0% found this document useful (0 votes)
116 views6 pages

Beams and Girders Ground Floor

The document provides calculations for the materials needed for beams and girders on multiple floors of a building. For the ground floor it calculates the need for 10 pieces of plywood, 76 pieces of 2"x2"x14' bracing, and 40 pieces of 2"x3"x14' scaffolding. Similar calculations are provided for the first, second, third and fourth floors. It then summarizes the total quantities of formworks, bracing and scaffolding needed for the entire building, and calculates the common wire nails required.

Uploaded by

ELI BUSLIG
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
116 views6 pages

Beams and Girders Ground Floor

The document provides calculations for the materials needed for beams and girders on multiple floors of a building. For the ground floor it calculates the need for 10 pieces of plywood, 76 pieces of 2"x2"x14' bracing, and 40 pieces of 2"x3"x14' scaffolding. Similar calculations are provided for the first, second, third and fourth floors. It then summarizes the total quantities of formworks, bracing and scaffolding needed for the entire building, and calculates the common wire nails required.

Uploaded by

ELI BUSLIG
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

BEAMS AND GIRDERS

GROUND FLOOR:
L = (5 - 0.4)(2) + (1.2 - 0.2)(2) + (5.5 - 0.4)(2) = 21.4 m
A = 0.45(21.4) x 2 + (0.3+0.05+0.05)(21.4) = 27.82 m 2
1. Form
nPlywood = 27.82 m2 / 1.2 x 2.4 = 9.6597 pcs ~ 10 pcs - 4' x 8' x 1/4"

2. Bracing
BFT = 27.82 m2 x 12.71 BF/m2 = 353.5922 BF
n2"x2"x14' = 353.5922 BF/4.67 BF/pc = 75.7157 pcs ~ 76 pcs - 2"x2"x14' RoL

3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 21.4 m (6 + 7) BF/m = 278.2 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 278.2 BF/7 BF/m = 39.7429 pcs ~ 40pcs - 2"x3"x14' RoL

FIRST FLOOR:
L = (5 - 0.4)(3) + (1.2 - 0.2)(3) + (5.5 - 0.4)(4) = 37.2 m
A = 0.45(37.2) x 2 + (0.3+0.05+0.05)(37.2) = 48.36 m 2
1. Form
nPlywood = 48.36 m2 / 1.2 x 2.4 = 16.7917 pcs ~ 17 pcs - 4' x 8' x 1/4"

2. Bracing
BFT = 48.36 m2 x 12.71 BF/m2 = 614.6556 BF
n2"x2"x14' = 614.6556 BF/4.67 BF/pc = 131.6179 pcs ~ 132 pcs - 2"x2"x14' RoL

3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 37.2 m (6 + 7) BF/m = 483.6 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 483.6 BF/7 BF/m = 69.0857pcs ~ 70 pcs - 2"x3"x14' RoL

SECOND FLOOR:
Overhang Beams
L=(1+1+1+1)=4m
A=(0.45 (2) + 0.3 + 0.05(2))(4)= 5.2m2
1. Form
nPlywood = 5.2m2 / 1.2 x 2.4 = 1.8056 pcs ~ 2 pcs - 4' x 8' x 1/4"

2. Bracing
BFT = 5.2m2 x 12.71 BF/m2 = 66.092 BF
n2"x2"x14' = 66.092 BF/4.67 BF/pc = 14.1525 pcs ~ 15 pcs - 2"x2"x14' RoL

3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 4 m (6 + 7) BF/m =52 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 52 BF/7 BF/m = 7.4286pcs ~ 8 pcs - 2"x3"x14' RoL

End Beams
L = (5 - 0.4)(2) + (5.5 - 0.4)(6) = 39.8 m
A=(0.45 + 0.35 + 0.3 + 0.05(2))(39.8)= 47.76m 2
1. Form
nPlywood = 47.76m2 / 1.2 x 2.4 = 16.5833pcs ~ 17pcs - 4' x 8' x 1/4"

2. Bracing
BFT = 47.76m2 x 12.71 BF/m2 = 607.0296 BF
n2"x2"x14' = 607.0296 BF/4.67 BF/pc =129.9849 pcs ~ 130 pcs - 2"x2"x14' RoL

3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 39.8 m (6 + 7) BF/m =517.4 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 517.4 BF/7 BF/m = 73.9143pcs ~ 74 pcs - 2"x3"x14' RoL

Inner Beams
L = (5 - 0.4)(2)= 9.2 m
A = (0.35(2) + (0.3+0.05+0.05))( 9.2 m) = 10.12 m 2
1. Form
nPlywood = 10.12 m2 / 1.2 x 2.4 = 3.5139pcs ~ 4 pcs - 4' x 8' x 1/4"

2. Bracing
BFT = 10.12 m2 x 12.71 BF/m2 =128.6252 BF
n2"x2"x14' = 128.6252 BF/4.67 BF/pc =27.5429 pcs ~ 28 pcs - 2"x2"x14' RoL

3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 9.2 m(6 + 7) BF/m =119.6 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 119.6 BF/7 BF/m = 17.0857pcs ~ 18 pcs - 2"x3"x14' RoL
THIRD FLOOR:
End Beams
L = (5 - 0.4)+ (1.2-0.2)(4) + (5.5 - 0.4)(3) = 23.9 m
A = (0.33 + 0.45+ (0.3+0.05+0.05))( 23.9 m) = 28.202 m 2
1. Form
nPlywood = 28.202 m2 / 1.2 x 2.4 = 9.7924pcs ~ 10 pcs - 4' x 8' x 1/4"

2. Bracing
BFT = 28.202 m2 x 12.71 BF/m2 =358.44742 BF
n2"x2"x14' = 358.44742 BF/4.67 BF/pc =76.7553 pcs ~ 77 pcs - 2"x2"x14' RoL

3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 23.9 m(6 + 7) BF/m =310.7BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 310.7BF/7 BF/m = 44.3857pcs ~ 45 pcs - 2"x3"x14' RoL

Inner Beams
L = (5 - 0.4)(3) +(5 - 0.4)(3)+ (1.2-0.2)(2) = 31.1m
A = (0.33 (2) + (0.3+0.05+0.05))( 31.1m) = 32.966 m 2
1. Form
nPlywood = 32.966 m2 / 1.2 x 2.4 = 11.4465 pcs ~ 12 pcs - 4' x 8' x 1/4"

2. Bracing
BFT = 32.966 m2 x 12.71 BF/m2 =418.99786 BF
n2"x2"x14' = 418.99786 BF /4.67 BF/pc =89.7212 pcs ~ 90 pcs - 2"x2"x14' RoL

3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 31.1m(6 + 7) BF/m =404.3 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 404.3 BF/7 BF/m = 57.7571pcs ~ 58 pcs - 2"x3"x14' RoL

FOURTH FLOOR:
End Beams
L = (5 - 0.4)+ (1.2-0.2)(4) + (5.5 - 0.4)(3) = 23.9 m
A = (0.28 + 0.4+ (0.3+0.05+0.05))( 23.9 m) = 25.812 m 2
1. Form
nPlywood = 25.812 m2 / 1.2 x 2.4 =8.9625pcs ~ 9 pcs - 4' x 8' x 1/4"

2. Bracing
BFT = 25.812 x 12.71 BF/m2 =328.07052 BF
n2"x2"x14' = 328.07052 BF/4.67 BF/pc =70.2506 pcs ~ 71 pcs - 2"x2"x14' RoL

3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 23.9 m(6 + 7) BF/m =310.7BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 310.7BF/7 BF/m = 44.3857pcs ~ 45 pcs - 2"x3"x14' RoL

Inner Beams
L = (5 - 0.4)(3) +(5 - 0.4)(3)+ (1.2-0.2)(2) = 31.1m
A = (0.28 (2) + (0.3+0.05+0.05))( 31.1m) = 29.856 m 2
1. Form
nPlywood = 29.856 m2 / 1.2 x 2.4 = 10.3667 pcs ~ 11 pcs - 4' x 8' x 1/4"

2. Bracing
BFT = 29.856 m2 x 12.71 BF/m2 =379.46976 BF
n2"x2"x14' = 379.46976 BF/4.67 BF/pc =81.2569 pcs ~ 82 pcs - 2"x2"x14' RoL

3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 31.1m(6 + 7) BF/m =404.3 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 404.3 BF/7 BF/m = 57.7571pcs ~ 58 pcs - 2"x3"x14' RoL

Summary:
Ground Floor
nPlywood = 10 pcs
n2"x2"x14' = 76 pcs
n2"x3"x14' = 40 pcs
First Floor
nPlywood = 17 pcs
n2"x2"x14' = 132 pcs
n2"x3"x14' = 70 pcs

Second Floor
nPlywood = 2 pcs
n2"x2"x14' = 15 pcs
n2"x3"x14' = 8 pcs

nPlywood = 17 pcs
n2"x2"x14' = 130 pcs
n2"x3"x14' = 74 pcs

nPlywood = 4 pcs
n2"x2"x14' = 28 pcs
n2"x3"x14' = 18 pcs

Third Floor
nPlywood = 10 pcs
n2"x2"x14' = 77 pcs
n2"x3"x14' = 45 pcs

nPlywood = 12 pcs
n2"x2"x14' = 90 pcs
n2"x3"x14' = 58 pcs

Fourth Floor

nPlywood = 9 pcs
n2"x2"x14' = 71 pcs
n2"x3"x14' = 45 pcs

nPlywood = 11 pcs
n2"x2"x14' = 82 pcs
n2"x3"x14' = 58 pcs

NOTE:
*Materials can be used up to 5 times.
*Ground floor materials can be used for the First floor.
*Second floor is adequate for the next following floors.

TOTAL QUANTITY:
FORMWORKS
nPlywood = 17 + 2 + 17 + 4 = 40 pcs - 4' x 8' x 1/4"

BRACING
n2"x2"x14' = 132 + 15 + 130 + 28 = 305 pcs - 2"x2"x14' RoL

SCAFFOLDING
n2"x3"x14' = 70 + 8 + 74 + 18 = 170 pcs - 2"x3"x14' RoL

COMMON WIRE NAILS


FORMWORKS:
No. 4 CWN = (21.4 + 37.2 + 4 + 39.8 + 9.2 + 23.9 + 31.1 + 23.9 + 31.1) m x 0.17 kg/m
No. 4 CWN = 221.6 m x 0.17 kg/m
No. 4 CWN = 37.672 kg = 38 kg

No. 1 1/2 CWN = 40 pcs x 0.17 kg/pc


No. 1 1/2 CWN = 6.8 kg= 7 kg

SCAFFOLDING:
No. 4 CWN = (21.4 + 37.2 + 4 + 39.8 + 9.2 + 23.9 + 31.1 + 23.9 + 31.1) m x 0.73 kg/m
No. 4 CWN = 221.6 m x 0.73 kg/m
No. 4 CWN = 161.768 kg = 162 kg