Concret Pouring External Areas
Concret Pouring External Areas
Concret Pouring External Areas
Task Planning
Permit/Work Order No: Name of Company: Dept: Date:
General Description:
CONCRETE POURING , RUBBER TILES & GRANITE TILES FIXING AND
LANDSCAPING IN EXTERIOR AREA OF HARBOR EAST SCHOOL
Emergency Action Plan (Risk Management)
Area / Unit / Building Name (please
HARBOR EAST SCHOOL
specify):
Communication
Stop work conditions (reminders)
Adjacent work hazards Chemical spills or releases Excessive noise Fires and explosions
RFI’s completed
/issued/attached.
Contractor
AMR OSAMA 146263 0581525855
Safety Rep.
E&PM Project
HARIS SIDDIQUE 100219 0544701257
Engineer.
E&PM Safety
REDENTOR ROBLES 139588 0501731516
Specialist.
Page 1 of 9
To be filled by service provider / contractor
BADGE/ID
DEPARTMENT NAME POSITION DATE
NO.
RONILO GUADES
QA/QC QA/QC 146038
ESCUADRO
Supervisor Details:
Yrs. Of
BADGE /ID
Name Company Qualifications Experience
No.
in Role
IBRAHIM AL-SAYED
ABC 145918 CIVIL FOREMAN 20
MOHAMMED
Operatives Details
Yrs. of
Name Company Badge/ID No. Trade/skills Experience
in Role
CONCRETE POURING & LANDSCAPING
MUHAMMAD IKRAM ABC 144142 LABOR 2
QAMAR SHAHZAD ABC 144113 LABOR 1
SHAHBAZ AHMED ABC 144140 LABOR 2
MOHAMMED MAHBOB ABC 143482 TILE FIXER 10
TARAN SAH ABC 145791 MASON 5
ABOBAKAR HAGGAG ABC 2392866022 MASON 6
AYMAN HUSSAIN ABC 145817 MASON 4
AHMED MAHMOUND ABC 2392866204 MASON 5
RUBBER TILES FIXING
REYHOLD PINAS VENDOR 2290569892 TILE FIXER 2
BARUN SHARMA RAM VENDOR 2353921059 TILE FIXER 3
ROHALD RELEZ CUA VENDOR 4037171669 TILE FIXER 1
KINGDE JESUS CABAIS VENDOR 4037171644 TILE FIXER 4
WAFI MOHAMMAD VENDOR 2370088276 TILE FIXER 2
JOHN FELIX MARTE VENDOR 4037171636 TILE FIXER 1
Page 2 of 9
RISK ASSESSMENT MATRIX
Damage Injury
4 4
Total Fatality 4 8 12 16
Failure
3 3
Major Major 3 6 9 12
OUTCOME
2 2
Minor Minor 2 4 6 8
1 1
Nil No Injury 1 2 3 4
1 2 3 4
Unlikely Possible Probable Definite
PROBABILITY
Page 3 of 9
RISK = PROBABILITY x OUTCOME
METHOD STATEMENT
A Method Statement is an agreement between the workforces, Service Provider and the Person
or Organization requesting the work and that the work being undertaken is being managed and
any risk is mitigated to an acceptable level.
The method of work must be clearly communicated and understood by all parties involved.
Operatives undertaking the works the works supervisor and line managers must sign the
document as agreement with the method of works.
It must be noted that more than one method statement may be required for any sequence of
works.
Method statements and risk assessments go hand in hand, as the method of work is dictated
by the risks identified, and the risk is identified by the proposed method of work.
When conducting risk assessments in the first instance all built in safety experience must be
ignored. This will allow true identity of the risks associated with what work is proposed. Then
methods of work can be developed to reduce risk to an acceptable level.
Page 4 of 9
ENSURE YOU COLOR CODE THE RISK SCORES (refer to above matrix)
Risk Risk
Score Score
Please write details of work to be undertaken step by step
Without After
Controls Controls
TASK:
CONCRETE POURING IN EXTERIOR AREAS. 8 3
a) The sub base is compacted; the forms are set.
a) Using of JCB to transport
b) Crew will pour wet concrete into the forms using wheelbarrow
until they are full to the top edge.
Hazard Identified:
Control Measure
Comply to Work Permit System
Machine guard
Standby fire extinguisher
Ensure that tools and equipment are in good condition and
shall be daily inspected
All workers shall wear proper PPE such as, safety shoes and
concrete boots, safety glasses, hand gloves, dust mask.
Safety Officer will discuss the hazards in the operation and
advise safe working procedures.
Preventive maintenance of power tools
Sufficient light in concrete area
Page 5 of 9
Risk Risk
Score Score
Please write details of work to be undertaken step by step
Without After
Controls Controls
TASK:
RUBBER TILES AND LANDSCAPING IN EXTERIOR 8 3
AREAS.
Hazard Identified:
Control Measure
Comply to Work Permit System
Ensure that tools and equipment are in good condition and
shall be daily inspected
All workers shall wear proper PPE such as, safety shoes, safety
glasses, hand gloves, dust mask.
Safety Officer will discuss the hazards in the operation and
advise safe working procedures.
Page 6 of 9
Risk Risk
Score Score
Please write details of work to be undertaken step by step
Without After
Controls Controls
TASK:
GRANITE TILES AND LANDSCAPING IN EXTERIOR 8 3
AREAS.
Hazard Identified:
Cutting of tiles
Tool equipment are source of ignition
Extension cable over heating
Dust
Tile sharp edge.
Breakage of cutting disk
Uncontrolled electric hand tools
Risk
Damage to property
Overheating of cables
Breakage of cutting disk
Hand injury
Cut wounds
Eye injury
Heat transfer
Ergonomics practice
Control Measure
Comply to Work Permit System
Ensure that tools and equipment are in good condition and
shall be daily inspected
Safety Officer will discuss the hazards in the operation and
advise safe working procedures.
Competent personnel supervised by a qualified and
experienced supervisor shall only carry out the works.
Daily hazard analysis shall be done.
Preventive maintenance of power tools
Power tool guard.
All workers shall wear proper PPE such as, safety shoes, safety
glasses, hand gloves and dust mask.
Page 7 of 9
PLANT AND EQUIPMENT
TEST
SERIAL DATE OF LAST
ITEM NAME CERTIFICATE REMARKS
NUMBER MAINTENANCE
ATTACHED
HAND TOOLS
BOBCAT
Wheelbarrow
GRINDER
TEST
SERIAL DATE OF LAST
ITEM NAME CERTIFICATE REMARKS
NUMBER MAINTENANCE
ATTACHED
SAFETY
HELMET
SAFETY GLASS
HAND GLOVES
SAFETY
SHOES/LONG
BOOTS
DUST MASK
Page 8 of 9
ACKNOWLEDGEMENT
I acknowledge receiving and understanding these instructions, I will fully comply with the assigned task
requirements
(Supervisor will ensure completed combined Method Statement and Risk Assessment forms are forwarded to the Area /Bldg. Manager and
PTW Office)
Page 9 of 9