UPVC high Pressure Water Supply Piping

System Installation Procedure

Prior to installation of uPVC High Pressure water Supply Piping System, the supervisor and foreman will verify
and ensure that all the safety requirements have been complied with and are in place. The supervisor will verify
that all relevant approved latest redivisions of shop drawing, technical submittals, inspection and test plans are
in the work place for installation reference. This also includes installation procedures.
The supervisor and foreman will inspect all the water supply piping materials delivered to the work place and
ensure that these are the required materials and also for damage or defect. Materials found not to be as per
requirement or with damage or defect will be set aside. These will also be reported in a Non-Conformance
Report to the QA/QC Engineer.

To ensure that deterioration of the material does not occur during storage, it is imperative that the following
recommendations are adhered to.

Storage of Water supply piping material shall be on the elevated rack above Ground level minimum 300mm.
uPVC high Pressure Pipes should be stored on well space secured area which separate the material from other
stored equipment to avoid mixed up and accidental clashing with other materials which may result to damage.
uPVC High pressure Pipes should be protected from weather elements by means of placing tarpaulins or similar
sheets over them securely fixed to the timber support posts.
The supervisor and foreman will orient and familiarize all the plumbers and labors involved in the installations
regarding the relevant approved shop drawings, technical submittals, installation procedures and details,
acceptance criteria and safety requirements.

The supervisor and foreman will examine surfaces to receive water supply system works for compliance with
installation tolerances and other required conditions, as described in the installation requirement. Installation
will not proceed until unsatisfactory conditions have been corrected.

Installation of uPVC High Pressure water supply piping System

Unless otherwise specified, all installation shall be according approved shop drawings and contract
specifications. Drawing plans, schematics, and diagrams indicate general, location and arrangement of water
supply piping system. Trench will be excavated by the civil contractor according to the approval levels.
Install water supply piping as indicated unless deviations to layout are approved on coordination drawings. Pipe
will be laid on uniform bedding material aid at the appropriate grade. Thrust block will installed at locations
where pipes change direction. Ensure that the two pipes are aligned correctly and then the pipes to be joined
using solvent welding process.

Cut the pipe at the right angle to the pipe axis using suitable sharp pipe cutter. The pipe may be cut quickly and
efficiently by wheel-type plastic tubing cutter or ratchet type cutters or fine-tooth saws. Remove burrs and
filings from the outside and inside of the tube. Clean the pipe and the fitting with dry cloth, in order to avoid
any dust or sand that might affect the quality of the joint. Clean the spigot and socket area with a dry cloth to
remove all dirt and moisture from spigot and socket.

Apply cleaner solution to the outside surface of the pipe and to the outside surface of the pipe and to the
outside surface of the fitting. Cleaner will prepare the surface for jointing for better quality joint. Using suitably
sized brush, apply a thin even coat of solvent cement to the internal surface of the fitting socket first then to the
pipe spigot. Excess solvent cement must be avoided as pools of solvent cement will continue to attack the PVC
and weaken the pipe. Excess solvent cement will accumulate inside the system and may cause a reduction in
the joint cross section.
While both surface are still wet with solvent cement, insert the pipe into the fitting in a single movement. Do
not stop halfway, since the bond will start to set immediately and it will be almost impossible to insert further.
For a better distribution of the solvent cement, twist the pipe ¼ turn during insertion into the socket. Wipe any
access cement from the pipe and leave the joint to dry completely.

Leave the system for at least 12 hours before pressure testing. Connect the pipe by flanges adapter to the
incoming main pipe with water meter chamber through the manhole. Ensure all pipes passing through the
manhole. Ensure all pipes passing through exterior walls, the opening shall be sealed with approved water
proofing material or approved caulking compound to seal against water, air and sand.

In process works shall be monitored for quality of workmanship and installation against approved construction
drawings by the relevant site engineer, supervisor and QA/QC Engineer.

Pressure Testing of uPVC High Pressure Water Supply Piping System


The following procedure to be adopted on site for pressure testing.

All draw off points have to be plugged with stopper and shut off main valve to section of pipe to be tested.
Connect pressure gauge to the lower of pipeline. Start filling water into pipes by using hand pump. The valve
located at higher section of the pipe has to be opened periodically to release air out from the pipeline when
water is being pumped. Subject piping to static water pressure of 1.5 times of operation pressure (150 psig/10
bar) without exceeding pressure rating of pipe.
Maintain the pressure inside the pipeline for 4 hours and inspect for leakages at pipe join and pipe body. The
final pressure reading at the pressure gauge should not drop more than 5% from the initial test pressure. Once
water test has been successfully carried out, remove all stoppers and drain off water from the pipeline. Cover all
open ends of pipes and fittings to prevent debris from going into pipeline.