Asbestos Policy V3
Asbestos Policy V3
Asbestos Policy V3
Asbestos Policy
Version: 3
Summary The Asbestos Policy sets out how Southern Health NHS Foundation
Trust will comply with all relevant Health and Safety legislation regarding
the management of Asbestos.
The Equality Impact Assessment has been completed. The assessment document is held centrally
and is available by contacting [email protected]
1
SH NCP 41 Asbestos Policy
Version 3
December 2019
Version Control
Change Record
Reviewers/contributors
2
SH NCP 41 Asbestos Policy
Version 3
December 2019
Asbestos Policy
Information on a page
This page summarises the key information or key steps in a process to follow. This does not
negate the need to be aware of and to follow the further detail provided in the document.
This Asbestos Policy sets out how Southern Health NHS Foundation Trust (the Trust) will manage
the risk posed to staff and contractors by asbestos-containing materials and how we will comply
with all relevant Health and Safety legislation regarding asbestos.
It also details the responsibilities of the Trust and its employees, contractors and regular building
users. All procedures outlined below are mandatory for all parties involved.
In order to meet statutory requirements, Trust objectives, healthcare requirements and best
practice, the Trust will:
This Policy requires the cooperation of all employees, all staff, building users and contractors who
also have responsibilities to ensure a safe and healthy working environment is maintained at all
times.
This policy is not applicable to social care supporting living services. Any concerns should be
raised with the relevant Housing Provider and the Locality Manager.
3
SH NCP 41 Asbestos Policy
Version 3
December 2019
Contents
Section Title Page
1. Introduction 5
4. Main content 9
4.1 Work with Asbestos 10
4.2 Identification of Asbestos 10
4.3 Asbestos Waste 11
4.4 Emergency Procedures 11
5. Training requirements 11
6. Monitoring compliance 12
7. Document review 12
9. Definitions 12
Appendices
1. Emergency Procedure Following Damage to Known or 14
Suspected ACM
2. Procedure Following Discovery of Suspect Asbestos Material 15
4
SH NCP 41 Asbestos Policy
Version 3
December 2019
Asbestos Policy
1. Introduction
Asbestos is a naturally occurring mineral fibre that was commonly used in building and
insulation products up until the 1990’s. Materials containing asbestos fibres can release
these into the air, usually when the asbestos-containing material (ACM) is disturbed.
Inhalation of airborne asbestos fibres leads to increased risk of lung cancer and other
illnesses.
This Asbestos Policy sets out how Southern Health NHS Foundation Trust (the Trust) will
manage the risk posed to staff and contractors by asbestos-containing materials and how we
will comply with all relevant Health and Safety legislation regarding asbestos.
It also details the responsibilities of the Trust and its employees, contractors and regular
building users. All procedures outlined below are mandatory for all parties involved.
In order to meet statutory requirements, Trust objectives, healthcare requirements and best
practice, the Trust will:
This Policy requires the cooperation of all employees, all staff, building users and contractors
who also have responsibilities to ensure a safe and healthy working environment is
maintained at all times.
This policy is not applicable to social care supporting living services. Any concerns should be
raised with the relevant Housing Provider and the Locality Manager.
The Trust recognises its duties under the Health and Safety at Work Act, 1974 and the
Control of Asbestos Regulations 2012 and is committed to the effective management of
asbestos containing materials.
The Trust recognises its responsibilities to contractors and others involved in building and
maintenance projects established through the Construction (Design and Management)
Regulations 2015 and its duties as the ‘Duty Holder’ of Trust owned buildings as defined by
Regulation 4 of the Control of Asbestos Regulations 2012.
This policy applies to ALL SHFT staff and contractors carrying out work on behalf of the trust.
Where Estates and FM Services are managed on our behalf by another organisation they will
abide by the same policy.
The statutory requirements addressed in this policy apply to all the Trust’s sites where there
is a risk to any employee, service user, or member of public. This also applies to Trust
activities on shared sites, where the Trust has a duty to ensure safe systems are in place.
The Trust’s duties also extend to people in the surrounding neighbourhood who might be
inadvertently exposed to risks due to the activities of the Trust.
The policy should be read in conjunction with the SHFT Asbestos Management Plan relevant
legislation and NHS guidance.
5
SH NCP 41 Asbestos Policy
Version 3
December 2019
3. Duties and responsibilities
The management structure below shows the key roles and appointments for the effective
and safe management of Asbestos.
Chief Executive
(Duty Holder)
Director of
Finance and
Corporate
Services
Associate Director
of Estate Services
Asbestos
Authorising
Engineer
Capital Projects
Team
6
SH NCP 41 Asbestos Policy
Version 3
December 2019
3.4 Senior Estates Capital Projects Manager
The Senior Estates Capital Projects Manager has delegated responsibilities for the
operational implementation and monitoring of asbestos management policies and
procedures.
The above named person should be available if any help is needed to understand this
document; if any asbestos information is required; if any works are planned which may affect
known or suspected asbestos containing materials (ACMs); or if accidental disturbance of
ACMs is suspected.
7
SH NCP 41 Asbestos Policy
Version 3
December 2019
h) Implement and regularly review suitable control measures to ensure that the risk
from ACMs is adequately managed.
i) Ensure that all relevant personnel will undertake initial Asbestos Awareness
training and then annual refresher training to ensure they are kept updated on
new developments in the management and control of asbestos to ensure
competent performance of their specific duties. Attendance will be recorded and
maintained ready for inspection if required.
j) Ensure all asbestos information is made available upon request.
k) Be actively involved in monitoring of any asbestos removal or consultancy works
completed by a third party (such as an asbestos consultant, laboratory, principle
contractor or a licensed contractor). Where records or documents are prepared or
maintained by a third party, this will be clearly stated, and centrally controlled by
the Trust.
l) Ensure that labelling is undertaken in non-public areas and/or areas where
labelling is deemed necessary to ensure the safety of building users. (Labelling to
be carried out at the Trust’s discretion).
m) Only used licensed asbestos removal contractors to carry out any works on
asbestos containing materials.
3.8 IA Asbestos
The Trust’s asbestos management policy and procedures will be subject to regular external
audits from an Independent Auditor (AI) to ensure compliance with all relevant statutes and
guidance.
3.10 IT Team
The SHFT IT team will ensure that any projects they undertake will comply with this policy.
The Asbestos Manager should be consulted prior to any project that may disturb the fabric of
any building constructed prior to 1999 as there may be a requirement for additional
“Refurbishment & Demolition” surveys, depending on the scope of the project.
The IT team must ensure that any work carried out does not disturb any ACM and any staff
carrying out any work should ensure that they have read and signed the asbestos register for
the site.
Any documents relating to asbestos removal or remediation must be sent to the Asbestos
Manager so that the asbestos management database can be updated accordingly.
The Asbestos Manager should be informed if the project scope changes to ensure all areas
affected by the planned works are included in the assessment.
In practice this will mean that the Asbestos Manager should be consulted prior to the start of
the project to ensure that any required project-specific ‘Refurbishment & Demolition’ surveys
8
SH NCP 41 Asbestos Policy
Version 3
December 2019
can be carried out in advance of any work and any ACMs that might be disturbed by the work
are removed or remediated as required.
The projects team must ensure that any project work carried out does not disturb any ACM
and any staff carrying out any work should ensure that they have read and signed the
asbestos register for the site.
Any documents relating to asbestos removal or remediation must be sent to the Asbestos
Manager so that the asbestos management database can be updated accordingly.
The Asbestos Manager should be informed if the project scope changes to ensure all areas
affected by the planned works are included in the assessment.
4. Main content
9
SH NCP 41 Asbestos Policy
Version 3
December 2019
i) Undertake the development of an Asbestos Management Plan which will be
monitored, reviewed and revised regularly, and which will state what steps will
be taken to manage the risk from known or suspected ACMs.
j) Undertake regular training of relevant staff and inform third party contractors
where necessary
k) Develop, implement and monitor safe systems of work to protect the safety,
health and welfare of employees, building users and third party contractors.
l) Provide appropriate precautionary health screening for relevant staff who may
have come into contact with ACMs during the course of their work.
The Trust will ensure that an asbestos register is maintained for each premise, containing
identification of likely or known locations of asbestos, an assessment of risks, and the
approach to management of those risks. The surveys will be carried out in accordance with
legislation and relevant ACOPs. This will be reviewed annually, and updated information
added whenever changes occur, e.g. at building refurbishment.
The Trust will also maintain an Asbestos Management Plan detailing how residual risks from
identified ACMs are managed.
The Control of Asbestos Regulations 2012 categorises work involving asbestos into three
broad areas.
SHFT will use a LARC for ALL work with asbestos in order to ensure the work is carried out
safely and in accordance with CAR2012. It is the responsibility of the LARC to ensure that
any relevant notifications are made to the enforcing authority.
If the work involves very low risk ACMs, SHFT may allow non-licensed contractors or
maintenance staff to carry out work with asbestos, provided the staff have received the
relevant training for working with asbestos and an appropriate method statement and risk
assessment has been prepared in advance. Any work with asbestos must have written
authorisation from the Asbestos Manager.
The Asbestos Manager will ensure that asbestos surveys are carried out in accordance with
HSG264 “Asbestos: The survey Guide”. If using an external organisation then they must be
UKAS accredited
All asbestos survey data will be held centrally within the Trusts asbestos management
database which is currently the MICAD system
Any samples for analysis will be sent to a company that is UKAS accredited for the
identification of asbestos fibres
Any air testing will be carried out by a company that is UKAS accredited for asbestos air
sampling and analysis.
SHFT do not routinely label asbestos, however labels may be fixed to ACMs where it has
been requested or local circumstances dictate that it would be beneficial to aid identification.
10
SH NCP 41 Asbestos Policy
Version 3
December 2019
4.3 Asbestos Waste
Any asbestos removed from a site must be done so in accordance with the hazardous waste
regulations and be accompanied by the relevant waste consignment note.
SHFT has provided a secure, lockable container for the temporary storage of asbestos waste
generated by surveys or inspections. This waste will be disposed of as required and WCN
retained.
The following procedure should be followed whenever suspected ACMs are found during
maintenance or refurbishment works:
In circumstances where a ‘site’ is under control of a Principal Contractor and ACMs are
discovered the procedures contained in the Health and Safety Plan should be followed and
the Project Manager and Planning Supervisor informed as soon as practical.
5. Training requirements
In accordance with regulation 10 of CAR2012 any worker liable to disturb asbestos while
performing their normal everyday work is required to receive adequate asbestos awareness
training
Every employer must ensure that adequate information, instruction and training is given to
those employees who are liable to be exposed to asbestos during the course of their work.
The Asbestos Manager will ensure that all relevant personnel will undertake initial training
and then annual refresher training to ensure they are kept updated on new developments in
the management and control of asbestos to ensure competent performance of their specific
duties. Attendance will be recorded and maintained ready for inspection if required.
11
SH NCP 41 Asbestos Policy
Version 3
December 2019
6. Monitoring Compliance
7. Document review
The document will be reviewed every 3 years, or sooner if changes in legislation occur or
new best practice evidence becomes available.
Supporting references
9. Definitions
Term Definition
SHFT, ‘The Trust’ Southern Health NHS Foundation Trust
Duty Holder the duty holder is, as defined in the ACOP;
Or:
12
SH NCP 41 Asbestos Policy
Version 3
December 2019
person in complying with the requirements
of the regulation will be determined by the
nature and extent of the maintenance and
repair obligation owed by that person.
Employee’s and Refers to all direct employees, agency staff, long term
‘regular building contracted suppliers and those employed by Trust
users’ Directorates.
‘contractors’ Refers to all parties who undertake work for the Trust
on a short term, limited contract basis. This would
include tradespersons brought in for a specific task or
time period, but not those who have an on-going supply
agreement with the Trust.
Control Limit The control limit for asbestos is 0.1 asbestos fibres per
cubic centimetre of air (0.1f/cm3). The control limit is
not a 'safe' level and exposure from work activities
involving asbestos must be reduced to as far below the
control limit as possible.
ACM Asbestos containing material
Asbestos A document that details how SHFT will reduce the risk
Management Plan from specific identified ACMs as far as reasonably
practicable
LARC Licenced asbestos removal contractor
ACOP Approved code of practice
CAR2012 Control of Asbestos regulations 2012
CDM Construction, Design & Management regulations
WCN Waste Consignment Note, as required by the
Hazardous Waste regulations
13
SH NCP 41 Asbestos Policy
Version 3
December 2019
APPENDIX 1 EMERGENCY PROCEDURE FOLLOWING DAMAGE TO KNOWN
OR SUSPECTED ACM
Evacuate all staff, visitors and personnel from the immediate area
Secure the area to prohibit anyone re-entering - by physical controls (locking rooms if possible) or
putting people on sentry duty
Inform the site manager and request immediate assistance in securing the immediate vicinity and limiting the
escape/spread of asbestos
The site manager must then contact the SHFT Asbestos Management Surveyor, the Facilities
Management team and any other specialist advisor deemed necessary - to assist in managing the
accident scene and checking the site asbestos register
Depending on the severity of the incident (the potential release of asbestos fibres) - names
and contact details of all person in the immediate vicinity of the accident scene should be
collated
Your facilities management team (normally SHFT Estate Services) will assume overall control of the
incident and subsequent isolation and remedial work in conjunction with the SHFT Asbestos
Management Surveyor
The site management team must also complete the SHFT Accident report form and forward
a copy to the SHFT H&S Unit
Note: The SHFT Asbestos Management Surveyor will attend site at the earliest opportunity
to inspect the area and take samples or arrange reassurance air testing, if necessary.
14
SH NCP 41 Asbestos Policy
Version 3
December 2019
APPENDIX 2 PROCEDURE FOLLOWING DISCOVERY OF
SUSPECT ASBESTOS MATERIAL
Restrict further access to the suspect material and control immediate vicinity if material damaged and
inform the school site manager (or senior manager in his/her absence) of the situation, location and
concerns
The site manager will review the 'Asbestos Register' to determine whether asbestos is known to
be in the location
YES NO UNKNOWN
15
SH NCP 41 Asbestos Policy
Version 3
December 2019