QC Procedure - Bored Pile Work: Project: ....................... Client: ........................

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Project : .......................

Revision: 0

Client : ......................... Date : ...........


Prepared by:

QC PROCEDURE - BORED PILE WORK


CHECK SV SUPERVISOR
RANDOM CHECK S SURVEYOR
S SURVEYOR

No. Flow of Activities Check item Method of measure Check Frequency Specification/Criteria Record
QC SV S
REMARK

1 Position Theodolite All As per drawing Check list △ △ ○


Pre - Installation
Radius 3m from casted bore pile which
Bore location sequence Casting record All
less then 2 days strength △ ○

Embankment Visual All To retain the water flow to adjacent △


Collection pit Visual All To pump back to collection pit △ △
Rebar fabrication Visual All As per drawing Check list ○ ○
Concrete cover Visual Random Sufficient spacer and cover i.e.75mm Check list △ △
Tremie Pipe Visual Random Clean condition △

2 Casing Reference peg All Verticality 1/100. Final position + 75mm Check list △ △ ○
Bore piling
Water level min. 2m above ground water
Water in bore hole Visual Random level i.e.RL -3m or up to ground level to
control

Drilling bar Spirit Level Random Verticality 1/500 △ △ ○

Drilling depth Tape All As per design requirement Check Sheet ○ △ △

Allow min.30min for sediment to settle


Sediment Time All
before final bore hole cleaning
Check list △ △

3 Toe depth Record All min.200 above bore hole toe Check list ○ △
Rebar installation

Length Record All As per specification Check list ○ △ △

Lapping Measure All As per specification i.e. 40D Check list △ ○

Joint Visual Random Spot weld △ △

4 Install tremie pipe Nos. of pipe All max. 200mm above toe level Check Sheet △ △
Concreting
Water plunger Visual All Before casting ○ △
Concrete Slump Random Slump 16 + 2 Check Sheet ○ △ △
Travel time Batching record Random Max. 2hrs ○ △
Tremie pipe Tape Random Min.1.5m below concrete upper surface - △
Casting height Tape All Cut of level + 1m Check Sheet △ ○ △
Extract casing Visual Random Remove soon after complete casting △

5 Cleaning tremie pipe Visual Random Soon after remove from concrete △ △
Cleaning & Curing
Min.7 days strength before allow for
Curing Casting record All
excavation
- △ ○
Back fill blind hole Visual All After concrete age >12 hrs △

6
Excavation & pile head
treatment
INSPECTION CHECKLIST - BOREPILING WORK

PROJECT : SENAYAN SQUARE OFFICE TOWER 3 DATE :

SUB-CONTRACTOR :

PILE NO.

CRITERIA / Acceptable
NO. ITEMS TO BE CHECKED
CH'K METHOD YES NO DATE

1 Pre-Installation
a) Peg position Theodolite
b) Bore location 6m from new casted pile Record Sign :
c) Collection pit Visual
d) Rebar cage Dwg
e) Concrete cover ; 75mm Measure Sign :

2 Bore piling
a) Casing position Offset line Actual :
b) Kelly bar verticality Spirit Level
c) Toe Level ; RL -30m Measure Actual :
d) Base cleaning min.30min after Record

e) Rebar Installation Measure Cage 1 : 12m Ø:

Cage 2 : 12m Ø:

Cage 3 :

f) Tremie pipe
- Cleanliness Visual
- Top level Measure Actual :
- Tremie total length Record Actual :
- Toe depth max.200mm above toe Calculate Actual :
g) Bore hole water level
min. 2m above ground water level Measure Water level : 3m
Bore hole water level :

Sign : Sign :

3 Concreting G30N
a) Concrete Slump ; 18 + 2 Slump test Actual :
b) Time Time Start :
c) Top level ; min.1 x Ø above cut off level Measure Actual :
d) Concrete Volume Record Dwg :
Differences % :

4 OTHER COMMENT IF ANY ;

Page 1 of 2 KI/FORM/QC/BP Rev.1


Page 1 of 2 KI/FORM/QC/BP Rev.1
ORK

Form Ref. : KI/FORM/QC/BP/01

REMARKS

( STS )

( KI )

Time :
Time :

Lapping 1 : mm

Lapping 2 : mm

hole water level :

Finish :

Actual

Page 1 of 2 KI/FORM/QC/BP Rev.1


Page 1 of 2 KI/FORM/QC/BP Rev.1