QC Procedure - Bored Pile Work: Project: ....................... Client: ........................
QC Procedure - Bored Pile Work: Project: ....................... Client: ........................
QC Procedure - Bored Pile Work: Project: ....................... Client: ........................
Revision: 0
No. Flow of Activities Check item Method of measure Check Frequency Specification/Criteria Record
QC SV S
REMARK
2 Casing Reference peg All Verticality 1/100. Final position + 75mm Check list △ △ ○
Bore piling
Water level min. 2m above ground water
Water in bore hole Visual Random level i.e.RL -3m or up to ground level to
control
△
3 Toe depth Record All min.200 above bore hole toe Check list ○ △
Rebar installation
4 Install tremie pipe Nos. of pipe All max. 200mm above toe level Check Sheet △ △
Concreting
Water plunger Visual All Before casting ○ △
Concrete Slump Random Slump 16 + 2 Check Sheet ○ △ △
Travel time Batching record Random Max. 2hrs ○ △
Tremie pipe Tape Random Min.1.5m below concrete upper surface - △
Casting height Tape All Cut of level + 1m Check Sheet △ ○ △
Extract casing Visual Random Remove soon after complete casting △
5 Cleaning tremie pipe Visual Random Soon after remove from concrete △ △
Cleaning & Curing
Min.7 days strength before allow for
Curing Casting record All
excavation
- △ ○
Back fill blind hole Visual All After concrete age >12 hrs △
6
Excavation & pile head
treatment
INSPECTION CHECKLIST - BOREPILING WORK
SUB-CONTRACTOR :
PILE NO.
CRITERIA / Acceptable
NO. ITEMS TO BE CHECKED
CH'K METHOD YES NO DATE
1 Pre-Installation
a) Peg position Theodolite
b) Bore location 6m from new casted pile Record Sign :
c) Collection pit Visual
d) Rebar cage Dwg
e) Concrete cover ; 75mm Measure Sign :
2 Bore piling
a) Casing position Offset line Actual :
b) Kelly bar verticality Spirit Level
c) Toe Level ; RL -30m Measure Actual :
d) Base cleaning min.30min after Record
Cage 2 : 12m Ø:
Cage 3 :
f) Tremie pipe
- Cleanliness Visual
- Top level Measure Actual :
- Tremie total length Record Actual :
- Toe depth max.200mm above toe Calculate Actual :
g) Bore hole water level
min. 2m above ground water level Measure Water level : 3m
Bore hole water level :
Sign : Sign :
3 Concreting G30N
a) Concrete Slump ; 18 + 2 Slump test Actual :
b) Time Time Start :
c) Top level ; min.1 x Ø above cut off level Measure Actual :
d) Concrete Volume Record Dwg :
Differences % :
REMARKS
( STS )
( KI )
Time :
Time :
Lapping 1 : mm
Lapping 2 : mm
Finish :
Actual