Systems Design: Job-Order Costing and Process Costing: MANAGEMENT ACCOUNTING - Solutions Manual
Systems Design: Job-Order Costing and Process Costing: MANAGEMENT ACCOUNTING - Solutions Manual
Systems Design: Job-Order Costing and Process Costing: MANAGEMENT ACCOUNTING - Solutions Manual
CHAPTER 8
I. Questions
1. Job-order costing is used in those manufacturing situations where there
are many different products produced each period. Each product or job
is different from all others and requires separate costing. Process costing
is used in those manufacturing situations where a single, homogeneous
product, such as cement, bricks, or gasoline, is produced for long periods
at a time.
2. The job cost sheet is used in accumulating all costs assignable to a
particular job. These costs would include direct materials cost traceable
to the job, and manufacturing overhead cost allocable to the job. When a
job is completed, the job cost sheet is used to compute the cost per
completed unit. The job cost sheet is then used as a control document
for: (1) determining how many units have been sold and determining the
cost of these units; and (2) determining how many units are still in
inventory at the end of a period and determining the cost of these units
on the balance sheet.
3. Many production costs cannot be traced directly to a particular product
or job, but rather are incurred as a result of overall production activities.
Therefore, in order to be assigned to products, such costs must be
allocated to the products in some manner. Examples of such costs
would include utilities, maintenance on machines, and depreciation of
the factory building. These costs are indirect production costs.
4. A firm will not know its actual manufacturing overhead costs until after
a period is over. Thus, if actual costs were used to cost products, it
would be necessary either (1) to wait until the period was over to add
overhead costs to jobs, or (2) to simply add overhead cost to jobs as the
overhead cost was incurred day by day. If the manager waits until after
the period is over to add overhead cost to jobs, then cost data will not be
available during the period. If the manager simply adds overhead cost
to jobs as the overhead cost is incurred, then unit costs may fluctuate
from month to month. This is because overhead cost tends to be
10-1
Chapter 10 Systems Design: Job-Order Costing and Process Costing
10-2
Systems Design: Job-Order Costing and Process Costing Chapter 10
II. Exercises
Requirement 1
Company X:
Company Y:
Company Z:
Requirement 2
Requirement 1
Milling Department:
Assembly Department:
Requirement 2
Overhead Applied
Milling Department: 90 MHs × P8.50 per MH P765
Assembly Department: P160 × 125% 200
Total overhead cost applied P965
10-4
Systems Design: Job-Order Costing and Process Costing Chapter 10
Requirement 3
Yes; if some jobs required a large amount of machine time and little labor
cost, they would be charged substantially less overhead cost if a plantwide
rate based on direct labor cost were being used. It appears, for example, that
this would be true of job 123 which required considerable machine time to
complete, but required only a small amount of labor cost.
Work in Process—Mixing......................................................................................
330,000
Raw Materials Inventory.................................................................................
330,000
Work in Process—Mixing......................................................................................
260,000
Work in Process—Baking.......................................................................................
120,000
Wages Payable................................................................................................
380,000
Work in Process—Mixing......................................................................................
190,000
Work in Process—Baking.......................................................................................
90,000
Manufacturing Overhead.................................................................................
280,000
Work in Process—Baking.......................................................................................
760,000
Work in Process—Mixing...............................................................................
760,000
Finished Goods.......................................................................................................
980,000
Work in Process—Baking...............................................................................
980,000
Requirement 1
Weighted-Average Method
Quantity
Schedule
10-5
Chapter 10 Systems Design: Job-Order Costing and Process Costing
Equivalent Units
Material
s Labor Overhead
Gallons accounted for as follows:
Transferred to the next department............. 790,000 790,000 790,000 790,000
Work in process, May 31 (materials 60%
complete, labor and overhead 20%
complete)................................................ 50,000 30,000 10,000 10,000
Total gallons accounted for.............................. 840,000 820,000 800,000 800,000
Requirement 2
Requirement 1
FIFO Method
Quantity
Schedule
Gallons to be accounted for:
10-6
Systems Design: Job-Order Costing and Process Costing Chapter 10
Equivalent Units
Material
s Labor Overhead
Gallons accounted for as follows:
Transferred to the next department:
From the beginning inventory................ 80,000 16,000* 20,000* 20,000*
Started and completed this month**..... 710,000 710,000 710,000 710,000
Work in process, May 31 (materials 60%
complete, labor and overhead 20%
complete)................................................ 50,000 30,000 10,000 10,000
Total gallons accounted for.............................. 840,000 756,000 740,000 740,000
Requirement 2
Exercise 7
Requirement (1)
The direct materials and direct labor costs listed in the exercise would have
been recorded on four different documents: the materials requisition form for
Job KC123, the time ticket for Kristine, the time ticket for Clarisse, and the
job cost sheet for Job KC123.
10-7
Chapter 10 Systems Design: Job-Order Costing and Process Costing
Requirement (2)
The costs for Job KC123 would have been recorded as follows:
Exercise 8
10-8
Systems Design: Job-Order Costing and Process Costing Chapter 10
Exercise 9
Weighted-Average Method
Materials Labor Overhead Total
Work in process, May 1................................ P 14,550 P23,620 P118,100
Cost added during May................................. 88,350 14,330 71,650
Total cost (a).................................................
P102,900 P37,950 P189,750
Equivalent units of
production (b)............................................ 1,200 1,100 1,100
Cost per equivalent unit
(a) ÷ (b).....................................................P85.75 P34.50 P172.50 P292.75
Exercise 10
FIFO Method
Materials Conversion
To complete beginning work in process:
Materials: 400 units x (100% – 75%).............................................................
100
Conversion: 400 units x (100% – 25%).......................................................... 300
Units started and completed during the period
(42,600 units started – 500 units in ending
inventory).........................................................................................................
42,100 42,100
Ending work in process
Materials: 500 units x 80% complete.............................................................
400
Conversion: 500 units x 30% complete.......................................................... 150
Equivalent units of production...............................................................................
42,600 42,550
III. Problems
Problem 1
Requirement 1
10-9
Chapter 10 Systems Design: Job-Order Costing and Process Costing
b. Work in Process...........................................................178,000
Manufacturing Overhead............................................. 12,000
Raw Materials Inventory......................................... 190,000
f. Work in Process...........................................................240,000
Manufacturing Overhead......................................... 240,000
30,000 MH x P8 per MH = P240,000.
g. Finished Goods............................................................520,000
Work in Process....................................................... 520,000
Accounts Receivable...................................................600,000
Sales........................................................................ 600,000
P480,000 × 1.25 = P600,000
Requirement 2
10-10
Systems Design: Job-Order Costing and Process Costing Chapter 10
Problem 2
Requirement 1
The costing problem does, indeed, lie with manufacturing overhead cost, as
suggested. Since manufacturing overhead is mostly fixed, the cost per unit
increases as the level of production decreases. The problem can be solved by
use of predetermined overhead rates, which should be based on expected
activity for the entire year. Many students will use units of product in
computing the predetermined overhead rate, as follows:
Estimated manufacturing overhead cost, P840,000
= P4.20 per unit.
Estimated units to be produced, 200,000
The predetermined overhead rate could also be set on the basis of either direct
labor cost or direct materials cost. The computations are:
Estimated manufacturing overhead cost, P840,000
= 350% of direct
Estimated direct labor cost, P240,000 labor cost
Requirement 2
10-11
Chapter 10 Systems Design: Job-Order Costing and Process Costing
Problem 3
Weighted-Average Method
Quantity
Schedule
Pounds to be accounted for:
Work in process, May 1
(all materials, 55% labor and
overhead added last month).......... 30,000
Started into production during
May................................................ 480,000
Total pounds............................ 510,000
Equivalent Units
Labor &
Materials Overhead
Pounds accounted for as follows:
Transferred to Department 2............ 490,000* 490,000 490,000
Work in process, May 31
(all materials, 90% labor and
overhead added this month).......... 20,000 20,000 18,000
Total pounds............................ 510,000 510,000 508,000
* 30,000 + 480,000 - 20,000 = 490,000.
Problem 4 (Weighted-Average Method; Interpreting a Production
Report)
Requirement 1
Weighted-Average Method
10-12
Systems Design: Job-Order Costing and Process Costing Chapter 10
Requirement 2
Equivalent units of
production (b) – 220,000 214,000
..........................................
Cost per EU (a) (b)........... – P2.94 + P1.30 = P4.24
Requirement 3
Requirement 4
No, the manager should not be rewarded for good cost control. The reason
for the Mixing Department’s low unit cost for April is traceable to the fact
that costs of the prior month have been averaged in with April’s costs in
computing the lower, P2.94 per unit figure. This is a major criticism of the
weighted-average method in that the figures computed for product costing
purposes can’t be used to evaluate cost control or measure performance for
the current period.
10-13
Chapter 10 Systems Design: Job-Order Costing and Process Costing
Requirement 1
Weighted-Average Method
Quantity
Schedule
Pounds to be accounted for:
Work in process, May 1
(materials all complete, labor
and overhead 4/5 complete)..... 35,000
Started into production................ 280,000
Total pounds to be accounted for..... 315,000
10-14
Systems Design: Job-Order Costing and Process Costing Chapter 10
Cost Reconciliation
Requirement 2
1. D 6. D 11. A 16. A
2. D 7. A 12. D 17. D
3. D 8. C 13. B 18. A
4. C 9. C 14. D 19. C
5. D 10. B 15. C 20. D
10-15
Chapter 10 Systems Design: Job-Order Costing and Process Costing
10-16