0% found this document useful (0 votes)
192 views30 pages

Estimation and Costing - Lig

1. The document provides details of the quantities of materials and labor required for the construction of a building, including excavation, foundation, masonry work, plastering, flooring, and other items. 2. It lists the quantities and costs of materials like cement, sand, gravel, bricks, tiles, as well as labor costs for various construction activities. 3. The total estimated costs are provided for items like earthwork excavation, PCC bed for foundation, sand filling, SSM foundation, and masonry work.

Uploaded by

R Sumithra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
192 views30 pages

Estimation and Costing - Lig

1. The document provides details of the quantities of materials and labor required for the construction of a building, including excavation, foundation, masonry work, plastering, flooring, and other items. 2. It lists the quantities and costs of materials like cement, sand, gravel, bricks, tiles, as well as labor costs for various construction activities. 3. The total estimated costs are provided for items like earthwork excavation, PCC bed for foundation, sand filling, SSM foundation, and masonry work.

Uploaded by

R Sumithra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 30

Sl. No.

A)
6

8
9
LCL = 4H1 + H2 + 2V1 + 2V2 = 66.4m
Number of T junctions = 5

Particulars Numbers
Earthwork Excavation 1

PCC Bed - 1:4:8 mix for foundation 1

Sand Filling - for plinth


a) Living Area 1
b) Kitchen 1
c) Room 1 1
d) Room 2 1
e) Toilet 1

SSM Foundation In CM (1:6)


a) Step 1 1
b) Step 2 1
c) Step 3 1
d) Step 4 1

Masonary - 1st class brick in CM (1:6)


a) In Plinth and Foundation 1
b) In superstructure 1
c) Parapet wall all around 1

Deductions
a) Doors
i) Main Door 1
ii) Room Door 1
iii) Toilet Door 2
iv) Utility Door 1
v) Opening 1 1
vi) Opening 2 1

b) Windows / Ventilators
i) Window 1 (1200mm wide) 6
ii) Window 2 (2400mm wide) 1
iii) Ventilator 2

c) Lintels
i) Main Door 1
ii) Room Door 2
iii) Toilet Door 2
iv) Utility Door 1
v) Opening 1 1
vi) Opening 2 1
vii) Window 1 6
viii) Window 2 1
ix) Ventilator 2

Total Brick Masonary


Deductions
Total Quantity of brick work for foundation, plinth and susperstucture

RCC Roof Slab - 1:1.5:3 1

RCC Chajja + Lintel - 1:2:4


i) Chajja
a) Window 1 (1200mm wide) 6
b) Window 2 (2400mm wide) 1
c) Ventilator 2

ii) Lintels
i) Main Door 1
ii) Room Door 2
iii) Toilet Door 2
iv) Utility Door 1
v) Opening 1 1
vi) Opening 2 1
vii) Window 1 6
viii) Window 2 1
ix) Ventilator 2

Total Quantity of RCC In Chajja and Lintel

Plastering For all Walls in CM (1:6) 12mm thick


i) Living Room 1
ii) Kitchen 1
iii) Room 1 1
iv) Room 2 1
v) Toilets 2
vi) Outer walls - External Plastering 1
DEDUCTIONS
Doors
i) Main Door 1
ii) Room Door 1
iii) Toilet Door 2
iv) Utility Door 1
v) Opening 1 1
vi) Opening 2 1

b) Windows / Ventilators
i) Window 1 (1200mm wide) 6
ii) Window 2 (2400mm wide) 1
iii) Ventilator 2

TOTAL PLASTERING AREA = 319.72 m2 ( after deductions )

Flooring - Vetrified Tile Flooring


i) Living Room 1
ii) Kitchen 1
iii) Room 1 1
iv) Room 2 1

Ceramic Tiles
Toilets 2

White Wash - Inner and Outer Walls


Same as plastering area - 319.72 m2

Colour Wash - Inner and Outer Walls


Same as plastering area - 319.72 m2

Dado Cladding
Kitchen 1
Deduction - Window 2
TOTAL =
Kitchen Dado Cladding using vitrium tiles = 18.12 m2

Toilet 2
Deductions
Door 1
Ventilator 1
TOTAL =
Toilet Dado Cladding using ceramic tiles = 20.01 m2

Earth Work Excavation


3 Labourers and 3 Mazdors can dig = 2.5 X 3 = 7.5 m3
Earth Excavation Required = 63.0315
Number of Days Required for this = 63.0315 / 7.5 =
Number of Days Required for this = 8.5
Rate of each Worker per day Rs 550
Amount for 6 people = Rs 3300
Amount for 8.5 days = Rs 28050
EARTH WORK EXCAVATION COST = Rs 28050

PCC Bed For Foundation - ( 1 : 4 : 8 )


Material Cost + Labour Cost
PCC Bed = 7.0015
Wet Volume of PCC = 7.0015
Dry Volume of PCC = 7.0015 X 1.54 =
Dry PCC Mix Volume = 1 + 4 + 8 = 13

Weight of Cement
Dry Volume X ( Cement Volume / PCC Mix ) = 10.782 X ( 1/ 13 ) =
Weight of Cement 0.829 X 1400 = 1160.60 kg
Number of Bags = 1160.60 / 50 = 23.21
NUMBER OF BAGS = 24 BAGS
Each bag = Rs 300
Cost for 24 Bags = 24 X 300 = Rs 7200

Weight of Sand
Volume of Sand = 10.782 X ( 4/13 ) = 3.31
Weight of Sand = 3.31 X 1500 = 4965 Kg
Total weight of Sand = 4965 kg
1 Truck Load = 2 Tonnes
Number of Truck Loads = 2.48
Number of Truck Loads = 2.5
Price of Truck Load = Rs 2075
Total Cost = Rs 5187.5

Weight of Gravel
Volume of Gravel = 10.782 X ( 8/13 ) = 6.63
Weight of Gravel = 6.63 X 1500 = 9945 Kg
9.94 tonnes
Price per tonne = Rs 640
Total Price = Rs 6361.6

TOTAL AMOUNT FOR PCC BED = Rs 18749.10

Labour Cost = Rs 1762.5


( Mason , Bhisti, Male and Female Coolie - 4)
Cost = 7.0015 X 1762.5 =
LABOUR COST FOR PCC BED = Rs 12340.14
TOATL CHARGES FOR PCC BED = Rs 31089.24

Sand Filling Upto Plinth Level


Amount of Sand Filling = 15.696
Weight of Sand = 15.696 X 1550 =
1 tonne of M Sand Rs 950
Total Cost = Rs 23104

Labour Cost
( Bhisti , Male and Female Coolie - 3 )
Labour Charges per 10m3 of sand = Rs 2275
Labour Charges for 15.696 m3 of sand = 2275 X 15.696 = 35708.4
Labour Charges = Rs 35708.4
TOTAL CHARGES FOR SAND FILLING = RS 58812.4

SSM FOUNDATION IN CM (1:6)


SSM Foundation Quantity = 32.345
Cost of Stone -
1m3 of stone costs - Rs 564. 347
For required volume cost = 564.347 X 32.345 =

Cost of Cement Mortar in 1:6


Calculating Volume of CM and SSM
Volume of 1 rubble stone = .45 X .60 X .50 =0.135 m3 ( 1 Stone)
Number of Stones = 32.345 / 0.135 = 239.59
Number of Stones = 240

Calculating Weight of Cement and Sand


Volume of CM = Vol ( SSM) - 1 Stone witout mortar * Number
32.345 - ( .44 x .59 x. 49 ) x 240 = 1.825
Dry Volume = 1.825 X 1.3 = 2.3725
Total Volume of CM = 1 + 6 = 7
Volume of Cement = 2.375 x ( 1/ 7 ) = 0.339 m3
Weight of Cement = 0.339 X 1400 = 474.6 Kg
Number of bags = 474.6 / 50 = 9.4 bags
Number of Bags = 9.5 Kg
Cost of Bags = 9.5 X 300 = Rs 2850

Volume of Sand = 2.3725 x ( 6/7 ) = 2.033


Weight of Sand = 2.033 X 1500 = 3049.5 Kg
Number of Tonnes = 3.1
Cost of Sand per tonne = Rs 2050
Total Cost = Rs 6355
TOTAL COST OF CEMENT AND SAND = Rs 9205

Labour Requirement Rs 2650


( Mason , 3 Male Coolie )
Labour Requirement for 32.345 m3 = Rs 85714.25
TOTAL COST = Rs 113173.05

Masonary - 1st Class Brick in CM ( 1 : 6 )

Total Quantity of brick work with plinth and foundation and ded. = 44.509 m3
No of bricks in 1 cubic meter of Masonary 500
Total Volume of brickwork 44.509
Number of bricks required 500 x 44.509 = 22254.5
NUMBER OF BRICKS REQUIRED = 22255

Cost of Brick = Rs 17
TOTAL COST OF BRICKS = Rs 378335

Cost of Cement and Sand in CM ratio - ( 1 : 6 )


Volume of CM in 1m3 of masonary = 0.25 m3
Volume of CM in 44.509 m3 = 0.25 X 44.509 =
Dry Volume of Cement Mortar = 11.127 X 1.3 =
Total Volume of CM = 1 + 6 = 7
Volume of Cement = 14.4651 x ( 1/ 7 ) = 2.066 m3
Weight of Cement = 2.066 X 1400 = 2892.4 Kg
Weight of Cement = 2900 kg

Number of bags = 2900 / 50 = 58 bags


Total Cost = Rs 17400

Volume of Sand = 14.4651 X ( 6/ 7 ) = 12.398 m3


Weight of Sand = 12.398 X 1550 = 19216.9 Kg = 19.21 tonnes
Cost of sand = 19.21 X 2050 = Rs 39380.50

Cost of Cement and Sand = Rs 56780.50

Labour Cost - per day per m3


( 1 Mason , 2 Male Coolies ) Rs 2100
Cost = 44.509 X 2100 = Rs 93468.90

TOTAL COST OF BUILDING THE SUPER STRUCTURE = Rs 528584.40

RCC ROOF SLAB - 1 : 1.5 : 3

CALCULATION FOR CEMENT, SAND AND AGGREGATE

Wet Volume of RCC ( 1: 1.5 : 3) 11.71


To find Dry Volume Multiply by 1.54
Dry Volume of RCC for Roof 1.54 x 11.71 = 18.03
DRY VOLUME OF RCC FOR ROOF 18.03

RCC MIX VOLUME (1 : 1.5 : 3 ) 1 + 1.5 + 3 =5.5


Calculations for Cement
Dry Volume of Concrete X ( Vol of Cement / RCC Mix) = 18.03 X ( 1/5.5 ) =
Weight of Cement Required = Volume X Density
Density of Cement = 1440
Weight of Cement = 3.278 X 1440 =
Weight of Cement = 4721
Number of kgs in one Bag = 50
Required Number of Bags = 4721 / 50 =
Number of Bags = 95
Cost = 95 x 300 = Rs 28500

Calculations for Sand


18.03 X ( 1.5 / 5.5 ) = 4.91
Weight of Sand Required = Volume X Density 4.91 X 1550 =
Number of Kg Required = 7611
1 Truck Loads = 2 Tonnes
Number of Sand Trucks Required = 7611 / 2000 =
Sand Trucks required for Roof = 4
Cost = 4 X 2050 = Rs 8200

Calculations for Aggregate


18.03 X ( 3 / 5.5 ) = 179.97
Density of Aggregate = 1500
Weight of Aggregate = Volume X Density 179.96 X 1500 =
1 Truck Loads = 2 Tonnes
Sand Trucks Required = 13
Cost = 13 X 640 = Rs 8320

Total Cost for Sand, Cement and Aggregate = Rs 45020

REINFORCEMENT FOR SLAB


For RCC Slab - 1- 1.5 % of steel per m3 of concrete
Volume of Concrete = 11.71 m3
1.5% of concrete - 0.175
Weight of steel = Density X Volume = 7850 X 0.175 = 1373.75 Kg
Fe 500 - Rs 58/ Kg
Cost = Rs 58 X 1373.75 = Rs 79,677.50

TOTAL COST FOR RCC ROOF SLAB = Rs 124697.50

ESTIMATION FOR RCC CHAJJA AND LINTELS - ( 1: 2 : 4 )

Quantity of RCC for Chajja and Lintel = 14.07 m3


RCC Ratio mix - 1 + 2 + 4 = 7
Dry Volume of RCC for Chajja and Lintel = 14.07 X 1.54 = 21.66m3
Calculations for Cement
Dry volume X ( Vol of Cement / RCC Mix ) = 21.66 X 1/7 = 3.09 m3
Weight of Cement = 3.09 X 1440 = 4449.6 Kg
Number of Bags = 4450 / 50 = 89 bags
Cost of the bags = 89 X 300 = Rs 26700

Calculations for Sand


Dry volume X ( Vol of Cement / RCC Mix ) = 21.66 X 2/7 = 6.18 m3
Weight of Sand = 6.18 X 1550 = 9579
Number of Truck Loads = 9580/2000 = 4.79
Number of Truck Loads = 5
Cost = 5 X 2050 = Rs 10250

Calculations for Aggregate


Dry volume X ( Vol of Cement / RCC Mix ) = 21.66 X 4/7 =12.37 m3
Weight of Aggregate = 12.37 X 1500 = 18555
Number of Truck Load Required = 18560/2000 = 9.28
Number of Truck loads = 10
Cost = 10 X 640 = Rs 6400

Total Cost for Chajja and Lintel =Rs 43350

PLASTERING COST FOR WALLS - 12MM THICK

Plastering Thickness = 12mm


TOTAL PLASTERING AREA = 319.72 m2 ( after deductions )
Wet Volume = 319.72 X 0.012 = 3.836 m3
Dry Volume = 38.36 X 1.3 = 4.9868 m3

COST OF MATERIALS :
Ratio - 1:5 = 1+5 = 6

Cement
Volume of Cement = 4.9868 X 1/6 = .8311m3
Weight of Cement = 0.8311 X 1450 = 1205.09 Kg
Number of bags of Cement = 1205.09 / 50 = 24.101
Cost = 24.101 X 300 = Rs 7230.570

Sand
Volume of Sand = 4.9868 X 5/6 = 4.151 m3
Weight of Sand = 4.151 X 1550 = 6434.50 Kg = 3.2 tonnes = 3.5 tonnes
Cost = 3.5 X 2050 = Rs 7157

COST OF LABOUR :
Everyday work done - 40 m2
Number of days required = 319.72/40 = 7.99 = 8 days
Payment per day = Rs 4900 ( for 3 masons and 3 mazdoors and 1 lab)
Total Labour Cost = 4900 X 8 = Rs 39200
Total cost = 7230.57 + 7157 + 39200 = Rs 53587.57

PLASTERING CEILING - 10MM THICK

i) Living Room 1
ii) Kitchen 1
iii) Room 1 1
iv) Room 2 1

Wet Volume of Platering = 49.65 X .010 = 0.4965 m3


Dry Volume of Plastering = 0.4965 X 1.3 = 0.645

Ratio - 1:5 = 1 + 5 = 6

COST OF MATERIALS :

Cement
Volume of Cement = 0.645 X 1/6 = 0.1075 m3
Weight of Cement = 0.1075 X 1450 = 155.98 Kg
Number of bags = 155.98 / 50 = 3.119 Bags = 3.2
Cost = 3.2 X 300 = Rs 960

Sand
Volume of Sand = 0.645 X 5/6 = 0.5375 m3
Weight of Sand = 0.5375 X 1550 = 833.125 Kg
Number of tonnes = 0.416 tonnes = 0.50 tonnes
Cost = Rs 0.50 X 2050 = Rs 1025

COST OF LABOUR :
Everyday work done - 40 m2
Number of days required = 49.65/40 = 1.24 = 1.3 days
Payment per day = Rs 4900 ( for 3 masons and 3 mazdoors and 1 lab)
Total Labour Cost = 4900 X 1.3 = Rs 6370

Total Cost = Rs 960 + 1025 + 6370 = Rs 8355

FLOORING - VETRIFIED TILES

i) Living Room 1
ii) Kitchen 1
iii) Room 1 1
iv) Room 2 1
One floor tile size =0.6m X 0.6m = 0.36 m2
Number of tiles required =49.65 / 0.36 = 137.9 tiles
Required Number of tiles = 140
Digital vitrified tile- antique beige
Costing - Rs 850/box
Each box - 4 tiles
For 140 tiles = 140/4 = 35 boxes
Cost = 35 X 850 = Rs 29750

Cement
Wet volume = 0.12 X 49.65 = 5.958 m3
Dry Volume = 5.958 X 1.3 = 7.745 m3
Bags required for 1m3 of CM in 1:3 mix = 7.25 bags
Bags required = 7.25 X 7.745 = 56.15 bags
Cost for this = 56.15 X 300 = Rs 16845.375

Sand
Sand required for 1m3 of CM in 1:3 mix = 1.163 tonnes
Sand required = 1.163 X 7.745 = 9 tonnes
Cost of Sand = 9 X 2050 = Rs 18450

Labour Cost
1 tiler + 1 helper - Can cover 12.5 m2/day
Days for 49.65 = 49.65/12.5 = 3.97 days = 4 days
Cost of labour per day = Rs 1000 + 550 = Rs 1550
Total cost = 1550 X 4 = Rs 6200

Total Cost of Laying Vitrified Tiles = 16845.70 + 18450 + 6200


TOTAL COST = Rs 41495.70

FLOORING - CERAMIC TILES

Toilets 2

One Ceramic Tile = 0.3 Xm 0.3m = 0.09 m2


Tiles required for4.8m2 = 4.8/0.09 = 53.33 tiles = 54 tiles
10% Wastage = 5.4 tiles = 6 tiles
Total required tiles = 60

Required Number of tiles = 140


Ceramic tile- antique beige
Costing - Rs 350/box
Each box - 10 tiles
Number of boxes required = 60/10 = 6 boxes
Cost = Rs 6 X 350 = Rs 2100

Cement
Wet Volume = 0.012 X 4.8 = 0.0576 m3
Dry Volume = 0.0576 X 1.3 = 0.074 m3
Cement Required for 1m3 of 1:3 CM mix = 7.25 bags
Bags Required = 7.25 X 0.074 = 0.5365 bags = 1 bag
Cost = Rs 1 X 300 = Rs 300

Sand
Sand required for 1m3 for CM in 1:3 mix = 1.163 tons
Sand required for 0.074 = 1.163 X 0.074 = 0.086 tons = 0.09 tons
Cost of Sand = 0.09 X 2050 = Rs 184.50

Labour Cost
1 tiler + 1 helper - Can cover 12.5 m2/day
Days for 4.8 m2 = 4.8/12.5 = 0.385 = 0.5 days
Cost per day = Rs 1000 + 550 = Rs 1550
Cost for 0.5 days = Rs 775
10% charges for grot and adhesives = Rs 77.5

TOTAL COST = 2100 + 300 + 184.50 + 775 + 77.50 = Rs 3437

WHITE WASH COAT FOR EXTERIOR AND INTERIOR

TOTAL PLASTERING AREA = 319.72 m2 ( after deductions )

Material Cost
Material Required = Base coat of putty / Wall primer
1 Litre of Putty = 12m2
Litres Required = 319.72 / 12 = 26.64 Litres
1 Kg = 1L
15 Kg of Asian Paint Primer Costs = Rs 2400
Cost = 26.64 X 2400 / 15 = Rs 4262.40

LABOUR COST
3 painters + 3 helpers - 45 m2 / day
Number of days required = 319.72 / 45 = 7.10 days = 7.5 days
Cost per day = Rs 1200 + 450 = Rs 1650
Total Cost = Rs 1650 X 7.5 = Rs 12375

COST = Rs 16637.40
10% adhesive and tool charges = Rs 1663.74
TOTAL COST = Rs 16836

EMULSION PAINTS FOR INTERIOR WALLS - 2 COATS

i) Living Room 1
ii) Kitchen 1
iii) bedroom 1 1
iv) bedroom 2 1
v) Toilets 2
Internal Plastering + Painting Area =

2 coats of paint on 12.5 m2 = Requires 1 Litre


Litres Required = 207 / 12.5 = 16.56 Litres = 17 Litres
Cost = Rs 17 X 18.625 = Rs 316.625

Labour Cost
3 Labourers + 3 Helpers - 45m2/day
Number of days required = 4.6 days
Cost per day = Rs 1200 + 450 = Rs 1650
Total Labour Cost = Rs 1650 X 4.6 = Rs 7590
10% for adhesives and tools = Rs 759
Total Cost = Rs 8349

TOTAL COST = Rs 316.625 + 8349 = Rs 8665.625

DADO CLADDING - KITCHEN - Vetrified Tiles


Kitchen Dado Cladding using vitrium tiles = 18.12 m2
One floor tile size =0.6m X 0.6m = 0.36 m2
Number of tiles = 18.12 / 0.36 = 50.33 tiles = 51 tiles
Number of tiles requird = 55 tiles
Digital vitrified tile- antique beige
Costing - Rs 850/box
Each box - 4 tiles
Number of tiles = 55/4 = 13.75 = 14 boxes
Cost for tiles = 14 x 850 = Rs 11900

Cement
Wet Volume = 0.012 X 18.12 = 0.217 m3
Dry Volume = 0.217 X 1.3 = 0.282 m3
1m3 of CM mix 1:3 requires = 7.25 bags
Number of bags = 0.282 X 7.25 = 2.044
Cost of bags = 2.044 X 300 = Rs 613.35

Sand
1 m3 of CM mix 1:3 requires = 1.163 tons
Sand required = 1.163 X 0.282 = 0.327 tons
Cost of Sand = 0.327 X 2050 = Rs 672.330

Labour Cost
1 tiler + 1 helper = 12.5 m2/ day
Number of days for this area = 18.12/12.5 = 1.44 = 1.5 days
Cost per day = Rs 1000 + 550 = Rs 1550 / day
Total Labour Cost = 1.5 X 1550 = Rs 2325

Total cost = Rs 11900 + 613.350 + 672.330 + 2325 = Rs 15510.83

DADO CLADDING - TOILETS - Ceramic Tiles


Toilet Dado Cladding using ceramic tiles = 20.01 m2
One cermaic Tile = 0.3m X 0.3m = 0.09m2
Number of tiles = 20.01 / 0.09 = 222.33 tiles = 225 tiles
Incld wastage = 230 tiles
Ceramic tile- antique beige
Costing - Rs 350/box
Each box - 10 tiles
Number of boxes = 230/10 = 23 boxes
Cost = 23 X 350 = Rs 8050

Cement
Wet Volume = 0.010 X 20.01 = 0.2 m3
Dry Volume = 0.2 X 1.3 = 0.26 m3
1 m3 of CM in 1:3 - 7.25 bags
Number of bags = 7.25 X 0.26 = 1.88 bags = 2 bags
Cost = 2 X 300 = Rs 600

Sand
1 m3 of CM in 1:3 - Requires 1.163 tons
Number of Tonnes = 0.26 X 1.163 =0.30 tonnes
Cost = Rs .30 X 2050 = Rs 615

Labour Cost
1 tiler + 1 helper - 12.5m2/day
Number of Days = 20.01 / 12.5 = 1.60
Cost per day = Rs 1000 + 550 = Rs 1550
Total Labour Cost = 1550 X 1.60 = Rs 2480

Total Cost = Rs 2480 + 615 + 600 + 8050 = Rs 11745


Length Breadth Depth Quantity Unit
63.65 1.1 0.9 63.0135 m3

63.65 1.1 0.1 7.0015 m3

5.7 3.6 0.3 6.156 m3


4 3 0.3 3.6 m3
3 3 0.3 2.7 m3
3 2.8 0.3 2.52 m3
1.2 2 0.3 0.72 m3
TOTAL = 15.696 m3

64.15 0.9 0.2 11.547 m3


64.65 0.7 0.2 9.051 m3
65.15 0.5 0.2 6.515 m3
65.4 0.4 0.2 5.232 m3
TOTAL = 32.345 m3

65.9 0.45 0.2 5.931 m3


65.9 3 0.2 39.54 m3
33.3 0.9 0.2 5.976 m3
TOTAL = 51.446 m3

1.2 2.1 0.2 0.504 m3


1 2.1 0.2 0.42 m3
0.9 2.1 0.2 0.756 m3
0.75 2.1 0.2 0.315 m3
2.6 2.1 0.2 1.092 m3
1.5 2.1 0.2 0.63 m3

1.2 1.2 0.2 1.728 m3


2.4 1.2 0.2 0.576 m3
0.6 0.6 0.2 0.144 m3

1.5 0.15 0.2 0.045 m3


1.3 0.15 0.2 0.078 m3
1.2 0.15 0.2 0.072 m3
1.05 0.15 0.2 0.0315 m3
2.9 0.15 0.2 0.087 m3
1.8 0.15 0.2 0.054 m3
1.5 0.15 0.2 0.27 m3
2.7 0.15 0.2 0.081 m3
0.9 0.15 0.2 0.054 m3
TOTAL = 6.937 m3

51.446
- 6.937
44.509 m3

8.4 9.3 0.15 11.71 m3

1.5 0.45 0.15 0.1 m3


2.7 0.45 0.15 0.18 m3
0.9 0.45 0.15 0.06 m3
TOTAL = 7.205 m3

1.5 0.15 0.2 0.045 m3


1.3 0.15 0.2 0.078 m3
1.2 0.15 0.2 0.072 m3
1.05 0.15 0.2 0.0315 m3
2.9 0.15 0.2 0.087 m3
1.8 0.15 0.2 0.054 m3
1.5 0.15 0.2 0.27 m3
2.7 0.15 0.2 0.081 m3
0.9 0.15 0.2 0.054 m3
TOTAL = 6.937 m3

14.07 m3

18.6 - 3 55.8 m2
14 - 3 42 m2
12 - 3 36 m2
11.6 - 3 34.8 m2
6.4 - 3 38.4 m2
31.9 - 4.5 143.55 m2

TOTAL = 350.55 m2
1.2 - 2.1 2.52 m2
1 - 2.1 2.1 m2
0.9 - 2.1 3.78 m2
0.75 - 2.1 1.575 m2
2.6 - 2.1 5.46 m2
1.5 - 2.1 3.15 m2

1.2 1.2 8.64 m2


2.4 1.2 2.88 m2
0.6 0.6 0.72 m2
TOTAL = 30.825 m2

5.7 3.6 - 20.52 m2


4 3- 12 m2
3 3- 9 m2
3 2.8 - 8.4 m2
TOTAL = 49.65

1.2 2- 4.8 m2
TOTAL = 4.8 m2

10 2.1 - 21 m2
1.2 1.2 - 2.88 m2
18.12 m2

5.3 2.1 - 22.26 m2

0.9 2.1 - 1.89 m2


0.6 0.6 - 0.36 m2
20.01 m2
per day
m3
8.4042 days

m3
m3
10.78231 m3

0.829 m3
m3
24328.8 24.32 tonnes

m3

Rs 18253.80
m3

11.127 m3
14.4651 m3

m3
3.278 m3

4720.32 kg
kg

94.52

7610.5 kg

3.8

269940 kg
5.7 3.6 - 20.52 m2
4 3- 12 m2
3 3- 9 m2
3 2.8 - 8.4 m2
TOTAL = 49.65

5.7 3.6 - 20.52 m2


4 3- 12 m2
3 3- 9 m2
3 2.8 - 8.4 m2
TOTAL = 49.65 m2
1.2 2- 4.8 m2
TOTAL = 4.8 m2
20.52 - 3 61.56 m2
12 - 3 36 m2
9 - 3 27 m2
8.4 - 3 25.2 m2
3.6 - 3 21.6 m2
171.36 m2
Explanation
L=66.4 -(1.1/2 x 5) = 63.65 D = (0.2 x 5) +0.1

L=66.4 -(1.1/2 x 5) = 63.66

D = 300mm (plinth level)


D = 300mm (plinth level)
D = 300mm (plinth level)
D = 300mm (plinth level)
D = 300mm (plinth level)

L = 66.4 - (0.9/2 x 5) = 64.15


L = 66.4 - (0.7/2 x 5) = 64.65
L = 66.4 - (0.5/2 x 5) = 65.15
L = 66.4 - (0.4/2 x 5) = 65.4

L = 66.4 - (0.2/2 x 5) = 65.9


L = 66.4 - (0.2/2 x 5) = 65.10
L = 3.2 + 8.8 + 7.9 + 7 + 4.7 + 1.7 = 33.3m

L = 1.2 + 0.15 + 0.15 = 1.5


L = 1 + 0.15 + 0.15 = 1.3
L = 0.9 + 0.15 + 0.15 = 1.2
L = 0.75 + 0.15 + 0.15 = 1.05
L = 2.6 + 0.15 + 0.15 = 2.9
L = 1.5 + 0.15 + 0.15 = 1.8
L = 1.2 + 0.15 + 0.15 = 1.5
L = 2.4 + 0.15 + 0.15 = 2.7
L = 0.6 + 0.15 + 0.15 = 0.9

L = 8.1 + 0.15 + 0.15 = 8.4 D = 9 + 0.15 + 0.15 = 9.3

L = 0.15 + 1.2 + 0.15 = 1.5


L = 0.15 + 2.4 + 0.15 = 2.7
L = 0.15 + 0.6 + 0.15 = 0.9

L = 1.2 + 0.15 + 0.15 = 1.5


L = 1 + 0.15 + 0.15 = 1.3
L = 0.9 + 0.15 + 0.15 = 1.2
L = 0.75 + 0.15 + 0.15 = 1.05
L = 2.6 + 0.15 + 0.15 = 2.9
L = 1.5 + 0.15 + 0.15 = 1.8
L = 1.2 + 0.15 + 0.15 = 1.5
L = 2.4 + 0.15 + 0.15 = 2.7
L = 0.6 + 0.15 + 0.15 = 0.9

L = 3.4 + 9 + 8.1 + 4.9 + 4.7 + 1.8 = 31.9


D = 3 + 0.15 + 0.45 + 0.9 = 4.5
L = 3 +4 + 3 = 10m

L = 2 + 1.2 + 1.2 + 2 = 6.4m

You might also like