Estimation and Costing - Lig
Estimation and Costing - Lig
A)
6
8
9
LCL = 4H1 + H2 + 2V1 + 2V2 = 66.4m
Number of T junctions = 5
Particulars Numbers
Earthwork Excavation 1
Deductions
a) Doors
i) Main Door 1
ii) Room Door 1
iii) Toilet Door 2
iv) Utility Door 1
v) Opening 1 1
vi) Opening 2 1
b) Windows / Ventilators
i) Window 1 (1200mm wide) 6
ii) Window 2 (2400mm wide) 1
iii) Ventilator 2
c) Lintels
i) Main Door 1
ii) Room Door 2
iii) Toilet Door 2
iv) Utility Door 1
v) Opening 1 1
vi) Opening 2 1
vii) Window 1 6
viii) Window 2 1
ix) Ventilator 2
ii) Lintels
i) Main Door 1
ii) Room Door 2
iii) Toilet Door 2
iv) Utility Door 1
v) Opening 1 1
vi) Opening 2 1
vii) Window 1 6
viii) Window 2 1
ix) Ventilator 2
b) Windows / Ventilators
i) Window 1 (1200mm wide) 6
ii) Window 2 (2400mm wide) 1
iii) Ventilator 2
Ceramic Tiles
Toilets 2
Dado Cladding
Kitchen 1
Deduction - Window 2
TOTAL =
Kitchen Dado Cladding using vitrium tiles = 18.12 m2
Toilet 2
Deductions
Door 1
Ventilator 1
TOTAL =
Toilet Dado Cladding using ceramic tiles = 20.01 m2
Weight of Cement
Dry Volume X ( Cement Volume / PCC Mix ) = 10.782 X ( 1/ 13 ) =
Weight of Cement 0.829 X 1400 = 1160.60 kg
Number of Bags = 1160.60 / 50 = 23.21
NUMBER OF BAGS = 24 BAGS
Each bag = Rs 300
Cost for 24 Bags = 24 X 300 = Rs 7200
Weight of Sand
Volume of Sand = 10.782 X ( 4/13 ) = 3.31
Weight of Sand = 3.31 X 1500 = 4965 Kg
Total weight of Sand = 4965 kg
1 Truck Load = 2 Tonnes
Number of Truck Loads = 2.48
Number of Truck Loads = 2.5
Price of Truck Load = Rs 2075
Total Cost = Rs 5187.5
Weight of Gravel
Volume of Gravel = 10.782 X ( 8/13 ) = 6.63
Weight of Gravel = 6.63 X 1500 = 9945 Kg
9.94 tonnes
Price per tonne = Rs 640
Total Price = Rs 6361.6
Labour Cost
( Bhisti , Male and Female Coolie - 3 )
Labour Charges per 10m3 of sand = Rs 2275
Labour Charges for 15.696 m3 of sand = 2275 X 15.696 = 35708.4
Labour Charges = Rs 35708.4
TOTAL CHARGES FOR SAND FILLING = RS 58812.4
Total Quantity of brick work with plinth and foundation and ded. = 44.509 m3
No of bricks in 1 cubic meter of Masonary 500
Total Volume of brickwork 44.509
Number of bricks required 500 x 44.509 = 22254.5
NUMBER OF BRICKS REQUIRED = 22255
Cost of Brick = Rs 17
TOTAL COST OF BRICKS = Rs 378335
COST OF MATERIALS :
Ratio - 1:5 = 1+5 = 6
Cement
Volume of Cement = 4.9868 X 1/6 = .8311m3
Weight of Cement = 0.8311 X 1450 = 1205.09 Kg
Number of bags of Cement = 1205.09 / 50 = 24.101
Cost = 24.101 X 300 = Rs 7230.570
Sand
Volume of Sand = 4.9868 X 5/6 = 4.151 m3
Weight of Sand = 4.151 X 1550 = 6434.50 Kg = 3.2 tonnes = 3.5 tonnes
Cost = 3.5 X 2050 = Rs 7157
COST OF LABOUR :
Everyday work done - 40 m2
Number of days required = 319.72/40 = 7.99 = 8 days
Payment per day = Rs 4900 ( for 3 masons and 3 mazdoors and 1 lab)
Total Labour Cost = 4900 X 8 = Rs 39200
Total cost = 7230.57 + 7157 + 39200 = Rs 53587.57
i) Living Room 1
ii) Kitchen 1
iii) Room 1 1
iv) Room 2 1
Ratio - 1:5 = 1 + 5 = 6
COST OF MATERIALS :
Cement
Volume of Cement = 0.645 X 1/6 = 0.1075 m3
Weight of Cement = 0.1075 X 1450 = 155.98 Kg
Number of bags = 155.98 / 50 = 3.119 Bags = 3.2
Cost = 3.2 X 300 = Rs 960
Sand
Volume of Sand = 0.645 X 5/6 = 0.5375 m3
Weight of Sand = 0.5375 X 1550 = 833.125 Kg
Number of tonnes = 0.416 tonnes = 0.50 tonnes
Cost = Rs 0.50 X 2050 = Rs 1025
COST OF LABOUR :
Everyday work done - 40 m2
Number of days required = 49.65/40 = 1.24 = 1.3 days
Payment per day = Rs 4900 ( for 3 masons and 3 mazdoors and 1 lab)
Total Labour Cost = 4900 X 1.3 = Rs 6370
i) Living Room 1
ii) Kitchen 1
iii) Room 1 1
iv) Room 2 1
One floor tile size =0.6m X 0.6m = 0.36 m2
Number of tiles required =49.65 / 0.36 = 137.9 tiles
Required Number of tiles = 140
Digital vitrified tile- antique beige
Costing - Rs 850/box
Each box - 4 tiles
For 140 tiles = 140/4 = 35 boxes
Cost = 35 X 850 = Rs 29750
Cement
Wet volume = 0.12 X 49.65 = 5.958 m3
Dry Volume = 5.958 X 1.3 = 7.745 m3
Bags required for 1m3 of CM in 1:3 mix = 7.25 bags
Bags required = 7.25 X 7.745 = 56.15 bags
Cost for this = 56.15 X 300 = Rs 16845.375
Sand
Sand required for 1m3 of CM in 1:3 mix = 1.163 tonnes
Sand required = 1.163 X 7.745 = 9 tonnes
Cost of Sand = 9 X 2050 = Rs 18450
Labour Cost
1 tiler + 1 helper - Can cover 12.5 m2/day
Days for 49.65 = 49.65/12.5 = 3.97 days = 4 days
Cost of labour per day = Rs 1000 + 550 = Rs 1550
Total cost = 1550 X 4 = Rs 6200
Toilets 2
Cement
Wet Volume = 0.012 X 4.8 = 0.0576 m3
Dry Volume = 0.0576 X 1.3 = 0.074 m3
Cement Required for 1m3 of 1:3 CM mix = 7.25 bags
Bags Required = 7.25 X 0.074 = 0.5365 bags = 1 bag
Cost = Rs 1 X 300 = Rs 300
Sand
Sand required for 1m3 for CM in 1:3 mix = 1.163 tons
Sand required for 0.074 = 1.163 X 0.074 = 0.086 tons = 0.09 tons
Cost of Sand = 0.09 X 2050 = Rs 184.50
Labour Cost
1 tiler + 1 helper - Can cover 12.5 m2/day
Days for 4.8 m2 = 4.8/12.5 = 0.385 = 0.5 days
Cost per day = Rs 1000 + 550 = Rs 1550
Cost for 0.5 days = Rs 775
10% charges for grot and adhesives = Rs 77.5
Material Cost
Material Required = Base coat of putty / Wall primer
1 Litre of Putty = 12m2
Litres Required = 319.72 / 12 = 26.64 Litres
1 Kg = 1L
15 Kg of Asian Paint Primer Costs = Rs 2400
Cost = 26.64 X 2400 / 15 = Rs 4262.40
LABOUR COST
3 painters + 3 helpers - 45 m2 / day
Number of days required = 319.72 / 45 = 7.10 days = 7.5 days
Cost per day = Rs 1200 + 450 = Rs 1650
Total Cost = Rs 1650 X 7.5 = Rs 12375
COST = Rs 16637.40
10% adhesive and tool charges = Rs 1663.74
TOTAL COST = Rs 16836
i) Living Room 1
ii) Kitchen 1
iii) bedroom 1 1
iv) bedroom 2 1
v) Toilets 2
Internal Plastering + Painting Area =
Labour Cost
3 Labourers + 3 Helpers - 45m2/day
Number of days required = 4.6 days
Cost per day = Rs 1200 + 450 = Rs 1650
Total Labour Cost = Rs 1650 X 4.6 = Rs 7590
10% for adhesives and tools = Rs 759
Total Cost = Rs 8349
Cement
Wet Volume = 0.012 X 18.12 = 0.217 m3
Dry Volume = 0.217 X 1.3 = 0.282 m3
1m3 of CM mix 1:3 requires = 7.25 bags
Number of bags = 0.282 X 7.25 = 2.044
Cost of bags = 2.044 X 300 = Rs 613.35
Sand
1 m3 of CM mix 1:3 requires = 1.163 tons
Sand required = 1.163 X 0.282 = 0.327 tons
Cost of Sand = 0.327 X 2050 = Rs 672.330
Labour Cost
1 tiler + 1 helper = 12.5 m2/ day
Number of days for this area = 18.12/12.5 = 1.44 = 1.5 days
Cost per day = Rs 1000 + 550 = Rs 1550 / day
Total Labour Cost = 1.5 X 1550 = Rs 2325
Cement
Wet Volume = 0.010 X 20.01 = 0.2 m3
Dry Volume = 0.2 X 1.3 = 0.26 m3
1 m3 of CM in 1:3 - 7.25 bags
Number of bags = 7.25 X 0.26 = 1.88 bags = 2 bags
Cost = 2 X 300 = Rs 600
Sand
1 m3 of CM in 1:3 - Requires 1.163 tons
Number of Tonnes = 0.26 X 1.163 =0.30 tonnes
Cost = Rs .30 X 2050 = Rs 615
Labour Cost
1 tiler + 1 helper - 12.5m2/day
Number of Days = 20.01 / 12.5 = 1.60
Cost per day = Rs 1000 + 550 = Rs 1550
Total Labour Cost = 1550 X 1.60 = Rs 2480
51.446
- 6.937
44.509 m3
14.07 m3
18.6 - 3 55.8 m2
14 - 3 42 m2
12 - 3 36 m2
11.6 - 3 34.8 m2
6.4 - 3 38.4 m2
31.9 - 4.5 143.55 m2
TOTAL = 350.55 m2
1.2 - 2.1 2.52 m2
1 - 2.1 2.1 m2
0.9 - 2.1 3.78 m2
0.75 - 2.1 1.575 m2
2.6 - 2.1 5.46 m2
1.5 - 2.1 3.15 m2
1.2 2- 4.8 m2
TOTAL = 4.8 m2
10 2.1 - 21 m2
1.2 1.2 - 2.88 m2
18.12 m2
m3
m3
10.78231 m3
0.829 m3
m3
24328.8 24.32 tonnes
m3
Rs 18253.80
m3
11.127 m3
14.4651 m3
m3
3.278 m3
4720.32 kg
kg
94.52
7610.5 kg
3.8
269940 kg
5.7 3.6 - 20.52 m2
4 3- 12 m2
3 3- 9 m2
3 2.8 - 8.4 m2
TOTAL = 49.65