBS) - Doc. No. xx-xx-xxxx-xx
COMPANY LOGO CLIENT LOGO

EPC Works for XYZ Project


Level 1 Level - 2 Level - 3 Level-4 Level - 0 Level - 1 Level - 2 Level-3 Level-4

EPC WORKS FOR XYZ PROJECT 100.00%

3.4.5.3 Pipe Lines (Export Line)


3.4.5.4 Pipe Lines (Flow Line)
3.4.5.5 Scrapper Launcher and Reciever
3.4.5.6 FOC
3.4.5.7 Others
3.4.6 Electrical Incl. CP
3.4.6.1 Elect. Equipments (Incl. SWGR, Transformers, DG Set, UPS etc.
3.4.6.2 Electrical Panel Installation
3.4.6.3 CP System Insllation
3.4.6.4 Cable Tray Installation and Cabling Work

From Control Register as per Man-hours

From Control Register as per Man-hours


3.4.6.5 Lighting Work
3.4.6.6 Earthing and Grounding Work
3.4.6.7 Others
3.4.7 Instrumentation
3.4.7.1 Control System (DCS, PCS, ESD, FGS)
3.4.7.2 Cable Tray Installation and Cabling Work
3.4.7.3 Field Instrument Installation
3.4.7.4 Hook-ups
3.4.7.5 Others
3.4.8 Telecom
3.4.8.1 FOC Laying
3.4.8.2 Telecom Equipment Installation (ACS, CCTV, PAGA)
3.4.8.3 Others
3.4.10 Safety
3.4.10.1 Installation of HSE items
3.4.10.2 Others
3.4.11 Tie - Ins with Existing Facilities
3.4.11.1 Piping Tie-Ins
3.4.11.2 Instrumentation Tie-Ins
3.4.11.3 Electrical Tie-Ins
3.4.11.4 Telecom Tie-Ins
3.5 Pre-Commissioning 4.00%
3.5.1 Process Systems
3.5.1.1 Oil Well
3.5.1.2 Multiport Selector Valve
3.5.1.3 Multiphase Flow Meter
3.5.1.4 Water Injection system
3.5.1.5 Oil Reception
3.5.2 Utility Systems
3.5.2.1 Air Compressor Package

From Control Register as per Man-hours

From Control Register as per Man-hours


3.5.2.2 Nitrogen Generation Package
3.5.2.3 Oxygen Scavanger Injection Package
3.5.2.4 Corrosion Inhibitior Injection Package
3.5.2.5 Biocide Inhibitor Injection Package
3.5.2.6 Diesel Bulk Storage Package
3.5.2.7 Portable Water System
3.5.2.8 Closed Drain Knockout System
3.5.2.9 Safety System
3.5.2.10 HVAC System
3.5.3 Electrical Systems
3.5.3.1 Electrical Distribution System at Well Head
3.5.3.2 Electrical Technical Room (ETR)
3.5.3.3 Cathodic Protection System
3.5.3.4 Sub-Station
3.5.4 Instrumentation/Telecom Systems
3.5.4.1 DCS, PCS, ESD, FGS
3.5.4.2 Well Head Control Panel (WHCP)/ Remote I/O
3.5.4.3 Intrument Technician Room (ITR)
3.5.4.4 F&G System

Page 6 of 7
Global Work Breakdown Structure (WBS) - Doc. No. xx-xx-xxxx-xx
COMPANY LOGO CLIENT LOGO

EPC Works for XYZ Project


Level 1 Level - 2 Level - 3 Level-4 Level - 0 Level - 1 Level - 2 Level-3 Level-4

EPC WORKS FOR XYZ PROJECT 100.00%

3.5.4.5 HIPPS System


3.5.4.6 Telecom System incl. PAGA
3.6 Commissioning & RFSU 3.00%
3.6.1 Process Systems
3.6.1.1 Oil Well
3.6.1.2 Multiport Selector Valve
3.6.1.3 Multiphase Flow Meter
3.6.1.4 Water Injection system
3.6.1.5 Oil Reception
3.6.2 Utility Systems
3.6.2.1 Air Compressor Package
3.6.2.2 Nitrogen Generation Package

From Control Register as per Man-hours

From Control Register as per Man-hours


3.6.2.3 Oxygen Scavanger Injection Package
3.6.2.4 Corrosion Inhibitior Injection Package
3.6.2.5 Biocide Inhibitor Injection Package
3.6.2.6 Diesel Bulk Storage Package
3.6.2.7 Portable Water System
3.6.2.8 Closed Drain Knockout System
3.6.2.9 Safety System
3.6.2.10 HVAC System
3.6.3 Electrical Systems
3.6.3.1 Electrical Distribution System at Well Head
3.6.3.2 Electrical Technical Room (ETR)
3.6.3.3 Cathodic Protection System
3.6.3.4 Sub-Station
3.6.4 Instrumentation/Telecom Systems
3.6.4.1 DCS, PCS, ESD, FGS
3.6.4.2 Well Head Control Panel (WHCP)/ Remote I/O
3.6.4.3 Intrument Technician Room (ITR)
3.6.4.4 F&G System
3.6.4.5 HIPPS System
3.6.4.6 Telecom System incl. PAGA
3.7 As Built, Final Documentation & Handover 2.00%
3.7.1 As-built
3.7.1.1 As-built Drawings/Documents
3.7.2 Final Documentations
3.7.2.1 Final Documentation
3.7.3 Handover/Close-out
3.7.3.1 Handover & Close-out (PAC)

NOTE: Areawise (Area-1, Area-2, Area-3 etc.) Functional WBS shall also be prepared considering above Work Breakdown Structure (WBS) for Engineering, Construction & Commissioning only