3 - Blowout Plan
3 - Blowout Plan
3 - Blowout Plan
Blowout
Classification Restricted
Distribution:-
Copy No. 1 Petronas
Document Control
Copy No. 2 IDC
Copy No.3-7 Rig Sites(IDC 54/IDC58)
The HSE Department is responsible for the development and maintenance of this procedure.
All subsequent revisions of the procedure shall be reviewed the HSE Manager and approved by
Project Manager.
HSE Manager is responsible that this procedure is updated after the organizational or operational
changes. Drilling department shall control the technical contents of this procedure before each
revision is approved.
1. GENERAL
This Procedure is details response plan for well incident and blowout situations arising out of any
IDC activity.
1.1 OBJECTIVES:-
The objective of this plan is to provide an overview of the required actions to be taken in the
event of a well incident with potential to escalate into a blowout, or in the event of a blowout.
The plan describes the requirement to support the existing rig site in an escalating phase, and
the organization and scope of work for a Task Force in case of a blowout. This also includes
the definition of the responsibilities and authority during mobilization and operation of a Task
Force.
The Blowout Response Plan is intended to cover well control activities during an escalation
phase and necessary activities to regain control over a blowout situation.
1.2 BLOWOUT: -
The term blowout covers undesirable events, such as uncontrolled flow of formation
fluid(s)/gases to the surface or between formations (underground blowout) from wells in
drilling, completion, work over, well service, or production mode. The situation will have a high
degree of criticality, and will involve elements like:
Well incidents, such as minor kicks are to be handled in accordance with established well control
procedures. However, even minor incidents, if not handled correctly, have the potential to develop
into a blowout situation. There are numerous causes for such well incidents. Common for all of
them is that the well integrity is jeopardized, due to loss or damage of one or several well barriers.
It must be recognized that such an incident can occur in all phases of a drilling and well
operations, i.e. during exploration and production drilling, completion, production, work over, well
service, and plug & abandonment.
Well incident severity and development over time will set requirement to the level of needed
organizational support to the operational team responsible for the well(s) in question.
Note: Since there are several types of possible well control incidents, sound judgment should be
used when deciding severity level.
In the day to day operation, the Rig Manager will be in charge of his operations team. His line
of report will be to the Project Manager in the operation area. This team will have available
professional support from the Operation Duty Managers and Discipline Support at the Main
Office.
The responsibility for taking the decision to mobilize support lies with the Project Manager.
The local Authority and Clients should be informed as soon as possible and immediately
support from them shall be proposed.
To organize the necessary support, he will alert the Operational Manager in main office
organization and request support in accordance with the defined classification level.
A Level 2 and 3 well incident, would call for more resources than available within the project
team staff, i.e. the situation might call for around the clock presence of superintendent,
engineers, and specialists in the Project Local office. The time factor will normally be of critical
importance in Level 2 and 3 well incident situations, so that all personnel/resources required,
shall immediately be relieved from all other engagements/duties. Local resources from clients
and other specialize company may be used if support from Main Office cannot be available in
due time.
The Operational Manager at Main Office will have the authority to mobilize the necessary
operational and technical support, in cooperation with the HSE Manager. He will also notify the
president and relevant authority.
Emergency Response Team Leader
The driller should immediately raise the Kelly to a position so that the pipe rams will close
on the pipe and not on the Kelly or tool joint. An annular BOP can be closed on Kelly or tool
joint if necessary but if possible it is best to get in position to use the ram type BOP’s.
The derrick man should go to the flow line area and note the pit level and whether or not the
pits are gaining or losing fluid and at what rate. He should be in position to signal these
conditions to the driller, and then be prepared to control the choke manifold when needed.
There should be no panic. The overall situation should be analyzed and a positive move
decided upon. Doing the wrong thing is the greatest hazard at this time. If no blowout is
evident, (as in a drill), normal drilling operations should be resumed
If it is apparent that a blowout is starting, the driller should stop the pump and then order the
motorman or floor man to close the pipe rams, then the motorman and floor man should
check for water on the exhausts or for any fire and eliminate any fire hazards. The derrick
man and other floor man should also eliminate any fire hazards they can find.
The driller should note and make record of the pressure on the stand pipe and annulus and
pit volume change. Leave the well shut-in long enough to analyze the situation and make
preparation for controlling the well. Under extreme conditions, if the pressure exceeds the
surface pressure limits, open the chokes to relieve pressure. It is better to leave the well shut
in than to do something wrong. As a last resort, a bull heading procedure could be
implemented
Notify the tool pusher or drilling superintendent as soon as possible. Use the standard Wait
and Weight method for circulating the gas out unless ordered to do otherwise by the
If pressure is not too high, the annular preventer should be closed with minimum pressure,
pipe rams opened, and the pipe moved occasionally to prevent pipe sticking. This procedure
should be a mutual agreement with the operating company.
The driller should immediately get the drill string in position to install the inside BOP. If drill
collars are in the rotary and time permits, he should get a joint of drill pipe or a stand of drill
pipe or a stand of drill pipe made up as soon as possible and get the pipe in position so the
pipe rams can be closed on the pipe and not a drill collar or tool joint.
The derrick man should get out of the derrick and be near the driller to receive orders.
The driller should analyze the situation and if the well is starting to blowout, have the
appropriate BOP closed. Leave the well shut in long enough to note pressures and to
determine the overall problem. Under Extreme conditions, if the pressure exceeds the
surface pressure limits, open the chokes to relieve pressure. It is better to leave the well
shut in than to do something wrong. As a last resort, a bull heading procedure could be
implemented.
Notify the tool pusher or supervisor t as soon as possible, and, depending upon the
situation, wait for help or material or proceed with bringing the well under control. If
practical, plan to get the bit, or bottom of drill string, to the bottom of the hole or bottom of
the casing. Use the standard Wait and Weight method for circulating out the gas, unless
ordered to do otherwise by the operator. Other methods of well control could be selected
depending on the situation
The driller should never keep the pipe out of the hole any longer than necessary, He
should always run pipe back to the casing shoe if possible before shutting down for
repairing rig, jetting pits, cutting drilling line, etc. A drill pipe full opening safety valve or the
Kelly with a lower Kelly safety valve should be in place on the drill pipe during this
operation.
Close the blind rams as soon as any obstructions are out of the way. Leave well shut in
until the pressure stabilizes and the overall problem is understood. It is better to leave the
well shut in than do something wrong. However, if the well reaches pressure limits, use a
pressure controlled volumetric bleed-off procedure. This should allow pressure and well
bore stress to be reduced minimizing formation pressure intrusion. as a last resort, a bull
heading procedure could be implemented.
Notify the tool pusher or drilling superintendent as soon as possible, and depending upon
the situation, wait for help or material or proceed with bringing the well under control. If
practical, the drill pipe should be run to the bottom of the hole or bottom of the casing. Use
the standard Wait and Weight method for circulating out the gas, unless ordered to do
otherwise by the operator.