Beams and Girders Ground Floor
Beams and Girders Ground Floor
GROUND FLOOR:
L = (5 - 0.4)(2) + (1.2 - 0.2)(2) + (5.5 - 0.4)(2) = 21.4 m
A = 0.45(21.4) x 2 + (0.3+0.05+0.05)(21.4) = 27.82 m 2
1. Form
nPlywood = 27.82 m2 / 1.2 x 2.4 = 9.6597 pcs ~ 10 pcs - 4' x 8' x 1/4"
2. Bracing
BFT = 27.82 m2 x 12.71 BF/m2 = 353.5922 BF
n2"x2"x14' = 353.5922 BF/4.67 BF/pc = 75.7157 pcs ~ 76 pcs - 2"x2"x14' RoL
3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 21.4 m (6 + 7) BF/m = 278.2 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 278.2 BF/7 BF/m = 39.7429 pcs ~ 40pcs - 2"x3"x14' RoL
FIRST FLOOR:
L = (5 - 0.4)(3) + (1.2 - 0.2)(3) + (5.5 - 0.4)(4) = 37.2 m
A = 0.45(37.2) x 2 + (0.3+0.05+0.05)(37.2) = 48.36 m 2
1. Form
nPlywood = 48.36 m2 / 1.2 x 2.4 = 16.7917 pcs ~ 17 pcs - 4' x 8' x 1/4"
2. Bracing
BFT = 48.36 m2 x 12.71 BF/m2 = 614.6556 BF
n2"x2"x14' = 614.6556 BF/4.67 BF/pc = 131.6179 pcs ~ 132 pcs - 2"x2"x14' RoL
3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 37.2 m (6 + 7) BF/m = 483.6 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 483.6 BF/7 BF/m = 69.0857pcs ~ 70 pcs - 2"x3"x14' RoL
SECOND FLOOR:
Overhang Beams
L=(1+1+1+1)=4m
A=(0.45 (2) + 0.3 + 0.05(2))(4)= 5.2m2
1. Form
nPlywood = 5.2m2 / 1.2 x 2.4 = 1.8056 pcs ~ 2 pcs - 4' x 8' x 1/4"
2. Bracing
BFT = 5.2m2 x 12.71 BF/m2 = 66.092 BF
n2"x2"x14' = 66.092 BF/4.67 BF/pc = 14.1525 pcs ~ 15 pcs - 2"x2"x14' RoL
3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 4 m (6 + 7) BF/m =52 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 52 BF/7 BF/m = 7.4286pcs ~ 8 pcs - 2"x3"x14' RoL
End Beams
L = (5 - 0.4)(2) + (5.5 - 0.4)(6) = 39.8 m
A=(0.45 + 0.35 + 0.3 + 0.05(2))(39.8)= 47.76m 2
1. Form
nPlywood = 47.76m2 / 1.2 x 2.4 = 16.5833pcs ~ 17pcs - 4' x 8' x 1/4"
2. Bracing
BFT = 47.76m2 x 12.71 BF/m2 = 607.0296 BF
n2"x2"x14' = 607.0296 BF/4.67 BF/pc =129.9849 pcs ~ 130 pcs - 2"x2"x14' RoL
3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 39.8 m (6 + 7) BF/m =517.4 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 517.4 BF/7 BF/m = 73.9143pcs ~ 74 pcs - 2"x3"x14' RoL
Inner Beams
L = (5 - 0.4)(2)= 9.2 m
A = (0.35(2) + (0.3+0.05+0.05))( 9.2 m) = 10.12 m 2
1. Form
nPlywood = 10.12 m2 / 1.2 x 2.4 = 3.5139pcs ~ 4 pcs - 4' x 8' x 1/4"
2. Bracing
BFT = 10.12 m2 x 12.71 BF/m2 =128.6252 BF
n2"x2"x14' = 128.6252 BF/4.67 BF/pc =27.5429 pcs ~ 28 pcs - 2"x2"x14' RoL
3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 9.2 m(6 + 7) BF/m =119.6 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 119.6 BF/7 BF/m = 17.0857pcs ~ 18 pcs - 2"x3"x14' RoL
THIRD FLOOR:
End Beams
L = (5 - 0.4)+ (1.2-0.2)(4) + (5.5 - 0.4)(3) = 23.9 m
A = (0.33 + 0.45+ (0.3+0.05+0.05))( 23.9 m) = 28.202 m 2
1. Form
nPlywood = 28.202 m2 / 1.2 x 2.4 = 9.7924pcs ~ 10 pcs - 4' x 8' x 1/4"
2. Bracing
BFT = 28.202 m2 x 12.71 BF/m2 =358.44742 BF
n2"x2"x14' = 358.44742 BF/4.67 BF/pc =76.7553 pcs ~ 77 pcs - 2"x2"x14' RoL
3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 23.9 m(6 + 7) BF/m =310.7BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 310.7BF/7 BF/m = 44.3857pcs ~ 45 pcs - 2"x3"x14' RoL
Inner Beams
L = (5 - 0.4)(3) +(5 - 0.4)(3)+ (1.2-0.2)(2) = 31.1m
A = (0.33 (2) + (0.3+0.05+0.05))( 31.1m) = 32.966 m 2
1. Form
nPlywood = 32.966 m2 / 1.2 x 2.4 = 11.4465 pcs ~ 12 pcs - 4' x 8' x 1/4"
2. Bracing
BFT = 32.966 m2 x 12.71 BF/m2 =418.99786 BF
n2"x2"x14' = 418.99786 BF /4.67 BF/pc =89.7212 pcs ~ 90 pcs - 2"x2"x14' RoL
3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 31.1m(6 + 7) BF/m =404.3 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 404.3 BF/7 BF/m = 57.7571pcs ~ 58 pcs - 2"x3"x14' RoL
FOURTH FLOOR:
End Beams
L = (5 - 0.4)+ (1.2-0.2)(4) + (5.5 - 0.4)(3) = 23.9 m
A = (0.28 + 0.4+ (0.3+0.05+0.05))( 23.9 m) = 25.812 m 2
1. Form
nPlywood = 25.812 m2 / 1.2 x 2.4 =8.9625pcs ~ 9 pcs - 4' x 8' x 1/4"
2. Bracing
BFT = 25.812 x 12.71 BF/m2 =328.07052 BF
n2"x2"x14' = 328.07052 BF/4.67 BF/pc =70.2506 pcs ~ 71 pcs - 2"x2"x14' RoL
3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 23.9 m(6 + 7) BF/m =310.7BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 310.7BF/7 BF/m = 44.3857pcs ~ 45 pcs - 2"x3"x14' RoL
Inner Beams
L = (5 - 0.4)(3) +(5 - 0.4)(3)+ (1.2-0.2)(2) = 31.1m
A = (0.28 (2) + (0.3+0.05+0.05))( 31.1m) = 29.856 m 2
1. Form
nPlywood = 29.856 m2 / 1.2 x 2.4 = 10.3667 pcs ~ 11 pcs - 4' x 8' x 1/4"
2. Bracing
BFT = 29.856 m2 x 12.71 BF/m2 =379.46976 BF
n2"x2"x14' = 379.46976 BF/4.67 BF/pc =81.2569 pcs ~ 82 pcs - 2"x2"x14' RoL
3. Scaffolding
2"x3"x14'
Vertical - 6
Horizontal - 7
BFT = 31.1m(6 + 7) BF/m =404.3 BF
2"x3"x14'/12 = 7 BF/pc
n2"x3"x14' = 404.3 BF/7 BF/m = 57.7571pcs ~ 58 pcs - 2"x3"x14' RoL
Summary:
Ground Floor
nPlywood = 10 pcs
n2"x2"x14' = 76 pcs
n2"x3"x14' = 40 pcs
First Floor
nPlywood = 17 pcs
n2"x2"x14' = 132 pcs
n2"x3"x14' = 70 pcs
Second Floor
nPlywood = 2 pcs
n2"x2"x14' = 15 pcs
n2"x3"x14' = 8 pcs
nPlywood = 17 pcs
n2"x2"x14' = 130 pcs
n2"x3"x14' = 74 pcs
nPlywood = 4 pcs
n2"x2"x14' = 28 pcs
n2"x3"x14' = 18 pcs
Third Floor
nPlywood = 10 pcs
n2"x2"x14' = 77 pcs
n2"x3"x14' = 45 pcs
nPlywood = 12 pcs
n2"x2"x14' = 90 pcs
n2"x3"x14' = 58 pcs
Fourth Floor
nPlywood = 9 pcs
n2"x2"x14' = 71 pcs
n2"x3"x14' = 45 pcs
nPlywood = 11 pcs
n2"x2"x14' = 82 pcs
n2"x3"x14' = 58 pcs
NOTE:
*Materials can be used up to 5 times.
*Ground floor materials can be used for the First floor.
*Second floor is adequate for the next following floors.
TOTAL QUANTITY:
FORMWORKS
nPlywood = 17 + 2 + 17 + 4 = 40 pcs - 4' x 8' x 1/4"
BRACING
n2"x2"x14' = 132 + 15 + 130 + 28 = 305 pcs - 2"x2"x14' RoL
SCAFFOLDING
n2"x3"x14' = 70 + 8 + 74 + 18 = 170 pcs - 2"x3"x14' RoL
SCAFFOLDING:
No. 4 CWN = (21.4 + 37.2 + 4 + 39.8 + 9.2 + 23.9 + 31.1 + 23.9 + 31.1) m x 0.73 kg/m
No. 4 CWN = 221.6 m x 0.73 kg/m
No. 4 CWN = 161.768 kg = 162 kg