Hydraulic Structures: Locks
Hydraulic Structures: Locks
Hydraulic Structures
Locks
Hydraulic Engineering
Faculty of Civil Engineering ii 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
TABLE OF CONTENTS
PREFACE......................................................................................................................................................1
2.3 Manoeuvrability while navigating through the lock and approach areas ............................................26
Hydraulic Engineering
Faculty of Civil Engineering iii 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
5. References ...........................................................................................................................................125
APPENDICES
Hydraulic Engineering
Faculty of Civil Engineering iv 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
PREFACE
Are these lecture notes finished for the next years? Probably not; big projects like the Panama Canal Lock
project and the Seine-Nord project are knocking on the door and shall find an entry into the material
written down here. But it is time to stick to the 80-20% efficiency rule.
And why did writing these lecture notes take so long if only an English translation of the already existing
Dutch lecture notes had to be produced in 2004? The answer is that opportunity knocked on the door:
there was a chance to include material from books published e.g. by Rijkswaterstaat, and the new
material that would be gathered by the PIANC Workgroup for the revision of the navigation lock report;
this update was recently published indeed, Of course, from the moment more considerable changes get
into view, minor items like upgrading the illustrations is taken at hand as well. It all boiled down to a very
substantial revision of the lecture notes on locks; it took the time that was needed, too long for the
impatient mind, but it was done with pleasure.
These lecture notes were written upon the backs, shoulders and brains of many predecessors, if anyone,
Kees Bezuyen has to be mentioned because he meant so much for many hydraulic engineering students,
so long. Students, graduate students and young engineers also contributed and I hope that especially
student readers will show the initiative to point the finger at mistakes, but what would be better, possible
improvements in the future.
In chapter 1 we will provide a general overview of the various sluice types that exist. Functions and their
application in different types of sluices will be discussed. A (navigation) lock has to suffice to most, if not
all the functions that will be reviewed. Therefore it is meaningful to produce a (preliminary) design of a
navigation lock to find out into what trouble the designer gets combining all the functions. In order to be
able to make a design the required theory will be presented in Chapters 2 through 4. Chapter 2 deals with
general design matters and subjects that are especially important in the initiative and feasibility stages of a
project. In following chapters the focus will be more and more on the structures of lock (complex) and the
constituting elements. Chapter 3 the main items to determine the overall navigation lock layout are
described, whilst Chapter 4 will treat the most important structural components (filling and emptying
systems, lock chamber, lock gates, lock head, etc.), in more detail.
For Dutch BSc-students this is probably one of the first courses in the English language, so some very
specific technical terms have been translated into Dutch (indicated between brackets and in italics).
Hydraulic Engineering
Faculty of Civil Engineering 1 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Hydraulic Engineering
Faculty of Civil Engineering 2 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The main functions of a sluice, as defined by the Dutch TAW (Technische Adviescommissie
Waterkeringen; this committee was abolished in 2005) are:
• Water retention (keren)
• Water locking (schutten)
• Water discharge (spuien)
• Shore connection (oeververbinding)
Before focusing on navigation locks some other sluices will be briefly described to illustrate the wide variety of
structures used for, on one hand, water retention, on the other hand, passage of the same water and e.g.
ships. The latter last but not least in many situations. Keep in mind that the word sluices is used to indicate
that the lock belongs to a larger family of structures constructed for similar reasons. The following sluices will
be dealt with in different sections:
• Dewatering gate - uitwateringssluis
• Stop lock - spuisluis
• Guard lock - keersluis
• Navigation lock schutsluis
In polders the discharge of water (from low to a high) is separated in two steps. First, the water is pumped
in a storage basin or reservoir, or discharge channel (boezem) located at a higher level than the polder.
Next, as soon as the water level in the basin or channel exceeds the water level of the sea or the nearest
river, the water is discharged through a dewatering gate. Typically such a dewatering gate is a duct
(duiker, (omloop)riool)) with a valve that serves as (adjustable) closing element (afsluitmiddel). This
implies that shipping through a dewatering gate is impossible.
Additionally, the dewatering gate may serve as fresh- salt water separator or retain water (for instance
between salt sea water and fresh or potable water of a canal or polder system). In case high external
water levels occur it acts as a barrier.
From the above the functions of a dewatering gate can be deduced, as follows:
- Discharge of water from the area taken into consideration (polder) when the basin level exceeds the
target or allowable level
- Retain water at high external water levels
- Separation of salt water and fresh water
Hydraulic Engineering
Faculty of Civil Engineering 3 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
There is an increasing demand for a more accurate control of the storage basin levels. This requirement
results in the application of gates that can be operated by will rather than as a result of coincidental
differences in water level. Moreover, the gates must be able to withstand water level differences in both
directions, generally lift gates (hefdeur) or rolling gates (roldeur) are more suitable than mitre gates. The
whole is referred to as the automatic dewatering gate. An advantage of this solution is that it can be used
for irrigation when the water levels are too low to meet for agricultural demands. Purpose built for that
situation the dewatering is more accurately referred to as an inlet sluice (inlaat sluis). In arid countries
these types of sluices are a common element of irrigation systems.
Obviously this doesn't apply to dewatering gates in coastal areas because of the salt content of the
seawater (e.g. the Haringvlietsluizen where segment gates were used).
Hydraulic Engineering
Faculty of Civil Engineering 4 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
In the design of the Haringvlietdam the following main functions are combined:
• Protection, retain water at high external water levels (protection North Sea)
• Diversion of water, forcing more water into the Nieuwe Waterweg (Rotterdam) to prevent the salt
water tongue to intrude too far landinward
• Discharge of water (river Rhine and Meuse) when the basin level exceeds the external water level
More info on the Haringvlietsluizen; see the website: http://www.haringvlietsluizen.nl (October 2005)
The higher the water level difference, the higher the flush velocity u, which results in increased sediment
transport s, which is illustrated by the following formula:
n
s = mu
Where:
s = sediment transport
m = ‘garbage’ coefficient or expression, not dimensionless, typically ≈ 0.01
u = velocity of water
n = constant, typically 3 ≤ n ≤ 5
Since the gates have to be opened at a water level difference, mitre gates cannot be applied for a stop
lock. An example of a stop lock in the Netherlands is illustrated in figure. In this particular case the stop
lock is positioned adjacent to a navigation lock.
Figure 1-3 Stop lock, Zandkreekdam Katse Figure 1-4 Stop lock, Afsluitdijk – Den Oever,
Heule, the Netherlands the Netherlands
More detailed information on the design of the Zandkreekdam - Katse Heule stop lock, on the east side of
the ‘Veerse meer’, can be found on the following website:
Hydraulic Engineering
Faculty of Civil Engineering 5 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The gate of the guard lock will be kept open as long as possible to allow ship passage, obviously, when
opened the guard lock can not retain water. A water level being too high or too low, not necessarily
extreme water levels, on either side of the lock may require closure of the gate, preventing further ship
navigation. Conditions for closure may be either extreme low water levels due to draught or extreme high
water levels due to a storm surge. Two types of guard locks exist: one-way retaining or both-ways
retaining.
Figure 1-5 Guard lock Kromme Nol near Heuschden, the Netherlands
In normal conditions, from water level point of view, the lock is open, only in certain extreme conditions
(during a storm) it retains water in one direction. This type of guard lock is commonly found in areas with a
small tidal range. The doors are closed when the outside water level reaches a certain predefined level.
When closed, the doors are part of a flood defense system, which also includes adjacent dikes or other
flood defense structures. The design height of the doors may be less than the design height of the
surrounding dikes pending on berm design of the dike and the allowable amount of water overtopping the
structure (wateroverslag).
In areas with large tidal ranges, as for instance along the English Channel, harbour entrances are usually
equipped with guard locks retaining water both ways. For instance, at the harbour side of the guard lock,
the water level is kept between certain boundaries, effectively a harbour basin is created. A minimum
water level is defined to enable a vessel to manoeuvre safely without the fear of running aground.
Obviously, also a maximum water level is defined to prevent flooding of e.g. the port facilities and the
town.
Hydraulic Engineering
Faculty of Civil Engineering 6 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The harbour basin level differs from the tidal range. During low tide the water must be kept within the
harbour basin, and during high tide the water must be kept out. This implies that the guard locks are only
opened during the period around the turn of the tide (kentering), between high tide and low tide. Ships can
only pass during this period with, fortunately, limited flow velocities. There may be a more restrictive limit
to the draught of vessels because the high water tidal wave, thus deeper water, cannot be used
As an alternative to double retaining mitre, rolling, or sliding gates, or a vertical lift gate can be used.
These types are able to retain water in both directions. A disadvantage of the vertical lift gate to be taken
into due consideration is the limitation to the air draught of ships.
Storm surge barriers are closed to provide protection against extreme water levels, e.g. in storm
conditions in coastal areas. The main purpose of the structure is to protect the land from the sea in
(extreme) storm conditions and to ensure the passage of vessels for the remaining time.
A well known example is the Maeslantkering, the storm surge barrier in the New Waterway the gateway to
the port of Rotterdam.
Hydraulic Engineering
Faculty of Civil Engineering 7 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Comparing rivers or waterways having a steep water profile with rivers or canals having a rather flat water
profile results in the obvious conclusion that either a bigger number of locks, or a lock designed for a
higher lift, will be required for the steep profile. The efficiency of navigation would benefit in general from
locks being spaced as far apart as possible, which reduces shipping delays, but may result in high lifts that
can not be accommodated in most of the (traditional) locks. Positioning a number, typically 4 or 5, locks
behind each other, i.e. construction of a flight of locks or lock ladder, could solve this problem. However, in
these cases the use of alternatives, e.g. a ship lift or pente d'eau, should be investigated. Typically the
water level difference of the latter type of structures is > 25 meter.
Since the lock generally is part of the flood defense system along the river, the decision for the lift of the
lock also has effects on the retaining height of those systems and vice versa. The costs of one single big
lift lock and having to increase the top level of the (whole) flood defense system, to match the retaining
heights, have to be weighed against the costs of a bigger number of locks and smaller or no changes to
the flood defenses.
Figure 1-7 shows a typical inland navigation lock in the Netherlands. Due to the Dutch topographical
situation the required lift generally varies from say 3 to 5 meter. Following chapters will deal extensively
with this type of lock.
Figure 1-7 Typical inland navigation lock Figure 1-8 Princess of Scandinavia entering the
Middensluis, IJmuiden, the Netherlands
Hydraulic Engineering
Faculty of Civil Engineering 8 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Locks in tidal areas differ in many respects from those in inland waterways. The generally much larger
dimensions, due to the larger size of maritime vessels, see Figure 1-8, is the first to be taken into account.
Besides this they operate under water level differences in either direction; may have to be designed to
reduce salt water intrusion and should be able to cope with more adverse weather circumstances,
including wave attack.
The following navigation lock types, which are able to lift the ship over a bigger water level difference from
traditional lock to e.g. the rotating wheel in Falkirk, will be described in the hereinafter:
• (Traditional) lock; for inland navigation and for coastal areas
• Lift lock
• Inclined plane
• Pente d'eau
• The rotating wheel at Falkirk - Scotland
Lift lock
The principle of a lift lock is vertical transport of a vessel with the surrounding water in a movable closed
lock chamber. Some times the lift lock has two movable chambers counterbalancing each others weight,
see the description of the lift lock in Henrichenburg – Germany below, but this system can be considered
as slightly outdated. More often the weight of the moveable lock chamber is balanced by a counterweight
and the chambers are designed and constructed as independent systems. Provided the weights of the
chamber and the counter weight are more or less in equilibrium, a relatively small 'force' is required to put
the system into motion. For the latter mechanical devices, e.g. winch-cable or worm screw-engine
systems, or electro-magnetic engines can be used. Note that the weight of the moveable chamber nearly
always remains the same, since the total volume of water displaced equals the mass of the vessel
entering the chamber.
Hydraulic Engineering
Faculty of Civil Engineering 9 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
the gates the bottom and walls of the chamber and canal have to be joined with a watertight connection
and water level differences between the chamber and the canal reach have to be equalized as well.
Figure 1-11 Lift lock Luneburg – Germany. Areal view and cross sections
Hydraulic Engineering
Faculty of Civil Engineering 10 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Inclined plane
The principle of an inclined plane is the use of a natural slope in the terrain to overcome a height
difference. A movable lock chamber is moved over a slope. The adjoining waterways must be sealed of
with a water retention structure and gates (e.g. Ronquires 1968). Inclined planes can de divided in two
types:
• Transport in longitudinal direction - in the axis of the vessel (Ronquieres – Belgium; not in these
lecture notes
• Transport in transversal direction - perpendicular to the axis of the vessel (Arzviller – France, see
below)
Depending on local circumstances a choice is made for the one or the other. Some advantages and
disadvantages of these systems are listed below.
• Movement of water in the chamber during acceleration or slowing down, which is especially
important for longitudinal systems
• Amount of required space
• Forces in the cable system
• Positioning in the landscape.
Pente d'eau
The principle is the same as the inclined plane; the use of a natural slope in the terrain to overcome a
height difference. In this case water is being moved using a more or less watertight door in a kind of canal
pushing the water up or down a slope. The advantage would be a simpler construction than an inclined
plane. The disadvantage is that more energy needed to transfer water plane and ship. Up to now only a
few have been built (Montech 1974, Béziers 1983).
Hydraulic Engineering
Faculty of Civil Engineering 11 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
On the following website a nice animation showing the working principle of the pente d’eau in Montech –
France can be found:
http://www.canaux-historiques.com/d2m/ouvrage/montech/fiche_ouvrage/fo_00.html#
For improving the inland shipping connection between Paris and Belgium & the Netherlands, known as Seine-
Nord, the feasibility of a large pente d’eau has been taken into consideration (2006).
Rotating wheel
The original concept of a wheel to act as a boat lift actually dates back to 19th century Europe; it was
seriously considered by British Waterways as the solution for Falkirk in 1994.
Artist impression
Landrot:
boatlift
Schipper / Zeeman:
shiplift
Figure 1-14 The wheel during construction, Falkirk, Scotland
The objective was to create a functional boat lift that could raise and lower boats swiftly, over a height of
24 m, with a structure worthy of a new millennium. The Falkirk Wheel lies at the end of a reinforced
concrete aqueduct that connects, via the Roughcastle tunnel and a double staircase lock, to the Union
Canal.
Ships entering the Wheel’s upper gondola are lowered by a rotational movement, along with the water that
they float in, to the level of the lower canal reach. At the same time, an equal weight is lifted up in the other
gondola, which acts as counterweight. Archimedes Principle of displacement is applicable on the total
weight of the gondolas. The mass of the boat sailing into the gondola displaces a volume of water having
exactly the same mass. The total weight of the gondola remains the same.
The gondolas, or moveable lock chambers, have to rotate in the opposite direction of the wheel, otherwise
the vessel and surrounding water would be thrown out like the water of a bucket being emptied. Therefore
small wheels. running on a single curved rail fixed to the inner edge of the opening, have been assembled
Hydraulic Engineering
Faculty of Civil Engineering 12 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
to the gondola, at both ends. In theory, the downward weight of the gondola should be sufficient to always
remain horizontal, but any friction or sudden movement could cause the gondola to get stuck or tilt. To
ensure that this could never happen and that the gondola, the water and the boats, always remain
perfectly level throughout the whole rotation cycle, an inventive series of linked cogwheels (tandwielen) is
used as safety system.
Given the precise balancing of the gondolas and the relatively simple, nonetheless clever system of
cogwheels, operating without too much friction, only a small amount of energy is required to turn the
Wheel. In fact, it is a group of ten hydraulic motors located within the central spine that provide the small
amount, just 1.5 kW, of electricity to turn it. The figure below shows their position.
http://www.falkirk-wheel.com
http://en.wikipedia.org/wiki/Falkirk_Wheel
Hydraulic Engineering
Faculty of Civil Engineering 13 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
During the whole design process the work proceeds from more general considerations and rule of thumb
use into more detailed calculations. Results of more detailed calculations are feedback for the previous
level. Use the feedback to decide whether or not design is still heading in the right direction.
At a certain moment the life stages of the project or structure have to be taken into account. It is easy to
imagine that e.g. construction methods or maintenance requirements (operation phase) influence the
design. The following phases should be distinguished in the life cycle of a navigation lock:
Hydraulic Engineering
Faculty of Civil Engineering 14 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
1. Water retention - maintain a water level difference e.g. for water management or flood defense
purposes
2. Ship passage – the water level difference and the means to maintain the water level difference
require solutions for vertical and horizontal transport of the vessels
3. Water quality management – depending on the surroundings or environment of the lock care may
have to be taken about e.g. sediment and debris discharge or separation of salt and fresh water
Note:
th
As mentioned in the Introduction the TAW defined ‘Shore connection’ as the 4 ‘main’ function of
locks. This is a matter of definition indeed; what is a main function and what is a secondary
function? Often it depends on a particular situation. One could argue that water quality
management is not a main function at all. Another example would be to consider ‘Provision of port
facilities’ as main function of a pleasure navigation lock, whereas this would not be applicable for
commercial navigation.
It is easily observed that (structural) solutions for water retention may get in the way of ship passage and
water management, and vice versa, which is illustrated by the (incomplete) table below.
Function
Retain water Transport vessels
Horizontal Vertical
Dike / levee In water & using ship’s engine Adjusting water level
*
Sheetpile wall Sliding Lifting / lowering *
Door / gate Rolling *
‘Return pumping’
*
with or without the surrounding water or lock chamber
Table 2-1 Functions and solutions
Depending on the point of view the lock will be considered as a flood defense structure or as transport
infrastructure. In the following the emphasis will be on inland navigation, hence the transport function.
Navigation locks play an important role in the inland waterway transport network for the transport of goods
in Europe and in the Netherlands in particular. More than 35 000 kilometers of waterways connect
hundreds of cities and industrial regions. In European inland waterway transport is a realistic alternative to
road and rail transport. It is energy-efficient; the energy consumption per ton-kilometer is only 17% and
50% of the consumption of road and rail transport respectively. Noise and gaseous emissions are modest.
Additionally, inland waterway transport ensures a high degree of safety, in particular when it comes to the
transport of dangerous cargoes.
For the most common Dutch inland navigation lock the solution developed for retaining water and
transport of the vessel is to use a lock chamber that can be closed by gates to maintain the water level
difference. Within the lock chamber the water level can be adjusted to allow for the vertical transport of the
ships, the horizontal transport is taken care of by the ship’s own propulsion. Generally cut-off screens
below and adjacent to the structure are used to prevent piping. The function analysis for the typical Dutch
Hydraulic Engineering
Faculty of Civil Engineering 15 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
lock would result in the following lock components being necessary: Gates and housing, lock chamber, a
water leveling solution and cut-off screen.
Note:
A clear cut between the analysis of functions and the analysis of operational aspects is not always
possible, and again, depends on definition. In these lecture notes the lock chamber will be the
result of the functional analysis, whereas the dimensions of the lock chamber will be the result of
operational considerations, see section 2.1.2. The result, a comprehensive list or document of
design criteria, matters much more than determining by which principal method or principal
analysis it has been or should be obtained.
A lock is situated in a waterway between two sections with a different water level. Combined with dikes
and other structures it is part of a water defense system. The upper lock head (at the side of the highest
water level) must be able to retain the highest water level. The lower head only retains the maximum
chamber level, which is not necessarily the highest water level. In tidal areas lock heads are referred to as
outer head (on the sea side), respectively inner head (on the land side).
As part of the water defense structure the navigation lock must be able to retain water under all
circumstances. If for any reason (e.g. a ship runs into a gate) the lock is damaged a back-up system, a
second set of gates or stop logs, must be available to take over the water retaining function.
Typically, water levels will be different at both sides of a lock. This will result in a groundwater flow under
and around the sides of the lock structure. At the downstream side where the groundwater flow exits the
soil, erosion will occur in case the flow velocity is high enough to induce soil movement. This is a self
sustaining and enlarging process; since the first erosion will result in decreased flow resistance and
subsequent increased groundwater flow, exit velocity and erosion. The phenomenon is known as seepage
and /or piping, and may undermine the whole lock structure To avoid piping locks are provided with
seepage or cut-off walls, often sheetpiles are used as cut-off screen, acting as an impermeable curtain
perpendicular to the axis of the lock chamber. Alternatively filter layers and scour protection are used
around the structure, provided the resulting seepage or piping remains within acceptable limits. These
limits may be enforced from retention, water management or structural point of view.
A lock can also be used for water management, for quantitative as well as qualitative aspects of a water
management, or combinations. Qualitative aspects generally boil down to keeping water masses with
different properties separated, for instance:
• Clean and polluted water.
• Salt and sweet or fresh water.
Quantitative aspects in the water management system are for instance:
• Discharge of a predefined amount of water within a certain period of time.
• Minimizing the fresh water loss from the upper canal reach.
Discharge of water through a navigation lock can be achieved in various ways, e.g. valves in the gates or
a drain system. In tidal areas, the drainage system can be used to dispose salt water that entered the
fresh water. At times of large river discharges (e.g. during a period of heavy rainfall) the full cross section
of the lock may be needed for discharge. Flow velocities will be too high for safe navigation and locking is
impossible in this situation anyway. The lock at Dintelsas, at the mouth of the Mark or Dintel to the
Volkerak – the Netherlands, is an example of this type of lock.
Hydraulic Engineering
Faculty of Civil Engineering 16 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
In case of smaller discharges the lock's drainage system can be used to get rid of a surplus of water.
However, sluicing and locking cannot take place simultaneously. Preferably the discharge of water is in
"quiet" shipping hours, e.g. at night time or during the weekends. This to minimise hindrance for vessel
traffic. In case of multiple lock chambers both functions are more easily combined. The lock near Wijk bij
Duurstede – the Netherlands, is used to maintain the right waterlevel on the Amsterdam –Rijn canal. The
whole lifting gate is used to manage the water supply; not just valves in the gate.
The amount of water lost per leveling cycle is: A ⋅ z + Wup − Wdown
Where:
A = horizontal area lock chamber
z = difference in water level, water head
Wup = amount of water which is displaced by ships going upstream
Wdown = amount of water which is displaced by ships going downstream
Generally there is an imbalance in traffic, either a different number of ships sail up or down, using
alternative routes to return to the point of origin or destination, or vessels are loaded in upstream direction
whilst they sail in ballast in the downstream direction, or vice versa. To minimise the amount of water lost,
the use of reservoirs or water saving basins could be considered, or much more rigorously, the amount of
lost water could be pumped back to the upstream river reach.
Hydraulic Engineering
Faculty of Civil Engineering 17 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Analysing navigation through the lock results amongst other, in the following three design requirements:
1. Lock dimensions must be large enough to accommodate the governing (maatgevend) vessel for
the considered waterway (design ship).
2. Lock capacity, defined as the number of ships passing the navigation lock within a certain time
interval, must match present and/or future demand.
3. Even if the capacity is not fully utilised the time losses during passage should be kept at a
minimum.
The intensity of a waterway is defined as the number of ships that pass a given cross section of the
waterway per time interval. The capacity of a lock is the number of ships a lock is able to process. If the
capacity is too small this will result in long waiting hours, if the capacity is too large this will result in an
expensive navigation lock. For instance:
According to the client 12 800 vessels are expected to pass the waterway in one year. The
navigation lock is available 7400 hrs per year. This results in an intensity of 1.7 vessel per hour. If
the lock capacity is smaller than required the lock will not be able to handle the amount of vessels.
To determine the lock capacity a quick-and-dirty method to estimate a figure would be to use a
multiplication factor of 2 - 2.5. In this case this would result in a required capacity of 3 - 4 vessels
per hour.
Capacity calculations and related subjects are treated more elaborately in the course on Ports and
Waterways (CT 4330).
In the above the focus was on dimensions or the quantitative aspects relevant for lock design, now a brief
illustration of more qualitative results of the operational analysis. In the following table the navigation
process has been described, not even in the greatest possible detail, in the left column, whilst the right
hand column shows required lock components or lock furniture:
Hydraulic Engineering
Faculty of Civil Engineering 18 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Every lock provides some discharge capacity for its surroundings. It depends on the specified function and
the location of the lock whether or not this has a large impact on design of the lock; some examples:
• Lock complex IJmuiden: the Netherlands: the required discharge capacity is large since a number
of polders surrounding the Northsea canal are dewatered by this system. The capacity requirement
resulted in construction of a separate pumping station (gemaal) instead of combining the navigation
and discharge function in one lock.
• Locks in the city of Amsterdam: the canal system in Amsterdam has to be flushed through at
regular intervals (daily) to prevent al sorts of health risks in the city. A number of the stop locks are
also available for navigation. Navigation is not possible when the gates are open for discharge,
generally during night hours.
• The lock in Dintelsas: after large rainfalls the north western part of Brabant is dewatered through
this lock. When the lock is used for dewatering, navigation is interrupted.
• The lock at Wijk bij Duurstede: to let water in into the Amsterdam-Rijn canal the lifting gates of the
lock are used. The whole gate is lifted for 1 – 2 meters for this purpose, instead of using valves in
the gates, or a culvert system around the lock heads.
See the (sub)section on ‘Filling and emptying systems’ in Chapter 4 to determine whether or not the
functions navigation and discharge (in fact the water management function) can be combined in one lock
from an operational point of view.
To avoid too much interference of regular maintenance (annual) with navigation through the lock it may be
decided to take some extra measures, e.g. providing extra concrete cover or an extra set of gates.
Obviously the costs involved throughout the years would have to be carefully considered.
When irregular maintenance (groot onderhoud) (say once in a decade) is required generally navigation is
influenced, occasionally ships may have to be rerouted when the lock is completely taken out of operation
during the maintenance period. Suppose the irregular maintenance requires the lock chamber to be laid
open (droog gezet), which would imply that a lock with a closed concrete section has to be checked for
floating up. During design it could be decided to prepare the structure for this condition by adding, for
instance, tension piles, extended bottom slabs, extra concrete weight or combinations. Often structural
measures of this kind result in a substantial increase of the initial investment. Alternatively it could be
decided to solve the possible floating up problem if/when it actually occurs in the future if it is ever (really)
necessary to lay the lock open.
Nowadays it is more common practice ‘not’ to design and construct for being laid open. As a consequence
maintenance to the lock chamber walls and floor has to be done underwater.
In the design stage a decision has to be made on the maintenance strategy taking into consideration the
extra initial investments, the future costs and last but not least, the 'negative' revenues. Commercial
navigation pays for the use of the lock. When the lock is not available due to maintenance it does not
generate revenues and on top of this there are extra transport costs due to rerouting (extra costs for the
society; not necessarily for private parties).
Hydraulic Engineering
Faculty of Civil Engineering 19 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Suppose the evaluation method uses the Net Present Value (NPV) technique for costs, than the costs for
regular, irregular or combinations of maintenance can be ranked as follows (indicative costs only):
Incidental + No extra
4: measures during 0 0 15% € 100 000 000,- € 116 462 999,-
construction
* this is a rough guestimate for a Class V canal lock with 2 chambers, one for each direction of travel.
It also includes landscaping of the surroundings and other related infrastructural works
** assume a lifetime of 50 year; irregular maintenance in the 10th, 20th, 30th and 40th year
*** the selection of the discount rate is important; the higher the rate, the more attractive it is to reduce
the initial investment as much as possible and move costs as much as possible into the future
Table 2-3 NPV’s of maintenance strategies
For the above example cost figures have used partially from the writers own experience and partially to
arrive at a plausible answer and conclusion. In any way it is left to the reader to dig up appropriate (cost)
figures in real life and ‘nowadays’ design situations.
The above is a mere illustration of the fact that the operational aspect 'maintenance' will require
considerable attention during design, most appropriate in the more detailed design stages. In the
preliminary design stages the designer has to use engineering judgement.
Hydraulic Engineering
Faculty of Civil Engineering 20 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
in detail in the PIANC Report of MarCom WG42, Life Cycle Management of Port Structures:
Recommended Practice for Implementation.
During the last 20 years Life Cycle Management has become of increasing importance. Increased costs of
labour and mechanical parts lead waterway authorities to design more efficient locks (i.e. with a higher
quality/cost ratio). The priorities of different owners of locks varies, with some requiring minimisation of
maintenance effort and cost even if this leads to higher initial construction costs, while others require
minimum construction cost even if this leads to higher maintenance costs. A third category aim to assess
and minimise Whole Life Cost (including operational and maintenance costs) as their main criterion, and
in the absence of other investment or maintenance constraints this should be considered to be the
preferred approach.
For locks, a reduced WLC should imply optimum levels of reliability (which must be determined
specifically for each project), and more efficient maintenance. This does not mean less inspection and
survey or less maintenance. Locks normally have to be designed to allow efficient inspection and
daily/weekly maintenance without stopping traffic. Other means can also be adopted to assist in achieving
the objective of minimum WLC, including quantitative assessment of the costs of closures for inspection
or maintenance, and use of standardization of components as a means of reducing construction and
maintenance costs. Operating costs should also be considered as part of the optimisation process. These
can be reduced by adopting automation or remote control. This subject has been covered by PIANC
InCom-WG18 (1992) and PIANC WG96 (2008)
This figure shows clearly that more time is required than just the time to navigate through the lock. What
the figure does not consider is the waiting time induced by a queue. Especially when lock capacity is lower
than the average traffic intensity, queuing time will be a substantial part of the delay faced by the vessel,
which is generally unacceptable. Before getting into the laborious work of optimizing the lock cycle and
reducing its duration, it is absolutely necessary to check, whether or not, the overall capacity of the lock is
sufficient regarding the vessel traffic to be handled.
The duration of lock passage has to be considered in terms of the vessel's journey, which includes looking
at the whole river or canal system, probably including more than one lock or even including series of locks.
Maritime navigation
1. Vessel reports in
2. Vessel decelerates 7. Sailing out & reporting out
3. Pilot boarding 8. Tugs loose
4. Tugs tying up Lock operation 9. Pilot disembarking
5. Vessel standby /not 10. Acceleration at ‘safe’
6. Entering lock chamber distance
Figure 2-4 Vessel passage through the sea lock (with assistance of a pilot)
Hydraulic Engineering
Faculty of Civil Engineering 21 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The reduction of the lock cycle of few minutes does not really seem significant with regard to vessel
journeys in the order of days. However, for container lines in ports behind a lock, fast locking and transit is
required. These container lines consider a lock as a general risk regarding the timetable to be respected.
The lock may even be considered as an unacceptable risk with regards of possible strikes or blockades,
or the occurrence of operational breakdowns.
Table 2-4 gives some information on the time required for some typical lock operations. The activities
required for locking have a duration in the order of ten's of minutes, except gate operation.
List of Events Average time % of the Average time % of the Possibilities for
Inland Navig. total Sea lock total optimisation to reduce
time time the total time
TOTAL LOCKING 28 min 100% 45 min (*) 100%
(1/2 cycle) (20 – 40 min) (40 – 90 min)
Entrance / Exit 5 min 18% 15 min (*) 33% Medium
(3 to 10 min) (10 to 20 min)
Mooring 5 min 18% 7 min (*) 15.5% High
(3 – 10 min) (3 – 10 min)
Gate manoeuvring 3 min 11% 3 min (*) 7% Low
(2-4 min) (2-5 min )
Filling / Emptying 15 min 53% 20 min (*) 44.5% High
(8 – 20 min) (10 – 25 min)
(*) For Panama the figures are: 45-60 mins for the existing Panamax locks and 80 minutes for the third
locks (in project)
• Entrance/exit: Existing locks 15 mins. Third locks 20 mins.
• Mooring: Existing locks 2 – 3 mins Third locks 5 mins.
• Gate maneuvering: Existing locks 2 mins. Third locks 5 mins.
• Filling/emptying: Existing 8-13 mins. Third locks 10-17 mins.
Table 2-4 Duration of navigation through a lock (1/2 lock cycle)
Figure 2-5 shows the lock cycle, distinguishing vessel and lock operations, for single and dual direction
use of an inland navigation lock. Looking for possibilities to optimize, read reduce the lock cycle in the
following circumstances and possible (counter) measures will be discussed influencing the duration. In
general, for single lock, dual direction use of a lock chamber is preferred because it maximizes the lock
capacity (compared to a single direction use). For a fleet of locks, as in Panama, single direction is
suitable.
In the absence of vessels in the lock chamber the emptying or filling operation can be executed much
faster because limiting the water movement and resulting mooring forces in the lock chamber is not
necessary.
Some ideas, which are not intended to limit, restrict or even prevent new innovative ideas, to reduce the
duration of the navigation cycle are:
- Pre-positioning of ships in the lock chamber to avoid waiting time – use of radio/radar/VTS : Use of
radio, radar or VTS to make sure the ship is being locked at the earliest possible lock cycle reduces
the waiting time.
Either the vessel may have to increase its speed or the lock operation is delayed until the vessel
arrives. The latter may be more feasible for a single direction lock chamber than for a dual direction
lock chamber.
- Faster movement of gates: It is imaginable that selection of a more innovative type of gates, other
than the traditional mitre, lift and rolling gate, reduces the time needed to open or close the gate.
- New concepts for the filling and emptying system to reduce the filling and emptying time: for instance
a non linear opening of the valves.
Equipment: self releasing mooring hooks, magnetic or vacuum based mooring devices, may be used to
reduce the time needed for mooring line handling and/or tending.
Hydraulic Engineering
Faculty of Civil Engineering 22 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Hydraulic Engineering
Faculty of Civil Engineering 23 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Traffic intensity expressed in e.g. numbers per hour could be combined with data on the dimensions or
deadweight tonnage of the vessels. Subsequently the traffic intensity in numbers per hour can be worked
3
into deadweight/hour (DWT/hour) or m /hour. Especially expression in tonnage per time unit would be
useful for economic evaluation of a lock project. For technical design of the lock a requirement for the lock
3 3
capacity expressed in time, m and combined m /time unit is needed. Given the required lock capacity the
lock cycle of an existing lock can be evaluated and, for a new lock, the lock cycle requirements can be
determined. In case of an existing lock, comparison of what is required and what is available, results
either in the positive answer that the capacity is and will remain sufficient in the future or not. In the latter
situation lock cycle requirements have to be determined as for the case of a new lock project.
The factors influencing the lock cycle and their effect on the lock capacity of an existing lock are the
following:
Hydraulic Engineering
Faculty of Civil Engineering 24 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
• Water management:
Water Management requirements may concern:
• Saving the upstream water,
• Prevention of upstream or downstream pollution,
• Separation of salt and fresh water.
Saving the upstream water: Due to the water management requirements, water from the lock
chamber may have to be stored in saving basins, instead of being discharged directly in the
downstream reach. Depending on the systems used, this may take less or more time. Regarding the
lock capacity similar comments can be made as under “Water level difference”.
Prevention of upstream or downstream pollution: Pollution may be caused e.g. due to a ship-collision
or accidental industrial spillages, resulting in the loss of dangerous cargo, such as oil, gasoline,
chemical fluids. Depending on the kind of pollution the lock can be closed while the pollution in the
upstream or downstream river reach is being removed. This will result in congestion for navigation. It
is also possible to increase the discharge to the sea or downstream reach, in order to speed up the
dissolving or dispersion process of the polluting material and get to an acceptable concentration level
in the water.
Separation of salt and fresh water: Some technical solutions to reduce the salt water intrusion on fresh
water storage basins increase the lock cycle time. In case the entire lock chamber content has to be
Hydraulic Engineering
Faculty of Civil Engineering 25 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
replaced, providing fresh water instead of salt water or vice versa, the lock cycle time increases very
much.
2.3 Manoeuvrability while navigating through the lock and approach areas
The operational analysis of a ship approaching the lock, being lifted up or down, and continuing it's
journey, reveals that manoeuvrability of vessels is a key issue. Other reasons making it necessary to look
into manoeuvrability are safety and the duration of the lock cycle. Manoeuvrability is influenced by:
• Visibility
• Available water depth
• Cross currents and/or cross wind
• Available water area
• Approach structures
• Tug boats or other means for manoeuvring the vessel
• Twin propellers or bow thrusters
• Visibility:
For safe and expeditious navigation a clear and unobstructed view is important. This results e.g. in
requirements for the alignment of lock approaches and for positions of waiting or overnight berths at
sufficient distance to the track to be navigated by ships sailing in or out of the lock. For night navigation
and bad weather situations (fog and/or heavy rain) sufficient navigation aids and lighting have to be
provided.
• Approach structures:
Besides protecting the main lock structure for ship collisions, approach walls provide physical and visual
guidance to the ship respectively Master of the ship, hence; have a positive effect on the manoeuvres.
Opposed to jetty type structures, which are structurally light and open, guard walls are generally closed to
prevent cross currents and, to a lesser extent, also reduce the effect of cross winds.
Hydraulic Engineering
Faculty of Civil Engineering 26 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
A reason not to construct a approach wall at a lock would be the availability of tug boat assistance. This
generally applies to locks in coastal areas and for locking maritime vessels. The extra space required for
the tug manoeuvres pushes the approach wall into an ineffective position for situations where tug boat
assistance is not required.
Poor visibility, small water depths and cross winds and currents negatively influence manoeuvrability,
therefore increase the size of the required water area. Approach walls, tug boats and extra propulsion of
the ship positively influence manoeuvrability. However, compared to a ship navigating through the lock
only using the main propeller, the use of these means does result in a slower process of ship passage,
thus a reduced capacity of the lock.
Other requirements, primarily the result of the ship passage function and important for the lock layout,
might be:
• Lightering area:
A zone or area where ships with too high a draught to pass the lock can be lightered. The lightering zone
includes manoeuvring areas around it and shall be at a safe distance from the sailing route in or out of the
lock.
A quick look at the functions of a lock, other than ship passage, might result in requirements, subsequent
facilities and space requirements regarding the following:
• Removal of floating objects and ice floes. (See InCom WG23, PIANC 2004 )
• Prevention of sediment settlement or enabling sediment transport through the lock
• Dewatering or discharge flows due to the water management function
• Basins for salt-fresh water separation
From a Life Cycle Management point of view the following should be duly considered regarding the
location of the lock and/or the layout:
• Master plan of the waterway under consideration. What is the traffic forecast, what will be the number
of locks (a few high lift locks or many small lift locks), etc.?
Hydraulic Engineering
Faculty of Civil Engineering 27 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The examples in the above are not intended to be exhaustive, but they are issues likely to be
encountered. Other items or subjects can and should be added, if appropriate for the design under
consideration. Requirements for the dimensions of the lock chamber can be found in Chapter 3. For outer
ports and connected approaches, guidelines to establish layouts, more specific dimensions and
alignments, are included there as well.
Provided there is sufficient water depth available for navigation, the lesser locks that have to be passed
the better. However, construction of a lock with a large head (large water level difference), where the
vessels have to be lifted or lowered over the full distance, may be more expensive than construction of a
couple of smaller locks. Considering e.g. the costs of dikes upstream of the lock may or may not swing the
balance. Those costs depend on the height and length of the dike. If h is the head, the height of the dike
2
varies linearly with h, but the costs vary with h ; because the area of the cross section has to be
considered. The length of the dike to be taking into account is related to h (again) and to the slope of the
river or waterway. Of canals without slope the length of the dikes is known (equal to the canal ‘s length).
Often the lock or lock complex is adjacent to weirs or barriers. In that case reasons to select the number
of weirs or the location of the barrier are of importance for lock design.
Hydraulic Engineering
Faculty of Civil Engineering 28 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Intermingled as it may be, the optimum number of weirs and/or locks is determined by a number of
economic factors, such as:
• The construction costs of the weirs, locks and the embankment or dikes etc.
• The ship navigation costs for the time delay having to pass the weirs or locks besides it
• The damage to the surroundings, the environment in general and the (increased) risk of flooding
• The maintenance and operation costs
• The revenue generated by lock operations (toll on ship passage)
• The revenue generated by hydroelectric power
• etcetera
In the following paragraphs we will take a closer look at some of these cost or economic factors in relation
to ‘a number’ of locks to be designed and constructed.
Nowadays Life Cycle Management is being introduced into all sorts of civil engineering projects and into
the design of the project, see section 2.1.3. In agreement with the life cycle stages the following costs
would have to considered:
• Design costs
• Construction costs
• Operational costs
• Reuse and/or Removal costs
Design costs
A rough, over the thumb figure for design costs would be between 5 and 10% of the overall project costs.
This indication is based on experience in the past decades, where design spanned from the idea or
initiative stage to the construction stage, hence, excluding design in or for operation, maintenance and
removal. Obviously within a Life Cycle Management approach of projects these stages have to be
included, increasing the mentioned percentages.
For larger civil infrastructure projects it is advised to take into account the upper boundary, 10%, because
the societal and/or governmental decision making process generally is very complicated, hence takes a
long time and continuously invokes extra design activities. Generally lock and/or weir or barrier projects
fall into this category.
Construction costs
The following costs will be included and described as construction costs:
• Construction costs per weir depending on water head
• Costs of mitigating measures
Obviously construction costs are not limited to the items mentioned.
The total horizontal force acting on a weir is a function of the water level difference over the weir. The
following force function can be written down:
1 1
F = b ρ g ( H + d ) 2 − ρ gd 2
2 2
Hydraulic Engineering
Faculty of Civil Engineering 29 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The weir structure may be a bit smaller or larger but there will be a base sum of money that has to be paid
anyway (Mobilisation of equipment, labour, temporary works). Besides the more or less fixed cost part
there will be a variable part of the costs that will vary with the water head (time variation) over a weir see
formula above. Thus, from a certain base sum the construction costs of the weir are proportional to the
load on the structure. Written down as:
Where:
1 3 c3 = costs per unit of load on structure
cweir = C1 + C2 ( H d + H + Hd )
2 2
3 C1 = fixed costs
C2, = constant
The construction costs of n weirs Cconstr,n for the full length of the river amounts to:
1
Cconstr ,n = ncweir = nC1 + nC2 ( H 2 d + H 3 + Hd 2 )
3
2 3
H tot 1 H tot H
Say that nH is roughly constant, then: Cconstr ,n = nC1 + nC2 ( 2 d + 3
+ tot d 2 )
n 3 n n
In the graph on the right there are
250 000 000
two examples of a function
representing total construction €
200 000 000
graph costs. Observe that the
construction costs in the first
150 000 000
example are minimal with the
construction of 3 weirs and in the
second example with the 100 000 000
fixed costs are relatively high and C1 = 10 000 000 €; C2 = 700 €/m2
C1 = 20 000 000 €; C2 = 560 €/m2 number of weirs ==>
the water depth is large compared
to the total water level difference,
Figure 2-7 Influence of C1 and C2 on construction costs
then the costs function behaves
350 000 000
itself as a linear function. This is
demonstrated in Figure 2-7. € 300 000 000
The graph shows that the least
possible number of weirs always 250 000 000
results in the lowest construction
200 000 000
costs, which is not a very
surprising conclusion, however the 150 000 000
choice for the number of weirs is
usually not based on minimum 100 000 000
costs alone; the benefits or
50 000 000
completely different criteria have
to be considered.
1 2 3 4 5 6 7 8 9 10
C1 = 10 000 000 €; C2 = 700 €/m2 number of weirs ==>
C1 = 30 000 000 €; C2 = 300 €/m2
Hydraulic Engineering
Faculty of Civil Engineering 30 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Side effects upstream from the weirs include a higher level of the ground water table, discharge problems
of local tributaries or discharge canals as a result of the higher water and groundwater levels, and of
course local levee (dike) enforcement. In case of a fixed weir, levee enforcement is necessary after
construction of the weir due to the achieved higher water levels in general and particularly during a high
runoff period. A movable variable weir allows for a temporary lapse in the weir-effect during this high
runoff period. However even for a movable weir, locally the water levels will be higher due to the smaller
cross section at the weir. Hence for both types of weir an enforcement of the levees is needed. For the
cross section of a river with forelands and summer levees, it is usually undesirable to have submerged
forelands during low runoff periods. In case of more permanent submerged forelands the summer levees
would have to be enforced.
Costs of mitigating measures can be approximated by a second order polynomial equation. The
2
construction costs of the levees and the costs of the draining are directly proportional to H . The costs for
the levee enforcement, more specific for bed or bank protection, are usually proportional to H.
H tot 2
Cmiti = nC3 +
l 1
n6
( C 4 H 2
+ C5 H ) = C 4
n 2
H
+ C5 tot
n
Besides the costs of additional civil engineering works, one must also take into consideration the full costs
of changes or damage to the ecologic system. By constructing the weir, the existing food cycle of the
surrounding waterway will be disturbed. Small animal species that can be counted as prey for larger fish
will be hampered in their descent of the river. This would lead to a disaster for the local fishing industry,
which can be translated fairly direct into financial costs. Alternatively the extra costs for provision and
maintaining fish migration facilities have to be taken into account.
The graph in Figure 2-9 illustrates the development of mitigation costs in time.
€
250 000 000
50 000 000
1 2 3 4 5 6 7 8 9 10
Hydraulic Engineering
Faculty of Civil Engineering 31 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The following costs will be included and described as operational costs, which is not completely correct; it
would be better to consider them as costs related to the operational stage of the project:
• Operational costs for every lock and weir complex
• Maintenance costs
• Delay costs ship navigation
Obviously the operational costs are not limited to the items previously mentioned.
Operational costs
The operational costs can be assumed to be proportional to the number of weirs. One should think about
the cost of operating of the weir and the locks (if required), electricity and other utilities for lighting, daily
maintenance etc.. In general manpower or labour costs are the major to be considered.
Maintenance costs
The maintenance costs per annum of a hydraulic structure are dependent on the nature of the structure
and the used materials. Usually the maintenance costs are a percentage of the construction costs, on
average 1% per year. For a first estimate of the number of weirs to be built, this percentage can be used
for the determination of the costs.
The nearly linear cost function for operation and maintenance is demonstrated by means of a graph in the
figure below.
160 000 000
€ 140 000 000
80 000 000
60 000 000
40 000 000
20 000 000
1 2 3 4 5 6 7 8 9 10
Hydraulic Engineering
Faculty of Civil Engineering 32 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The cost of shipping delay is caused by the time it takes to pass the weirs or adjacent locks. Depending
on the intensity of ship traffic and the capacity of the weir or lock a queue may develop, resulting in ship
waiting time. Obviously, time is also consumed by the lock process; which includes the time needed to
open and shut the gates of the lock, the time required for adjusting the water level in the lock chamber, the
time needed for the ships to sail in and out of the lock and last not but not least, the number and size of
the ships per lock cycle. Simulation techniques are used to estimate the delay time for the (overall)
shipping process and in particular for the lock navigation process. Using the delay costs per unit of time,
the number of ships etc. one arrives at the (total) delay costs. A considerable number of simulations will
be made to vary the number of weirs with varying water level differences to estimate the delay the ships
will endure. Meaningful use of the simulation is a job on itself and, unfortunately, often simulation is not
possible in the early stages of a project because the necessary data is not available, or there may not be
enough budget.
For the purpose of rough cost calculation, needed to decide on the number of required weirs, a simple
method of approximation can be used. It is assumed that the delay time to for ships is divided in a waiting
period tw (the ship in the queue), and a lock period ts (the time to pass the lock).
t0 = t w + t s
If there is a stretch of river in which there is more than one sluice, then the ideal situation would be that;
for the first sluice there is a queue and lock cycle time and that for each sluice after that only lock cycle
time. In this scenario the shipping traffic is running optimally and the shipping speed is equal for all ships.
At the entrance of the first sluice the shipping traffic is optimised.
ts = α + β H
Where:
α = the time for opening and closing of the lock gates and the time required
(by ships) for entering and leaving the lock chamber
β = coefficient, dependent on the dimensions of the lock chamber and the
capacity of the (water) filling and emptying system
If per year there are N ships that pass through the weirs and the costs for the delay per ship on average is
equal to P Euros per hour, see Table 2-5 below for information on inland navigation costs, then the total
costs per annum:
C j = PN (t w + nα + β ( n H tot )
If a comparison is to be made between the construction costs and the total ship delay costs Ctot,o, the net
present value of both costs should be used and the lifetime of the weir has to be known. Usually weirs are
designed for a lifespan of 50 years.
Hydraulic Engineering
Faculty of Civil Engineering 33 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The costs over the full lifespan n years can be transferred to their net present with the formula below,
which takes inflation and interest rates into account:
T 100* C j
Ctot ,o = ∑
j =1 (100 + r ) j
In the previous formula the costs of ship delay (may) vary from year to year. If the costs per annum remain
constant then the net present value of the costs is:
T 100 * C j T
100
Ctot ,o = ∑ = Cj ∑ = C j cwf
j =1 (100 + r ) j
j =1 (100 + r )
j
With a lifespan of 50 years, 50 discount factors and their sum have to be computed, e.g. by means of a
spreadsheet. To avoid this cwf can be approximated by:
T
100 100 100
cwf = ∑ = 1 − for r < 8 this approximation is very inaccurate
j =1 (100 + r ) r (100 + r )T
j
The total costs for the delay can now be defined as:
(
Cdelay = cwf * P * N tw + nα + β nH tot )
The delay costs function increases monotonously with n. An example of this can be found in Figure 2-11.
1 000 000 000
€ 900 000 000
800 000 000
700 000 000
600 000 000
500 000 000
400 000 000
300 000 000
200 000 000
100 000 000
1 2 3 4 5 6 7 8 9 10
N = 21000 -; tw = 1 hour number of weirs ==>
N = 21000 -; tw = 2 hour
Stating the obvious: a minimum number of weirs results in minimum ship delay costs.
In Table 2-5 the cost and relative cost of inland waterway vessels can be found. Actually this information is
very hard to find if at all; so it should be used wisely.
Hydraulic Engineering
Faculty of Civil Engineering 34 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Reuse and/or removal costs are by nature hard to predict when considering a lifespan of the structure in
the order of 50 to 100 years, which is not uncommon at all for lock and weir projects. The lifespan that
complicates the actual estimate, at the same time makes the cost estimating work easier because the
number of years inevitably results in a low discount factor cwf.
Reuse costs will be similar to costs that have to be made for any Greenfield or new built project, except for
having to consider costs for removal of parts of the existing structure; those costs come on top of the
required budget. Off course only the relevant ‘to be reused’ parts of the structure will be taken into
account.
Removal costs can be split in costs for demolishing the structure, or parts of the structure, and costs for
disposal of the construction and demolition waste or rubble. It is not uncommon to find there is a supply
and demand market for demolition material, especially (crushed) concrete and steel, resulting in negligible
disposal costs. On the other hand, take good notice of the fact that the costs for disposal of polluted
materials, e.g. polluted sediments or soil, can be considerable.
Hydraulic Engineering
Faculty of Civil Engineering 35 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The total costs to be considered when one or more weirs have to be constructed and operated can be
estimated by taking the sum of all the above mentioned costs. The total costs Ctot are:
In the following figures first a graph showing all the contributing cost items for one set of C-coefficients,
see Figure 2-12. Then 4 sets of C-coefficients have been used to produce the graph in Figure 2-13; for all
variations of C-coefficients an optimum can be seen for 2 weirs.
1 2 3 4 5 6 7 8 9 10
number of weirs ==>
1 2 3 4 5 6 7 8 9 10
number of weirs ==>
Figure 2-13 Total costs for different sets of C-coefficients
Hydraulic Engineering
Faculty of Civil Engineering 36 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Hydraulic Engineering
Faculty of Civil Engineering 37 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
In general the lock process can be described as follows: The lock chamber is closed off from the outside
water by closing the gates [3]. Subsequently the water level inside the chamber must be adjusted to the
desired level; assuming the ship sails from left to right in the above figure, the water level must be raised.
When locking in the opposite direction the water level in the lock chamber will be lowered. In order to
achieve this, a filling and emptying system [6] is required, e.g. ducts in the lock heads [4]. After adjusting
the water level to the outside level the gates are opened, the ship sails out and continues its journey.
Usually the lock chamber is provided with berthing and mooring furniture, such as fenders, bollards,
mooring rings and ladders in recesses (inkassingen). All furniture has to be able to resist (predominantly)
horizontal forces due to berthing, mooring and deberthing.
Filling and emptying the lock chamber will cause local currents. These currents, as well as the propeller
wash caused by the navigating ships, may result in scour in front of the lock heads (on either side), which
in time may compromise the stability of the lock structure. To prevent this bottom protection [8] can be
provided.
Typically, water levels will be different at both ends of a lock. This will result in a ground water flow
underneath and on both sides of the lock structure. This seepage may lead to movement of soil particles
leading to cavities under and alongside the lock. To prevent this, locks must be provided with seepage or
cut-off walls and/or cut-off screens (kwelschermen), usually made of sheetpiles [7], acting as an
impermeable curtain perpendicular to the axis of the lock chamber.
Together with dikes (US: levees) and other structures the lock may be part of a water defense system.
The upper lock head (at the side of the highest water level) [4a], the upper head, must be able to retain
the highest water level. The lock head at the side with the lowest water level, the lower head [4], retains
the highest water level in the lock chamber, which is selected by the designer and not necessarily the
highest outer water level. In tidal areas lock heads are referred to as outer head (on the sea side) and
respectively inner head (on the land side).
As part of the water defense structure the navigation lock must be able to retain water under all
circumstances. If for any reason (e.g. a ship runs into a gate) the lock is damaged other measures must
allowed for. E.g. locks are often equipped with spare gates, bulkheads or stop logs (schotbalken) are
available to replace damaged gates and maintain the water retention function.
In modern times the ships must enter and leave the lock as soon as possible, time seems to be money,
and this has resulted in a more rational layout of the lock. The chamber width is the same as the entrance
width in the lock head. A cross section of the lock often has an U-shape, vertical retaining walls and of
course the horizontal floor. Together with well positioned guard walls this facilitates navigation because
the situation is easily observed and assessed by the master of the ship; a clear situation enables efficient
Hydraulic Engineering
Faculty of Civil Engineering 38 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
navigation. A big help is to avoid assembling all sorts of furniture to the lock walls. If bollards, fendering
and ladders protrude from the wall they are observed as bigger obstacles than they are because of their
actual size; they cloud observation by the master of the ship who reduces speed accordingly. The furniture
should be assembled in recesses (uitsparingen) in the wall, maintaining a flat face, see Figure 3-3
Depending on the capacity and intensity of a waterway one could consider constructing an extra set of
gates to subdivide the lock chamber in segments. In this way the lock cycle can be managed more
efficiently. The extra gates are often positioned at 1/3rd of the lock length, see Figure 3-4 (not to scale).
Advantages of such lock chamber partitions are:
• Time needed for filling and emptying the lock chamber is being reduced;
• In coastal areas the intrusion of salt water is being reduced;
• In case of damage due to collision the navigation lock is still partially operational.
Hydraulic Engineering
Faculty of Civil Engineering 39 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
General reference is made to the RVW (2005). The Figures below show the approach area or outer of a
lock. Often the adjectives upstream or downstream are added. Some times upper or lower pond is also
used as a name or description. Shown in the Figures are the length and widths, if applicable, and their
definitions. Subsequently Table 3-1 shows the dimensions of these lengths and widths depending on the
inland navigation vessel type (according to the CEMT class).
Hydraulic Engineering
Faculty of Civil Engineering 40 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Figure 3-7 Outer port for twin lock and berths on both sides
Hydraulic Engineering
Faculty of Civil Engineering 41 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
When the waterway is a river where the discharge is controlled by a weir, often the lock and weir are
positioned adjacent to each other at one location. Multiple functions combined in one complex, resulting in
some extra demands to the layout of the lock outer port, or, vice versa, demands to the inlet and outlet of
the weir, as schematically shown in Figure 3-9. Care has to be taken that eddies or cross currents are
kept away far enough from the areas where manoeuvring is complicated, e.g. close to the lock entrance
areas. Approach walls can be used to mitigate the effects of adverse currents.
3.2.2 Alignment requirements with respect to the inland waterway - inland navigation
General references are available in RVW (2005), PIANC InCom WG16 (1996b), PIANC InCom WG20
(1999), and PIANC Marcom WG49 “Horizontal and vertical dimensions of fairways”.
Numerous locks are or will be constructed in a curve of a waterway. Therefore the alignment of lock and
approaches has to suffice to requirements that apply curves in the waterway. The following applies to a
two lane waterway where the maximum current is 0.5 m/s.
Minimum radius: R ≥ 4L
Preferred radius: R = 6L
Sailing through a curve the ship needs extra space, hence a width allowance ∆B should be added to the
lane width as follows:
2
∆B = 0.75 L /R
o
However, the width allowance can be reduced for β ≤ 30 , where β is the angle between the axes of the
straight stretches adjacent to the curve.
2 o
∆B = 0.75 L /R *β/30 for β ≤ 30
o
For R>10L, in that case β<20 , no width allowance is required, the curve is already sufficiently smooth or
wide enough.
Hydraulic Engineering
Faculty of Civil Engineering 42 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Preferably the extra width in the curve will be provided in the inside curve. If this is not possible the outside
can be used or distribution over the in- and outside is possible.
Taking care of a clear unobstructed view in a curve, air draught of the vessel, prevailing water levels and
level of the bank, including buildings, come into play. Over a length of 5L the view has to be unobstructed,
see Figure 3-11. Visibility requirements for junctions of waterways are shown in Figure 3-12.
Figure 3-11 Required clearance for Figure 3-12 Required clearance for visibility at
visibility in curves junctions
Hydraulic Engineering
Faculty of Civil Engineering 43 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Figure 3-13 Construction of lock-weir complex Hagestein, river Lek the Netherlands
a) Inland navigation
The dimensions of a lock chamber in Europe are shown in Table 3-2 (RVW, 2005). The dimensions are
based on the CEMT table of 1992, for all waterways west of the river Elbe - Germany, and are applicable
for the so called minimum lock, which is a lock operating in a traffic situation where less than 10 000
inland navigation vessels, either in the up- or downstream direction, are locked every year.
Hydraulic Engineering
Faculty of Civil Engineering 44 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
b) Maritime navigation
Generally the variety in ships and ship sizes passing a maritime navigation lock is quite large. This may
explain why a convenient table with lock dimensions related to maritime vessels can not be found. Some
guidance on the dimensions of ships can be found in EAU 2004 (Recommendations on Waterfront
Structures Harbours and Waterways); PIANC MarCom WG48 Guidelines for Berthing Structures;
Thoresen C. (2003); and in ROM3.1-99, 2000 (Recommendations for the design of the maritime
configuration of ports, approach channels and harbour basins).
Usually the nautical conditions in coastal areas are more adverse than in inland regions and the shape of
maritime vessels is prone to a larger impact of those conditions on manoeuvrability. The faster the vessels
are able to manoeuvre in and out of the lock (chamber), the higher the traffic capacity. It all adds to the
recommendation to use simulation to determine the size of the lock chamber for maritime locks.
To start real or fast-time simulations to find the required size of the lock chamber a set of initial values for
the width and length has to be available. It is advised to do the following:
• Define the governing or design ship that should be able to pass the lock
• Assume a minimum lock chamber suffices from a traffic capacity point of view
• The length of the chamber is approximately 1.1 times the length of the design vessel.
• The width is 1.25 times the width of the design vessel.
The simulation work will be continued to check the assumption made. A variety of vessels with different
transit times has to be used to find out whether or not the capacity of the lock is sufficient.
In case the lock chamber is designed to accommodate 2 vessels, either in length or in width direction,
space for manoeuvring will be added only once, since the vessels enter the lock one by one. Hence, the
length is:
Lchamber= L+ (L x 1.1).
and similarly:
Bchamber= B+ (B x 1.25)
An upper boundary for the width of a lock chamber, assuming the ship is navigating on its own propeller
would be:
Bchamber= 2 x Bvessel.
The above initial lock chamber dimensions do not take into account that the governing ship might be
entering the lock chamber with tug assistance.
When tugs or other active means, other than the vessels own rudder and propellers, are used to control
the course of the vessel the required lateral clearance will be smaller than without assistance. The design
vessel for the new Panama lock complexes is a 12,000 TEU containership with a beam of 48.8 m. The
specified width between the lock chamber walls is 55 m, the minimum clearance on each side of the
chamber is 0.3 m. Hence, the usable width is specified at 54.4 m. If the useable width were to be used
completely the lock width over beam ratio would be 1.01. The useable lock width over design vessel’s
beam ratio is 1.15.
Obviously it is not recommended to use the ratio of 1.01 to start simulations for new lock design because
it applies to exceptional events. For the more frequent event of the design vessel navigating the lock, the
ratio of 1.15 can be considered as the minimum to start.
The depth of the sill should be determined using the maximum draught of the design ship with regard to
the selected minimum water level in the lock chamber, and including at least 1 meter nett keel clearance.
Selection of the minimum waterlevel in the lock chamber is governed by operational or availability criteria,
and depends on waterlevel variations, and related frequency of occurrence on both sides of the lock. Note
Hydraulic Engineering
Faculty of Civil Engineering 45 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
that the stern of the vessels sinks deeper into the water when the engine is put to work again. Sometimes
it may be necessary to construct the sill at a lower level considering the volume of water that has to be
discharged and the ratio between the cross sectional area of the ship and the water area in the locks
cross section, when the ship enters the lock chamber. Fresh versus salt water phenomena may add to
this requirement.
c) Recreational navigation:
Depending on the traffic intensity recreational craft will have its own dedicated lock chamber or has to
make use of the spare capacity of the lock chamber dedicated to commercial navigation.
Considering the construction costs of a lock, a dedicated lock for recreational craft will not be a minimum
lock chamber, i.e. for use of one yacht only. To determine the size of the chamber it is advised to simulate
the traffic and lock situation.
Figure 3-14 shows some configurations for locking both commercial and recreational craft in one lock
chamber at the same time. Commercial vessels should get the highest priority, allowing these ships to sail
into and sail out of the lock before recreational craft. A complicating factor might be the difference in
allowable mooring forces on the different types of vessel due to emptying or filling the lock.
When two different types of traffic have to be locked in the same chamber it is advised to determine the
size of the chamber by means of simulation.
Hydraulic Engineering
Faculty of Civil Engineering 46 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Since the lock often is a part of a flood defense system, but always part of a water retaining system, one
of the components along with dikes or levees and other ‘hard’ structures, Top of Structure (ToS) is an
important issue to be considered. Figure 3-15 shows contributors, definitions and some comments, to the
construction height of structures like dikes and breakwaters. Note this figure is the same as in the ‘Dutch’
CT2320 lecture notes, however, translated for convenience sake. For earth structures generally there will
be a significant difference between the construction height and Top of Structure level because the latter
has to be maintained throughout the years in spite of e.g. settlement.
For structures like locks and quays etc., apart from agreed and accepted construction tolerances,
generally construction height is equal to ToS, see Figure 3-16 below. Indeed, contrary to earth structures,
for this type of structures ‘surplus height’ as a contributor to ToS generally could be neglected, although it
could be considered to take into account construction tolerances here.
Hydraulic Engineering
Faculty of Civil Engineering 47 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The gates of the lock are moveable, contrary to e.g. other concrete lock structures or dikes. In closed
position the same ToS requirements apply to top of gate. Generally bottom of gate will be the same level
as top of the sill or top of the lock head floor, when closed; detailing issues related to seals taking care of
water tightness may result in some deviation to the previous. For some gate types, e.g. a lift gate or radial
gate, bottom of gate will have to be determined for the gate in opened position, considering the required
air draught and the design (high) water levels. Obviously, in opened position, top of gate and top of the
gate support structure are ‘practically’ related to bottom of gate in the opened position, not to flood
defense requirements.
Gates being frequently moved, and ships frequently manoeuvring in their vicinity, introduces the risk of
gate failure resulting in failure of the flood defense or water retaining system. Too increase safety of the
whole system, often a double gate will be provided, or at least provisions will be made for stop logs. The
double gate could be positioned in the same (outer) lock head, or the gate in the other (inner) lock head
could be considered as the back-up gate. In the latter situation the whole structure between inner and
outer gate has to at the same required ToS level.
There are other reasons to provide the lock with more than one gate in the lock heads, or to provide
intermediate gates, because a good intermediate gate arrangement has the following advantages:
• It takes less time to handle a small vessel
• Water will be saved in periods of draught
• The amount of salt water penetrating into fresh water channels is reduced
• It permits gates to be repaired or removed without shutting the lock down for traffic
See following Chapters and the Appendix for further elaboration.
In case the head difference between the upper head and the lower head exceeds 2 meters (A>2), see
Figure 3-17, it is usually considered better, from a construction costs point of view, to design the upper
lock head higher than the lock chamber and the lower lock head. In case the difference water between the
lower canal level (LCL) and the lower lock chamber level is larger than 2 meters (A>2) it is usually better
Hydraulic Engineering
Faculty of Civil Engineering 48 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
to design a sill (drempel) at the lower lock head. In case the level difference is smaller than 2 meters
(A<meters) usually the most economic way is to construct the lock in the same plane by constructing the
lower lock head higher or by removing the sill.
For navigation lock in a conventional waterway the height of the chamber wall and the gate (4) is 1 meter
above the highest water level (HLL) in the chamber. The gates positioned at (3) and (5), see Figure 3-17,
have the top of the gate between 0.5 to 1 meter above Highest Canal Level (HCL), pending on the waves
to be expected. For reasons of practicality these doors (3&5) are at times designed and constructed to
match the height of doors at position (2) and (4). In this way only 2 different sizes of spare gates are
needed.
Figure 3-17 Characteristic water levels combined with direction mitre gates;
Construction level differences
Bottom of Structure:
In the above it was described how to determine ToS and it was mentioned that bottom of gate is generally
at the same level as top of sill or top of lock head floor. To determine top of sill or top of floor, the ship’s
draught, the keel clearance and water levels have to be taken into consideration, see section 3.4.2. Only
after knowing top of floor a start can be made to derive Bottom of Structure (BoS). If strength and stiffness
is the only requirement to the sill or floor structural calculations will result in the required floor thickness
and finally simply subtracting this thickness from top of floor will lead to BoS. Other functional
requirements, e.g. an emptying and filling system using culverts in the floor of the lock, may increase the
thickness of the floor, see Chapter 5.
Be aware that the deeper the level of BoS, generally, the higher the cost of lock construction.
Hydraulic Engineering
Faculty of Civil Engineering 49 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
When designing for recreational (sailing) craft the above formula reduces to: Dwater = D + 0.5 m.
This because the shape of the keel of recreational craft, in cross section and longitudinal section is much
more curved than inland or maritime vessels, therefore, leaves more water area available for return lows
that would result in sinkage of the ship.
The rule of thumb for the water depth is quite an approximation; often it will be necessary to produce a
better estimate for the required water depth. The minimum depth in a lock chamber is determined by the
following components, see Figure 3-18 as well:
1. Margin for transitional waves, seiches, etcetera (wave phenomena which can cause fluctuations)
2. Vessel draught
3. Squat (inzinken), which includes sinkage and trim of the vessel. A moving vessel increases its draught
due to return flow phenomena.
4. Hydraulic margin (influenced by the relation between the cross sectional area of the vessel versus the
lock chamber)
5. Safety margin (to compensate for margins in the previous components)
Please refer to e.g. the CT4330 lecture notes for further elaboration of these minimum water depth
components.
In Figure 3-19 typical water levels situation for a lock in coastal area are shown; it is left to the reader to
make a similar schematisation for a lock in an inland waterway.
Hydraulic Engineering
Faculty of Civil Engineering 50 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Looking at a lock in coastal area, attention will be focused on sea levels first because (in general) the
variation in water levels is larger than those of the inland waterway, secondly there is an obvious water
retention aspect, the lock is part of the flood defense system.
Flood defense will require that the lock retains water up to a defined extreme high water level, here
referred to as the Storm Surge Level (SSL) but it could also be described as ‘Design Water Level’ (DWL).
Although it could be allowed that waves, generated by a storm surge, overtop the structure, obviously, the
structural integrity shall and will not be threatened. Often extra height of the structure will be added to
prevent wave overtopping. This will depend on the requirements for the amount of water allowed to
overtop the structure in relation to the quality of the water (salt or fresh water). Both the SSL and the wave
should be related to a probability of exceedance (for instance 1:10.000 for a storm surge).
Generally High High Water Spring (HHWS) and Low Low Water Spring (LLWS) are known all over the
world; often the values can be derived from tide tables for a given location. Using wind speed and fetch
(strijklengte), both wind set-up and wave height could be calculated to determine SSL or DWL, or at least
a fair approximation, and similarly the extreme lower water levels are estimated. Both the wind speed and
fetch depend on the wind direction and could be related to a probability of exceedance (for instance
1:10.000 for a storm surge). For many locations waterlevels and the related probability of exceedance are
known and e.g. presented in a graph, see Figure 3-20.
Hydraulic Engineering
Faculty of Civil Engineering 51 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
When designing the lower lock head the highest and lowest water level in the canal (HCL, LCL) are the
dominating factors.
In the absence of any wave data a minimum wave height of 1 meter should be taken into account for
coastal areas and 0.5 meter for inland navigation areas for the outer lock head. Note that incident waves
may be reflected, which increases the local wave height and the original Still Water Level (SWL), which
was equal to SSL.
Determining the extreme water levels to be maintained in the lock chamber, a balance has to be found,
between construction costs and safety, but it may be more important to consider the effect of water levels
on the emptying and filling time, hence on the capacity, of the lock.
Highest Lock Level (HLL) is chosen somewhere in the middle of the water level in the outer approach area
(SSL or DWL) and the water level in the inner approach area (HCL). The lowest Lock Level (LLL) is in
between the lowest water level in the outer approach area and lowest mean water level of the lower canal.
As a rule of thumb a navigation lock is designed to retain a water level that exceeds once a year the
highest lock level and the lowest lock level. Obviously the mentioned frequency depends on the
importance of the waterway and the traffic on the waterway.
Hydraulic Engineering
Faculty of Civil Engineering 52 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Through the heads Through the heads / longitudinal culverts Through longitudinal culverts
Figure 4-1 Turbulent water, due to a water jet, spreading through lock chamber
Hydraulic Engineering
Faculty of Civil Engineering 53 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Translation waves not only run through the lock chamber during the filling process, but a negative
translation wave runs through the outer port of the lock and upstream reach as well. Vice versa, a
negative wave travels through the lock chamber when it is being emptied and a positive wave moves
through the downstream approach and further. In the lock chamber, generally with vertical concrete walls,
the wave will be reflected (more than once), whilst in the approach area, due to spread and e.g. bottom
friction the wave energy will usually dissipate quickly. Safe mooring of the vessels and safety of lock and
approach structures will be matter of concern. See section 4.1.3 for further discussion.
Head filling
Hydraulic Engineering
Faculty of Civil Engineering 54 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
range the combination of short culvert and stilling chambers has to compete with the longitudinal culvert
system.
Figure 4-4 Head filling: a pipe Figure 4-5 Stilling chamber below the lock gates
culvert around the lock head
If the requirements for F/E time and safe mooring are met, to make a choice between filling through the
gate, or by means of a short culvert system in or around the lock head with or without stilling chamber(s),
it will be best to look at the simplicity or complexity of providing valves in the gate versus culverts, possibly
with stilling chambers, in the lock head and the resulting costs.
Longitudinal culverts:
For lock with lifts larger than 6 meter, going up to 25 meters or even over 25m, longitudinal culvert
systems are used. The principle is to distribute the inflow or discharge of water over (many) more
positions or locations in the lock chamber to avoid water zones too turbulent to moor ships. Many in or
outflow positions along the whole lock chamber length are used, hence the name longitudinal culverts.
Hydraulic Engineering
Faculty of Civil Engineering 55 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The ILCS was developed to reduce the construction costs associated with
large concrete gravity walls. Because the longitudinal culverts are located
within the lock chamber, on top of the bottom floor, the lock walls can be
thinner, which results in a less costly wall design. Assuming the culverts have
to be ‘outside’ the navigable cross section, putting the culvert on top of the
bottom has to result in a lower level of the lock chamber floor. Hence, the cost
savings on the walls are reduced by deeper construction of the lock bottom.
Obviously there is the risk that the exits/inlets of the culverts are damaged,
e.g. by debris in the water or fallen anchors. Presumably it will take some extra
precautions to provide sufficient robustness of these exits/inlets; this will
further reduce the costs savings.
Hydraulic Engineering
Faculty of Civil Engineering 56 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
In literature all sorts of similar or more specific names or descriptions for longitudinal culvert systems can
be found. Look for instance in Table 2-1 for the names and descriptions of simple and complicated
longitudinal culvert systems.
2 More complex longitudinal - Wall culvert bottom lateral system Intermediate lift height:
culvert systems - Wall culvert bottom longitudinal system between 10 and 15 m
- Longitudinal culverts under the lock floor
3 Very complex longitudinal - Dynamically balanced lock filling system High lift height:
culvert systems • Pressure chamber under the floor above 15 m
Table 4-2 Names and/or descriptions for longitudinal culvert systems PIANC (2009)
Obviously longitudinal culvert systems generally will be substantially longer than ‘short’ ones used for head
filling, thus, the literal length of the culvert could be a distinctive criterion. Remember this: rather than
looking at the length of the culverts used, it is better to look at the position and/or concentration of the
inflow and/or outflow ports in the lock chamber to characterize the F/E system.
The water may enter or leave the lock chamber in horizontal direction along or perpendicular to the lock
axis, vertical or in any angle or orientation that is deemed necessary. The culverts can be positioned in or
adjacent to the lock walls, in, below or above the lock chamber floor. For al these situations the culverts
may be separated or integrated into the structure, see Figure 4-9 trough Figure 4-8.
Figure 4-9 F/E system with culverts in the lock chamber wall; culvert
exits near or on the lock chamber bottom
Separate culvert systems have to constructed in any way in case the intake or discharge points of the
water are at some distance from the lock chamber, see for instance the plan view in Figure 4-10.
Positioning the intake or outlet a bit further away could be necessary due to the effects of the negative
(inlet) or positive (outlet) translation waves in the approach areas of the lock.
Separation or integration of the culverts and either the wall or bottom of the lock chamber depends, on
one hand, on the required size of culvert, on the other hand, on the available area or space in the lock wall
or bottom. The structural integrity of these elements should not be compromised. Figure 4-6 and substory,
see previous page, describe a culvert solution for an ‘out of’ the wall and ‘out of’ the bottom culvert
structure.
Hydraulic Engineering
Faculty of Civil Engineering 57 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Longitudinal section
Figure 4-10 F/E system with external culverts and pressure chamber
in the lock chamber floor
rd
A 3 F/E system:
In the above description an underlying assumption was the use of natural water head. In some situations
management of either the quantity, or the quality of water at the upstream side of the lock, results in
alternative F/E systems. Gates and culverts may do part of the work, but basically pumps are used to
overrule the natural water head or water level difference.
Hydraulic Engineering
Faculty of Civil Engineering 58 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
illustration of the water saving basins and their emptying and filling system. Safety of mooring is not an
issue in the basins but it is in the lock chamber. Thus the lock chamber has more and better distributed
inlet/exit ports than the water basins. Look at the size, shape and position of the culverts between basin
and chamber; it all may be described by the phrase large underground tunneling work. It is not hard to
imagine that the water saving basins and underground culverts significantly increase the cost of a lock
complex (in the order of 2-4 times the costs).
Given the importance of the F/E system for the design and construction of the whole lock it is best to
carefully select the system; if need be, use a multi criteria analysis or evaluation. Looking at the
description of the F/E systems in the above the following criteria for emptying and filling a lock can be
defined:
1. time/duration: the time required for emptying or filling the lock linearly adds to the lock cycle, thus
to the capacity of the lock, see Chapter 2. In the next section formulas for computation of the F/E
time will be derived. In general F/E has to take as less time as possible, under the condition of the
next criterion on hawser forces (tros krachten);
2. hawser forces of the vessels moored in the lock chamber have to remain well below preset limits,
depending on the traffic type and/or chosen design vessels. Safety for the ship and the lock
(structure) is the background for this criterion; ships should not break loose from their mooring
lines. See section 4.1.3 for calculation of the forces and limits to hawser forces. Do mind that the
water discharging from the lock chamber should not create mooring problems for vessels laying
by or moored in the approach area of the lock;
3. water management usually requires very specific measures determined by the situation at hand
and it will result in special criteria. It would either be not very meaningful, or simply impossible to
provide ‘general’ criteria in these lecture notes;
4. operation and maintenance robustness;
5. costs
6. etc.
The issues of point 1 and 2 in the above will be dealt with in Sections 4.1.2 and 4.1.3 respectively; they set
forth the basic requirements a filling system has to suffice to in a given situation. If more than one
alternative suffices and if budget permits, the issues under point 3 to 6 come into play and a multi criteria
analysis, to find more selection criteria, followed by the multi criteria evaluation, will result in selection of
the F/E system to be further elaborated.
In PIANC report, Innovations in navigation lock design (2009), the M factor method, from China, for selection
of the type of filling system, is introduced to the greater global public. M is defined as follows:
T
M= where T is the time to fill the chamber in [min] and H is the lift height in [m]
H
The values for M and choices for the F/E For Chinese inland waterways:
system on the right have been defined for a
certain set of maximum hawser forces 3.5<M through heads system
2.5<M<3.5 through heads system or simple
used in China.
longitudinal culvert system
2.4<M simple longitudinal culvert system
(Only for conceptual design it may be 1.8<M<2.4 a more complex longitudinal culvert
assumed, there is not a significant system
difference between the maxima in China or M<1.8 a rather/very complex (advanced)
elsewhere). longitudinal culvert system
Hydraulic Engineering
Faculty of Civil Engineering 59 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Head filling
To analyse the process of filling or emptying the lock chamber and finally determining the total time Ttotal
required for F/E, it is useful to obtain formulas describing, for instance the discharge and the changing
water level. For that purpose several assumptions have to be made:
• Both the upstream and downstream canal are assumed to be infinitely large basins, therefore the
average water level remains the same in both canals
• The lock chamber will be filled or emptied through valves in the gate or using a (short) culvert
system through or around the lock head; see next assumption
• Inertia of the water mass in the lock chamber, in the (short) culvert system or stilling chamber will
be neglected in the following. Friction of the water flow is neglected
• The translation wave resulting from the filling process has a relatively small wave height compared
to the considered water depth
From a fluid mechanics point of view, head filling through valves in the gate could be considered as a
case of ‘submerged’ flow (verdronken uitstroming), see Figure 4-12 and lecture notes ‘Introduction to
Hydraulic Engineering’ CT2320. Formula (1) may be used to determine the discharge Q:
2 3
1
Q = ms ⋅ b ⋅ a ⋅ 2g(h1 − h3 )
2
U 1
2g
where:
ms = discharge coefficient for
2 2
U2 U3 submerged flow (≈0,8)
2g 2g
b = width of the valve(s) [m]
H1 h1
a = height of the valve [m]
H3
(µ = contraction coefficient [-])
h3 In the following:
a 2
µa f = a * b = total valve area [m ]
z = h1 – h3 = water level difference
Q = ms ⋅ f ⋅ 2gz (1)
Figure 4-12 Submerged flow under a gate. Discharge formula
Formula (1) describes a static situation, which disagrees with the ‘dynamic’ reality of a water level
difference z that is changing in time due to filling or emptying the lock chamber. Q and z have to be
considered as time dependent variables. The principle of mass conservation can be used to find a relation
between the discharge Q(t) and the water level change dz. Multiplying the time dependent discharge Q(t)
with sufficiently small time periods dt, mathematically spoken integrating Q(t) over time, has to equal the
volume of water flowing in or out the lock chamber. The same volume is also equal to the horizontal area
A of the lock chamber multiplied with the change in water level dz.
Hydraulic Engineering
Faculty of Civil Engineering 60 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
dz m f ms f
=− s 2 g dt after integration: z(t ) = − 2g * t + Const. (3)
z(t ) A 2A
First the valves in the gate are closed and there is no water flow, then, at t = 0, the valves are opened and
discharge starts due to the initial water level difference z = ∆H. (Suppose, for the time being, opening or
closing of the valves takes no time at all). Hence, the boundary condition z=∆H at t=0 can be defined and
used to solve the constant in Formula (3):
ms f
For t = 0; z = ∆H ⇒ z =− 2 g * t + ∆H ⇒
2A
2
m f mf
z = s 2g * 1 t 2 − s 2g ∆H * t + ∆H (4)
A 4 A
ms 2 f 2 g
Q=− t + ms f 2g ∆H (5)
A
The total filling time is easily determined, by using Formula (5) and the boundary condition t = 0; z = ∆H
and Q = 0:
ms 2 f 2 g 2 A ∆H
Q=− t + ms f 2g ∆H = 0 ⇒ Ttotal = (6)
A ms f 2g
With Formulas (5) & (6), and the data below, the
45.00 5.00
graph(s) on the right, for z(t) and Q(t) respectively, have
4.50
been drawn. 40.00
2
A = 1080 [m ] 35.00
4.00
2 25.00
z [m]
0.00 0.00
0 50 100 150 200 250 300
Observe that the discharge Q decreases linearly in time,
Discharge Q
whilst the water level difference z shows a parabolic ==> t [s]
Water level diff erence z
decrease.
Since the water level difference does not change a lot in Figure 4-13 Graph for the decrease in Q
the later stage of the process, z slowly approaches zero, and z over time
it is more or less common practice to open the whole gate before t = Ttotal. The criterion for z being
acceptably low or not is determined by the sudden water movement in the lock chamber or in the
approach area of the lock, hence, by the order of magnitude of ship displacements and hawser forces.
Hydraulic Engineering
Faculty of Civil Engineering 61 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
In reality gates or valves can not be opened or closed without the passing of some time. The time required
for opening the valves will be denoted by th. In the previous paragraphs the formulas for Q(t) and z(t) have
been derived under the condition of fully opened valves, hence, t ≥ th. Now the development of the
discharge and water level difference for 0 ≤ t ≤ th, will be determined to find an expression for Ttotal again.
Assume a linear lifting process of the valves. Therefore a term t/th will be added to Formula (1) for the
discharge, hence:
t
Q(t ) = ms f 2 gz (7)
th
Equating the Formulas (2) and (7), followed by some rearrangement makes the left and right hand side of
equation (8) ready for integration:
t dz ms f 2g dz
ms f
th
2 g z = −A
dt
⇒ ∫ Ath
t dt = −∫
z
(8)
Use the start or boundary condition t = 0, then the water level difference z = ∆H, and find:
ms f 2g 1 2 ms f 2 g 2
2
t = −2 z + 2 ∆H ⇒ z = ∆H − t ( 9)
Ath 4 Ath
Take the square of z to find z for t ≤ th:
2
m f m f
z = ∆H − s 2 g∆H 1 t 2 + s g 1 t 4 (10)
Ath 2 8
Ath
t m f 2g 2 ms f 2 g∆H m2 f 2 g
Q = ms f 2 g ∆H − s t ⇒ Q= t − s 2 t3 (11)
th 4 Ath th 2 Ath
In case filling or emptying continues after t = th there will be a remaining water level difference ∆Hrest and it
will take some time to complete the process with the valve(s) completely opened. The total time will be
equal to the addition of th to twide open. Formula (6) can be used to compute twide open if the remaining water
level difference ∆Hrest is known. Use Formula (10) for t = th to find the remaining water level difference
∆Hrest.
2
mf m f
Formula (10) for t = th : z(th ) = ∆H rest = ∆H − s 2g∆H 1 th2 + s g 1 th4
Ath 2 8
Ath
2
m f 2 A ∆H rest 2A
∆H rest = ∆H − s 2g 1 t 2
subst. in (6) : twide open = = ∆H rest
Ath 4 h
ms f 2g ms f 2g
2A ms f 2 A ∆H
twide open = ∆H − 2g 1 th2 = − 1 th ⇒
ms f 2g Ath 4 2
ms f 2g
Hydraulic Engineering
Faculty of Civil Engineering 62 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
2 A ∆H 1
Ttotal = th + twide open = + th (12)
ms f 2g 2
Do note the effect of more accurately including the lifting period th. The total time Ttotal, increases with
(only) 50% of the lifting period th compared to the period with an immediately wide open valve.
In the above it has been assumed that the lock chamber was not completely filled or emptied when the
process of lifting the valve came to a stop. In one of the following paragraphs Ttotal will be determined
when filling and emptying does come to a stop before the valve is completely opened, hence Ttotal < th.
Some observations with regard to the relation between valve opening time th and discharge Q(t)
In situation 2 the maximum discharge has to be determined by time derivation of Formula (11) and finding
the time t for which the derivative equals 0. At that moment, for that value of t, Q=Qmax. Substitution of the
obtained expression for t into (11) results in Qmax for situation 2.
dQ ms f 2 g ∆H m2 f 2 g 2 A 2 g ∆H
= − 3 s 2 t2 = 0 ⇒ t2 = th
dt th 2 Ath 3ms fg
4 A ∆H
substitute t= th in (11) and find :
3ms f 2 g
Hydraulic Engineering
Faculty of Civil Engineering 63 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
3
m f 2 g ∆H 4 A ∆H m 2 f 2 g 4 A ∆H
Qmax = s . th − s 2 th (14)
th 3ms f 2 g 2 Ath 3ms f 2 g
There is a third situation to be considered besides the two already mentioned in the above:
Notes:
- The negative values for Q have no physical
meaning. The water stops flowing at t≈ 540
s before t=th=600 s.
- The maximum discharge for this situation
can be computed using Formula (14).
ms f 2 g ∆H m f 2g
Q= t − s 2 t3 = 0 0 < Ttotal ≤ th (11)
th 2 Ath
ms f 2 g ∆H m f 2g 4 A ∆H th
t = s 2 t3 ⇒ t= (14)
th 2 Ath ms f 2 g
Alternatively, for situation 3, it is possible to find Ttotal using the condition that the volume of water V being
discharged over this period is equal to A∆H.
Ttotal
t =0
∫ Q(t ) dt = V t = 0, V = 0 t = Ttotal , V = A∆H
The boundary condition for t=0 does not result in extra information (Why?); the one for t=Ttotal does. For
convenience sake notation t will be written instead of Ttotal..
t
ms f 2 g ∆H ms2 f 2 g 3 mf 2 g ∆H 1 2 ms2 f 2 g 1 4
∫0 Q (t ) dt = ∫
th
t −
2 Ath2
t dt
⇒
th 2
t −
2 Ath2 4
t = A∆H
8 A ∆H t h 2 16 A2 ∆H th2
Finally this results in : t4 − t + =0 use the
m f 2g 2 2
s ms f 2 g
4 A ∆H t h 4 A ∆H th
ABC - formula to find : t2 = ⇒ Ttotal = (15)
ms f 2 g ms f 2 g
Hydraulic Engineering
Faculty of Civil Engineering 64 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Notes:
- For the situations 1&2, as well as for situation 3, it is possible to use the integration below to find the
volume of discharged water for any t as long as t ≤ th , for situation 1&2, respectively as long
as t ≤ Ttotal for situation 3.
t
m f 2 g ∆H m f 2g
∫0 Q (t ) dt = V (t ) ⇒ V (t ) = ∫ s
th
t − s 2 t 3 dt
2 At h
- It is important to observe that the slower the valves in the gate are lifted the smaller the resulting
maximum discharge, see the graphs in the above.
Figure 4-16 Graphs showing discharge during the whole lifting period
Note:
In section 4.1.3 it will be shown that hawser forces vary in agreement with the derivative (afgeleide) of Q
with respect to time.
- Look at the graphs in Figure 4-16 for the discharge Q, and observe that going from the first branch
(t<th) to the second branch (t>th) of the graph, there is not a smooth transition in Q for t=th:
o In the right-hand graph for th=180 s, the tangents (raaklijnen) on either side of th do not have
the same direction. Mathematically spoken, the derivative on the left of th has a different value
than the derivative on the right of th.
o In the left-hand graph for th=90 s, the derivative of Q not only has a different (absolute) value
but changes sign as well from plus to minus. From a mathematical point of view, when
increase changes into decrease, the derivative changes sign from + to -.
- Look at the graph in Figure 4-15 and note that, when comparing the three graphs, this one has the
smoothest development of discharge Q and of its derivative.
Manipulating the lifting of the gate(s), selecting a smaller or larger th, in other words, faster or slower
opening, is an effective way to influence the hawser forces in the lock.
with regard to ship movements and hawser forces. Figure 4-17 Variation of z in time
Hydraulic Engineering
Faculty of Civil Engineering 65 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
In contrast with the head filling system, described in the previous section, energy losses in the culvert
system have to be considered, viz.:
1. energy loss due to:
• wall friction in the culverts
• local energy dissipation while entering and exiting the culvert
• losses in bends and at bifurcation points (splitsingspunten),
• etcetera (trash racks, valve shafts, transitions in culvert shapes and/or size).
2. Besides this, rectangular shaped conduits perform worse than smooth and/or rounded (pipe)
conduits having the same cross sectional area. The rectangular shape increases the order of
magnitude of several of the losses previously mentioned under point 1.
Looking at all the loss phenomena involved it seems hard to imagine that similar formulas for the
calculation of Q, development and maximum, and the F/E time Ttotal can be used culvert filling, as the
ones for heaf filling, see e.g. Formula (11) and (5) for Q, and Formula (12) for Ttotal. However, it would be
very convenient to use similar expressions and be able to compare the two types of F/E systems. The
solution is to use the discharge coefficient ms as the dust bin or garbage can (vuilnisbak), and translate all
those extra losses into a lower value for ms. Before determining the ms for a culvert system some
comparisons will be made between “through the heads” and “through longitudinal culverts” systems.
Figure 4-18shows the differences between head filling and culvert filling of the lock chamber with regard to
the discharge Q and the period required for filing Ttotal. The Q(t) line for head filling was already shown
before in Figure 4-16, three culvert alternatives are added to the graph. The alternative culverts have a
shape or configuration similar to the one drawn in Figure 4-21. The single culvert 100% has a cross
sectional area just as big as the area used for the openings in the gate in the head filling alternative. A
single wall culvert would fill the lock chamber from one side, which has big disadvantages regarding
turbulence of water in the lock. To fill the lock chamber from both sides, two wall culverts have to be
constructed. A 50% discharge on either side requires half the cross sectional area, which means that the
width and height dimensions have to be scaled down with √2 for the two smaller culverts.
Figure 4-18 Head filling versus culvert filling with regard to discharge Q and period Ttotal
The graphs in Figure 4-18 were made for a lock chamber servicing CEMT class IV or class Va vessels;
inland waterway navigation. With 5½ to 8 minutes, the systems fill or empty fast enough from a lock
operation point of view, see Table 1-4. Hawser forces need to be checked for this situation, see section
4.1.3 on hawser forces.
In Figure 4-19 the discharge curve for a bigger lock and a higher lift are presented. (The horizontal area of
2
the chamber is 7500 instead of 1080 m ; the lift 20 m i.o. 4.5 m). The lock should service a push convoy,
consisting of 3*2 barges and a 40 m long push barge, which is beyond the largest CEMT class. In spite of
Hydraulic Engineering
Faculty of Civil Engineering 66 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
the (much) larger openings or cross sections of the culverts the time required for F/E increases
substantially to about 12 or 18 minutes. For new lock construction the latter would have to be considered
as too long. The discharge curves are smoother because the valves are opened slowly, in 10 minutes.
Hawser forces need to be checked for this situation as well, however, it is easy to predict that head filling
will fail the test, because in the worst case the water is jetting through the valves with a velocity of about 8
m/s (simply divide Qmax by f). Head filling using short culverts around or through the head will do better
provided quite a large stilling chamber is being used. In case of longitudinal culverts, the distributed inflow
of water should prevent potential hawser problems.
Figure 4-19 Discharge curves for head and culvert filling, for a large lift lock (∆H=20)
Remember that, for the same water head ∆H and the same cross sectional area f, the discharge Q will
develop slower and the maximum discharge will always be lower for a culvert system than for a head
filling system. Longitudinal culverts may be designed and constructed with a larger cross sectional area to
obtain the same capacity. There is quite a big cost difference between filling through the gate valves or
through longitudinal culverts. Construction of even larger culverts has less bearing on costs than the
switch from head to culvert filling.
the water in the culvert. At the end of the F/E head filling
culvert - overtravel
based on the formulas the water in the culverts
should stop flowing, but it won’t. The kinetic 20
energy of the mass of water in the culvert will
act as the new driving force. The water will
15
overtravel up to the moment that driving force
will be compensated by the newly created
water level difference. This water head ‘on the 10
Hydraulic Engineering
Faculty of Civil Engineering 67 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
time to wait for the overtravel effect to dampen out. A possibility to shorten the process is to close the
valve(s) in the culvert. The closing of the valve from a certain moment close to the end of the F/E period
would have to be introduced into the formulas, as was the opening of the valve. It will definitely change the
discharge graph negatively. Discharge will start to decrease earlier and faster, and the time required for
F/E will increase. There are some other downsides to be taken care of when a valve in a culvert is being
closed, viz. cavitation and water hammer, see section 4.1.4.
To explain how the discharge coefficient for a longitudinal culvert has to be determined it is best to use an
example. A more or less realistic example of a longitudinal culvert, constructed into the wall of a lock, is
shown in Figure 4-21. Although the sketch is schematic, it does include the main energy loss contributors
like entrance and exit losses, bends, and bifurcations and obviously wall friction. The flow of water is as
follows:
1. from the upstream or upper pool more or less horizontal, depending on the shape of the entrance,
but in any way sideways out of the waterway into the culvert entrance.
0
2. through a bend; here vertically down in 90 . The bend may be less sharp and the culvert axis may
be inclined instead vertical, all depending on the actual situation. The vertical distance bridged will
be in the order of the difference in bottom level between the up and downstream water pool
respectively.
0
3. through a bend, here 90 again, and further in horizontal direction into the (bottom) culvert that
runs along the biggest part of the lock chamber and close to the lock bottom. The water passes
the shaft with the lifted upstream valve, which opened up the culvert for the flow of water.
4. every so much meters a part of the water takes an exit turn, here in the horizontal plane, and
flows into the lock chamber. The exit ports are close to the lock chamber bottom.
5. the closed downstream valve prevents the water from flowing through the remaining culvert into
the lower pool.
uppe r poo l
o pe n ed lo w e r p o o l
va lv e cl os ed
m a in c ulv e rt v alv e
w a ll/ bo tt om
lo c k
cha
m be
r
Below, for convenience sake, once more the basic formula to describe the discharge Q, depending on a
water level difference (z or ∆H) and discharge coefficient ms:
Hydraulic Engineering
Faculty of Civil Engineering 68 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
L U2
∆Htot = λ + ∑ξi (16)
Deq i 2 g
Where: ∆Htot = total energy loss [m]
L U 2 ∆Hf = energy loss due to wall [m]
∆H f = λ
D 2 g
(17) friction
eq
is the part of the losses due to wall friction, ∆Hi = any other energy loss [m]
and: λ = friction coefficient [-]
U2 L = length of the culvert [m]
∆H i = ∑ ξi (18)
i 2g Deq = equivalent diameter for the [m]
rectangular profile
accounts for all the other losses, such as ξi = loss/ dissipation coefficient i [-]
2
entrance, exit losses, elbows or bends, g = gravitational acceleration [m/s ]
bifurcations (splitsingspunt), etc.. U = flow velocity [m/s]
Rewrite Formula (16) to make it look like Formula (1) and introduce the cross sectional culvert area f in
order to replace U by Q; then find an expression for discharge coefficient ms for closed conduit flow:
L U2 2 g ∆Htot
∆Htot = λ + ∑ ξi ⇒ U2 =
L
Deq i 2 g + ∑ ξi
λ ⇒
Deq i
Q = fU
f2 f
Q2 = 2 g ∆Htot ⇒ Q= 2 g ∆Htot ⇒
L L
λ + ∑ ξi λ + ∑ ξi
D
eq i Deq i
− 12
L
Combine with Formula (1) and find : ms = λ + ∑ ξi (19)
D
eq i
Having found a formula linking ms to all sorts of losses that occur in close conduit flow the, remaining task,
in following paragraphs, is to find or determine the values to be used for the appropriate loss coefficients.
The work may be laboriously, depending on the number of losses to be taken into account, but is not too
complicated.
The previous statement, ‘not too complicated but laboriously’, is correct from a more general point of view,
even for a single pipeline, however, a pipeline network is subject of investigation here. Looking a bit more
detailed, a first complication is the fact that the discharge in each pipeline, or part of the pipeline of the
network, is different, see Figure 4-35. There is a main pipeline, the main longitudinal culvert, and then
multiple exits into the lock chamber, which are schematised as smaller branching off pipelines. The whole
discharge Q flows through the first or main branch(es), then at every exit branch or chamber outlet, Q is
getting smaller and smaller in the main branch. Even without the losses it needs an iteration to find Q in
every part of the system. On top of it friction and other losses depend on Q, vice versa Q depends on
those losses; an iterative process involving more than 2 variables is the result.
It is practical to start with determination of the losses ξi, depending on a varying Q. After that step the
losses in the individual pipes, and possibly derived individual discharge coefficients ms,i, have to combined
to an overall discharge coefficient for the whole pipe network. However, first some remarks on the cross
sectional shape.
General reference is made to the lecture notes of the course CT2140 or CT2320 or any other reference
work in the field of hydraulic engineering or fluid mechanics. Look specifically for the sections on closed
conduit flow in pipelines,
Hydraulic Engineering
Faculty of Civil Engineering 69 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Circular versus rectangular cross section; steel pipe versus concrete culvert:
In following paragraphs, losses will be discussed for closed conduit flow in pipeline networks. Figure 4-23
shows secondary flows in a rectangular and a triangular shaped cross section, which typically do not occur
in circular shaped cross sections. Travelling along the wall of a circular pipe, a water particle would not
encounter discontinuities, whilst the perimeters of
e.g. rectangular and triangular shaped pipes
contain pronounced discontinuities in every corner.
The energy consumed by the resulting secondary
flows or eddies reduces the energy available for
the primary flow parallel to the axis of the pipe. The
available area, and the width-height ratio of the
cross section, are factors determining the number
and the development into smaller or larger eddies.
Hydraulic Engineering
Faculty of Civil Engineering 70 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Colebrook (1939), combining the work of e.g. Chézy, Von Karman, Darcy and Weisbach, proposed one
formula for calculation of the friction coefficient λ for both smooth and rough pipes of circular cross
sections:
1 k / D 2.51
= 2log10 s + (23)
λ 3.7 Re λ
The Colebrook formula is an implicit equation for λ, which requires quite some iteration to find a result.
Alternatively the Moody diagram could be used to find the friction factor, see Figure 4-24.
The drawback of iteration using the Colebrook formula, or reading the Moody diagram numerous times,
was circumvented by Jain (1976), who suggested the following explicit equation for the friction factor:
1 k / D 5.74 0.25
= −2log10 s + 0.9 or f = 2
(24)
f 3.7 Re ks / D 5.74
log10 3.7 + Re0.9
ks
for : 10−6 ≤ ≤ 10−2 and 5000 ≤ Re ≤ 108
D
The Jain formula saves quite some computational time, especially when a spreadsheet will be used to
calculate through all the individual pipelines and determine the overall ms of the pipeline network as well.
2
Note: Don’t get confused in the following where the symbol f is used for either the area [m ] of the valve,
or for the friction coefficient [-].
Next, the information to determine loss coefficients for entrance, bend elbow, bifurcation, end bend, and
exit losses will be presented and discussed.
Hydraulic Engineering
Faculty of Civil Engineering 71 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Hydraulic Engineering
Faculty of Civil Engineering 72 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
In the culvert considered, the angle of the two pipe may not be the only
property that changes, but the size may change as well; look for
instance at the connection main culvert to exit port in Figure 4-21. For
situations where only the width changes, from bo to b1 as shown at the
top of Figure 4-31, the loss coefficient is calculated as follows:
a
−0.09 −0.4 −0.727*ln o
a b bo
ξ = 1.15 o * 1 (26)
bo b0
Looking at the exit ports, not only the width b changes but the height a
changes as well. In that case, it is probably better to use Formula (23)
and consider the loss as a bifurcation loss instead of a bend loss.
Hydraulic Engineering
Faculty of Civil Engineering 73 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Fp Fr
Qprimaire Qremain
Fl
When exiting from the culvert and entering the lock chamber
the flow decelerates because of being distributed over a (much) D2
D1
larger space. The loss coefficient is calculated as follows: U1
2
U2
U
ξexit = 1 − 2 since : Q = AU
1 1 = A2U 2
U1
2
A
ξexit = 1 − 1
Deceleration
(29) area
A2
Figure 4-34 Exit loss
Here:
coefficient
A2 = bexit hexit
bexit = the lock chamber length divided by the number of exits in the wall
hexit = the water depth in the lock chamber.
Since the water depth varies during the F/E process, hexit would be dependent on z(t); this complicates
computation of ξexit and the whole calculation of the overall discharge coefficient ms. Generally A2 is
substantially larger than A1, the cross sectional area of the exit port, and the resulting ξexit will be small.
Therefore it will be justified to use the average water depth in the lock chamber during F/E.
Hydraulic Engineering
Faculty of Civil Engineering 74 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Loss Qi A Dequi U Re f ξ
3 2
contributions [m /s] [m ] [m] [m/s] [-] [-] [-]
µentrance = 0,85 [-] 25,0 5 5,0 11111111 0,031 ξentrance
L1 = 2 [m] 25,0 5 2,222 5,0 11111111 0,010282 0,002 ξfriction
Bend 1 = 90 [degrees] 1,2 ξbend
L 2 = 4,5 [m] 25,0 5 2,222 5,0 11111111 0,010282 0,005 ξfriction
Bend 2 = 90 [degrees] 1,2 ξbend
L3= 8 [m] 25,0 5 2,222 5,0 11111111 0,010282 0,009 ξfriction
+ =====
U2 25 2,448 Σξ
∆Hloss = Σξ = 2.448 = 3.12 [m]
2g 2*9.81 Hence, in the supply culvert the loss in water head
Q 25 amounts to about 3 m.
ms = = = 0.64
f 2 g ∆H 5* 2*9.81*3.12 The discharge coefficient ms, computed in two different
− 12 ways, see Formulas (1) and (19), is equal to 0.64.
L
= ( 2.448)
− 12
ms = λ + ∑ξi = 0.64
Deq i
Note: the biggest loss contributors are the two bends.
Some basic rules and/or start conditions to be able to calculate through a pipe network, see Figure 4-35:
• The network consists of pipes (e.g. pipe AD or pipe IJ) and nodes (here A through J)
• Each node in the network can only have one pressure
• The pressure change from A to D by a clockwise path, pipe AC then CD, must equal to the
pressure change using the anti-clockwise path, pipe AB then BD
• For this specific pipe network for culvert and lock chamber:
– There are four loops, respectively ACDB, CEFD, EGHF and GIJH
– The water head between the upper pool and the lock chamber, ∆H, is known, or has to be
assumed.
– The pressure in the nodes B, D, F, H and J is assumed to be the same because the average
water level of the lock chamber will be the same in all these nodes. Hence, the pressure drop
over AB, is equal to, for instance, the pressure drop over ACEGIJ, irrespective of the
increasing number of pipe pieces. (AB only one pipe; from A to J 5 pipe pieces)
• Flow into each node or junction must be equal to flow out of the node or junction
• For this specific pipe network for culvert and lock chamber:
– The inflow into the pipe network will be in node A, the outflow out of the network in the nodes
B, D, F, H and J
– The sum of the outflow or discharge in the nodes B, D, F, H and J is equal to the inflow in
node A
• Given a certain flow in the pipes, losses can be calculated for every pipe, hence, the pressure
drop or head loss is known for each pipe.
Hydraulic Engineering
Faculty of Civil Engineering 75 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Clearly the computational process described in the above is best done by means of a spreadsheet or
using some other network analysis software. (In Excel the iteration option and the Solver add-in are very
convenient).
Qinflow, H1 A C E G I Q=0
Upper Lower
pool gate B D F H J pool
gate
closed closed
Q=0 Q=0
H2 Qoutflow
Lock chamber
Figure 4-35 Culvert and lock chamber schematized to pipe network
Hydraulic Engineering
Faculty of Civil Engineering 76 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Notes:
- An alternative for iterative calculation trough a pipe network can be found by comparing the pipe
network with an electricity network. There is an analogy between the voltage (Volt), current (Ampere)
& resistance (Ohm), and the water head (∆H), discharge (Q) & losses or the flow resistance K.
U2 Σξ
∆H = Σξ ⇒ ∆H = U 2
or ∆H = KU 2
≙ V = RI
2g 2g
Observe the square sign above U, which is not there for I, compare the expressions for (total)
resistance, and see the extra term 2/√(K1K2) in the denominator for parallel resistance.
- In terms of hydraulics, the system should be balanced so that the hydraulic loss for the filling process
is governed by the nozzles in the floor and not by the hydraulic losses in inlet, culverts or pressure
chamber. As a rough estimate the cross-sectional area of the pressure chamber should be at least
the same as the sum of the cross-sectional areas of the feeding culverts. As a rule of thumb, the ratio
between the sums of cross-sectional areas for the nozzles and the culverts can be used for an initial
design:
α= ∑
nozzles
Anozzle ∑
culverts
Aculvert
If the parameter α is small (<1), the filling process will be slower but smoother. If it is bigger (>1.5), the
filling will be faster but rougher. The indicative figures for α give some guidance for the ratio between
the cross sectional areas of the nozzles and culvert or the pressure chamber. Later the ratio should be
optimized on the basis of a laboratory or numerical model.
- How to incorporate the closing of the valve at the end of the filling period is a subject left to the reader.
It makes sense to assume a linear closing process; linear with regard tot time.
- In the previous all the explanations and (example) calculations were in fact dedicated to the filling
proces. When the emptying process has to be calculated through, a first obvious difference is that
entrance and exit, and the related losses, switch; pipe lengths and bends are different, no bifurcations
but joints where flows come together. Setting up the calculation (process) for emptying is left to the
(student) readeer and considered good practice to get to an understanding of all the previous.
Hydraulic Engineering
Faculty of Civil Engineering 77 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
a. Translation waves:
Because of the non-permanent character of
the discharge through the openings, series
of translation waves are generated at these
openings, which propagate in the chamber.
The waves fully reflect against the gates of
both chamber ends, only partial against the
bow and the stern of the vessel.
The translation waves create an oscillating
movement corresponding to the own
frequency of oscillation of the chamber.
(The oscillation period is the time needed to Figure 4-36 Forces in longitudinal direction
travel up and down through the chamber). during filling
b. Difference in impulse over the vessel length; see the frame ‘Analogy’ on the next page:
Concentrated water jets with high flow velocity may occur behind the gate openings. These high flow
velocities decrease in the longitudinal direction of the chamber due to turbulent exchange with the
surrounding water. Besides and under the vessel, the flow pattern changes substantially due to
Hydraulic Engineering
Faculty of Civil Engineering 78 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Analogy: impuls force on a broad crested weir (lange overlaat) and a ship in a lock chamber during
F/E. Flip the weir over the horizontal axis in the Figure below and recognize the floating
ship. (Reference is made to the courses CT2320 or CT3310).
= 1 2 ρ gh1
F1 = Force on water body in 2
section 1 [N]
= 1 2 ρ gh2
F2 = Force on water body in 2
section 2 [N]
q = Discharge per running = U1.h1
3
meter [m /s/m’] = U 2 .h2
Impuls balance: U1 = ‘Average’ flow velocity in = q / .h1
dU section 1 [m/s]
F = m.a = m. ⇒ F .dt = d (mU )
dt U2 = ‘Average’ flow velocity in = q / .h2
F1 − F2 − F3 = ρ q (u1 − u2 ) section 2 [m/s]
partial blocking of the cross section by the vessel. At the bow of the vessel the concentrated filling flow
is less able to break down rapidly because of the limited surrounding water available, at the stern of
the vessel the flow detaches and only starts spreading and breaking down further on. From the filling
point at the upper head to the lower head, the average discharge decreases because a shorter part of
the chamber behind the preceding cross section has to be filled. The product of ρqu (impuls) is not the
same in every section, and varies from moment to moment. On top of this, the water levels, h1 and h2,
vary in time and from section to section as well. Use of a stilling chamber results in a substantially
lesser concentrated flow near the head, hence less turbulent exchange will occur in the lock chamber,
nonetheless, an impuls force will develop.
When emptying a lock the energy is not broken down in the chamber but outside the lock, thus the
turbulence exchange in the lock is considerably less, which reduces impuls differences.
The F/E system should be designed such that a water jet directly hitting the ship is impossible. Of the
other longitudinal force contributors, only the translation waves and the differences in impuls over the
ships length are significantly contributing to hawser forces.
Hydraulic Engineering
Faculty of Civil Engineering 79 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Since translation waves and the differences in impuls over the ships length were identified as significant
contributors to hawser forces, further analysis to develop a formula for calculation is meaningful:
• For impuls differences the formulas are shown in the frame ‘Analogy’ on the previous page. The
difficulty is to estimate the different water levels and flow velocities in two different sections at the
same time. The subject will not be further elaborated in these lecture notes.
• For translation waves a formula will be derived below.
Assume the water surface in the lock remains a straight plane, on average, in spite of al local turbulences
or a running wave front. However, on one end of the lock the water level is higher than on the other. With
a bit of imagination it is clear that the average water surface rotates due to the translation wave, see
Figure 4-38. The rotation or slope of the water surface is equal to dz/dx. A force, the hawser force, is
required to prevent the ship from sliding down, which would be initiated by the dead weight G of the ship.
Examine the translation wave, which is between Q and i and start with the translation wave velocity:
c = wave velocity [m/s]
c = g ⋅h (31) g = gravitation constant
2
[m/s ]
h = water depth (average) [m]
The wave velocity is influenced by vessel presence; the vessel blocks the available water area in the cross
section. This is compensated for in the following formula:
2
g ( Av - n) Av = area of the cross section of the lock; bh [m ]
c= (32) n = cross section area of the ship below water level 2
[m ]
b b = width of the lock chamber [m]
The time needed for a translation wave to pass a vessel with a length L can be calculated by:
L
T= (33)
c
Discharge Q into the lock and the change of water level dz in the lock should be equal to each other. Use
this to link Q, dz and the translation wave velocity c. First assume a constant discharge Q, then consider a
constant increase of the discharge in time:
Q dz dQ 1
dz = ⇒ = ⋅ (34)
b⋅c dt dt b ⋅ c
Now Formula (35) for the water surface slope i is derived using the above Formulas (30) through (34):
dz z dt ⋅ T dQ 1
dz
dQ 1
i= = = = ⋅ ⇒ i= ⋅ (35)
dx L L dt bc 2 dt g ( Av − n)
The water slope i is proportional to the change in the discharge Q with regard to time, in other words,
proportional to the time derivative of Q.
Hydraulic Engineering
Faculty of Civil Engineering 80 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
In section 4.1.2 formulas for the discharge and its time derivative were found. The second derivative with
respect to time yields the maximum dQ/dt. For the period the valves are being lifted, t ≤ th:
ms f 2 g ∆H m2 f 2 g dQ ms f 2 g ∆H m2 f 2 g
Q= t − s 2 t3 (11) = − 3 s 2 t2 (36)
th 2 Ath dt th 2 Ath
d 2 (Q) 3ms2 f 2 g dQ ms f 2 g ∆H
= − t =0 ⇒ t =0 ⇒ Maximum = (37)
dt 2 Ath2 dt th
For t ≥ th:
ms 2 f 2 g dQ m 2 f 2g
Q=− t + ms f 2g ∆H (5) =− s (38)
A dt A
Depending on the data for ms, f, ∆H, th, and A, the maximum for dQ/dt will be calculated either by Formula
(37) or Formula (38). Equating the modulus or absolute value of Formulas (37) and (38) results in:
ms f 2 g ∆H m 2 f 2g 2 A ∆H
=− s ⇒ th = (39)
th A ms f 2 g
Note:
- Select a th smaller than calculated by Formula (39) and the dQ/dt will be the largest right at the start of
the F/E process; calculate dQ/dt with Formula (37).
- Using a th larger than calculated by Formula (39) has the effect that the maximum of |dQ/dt| occurs
when the valves are completely opened, at the end of the F/E process. The maximum |dQ/dt| has to be
calculated with Formula (38).
- th equal to the value calculated by Formula (39): Recall Formula (6) and (12) from section 4.1.2,
which compute the total F/E time Ttotal for a process with valves being lifted linearly in time and for a
process with instantaneously lifting (th = 0) of the valves. Substitute Formula (39) in Formula (12) to
find:
2 A ∆H 1
Ttotal = + th (12) ⇒ Ttotal = 1 1 th (40)
ms f 2 g 2 2
The frame below shows a short hawser force calculation to illustrate the different results for head filling
and longitudinal culvert filling, but, more important, to get a quantitative feel for the matter.
Hawser force calculation: Head filling: ms = 0.85
2 2
dQ m f g 0.85 *52 *9.81 2
Hydraulic Engineering
Faculty of Civil Engineering 81 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
- The permillages are slightly smaller than the guideline figures mentioned in the next section. This
agrees with the fact that only the hawser force due to translation waves has been computed. Other
force contributions, e.g. impuls differences or friction, were not included.
Often a vessel in a navigation lock will be stopped in its manoeuvers by putting the forward hawser around
a lock bollard and the ship’s bollards. By easing the hawser of one of the ship’s bollards carefully, the
hawser force has to be controlled by tightening or slipping of the free hawser end, the friction will slow the
vessel down. It is a matter of definition, whether the hawser forces in the previously described process,
should be considered as mooring load or as a berthing load because it slows down the ship.
At rest, in the lock chamber or in the outer ports, emptying and filling the lock chamber results in loads on
the vessel that have to be resisted by the mooring lines. Moored vessels with a mooring or hawser line
configuration as shown in Figure 4-39 are not able to resist much transverse forces. The resistance to
transverse forces is especially low when fixed lock bollards are used and the lines are continuously
slipping to allow the ship to rise and fall with the changing water level. The preferred direction of
transverse mooring forces is towards the wall (contact pressure between ship and wall, no hawser force).
Figure 4-39 Hawser configuration for different type of vessels in the lock chamber
Generally the smaller the ship (recreational craft) the smaller the number of mooring lines, and the larger
the probability that only one hawser at the time is transferring the whole tensile force, or not, in case of
slipping or breaking. For the lock the resulting mishap will be fairly negligable.
Inland navigation vessels are generally moored using 2 hawsers. The following is an indication for the
mooring force to be expected in one hawser:
• Ships up to
0
600 tonnes: 1,5 /00 of the water displacement
• Ships up to
0
2 000 tonnes: 1,0 /00 of the water displacement
• Push barge convoy up to
0 0
10 800 tonnes: 0,7 /00 - 1,0 /00 of the water displacement
Mooring of seagoing vessels is different because generally four hawsers will be used, which will be held
under constant tension by the winches of the ship. In conditions of transverse wind or water flow
sometimes one or more extra hawsers will be used in the transverse direction (imagine the amount of time
required to handle all the hawsers). An indication for mooring loads of seagoing vessels, mainly
determined by the tension winch:
• Vessels of over 20.000 DWT:
0
0,25 /00
• Vessels of over 100.000 DWT:
0
0,12 /00
During design the above indications for the mooring forces, related to the water displacement or DWT of
the vessel, can be used. Obviously the governing ship has to be selected wisely, and this might prove to
be difficult in case of large variations in the types of vessels using the lock.
Another approach would be to determine the governing mooring load based on the type of hawser most
probably used. Instead of selecting a governing ship a hawser type has to be selected, which still requires
the designer to consider one or more design ships, however, generally there is considerably less variation
in the break loads of hawsers. The heaviest cables which can still be operated manually are steel cables
with a diameter of 22 mm and a fracture load of circa 105 kN. If hand winches are present, like on push
barges, heavier cables can be used. Nylon hawsers absorb more energy due to their larger elasticity.
Hydraulic Engineering
Faculty of Civil Engineering 82 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The above calculations or methods are used to obtain a first estimate of the water level gradients caused
by translation waves and the hawser forces. The maximum hawser force is either the result of reducing
the vessel’s speed when slowing down or mooring, or forces induced by filling and emptying the lock
chamber. Seemingly more accurate calculation of the hawser force could be possible e.g. using the
program named LOCKFILL. Figure 4-40 shows the graphical results of a calculation with the program for
the forces in longitudinal direction.
Hydraulic Engineering
Faculty of Civil Engineering 83 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
As explained in Section 2.1.1 every lock cycle water is lost in the upstream reach of the waterway and
added to the downstream reach. The amount of water lost per leveling cycle, Vloss is:
There are several options to reduce the water loss due to locking ships. For instance instead of
constructing one large navigation lock, two smaller locks could be constructed. One large lock, leveling
over ∆H, uses twice as much water as two smaller locks, leveling over ½∆H, placed serially.
Hydraulic Engineering
Faculty of Civil Engineering 84 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Another option would be to construct one or more water saving basins or side ponds (spaarbekken). Part
of the water will be stored in the basin(s) when the lock chamber is emptied. During filling the water from
the basins will be discharged into the lock chamber. One side pond with a horizontal water surface equal
to the lock chamber will save 33% water. During emptying of the chamber ⅓ will flow into the side pond
and ⅔ will be lost. The construction of two side ponds will result in a reduction of 50 %, see Figure 4-41.
N ≥3 (42)
N −n 70.0
The graph in Figure 4-42 shows that there is little extra 50.0
30.0
Disadvantages of the use of water saving basins are the 0 1 2 3 4 5 6 7 8
n
costs and the extended passage time.
Figure 4-42 Water saved per lock cycle
versus number of basins n
Ice control
See Appendix 3
(Both Appendices more or less correspond with text from the report PIANC, Innovations in navigation lock
design, InCom-106, Brussels, 2009, (ISBN 978-2-87223-175-1).
Hydraulic Engineering
Faculty of Civil Engineering 85 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Water hammer and/or cavitation are phenomena that are closely related to larger water head differences.
Water hammer
To prevent overtravel in longitudinal culverts, the valve in the supply line will be shut when the discharge Q
drops below a certain (low) limit. If a valve was immediately closed in a culvert the force, using a/the
momentum equation, necessary to stop the water movement would be equal to:
du
F = m.a = m (43)
dt
Immediate closure would imply dt = 0 resulting in an infinitely large force. Fortunately the equipment used
for closing the valve is not that fast. What does develop is a shock, however, the compressibility of the
water and the elasticity of the culvert will reduce the impact. The shock wave (over pressure) travels back
through the culvert to the upstream reach, where it is reflected by water surface of the infinitely large water
volume and returns as an under pressure wave to the valve. The reflection process will continue as long
as the wave energy is not dissipated by the friction along the culvert walls. The wave celerity c can be
expressed as:
1 If:
c= (44) ρ = 1000 kg/m
3
1 D 6 2 o
ρ + Ebulk = 2.18 * 10 kN/m (for 20
Ebulk twall .E young Celcius)
D =5m
Where:
twall = 1 m
c = wave celerity [m/s] 6 2
3 Eyoung = 10 * 10 kN/m (cracked
ρ = density of the water [kg/m ]
concrete)
Ebulk = bulk modulus of water; a measure for the
2 then:
compressibility of water [kN/m ]
c = 1021 m/s
D = pipe or equivalent culvert diameter [m]
twall = wall thickness of the pipe or culvert [m]
Travelling back and forth in a 300 m long
Eyoung = Young’s modulus of pipe or culvert walls
2 culvert, takes 2*300/1021≈ 0.6 s
[kN/m ]
Suppose:
The pressure increase due to sudden interruption of
U0 = Q0/A = 25/20 = 1.25 m/s
the flow is; Rankine (1870), Joukowski (1898):
then for sudden closure:
∆p = ρ cU 0 (45) ∆p = ρ cU 0 = 1000*1021*1.25 ⇒
∆p ≈ 1.25 . 106 kg / ms 2 = 1250 kN / m 2
The pressure increase for slow closure of the valve,
formula by Allievi (1929): If:
L = 300 m
N N2
∆p = p0 + +N (46) tvalve = 180 s
2 4 p0
2
= 200 kN/m (∆H*γ= 20*10)
ρ LU 0
N= (47) then for slow closure:
p0tvalve ρ LU 0 1000*300*5
N= = = 0.042
Where: p0 tvalve 200 000*180
2
∆p = pressure increase [kN/m ] 0.042
0.0422
U0 = water velocity when valve closes [m/s] ∆p = 200 + + 0.042 ⇒
2 2 4
p0 = original (hydrostatic) water pressure [kN/m ]
∆p = 45 kN / m 2
Hydraulic Engineering
Faculty of Civil Engineering 86 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Note:
- Given a wave shock celerity in the order of magnitude of hundreds meters per second, it is safe to
assume that the return shock wave arrives back at the valve when the closing process is still
continuing. As a result Formula (46) for ‘slow’ closure of the valve has to be used for computation of
the extra pressure on the valve due to water hammer.
- In the exceptional case that the time needed for closing the gate is smaller than the time needed for
the shock wave to travel back and forth, then Formula (45) for ‘sudden’ closure has to be used to find
the extra pressure on the valve due to water hammer.
- An over pressure shock wave travels back in the opposite discharge direction, however, at the other
side of the valve an under pressure wave travels in the same direction as the discharge. Once
reflected by the downstream water mass, this wave returns as over pressure to the valve.
Cavitation
Some times the flow velocity can become so high that the local pressure decreases to below the vapour
pressure, or the negative shock wave due to valve closure results in under pressure. Below the vapour
pressure bubbles filled with vapour will develop in the fluid. When these bubbles reach places where the
pressure is higher again, they implode and cause damage to structures and equipment (concrete or steel
lining, valves, etc). This phenomenon is known as cavitation; some characteristics of cavitation:
• unstable flow pattern;
• less efficient discharge through the culverts (loss coefficient cavitation to be introduced);
• vibration of the valves and their lifting equipment;
• considerable wear of the valves etc., or the concrete culvert walls (cavitation erosion);
• a lot of noise.
It is possible to reduce cavitation at the inlet/outlet valves by adding air to the water. Damage can be
reduced by linings made of steel or the use of high strength concrete with steel fibers. An additional
measure which has a positive effect is by widening the culvert down stream. The implosion of the bubbles
will occur further away from the culvert or lock wall.
- Fluid-structure interaction in case of waterhammer with cavitation, A.S. Tijsseling, Doctoral thesis
Delft University of Technology, 1993
- Elementary Hydraulics, J.F. Cruise, M.M. Sheriff, V.P. Singh, Thomas Nelson, Student edition,
2007
- Water-resources engineering, D.A. Chin, Pearson Prentice Hall, Upper Saddle River, New Jersey,
nd
2 Edition, 2006
- Pipeline design for water engineers, David Stephenson, Elsevier scientific publishing company,
Amsterdam, 1976
Hydraulic Engineering
Faculty of Civil Engineering 87 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Hydraulic Engineering
Faculty of Civil Engineering 88 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Mitre gates generally should not be exposed to significant current or wave actions when partially open. For
this reason mitre gates are unsuitable for use as a weir (stuw) or flood gate (vloed deur) but are frequently
used as lock gates. In some cases, when for instance hydraulic cylinders are used to open en close the
gates, the gates can be designed to resist a small reverse water head difference.
In open position the gates are turned in recesses in the walls of the lock head. In order to prevent damage
when vessels navigate through the lock head, there should be enough distance between the gate and the
face of the recess wall, or fenders should be attached either to the gate or the face of the recess wall.
Figure 4-43 Water pressure (W), contact force (H) and spalling force (S) on a mitre gate
Stresses due to the weight of the gates are transmitted to the heel post (achterhar) and then via the pivots
to the collar strap (halsbeugel) and socket (taats). All the items must be designed to resist the horizontal
forces; the bottom pivot and socket also carry the whole (underwater) weight of the gate. The axis of
rotation of the gate should be in such a position that, on one hand, separation of the gate and the concrete
Hydraulic Engineering
Faculty of Civil Engineering 89 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
of the recess walls is ensured during the whole move from open to closed gate position and vice versa.
On the other hand, to retain water in closed position the space between the gate, hence the axis, and the
recess wall should be as small as possible to limit water flow around the gate. To accomplish both, a
solution would be to choose an eccentric position for the gate in the gate, i.e. at some distance from the
centre line.
A Elevation (Aanzicht)
B Section (Doorsnede)
Generally speaking, the equipment for operating the gates is located above the highest upstream water
level and as near as possible to the lock wall (so there is a danger of being damaged by downstream
bound ships). Operation of a mitre gate, results in torsion stress which should be taken into account when
designing and dimensioning a gate. Some basic information on the equipment will be presented below;
the civil engineer has to keep in mind that design of the equipment, including all the necessary mechanical
and electrical items, the installation and control systems, is a job on its own, best done by engineers with
relevant experience.
Electro mechanical:
The so called "panama wheel" is most widely used in locks to operate the gate. The wheel is operated
through a set of gears put into motion by an asynchronous motor. In spite of the constant speed of the
gear wheel the rate of angular displacement of the leaf is reduced at the beginning and at the end of the
operation, when stresses to be resisted may be the largest.
Hydraulically (oil):
Today almost exclusively hydraulic cylinders are used in new design. A hydraulic jack fed by a volumetric
pump and attached to a frame in its centre, acts on the piston rod, the end of which is connected to the
gate. The jack is positioned at 1/4 to 1/2 of the gate length from the axis of rotation.
Hydraulic Engineering
Faculty of Civil Engineering 90 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Disadvantages are:
• The length of the lock chamber needs lengthening as well as the upper head by the recesses of the
gates.
• To retain water in both directions a double set of doors is required.
• Very accurate mounting and frequent checking of the contact at points of load transmission (thrust
blocks and quoin blocks) is necessary.
• Mitre gates can not be opened or closed under a water head difference
• Operation may be disturbed by debris and ice.
For increasing widths of the sluice, the type of material and the design of gates changes. Mitre gates
(puntdeuren) which are often constructed in wood become less suitable and are replaced e.g. by steel
rolling gates. The width of mitre gates is limited to approximately 20-25 meter (10-12.5 m per door). What
is especially important for this is the height width ratio. When the ratio is smaller than 1 the forces on the
pivot points are relatively large and may become a problem, especially the (horizontal) force on the upper
one.
Advantages of mitre gates often outweigh their disadvantages as is demonstrated by their utilization
throughout the world. However, since vessel size is increasing this type is less frequently applied. For
reasons of construction and maintenance costs (and sometimes the status as monument) the gates of
small and medium size of navigation locks are made of either steel or wood. A new development is the
use of glass fiber reinforced plastics (GFRP), which have little need for maintenance.
Hydraulic Engineering
Faculty of Civil Engineering 91 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
If selected at all, the single leaf gate is most frequently used for locks having a small width, e.g. for the
locking of recreational craft.
Advantages
• Very suitable for locks of smaller width because of simple construction and operation.
• No air draught limitations.
• It is possible to lock the door on the free end which will make it possible to retain water in two
directions.
• Forces on the gates are transferred parallel to the lock wall (when the closed leaf gate is
perpendicular to the lock axis).
Disadvantages
• Recesses for single leaf gates are longer than those for equivalent mitre gates, thus single leaf gates
need longer structures.
• Opening and closing of the gate results in a lot of water displacement.
• More rigid and thus heavy construction needed for the pivots, socket and collar strap.
• Vulnerability for ice ad debris.
• Not suitable for wide locks because the supports will be very heavy.
Hydraulic Engineering
Faculty of Civil Engineering 92 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
the large and deep recesses in the lock heads. Sector gates are more often used for guard locks or storm
surge barriers where closure under free flow and unlimited air draught is needed.
Similar to mitre gates, sector gates can be pushed into movement using mechanical equipment, e.g.
machinery or hydraulic jacks. The driving force can be applied to the upper gate arm. Contrary to mitre
gates, those have to push away the water body in front of the gate, the sector gate cuts through the water
with its edge. Therefore the installed power of the equipment used is relatively small, even though the gate
itself is heavier. Again, the design of the equipment to be used, including all the necessary mechanical
and electrical items, the installation and control systems, is best done by engineers with relevant
experience. Note: the space for the recesses, the equipment and the ‘wiring’ that has to be provided,
generally requires quite a lot of detailing work to be done during concrete structure design and results in
quite some complications during construction due to all the required cast-in items.
Disadvantages are:
• Relatively large amount of material because of the developed length of skin plate and the gate arm
trusses that have to be braced.
• High support loads at the pivots resulting in heavy cast-in items in the lock head wall due to weight
of the gate. To mitigate this disadvantage float elements assembled to or integrated in the gate may
be used.
• The recesses required to move the gates out of the way are large and substantially increase the
size of the lock head structure.
• Operation may be disturbed by debris and ice.
Hydraulic Engineering
Faculty of Civil Engineering 93 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Note:
If the sector gate is moved using hydrostatic water pressure some of the advantages and
disadvantages mentioned for sector gated in the hereinabove, become bigger, others may even
be reversed.
It is possible to use this type of gate for guard gates, flood defense or storm surge barriers, provided the
gate body is designed high and strong enough to resist underflow or/and overflow.
Figure 4-51 Radial or tainter gate during construction (left & middle); hydraulic jack (right)
Hydraulic Engineering
Faculty of Civil Engineering 94 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Hydraulic Engineering
Faculty of Civil Engineering 95 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
However, it requires a large recess deep into the ground to accommodate the gate and its construction
and maintenance costs are high.
Most of the horizontal loads on the gate are diverted to the side recesses; a small amount is transferred to
the bottom support (onderaanslag). The submersible gate is able to retain water in 2 directions.
The rolling gate moves on underwater rails or sliding tracks, which bears the risk of the gate getting
jammed due to accumulation of sediments or debris on those tracks. Especially if the gate frequently
remains in the open position it should be considered to wipe the rail or track clean before or during gate
operation. Moving the gate, reducing weight and frictional forces, thus reducing wear and tear as well, is
easier when buoyancy tanks are used. When the gate is in closed position the tanks can be filled, now
they serve as ballast tanks, to ensure the necessary contact pressure.
Figure 4-54 Rolling lock gate and its lock head; cross sections and 3D impression
A combination of factors results in the generally considerable thickness of rolling gates. Obviously one
factor is the large width of the lock to be spanned by the gate. The need for stability results in wheels or
slides on both sides of the gate and two rails or sliding tracks under one door, not just one in the center of
Hydraulic Engineering
Faculty of Civil Engineering 96 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
the door, which adds to the thickness. Ever so often the thickness of rolling gates can be used to provide
passage to light traffic.
In closed position the rolling gate can be considered as a simply supported beam; in fully opened position
there are hardly any horizontal forces on the door. In those positions stability of the gate is not a problem.
During the opening or closing process the ‘upper’ corner of the gate is completely unsupported. A force on
this door area, e.g. due to a remaining water level difference or large flow, may result in significant stability
problems. Keeping the resulting vertical force within a distance of 1/6 of the gate’s thickness to the centre
line of the gate is a good measure for providing stability, but requires a certain thickness of the gate.
Disadvantages:
• Requires a lot of space besides the lock (head).
• Requires a large recess or lock head.
• Can not be opened or closed under water head conditions.
suspended gate
Figure 4-55 Innovations of mitre gates
Hydraulic Engineering
Faculty of Civil Engineering 97 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
a. Identify possible loads and load combinations and calculate their magnitude
To identify loads and the combinations it helps to look at the gate in opened and closed position, or
consider the situation when the gate is being moved.
1. Load on a mitre gate in closed position: e.g. hydrostatic water pressure
2. Load on a mitre gate in opened position: e.g. dead weight
3. Loads on the doors due to debris when trying to close
4. Loads on the mitre gate subjected to ice
5. Loads on mitre gates due to ship impact
6. Loads on a mitre gate under wave attack
7. etc.
These situations and loads combine to a number of load combinations. As example combinations 1 and 2
will be elaborated in the hereinafter.
When schematising and selecting the type of supports for the gate, not only the transfer of forces has to
be taken into consideration, but preventing leakages or flow under or around the closed gate as well.
In opened position the gate is simply supported, see left-hand side illustration in Figure 4-57. The bottom
pivot provides both the vertical reaction and a horizontal reaction force. The upper pivot provides the
horizontal reaction in the opposite direction. Rotation in the horizontal plane around the axis through the
supports is possible. Looking at deformations globally, the gate will get out of square (schranken) if it is
not stiffened sufficiently in its plane. This is a problem if there is too little clearance (speling) between the
bottom of the gate and top of the lock head floor. In the act of opening or closing the gate, the bottom of
the mitre post (voorhar) would touch and scratch the floor.
Obviously leakage of water or sealing is not an issue at al when the gate is open (or being opened).
When closed and retaining water, there are two (main) alternative systems to support a mitre gate. In the
first alternative, in the middle in Figure 4-57, the mitre gate has a vertical support at the bottom pivot point
(taats). Horizontally there will be a line support at the mitre post (voorhar), and either one or two simple
supports at the heelpost (achterhar), the last depending on the clearance in the bottom pivot shoe.
To be able to install the gates, there has to be a certain clearance or construction tolerance available in
the bottom pivot point. After installation of the door into the lock head, little can be done about the bottom
pivot or the available clearance. Often the upper pivot is readjustable to facilitate installation, which is also
convenient for later operational stages.
It is possible to design and construct the pivot shoe and socket (bottom) with such a large clearance that
the heel post is being pushed against the concrete wall of the recess by the water pressure. Suppose
enough (horizontal) clearance is available in upper pivot as well, than the heel post touches the wall over
its entire length. This is the second support alternative in closed position. In that case the gate has line
Hydraulic Engineering
Faculty of Civil Engineering 98 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
supports on three sides for horizontal loads, the fourth side, the top girder, is free or unsupported, see
Figure 4-57 on the right.
For both alternatives supports and loads have been drawn at the right-hand side door, the deformations
have been indicated at the left-hand side door. The deformations of the gate are important for analysing
and preventing the leakage of water, usually done by providing sealing between the gate’s edges and the
‘surrounding’ concrete. Hand in hand with larger shear and torsion stresses, that are bigger for simply
supported plates than for line supported plates, go larger deformations of the gate that result in more
leakage. Larger deformations and leakages require larger seals, see Section 4.2.4, which increases initial
and maintenance costs.
Sketch how forces acting on a structure are being transferred. In case of a mitre gate draw up how the
loads are transferred by beams, girders, the axis and hinges to the lock head.
This time consider a closed mitre gate first: the governing load to be considered is the maximum water
level difference.
From construction mechanics point of view, the V-shape of the two leaves is a statistically determinate
three-hinged truss, which transfers the water pressures by normal forces to the supports in the gate
recesses; this is the global or overall force action. Locally the water pressure results in bending moments
in the truss.
Figure 4-58 shows a top view of forces acting on a closed mitre gate, only one of the doors has been
included, as well as the force vector diagrams for decomposition of the main forces. The resulting
hydrostatic load W is resisted by the force H, the force between the 2 doors of the mitre gate, and spalling
force S (spatkracht), the force acting on the lock head and vice versa. For reasons of symmetry the forces
H between the 2 doors, in the point(s) of contact of the mitre posts (voorharren) are in equilibrium. They
are of the same magnitude but their direction is exactly opposite. Both H and S can be split up in a
direction parallel (N) and a direction perpendicular (F) to the door.
S W │S│=│H│
½W = -F
H
N N F
S
F H
Since the reaction force S can be divided in a force parallel and a force perpendicular to the gate these
forces are a function of the hydrostatic pressure W and the angle α. Expressed in formulas:
W W
S=H = F =½ W N=
2sin α 2 tan α
From the above formulas it can be derived that for small angles α the spalling force is high. This would
suggest using a larger deflection angle α. However, when increasing this angle the gates will become
larger, therefore requiring a heavier structure, but the soliciting load will be larger as well, hence the gate
will be heavier. For reasons of economics usually an angle of tan α = 1:3 has been determined as the
most optimum one.
Hydraulic Engineering
Faculty of Civil Engineering 99 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
As shown in the previous section, the spalling force S at the heelpost, or F and N, may work as a
concentrated load (puntlast) or as a distributed load on the lock head structure and gate, action is
reaction, depending on the support conditions. The same goes for the mitre post; depending on the
detailing of the gate the force H will either be more concentrated or distributed.
The flow of forces through the gate, the local or internal force transfer, is strongly influenced by the type,
the arrangement or composition the girders and posts of the gate. The ‘local’ arrangement has to be in
agreement with the ‘global’ situation, ie. the support conditions of the gate, see previous paragraphs. For
the girder and post arrangement the following two main options exist:
1. Load transfer equally distributed along the vertical posts, illustrated in Figure 4-59. The gate will be
constructed using a relatively large number of horizontal girders (regeldeur), more or less equally
spaced, which results in an equally distributed load on the heel and mitre post. The horizontal water
pressure is predominantly carried away by horizontal internal forces. In agreement with the equal
distribution the pivots should have quite some clearance to allow contact, either direct or via sealing,
of the heel post along the whole height with the lock head wall. As such, load transfer along the post
of the lock head is via distributed line loads N and F.
2. Load transfer concentrated in a view points, see Figure 4-60. Instead of a predominant horizontal
force flow, a larger part of the load is flowing to the supports via vertical routes. The gate will be
constructed using two heavy girders (regels) between the heel and mitre post. The water pressure is
transferred via plates and subsequently posts (stijlen) to the main girders. Positioning of the 2 heavy
girders should be such that they carry away about the same load and such that there is an optimum
between the bending moments in the heelpost and the other posts.
Both the heel and mitre post are simply supported, the heel post by the upper and bottom pivot, the
mitre post will be provided with two contact points or surfaces that can be less or more pronounced.
No, or only very little clearance will be allowed in the pivots at the heel post. In view of nowadays
abundant availability of high precision (with very little clearance) ball bearings (kogellagers), being able
to resist large loads, this is not a problem anymore.
Hydraulic Engineering
Faculty of Civil Engineering 100 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The governing load in, when the gate is in an open position, will be the dead weight of the gate. Unless a
very special upper pivot point is designed and constructed (this was done for the gates of the
Oranjesluizen in Amsterdam), the downward dead weight will be resisted by an upward reaction force in
the lower pivot point. The destabilizing moment to be resisted will result in 2 equally large horizontal forces
in opposite directions; tension on the upper support and compression on the lower support, if the lock
head is taken as reference. This is illustrated in Figure 4-61.
ΣV = 0 → FV = W
ΣH = 0 → FHbot = FHtop
ΣM = 0 → FHbot * h = W * a
a
→ FHbot = W *
h
a = 21 b
When the size of the gate increases, the gate will tend to get out
of square (schranken) due to its dead weight. This is a problem
especially for gates made of wood, because wood elements are
usually limited to a certain size and need a lot of connections.
From a stiffness or deformation point of view the welding of
steel is much more convenient. The shear deflection of wooden
mitre gates can be limited by using beams or girders in a
diagonal position, i.e. by using (wooden) struts. A steel tension
bar is a better solution because it adds considerably less
weight. This is illustrated in Figure 4-62.
Steel gates with appropriate stiffener arrangements are much Figure 4-62 Strut or tension bar
stiffer than wooden gates, and getting out of square is rather
easily solved, if it would be a problem at all.
4.2.4 Sealing
Retention of water is one of the main functions of the lock and the gate is the means to this end. To retain
all the water the gates must be connected completely watertight to the surrounding lock head structure,
and the doors of e.g. sector or mitre gates should not be left ajar (op een kier). However, to move the gate
there must be some clearance between the gate and the lock head and to leave a small gap between two
doors could be better than running the risk of damaging then during closure. To prevent the flow of water
through these clearances and to allow movement of the gate as well, sealing (waterafdichting), generally
(soft) wood or rubber profiles attached to either the gate or the lock head, is being used.
Hydraulic Engineering
Faculty of Civil Engineering 101 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Sealing between the heel post of a wooden mitre gate and the lock head:
In Figure 4-64 on the left-hand side, the heelpost of a wooden mitre gate door and the posts on the wall of
the lock head are shown. If there is sufficient clearance in the pivots, the door is firmly pushed against the
posts on the wall. The usually hard wood heel post is not equally stiff in both directions, as a result sealing
is not perfect at the spot where line support N works. Using a compressible seal is in conflict with transfer
of the line force N. Use of a soft wood seal, pine or oak (grenen of eik), at the spot where line force F
works solves the leakage problem. On the right-hand side of the Figure a sketch to illustrate what is the
result, considering the displacement of points of the heel post, of the eccentric position of the axis;
eccentric to the heel post centre. Especially when there is little or no clearance in the pivots such a sketch
is better used to determine the best position for one or two seals. In this situation the advise is to use
rubber sealing which is more easily compressed.
Figure 4-64 Top view on the heel post of a wooden mitre gate and the post on the lock head
In both figures in the hereinabove the steel strips (aanslagstrippen) on/at the surface of the concrete, have
steel anchors at the back to cast them into the wall. The usually stainless steel strips have to be
positioned with more than the usual accuracy. It is not uncommon to cast the biggest part of the concrete
walls first using block outs, which keeps hollow spaces free in the wall. In a later stage anchors and stips
are positioned in the block outs and on the wall and carefully casted into the wall.
Hydraulic Engineering
Faculty of Civil Engineering 102 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Table 4-5 Gate selection per type of navigation lock and depending on lock width
Type of Lock Rolling
Mitre gate Single leaf gate Vertical lift gate
lock width* gate
Single Double Double Single Double Double Single Double
sided sided sided sided sided sided sided sided
water water water water water water water water
retention retention retention retention retention retention retention retention
Very
X
Single small
sided
Small X X
water
retaining
inland
Medium X X
lock
Large X X
Very
X
Double small
sided
Small X X X
water
retaining
inland
Medium X X X
lock
Large X X X X
Small X X X
Double
sided Medium X X X
water
retaining Large X X X
sea lock
Very
X
large
* Lock width explanation:
• Very small 4-6 m • Medium 10-16 m • Very large >24 m
• Small 6-10 m • Large 16-24 m
Hydraulic Engineering
Faculty of Civil Engineering 103 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
vessels. Due to their height lift gates often are a landmark, which is difficult to fit in harmonically with
the surrounding environment. Except the submersible gate, all the other gate types have a larger
horizontal footprint, relatively spoken, than the lift gate. The construction and maintenance cost
disadvantage of submersible gates generally overrides the horizontal space advantage.
1. Accommodate the gate and whatever is necessary for opening and closing the gate:
The lock head needs recesses for the gate in open position. The recess must be designed in such a
way that collision with the gate is prevented as much as possible when ships are passing. Furthermore
all the equipment and other items to operate the gate need space or a place in the lock head structure.
Hydraulic Engineering
Faculty of Civil Engineering 104 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Below, some of the principal design requirements for the lock heads are derived from the functions, others
are the result of operational considerations or boundary conditions.
Hydraulic Engineering
Faculty of Civil Engineering 105 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Figure 4-65 Cross section of a monolithic U-shaped structure for a lock head
As mentioned before the standard U-shape will transform in more complicated 3D shapes because
recesses for the gates have to be provided and enclosed spaces for machinery and equipment.
Depending on the gate type, the construction method and local conditions variations to this theme are
designed and constructed. In Table 4-6 a number of alternatives are shown with description of the
situations where or when to apply them, for a lock head with mitre gates. It may help to look at the Figures
in the previous section on gates to develop similar ideas for lock heads for other gate types.
Hydraulic Engineering
Faculty of Civil Engineering 106 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Besides the normal lock head alternatives in Table 4-6, Table 4-7 represents two flexible lock head
alternatives. The purpose of a flexible lock head is to be relative easy extendable. This way, with minor
structural adjustments, the lock will be capable of serving the shipping traffic for its whole structural
lifespan. In general locks become already too small in 25-50 years, while a normal lock structure as a
lifespan of about 100 years. Thus, this type of locks is from a Life Cycle Management (LCM) point of view
a good alternative for lock (re)construction.
Stability
For overall stability the following failure mechanisms must be checked:
In the listing above ‘Overturning’ has been mentioned twice. The check on overturning using the criterion
of no tensile stresses under bottom of structure is more conservative, i.e. results in bigger foundations,
than the criterion for overturning where redistribution of stresses is allowed, provided the maximum
bearing capacity of the subsoil is not exceeded.
Hydraulic Engineering
Faculty of Civil Engineering 107 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
If a pile foundation is necessary an initial pile bearing capacity of 1000 kN per □ 450 pile (square 450 x
2
450 mm pile), compression, is a safe figure to work with, provided the pile toe is in a layer where the cone
2
value is around 10 N/mm (CPT-value). Generally the use of the Koppenjan formulas for pile bearing
capacity results in higher figures.
The upward groundwater pressure is a very important parameter because it reduces Σ Vs, the resulting
vertical downward force. In a first, strongly simplified, approximation the decrease in piezometric level can
be assumed to vary linearly with the position along the longitudinal axis of the construction. When vertical
seepage cut-off screens (schermen tegen onderloopsheid) are applied, the seepage length can be
approximated as sketched in Figure 4-66; a 2D-approach is used here. With total seepage length the
formula, shown in the Figure, for the upward pressure at a given x-coordinate can be found.
The true pressures will have to be determined by drawing a square net or by using a finite element flow
model; see the Manual 'Ground water flow' for an example. From the above it will be clear that the
locations of the seepage cut-off screens are an important factor in the determination of the upward
pressure under the lock floor, hence, in the stability of the lock head.
Keep in mind that short time intervals of high or low water levels will hardly have any noticeable effect on
the upward ground water pressure.
Note:
− The soil pressure under the structure remains the same from left (h1) to right (h2) whether the
piezometric level, read the water pressure, varies or not, assuming the dead weight of the structure is
nicely distributed. The latter also depends on the stiffness of the whole structure, lock heads and lock
chamber. Since the soil pressure is equal to the sum of the effective stress plus the water pressure
(σsoil = σ’eff + σw), an increase in water pressure reduces the effective stress.
− A reduced effective stress requires less vertical bearing capacity of the soil. Water carries a part of
the load. However, less effective stress reduces the lateral or horizontal bearing capacity, see next
paragraph.
Hydraulic Engineering
Faculty of Civil Engineering 108 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Overturning in general
After checking the vertical and horizontal equilibrium, the structure has to be checked on overturning.
Considering shallow foundations, soil pressures, generally linearly varying, have to provide the resisting or
stabilizing moment. Similar to the checks on vertical and horizontal stability, and using the already
computed results of those checks, the resultants of the vertical and horizontal forces are calculated. The
overturning moment will be computed using the arm between Bottom of Structure (BoS) and the working
line of the horizontal resultant, and the arm or eccentricities of the vertical force(s). Instead of continuing
the analysis with an overturning moment M, the calculated moment is translated into the resultant vertical
force and an eccentricity e of this force. The multiplication ΣV.e has to equal ΣM.
Note:
In construction mechanics courses the point of origin used to do calculations is often chosen at
the utmost right hand side and in the centre line of the structure or centre line of a part of it. From
a mathematical or systematical point of view this is a wise decision because it avoids most of the
confusion about plus-minus signs to be used for forces and their contributions to the moments,
which depends on direction and position.
In hydraulic engineering it is more convenient to select the centre and bottom of the structure as
the point of origin to check overturning stability, see Figure 4-68 and further explanations
hereafter. Often the use of the centre bottom point of the structure has the advantage that the
large dead weight force does not contribute to the moment.
In Figure 4-69 the effect of an increasing eccentricity, from left to right, on the soil pressures under the
bottom slab is shown, assuming a homogeneous soil body of constant stiffness under the structure (the
stiffness may vary from layer to layer though). Alternatively the force Vs could be larger, or both the
Hydraulic Engineering
Faculty of Civil Engineering 109 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
eccentricity and force could increase. As explained a larger force Vs is the result of a larger overturning
moment due to either larger forces or larger eccentricities (in order not to cloud the Figure, M and H have
not been drawn).
In the middle and right-hand side illustration of Figure 4-69, the largest effective stress σeff under the
foundation is calculated as follows:
1. the stabilizing or resisting force Vr is working opposite and in the same working line as the
soliciting force Vs
2. knowing the eccentricity e of the force Vs, the distance a can be determined
3. Vr is the resultant force of the soil pressures, which are assumed to vary linearly. Given the linear
variation of soil pressures, there has to be a triangular pressure distribution. The work line of Vr
has to run through the centre of gravity of the triangle, hence, a is equal to ⅓ of the base of
triangle. As a result Vr equals ½ * σeff * 3a; with some rearranging σeff is ⅔Vr/a.
3. Overturning – No tension
When Vr is the equal opposite in the same working line as Vs the structure is stable; there is no danger for
overturning. However, often the requirement that the whole base has to remain in contact with the soil
beneath it will be put forward. This demand can be presented in formulas as follows for foundations with a
rectangular footprint:
ΣV ΣMs,tot ΣV ΣV
σ eff
'
= − s,tot − 2
= − s,tot − s,tot ≥0 hence : e ≤ 16 b
b b 1 b2
6b
1
6
The above mentioned requirement could be popularly phrased as: ‘No tension allowed’ under the base
slab of the structure’. To suffice to this requirement the vertical component of the resulting force has to
stay within the core of the foundation, e has to smaller than 1/6 of the base.
Obviously it has to checked that the effective stress σ’eff is not exceeding the maximum bearing capacity
of the (sub)soil, which can be determined using the Brinch Hansen.
4. Overturning – Redistribution
As illustrated in Figure 4-68 the overturning moment, thus the eccentricity and/or vertical force, may be
very large. In steel material this would result in compression ‘and’ tension stresses, but the only possible
force interaction between the bottom of the structure and the soil is a compression pressure, tension is not
possible due to the nature of soil. The tension pressures that would be needed to resist the overturning
moment are redistributed. As a matter of fact there are no ‘tension pressures’, but there will be increased
compressive stresses under the part of the base that remains in contact with the soil.
Again a check has to be made on the effective stress σ’eff, which should not exceed the maximum bearing
capacity of the (sub)soil. Compared to the similar check when the ‘No tension’ requirement is used, there
Hydraulic Engineering
Faculty of Civil Engineering 110 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
is a higher chance on failure, i.e. the bearing capacity being too small for the required effective stress,
because the stresses under the effectively working part of the base are definitely higher.
Piping is influenced by the type of lock chamber that is applied: is it a closed basin or has a permeable
chamber floor, for instance a filter and rubble stone protection, been used? In the first case the piping
length (kwellengte) is related to the full length of the lock, in the second case the piping length is related to
the length of the lock head only. The second case results in a larger hydraulic gradient and a greater risk
of piping.
From a structural engineering point of view lock heads are structures that should be designed using 3D
models. 2D schematisation is less meaningful because of the truly 3D shape of the lock head, see e.g.
Figure 4-54. Also forces are acting along all 3 axes, for instance ‘free’ water pressures acting along the
lock axis, soil and ground water pressures perpendicular to the same axis. The forces and the resulting
load combinations to be analysed for the head and the spreading of these forces through the 3D structure
is quite laborious if not complex. Nonetheless, starting from scratch 2D approximations can and will be
used to arrive at a first conceptual design for the 3D lock head, but in following design loops the 3D FEM
models will be used to do the final checks on strength and stiffness.
Hydraulic Engineering
Faculty of Civil Engineering 111 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
A large part of the lock head has to be constructed below the existing ground water level. Consequently a
construction pit or braced excavation is needed, to construct the lock head. Design of the construction pit
or braced excavation depends on several conditions at the lock location:
• Available space for construction (horizontal)
• Strength of the soil
• Permeability of the soil in combination with (differences in) piezometric levels or groundwater
head(s)
Based on these conditions some construction methods and the temporary structures required are
mentioned in Table 4-8. All the options need dewatering to a certain extend to keep the building pit dry.
Table 4-8 Characteristics of some construction methods for a U-shaped lock head
Slope combined with a seepage screen Sheet pile wall
Deep
impermeable
layer
This option is selected when there is This option is selected, when there is an
enough building space and an impermeable layer, but not so much space
impermeable layer is available to build the lock head
Underwater
concrete with
tensions piles
Not possible
Not possible
Hydraulic Engineering
Faculty of Civil Engineering 112 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Important for the preliminary design are the forces due to horizontal earth pressure, generally the
governing load, water pressure, deadweight, surcharge load, hawser forces and ship's impacts. The wall
has to be designed such that overall stability is guaranteed (∑M=∑V=∑H=0) and that it is able to resist all
the forces (material strength > load). Stability and strength are generally considered in the Ultimate Limit
State (ULS).
In addition, in Serviceability Limit State (SLS), to these forces the lock walls are subjected to (tensile)
stresses induced by temperature. These stresses result in cracks. A way to prevent this problem is the
use of expansion joints (dilatatievoeg). Depending on the wall thickness these joints are positioned at a
distances of approximately 25 meter.
The horizontal forces can be resisted in several ways, e.g. by means of:
- a gravity structure
- a retaining wall structure
- a wall combined with a deep foundation
The vertical forces will be taken up by the soil, either more uniformly distributed by a shallow foundation
or more concentrated by using a deep or pile foundation. In following paragraphs several wall structures
will be discussed in more detail.
The vertical dead weight forces G and V are reduced by the upward water pressure (not shown in Figure
4-70). The resulting vertical downward force has to be resisted by the soil pressure O beneath the wall.
Hydraulic Engineering
Faculty of Civil Engineering 113 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The horizontal force H must be resisted by soil friction W at the bottom of the structure. The following must
be valid:
W >H Where: f = friction factor
W = f (G + V ) G = dead weight of the structure
V = weight of the soil
To provide a large enough soil friction force W, care has to be taken of:
a. Sufficient friction between structure and soil. Make sure that the bottom surface of the wall is rougher
than the soil. The formula f = tan(δ) can be applied. For neutral soil pressures δ≈½φ, whilst for sheet
pile walls δ≈⅔φ, where φ is the angle of internal friction. For a smooth wall f is considerably smaller;
use a δ << /3φ.
2
b. Enough deadweight G. This may lead to larger dimensions of the structure; alternatively heavier
materials may be used, e.g. natural stone. (Rock obtained during excavation can be used in the
concrete mix).
c. A large external force V, if the above measures were not sufficient. The reinforced concrete wall
structure may be designed and constructed as an L-shaped retaining wall; the bottom slab large
enough to be loaded with sufficient deadweight force V.
Note:
- Horizontal support for the wall may be partially or fully produced by the lock floor structure, see
section 4.4.3;
- Typically, gravity structures are structures on or with a shallow foundation.
To reduce the bending moments in the wall, several measures are possible:
a. Put the anchor at an efficient position. By moving the anchor down, the span reduces and the span
moment decreases as well. An optimum level of the anchor results in a span moment has the same
order as the support moments.
b. Use more than one anchor.
c. If B is not the result of passive soil pressure, but the reaction force of another structure, B should be
positioned as high as possible, thus reducing the span. B is obviously often supplied by the bottom of
Hydraulic Engineering
Faculty of Civil Engineering 114 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
the lock chamber. The lock bottom slab and opposite lock wall form a system, which may be
optimised, see section 4.4.3.
d. Drive the sheet pile deeper into the soil; instead of a simply supported beam, a beam with a simple
and a fixed support, is a better schematisation for this situation. The anchor is still a simple support,
however, deeper down there is a fixed support. The sheet pile will rotate around point S. Due to the
rotation a passive soil force C is being introduced. Combined with force B the sheet pile is fixed in the
soil; the wall structure is statically indeterminate. The anchor force could be considered obsolete, not
necessary for the stability anymore, however, the anchor generally is not omitted in order to limit the
bending moments and to limit the deformations of the wall.
Note:
- When steel sheet piles are used, they will be covered with wooden posts, or concrete slabs, and
fender beams (regels), to prevent corrosion and damage to wall and ships.
- For steel structures, considering maintenance, preventing corrosion is the key issue. Usually steel
sheet piles have a shorter life span than concrete diaphragm walls.
Hydraulic Engineering
Faculty of Civil Engineering 115 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
A distinction can be made in a water-tight floor, a permeable floor without support function and a
permeable floor that supports the lock walls. In general impermeable structures are rigid. Therefore scour
is not a threat. The three types mentioned will be discussed a bit further, focusing on loads and load
combinations.
Impermeable floor:
The impermeable floor has to be able to resist the two extreme load situations listed below. Usually the
second situation, and the resulting load combination, is governing structural design.
1. Low ground-water level outside and HLD (high locking datum, HSP) inside the lock chamber:
This results in a force in a vertical downward direction which, together with the dead weight of the
floor, has to be resisted by the soil underneath the structure. In case the soil has insufficient bearing
capacity for a shallow foundation piles have to be used.
2. High ground-water level outside and LLD (low locking datum, LSP) inside the lock chamber, or even
no water in the lock for maintenance reasons:
The resulting vertical load is equal to G times the difference between the piezometric level of the
ground-water under the floor and the height of the column of water above the floor, reduced with the
dead weight of the floor.
If the resulting vertical load on the floor is positive, upwards, then the following structural solutions could
be considered:
a. Increase the dead weight of the floor structure by applying a thicker floor or using heavier
material.
b. Supply the floor with anchors or piles. Duly consider the fact that the load on the piles may change
from tension to compression, and vice versa, caused by varying ground-water levels or the
filling/emptying of the lock chamber.
c. Connect the floor with the chamber walls. The walls provide support to the floor if there is a
resulting upward force on the floor; in the other case they transfer vertical downward to the floor.
d. A combination of the solutions a, b and c.
With a high load in upward direction (risk of floatation!) solution b is financially more attractive than
solution a, especially when tension piles are used. Solution c generally is a good option. Nowadays the
requirement that a lock has to be set dry is demanded less frequent than in the past.
In a permeable floor the relation between the permeability of the floor kfl and of the underground kgr is of
importance. Consider the following situations:
1. kfl ≥ kgr
By using a flow net or a finite element program the ground-water flow can be calculated. The hydraulic
load due to ground water flow has to be combined with flows and turbulences, caused by ships or the
filling and emptying system. Next step is to investigate the stability of the upper layer of the floor
structure; the soil or the top stones of the filter have to be cohesive, heavy or large enough to resist
the hydraulic loads.
2. kfl < kgr
Especially when kfl << kgr (in that case the floor is almost impermeable) the total upward pressure has
to be resisted by the floor structure, the bottom soil or filter layers. In fact the situation agrees with a
clay layer above permeable sand layers: there is great risk of hydraulic burst-up. To prevent this, the
clay layer has to be thick enough (to provide a counter load) and has to be of homogeneous
constitution and thickness.
Hydraulic Engineering
Faculty of Civil Engineering 116 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
If a filter is used as lock bottom, groundwater will flow into the lock chamber. If the filter is not working
properly water pressure will built up in the filter and in combination with other hydraulic loads scour will
occur, which might endanger the stability. To reduce groundwater flow or piping, short sheet pile walls
may be used to increase the seepage length, which results in a smaller exit velocity of the groundwater
flow.
This type of lock chamber floor is almost the same as the impermeable floor option, however, in this
option, holes are made in the floor and filled with gravel, so the water pressures under and above the floor
are equal. Consequently, the lock chamber cannot be dewatered, but it is protected against scour; piping
is an issue. If the holes in the floor are large, it might be better to describe the floor structure as a number
of beams, acting as struts stempels) between the walls, with a gravel filling besides or between them.
In any way, this floor type maintains the wall support function, so the lock chamber wall can be more
slender compared to a normal permeable floor.
A stand alone concrete floor of certain minimum thickness is impermeable, but may not be heavy enough
to resist upward water pressures. Increasing the thickness of the floor will solve this problem, usually at
the cost of a large amount of extra concrete and extra excavation with all the related problems. Very thick
floors are generally made of mass concrete (stamp beton) and structural reinforcement is ‘not’ used. (The
thinner the concrete floor, the more need there is to use reinforcement). As a result of the horizontal earth
pressures behind the walls a normal force (compression) will is introduced in the floor, vice versa the floor
provides a support force to the walls. Although stand alone, there is structural interaction.
Quite some (design) effort would be necessary to provide a watertight joint between the floor and the wall
structures. Even in this stand alone version, due to the normal load and floor-wall interaction, bending
moments may be introduced, which result in vertical forces on the wall. To prevent this, a watertight joint
could be designed, which transfers the normal forces but not the shear forces and moments. In a following
alternative the thick gravity floor is replaced by a reinforced concrete floor able to resist bending moments.
However, the bending moment is not transferred into the walls, normal and shear forces are, see Figure
4-73. Water tightness can be obtained by positioning rubber slabs at the contact surfaces between floor
and wall.
Since the bending moment in the floor increases quadratically with increasing lock width, a possibility to
reduce this is the introduction of support moments on the floor. Hence, the joint connection develops into
a full connection stiff concrete joint between the walls and the floor. The continuous concrete cross
section, fully integrated or monolithic structure is the result, see Figure 4-74.
Hydraulic Engineering
Faculty of Civil Engineering 117 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
An additional advantage of this option is that the large weight of the wall is transferred via the floor to the
soil resulting in a more equal distributed load on the subsoil. There will be less problems with peak soil
pressures and settlements and displacements in the soil will be less.
In the above the focus was on the cross section of the lock chamber; now some attention will be paid to the
longitudinal section.
Usually locks are built with expansion joints which separate the chamber into sections with a typical length
of 25-30 meter, see Figure 4-76. The expansion joints allow each block to move independently and
reduce stresses that otherwise might occur due to differential settlement or expansions due to concrete
hardening or other changes in temperature. The expansion joint needs to be water tight, to keep the water
in the lock and to prevent groundwater and soil from coming into the lock.
Figure 4-76 Standard lock with 25 m long Figure 4-77 Monolithic lock
elements and water stops
If the calculated differential settlements are above the limit, the only solution may be to construct the lock
chamber without expansion joints. This joint less monolithic structure results in a very robust structure that
can resist not only differential settlement in general but also local unexpected settlements (e.g. due to
scour), see Figure 4-77. It is not necessary to build the whole structure at once. Construction joints can be
used to separate different segments. Reinforcement can be carried through the construction joints.
A monolithic lock design results in increased internal stresses. Joints normally reduce these stresses by a
small translation or rotation, compressing the (rubber) expansion joint material. The extra internal stresses
Hydraulic Engineering
Faculty of Civil Engineering 118 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
in monolithic design have to be combined with the other loads (water pressure, earth pressure,
deadweight, etc.) and the structure has to be designed for the Ultimate Limit State and the Serviceability
Limit State.
For the future, a properly designed and constructed monolith structure without joints can reduce
maintenance and eliminate major problems with leaking expansion joints that appeared on a regular basis
in the past. [PIANC 2009, Innovations in Navigation lock design]
Retaining wall
structure
Retaining wall
with a deep
foundation
Continuous
concrete cross
section No additional value No additional value
One joint
concrete cross
section No additional value No additional value
C* : Floor option C has the same layout as floor option A, but the lock floor contains holes, so no large
water pressures differences will occur.
Hydraulic Engineering
Faculty of Civil Engineering 119 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The cut-off screens under and besides the lock must be positioned in the same vertical plane; in this way
they form a continuous flange or collar around the structure, in the ground. The top of the screens besides
the lock will b slightly above the local groundwater level. Cut-off screens are constructed from sheet piles
and their length is determined by a hydraulic study. The minimum width of the screens must be equal to
the width of the construction pit used for construction of the lock, because backfilled soil is generally more
loosely packed than the undisturbed soil. For this reason the permeability will be higher and piping a
greater risk.
Leakage through the sheet pile wall must be avoided, so during the pile driving attention must be paid to
the correct interlocking of the sheets.
The connection between the sheet pile wall and the lock floor must be and must remain impermeable.
This may be problematic under the lock bottom. When the lock design is based on a pile foundation, the
soil underneath the floor may settle a little with respect to the lock itself. The embedded cut–off screen will
settle along with it, which results in a gap between the screen and the lock floor, the pipe that has to be
prevented. The solution is to embed or anchor the top of the sheet piling into the floor.
An additional number of small cut-off screens in between the main screens may be necessary to close the
gap under a pile foundation lock. These screens can be relatively short, about one meter, since their only
function is to seal the gap due to settlement.
Hydraulic Engineering
Faculty of Civil Engineering 120 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
When the lock has a shallow foundation a different problem occurs. In this case, settlement of the subsoil
may cause the lock floor to settle more than the sheet piles, so the lock floor will effectively be resting on
the sheet pile wall, introducing undesirable bending moments in the lock floor. This situation can be
avoided by installing a compressible material, e.g. cork or foam plastic, at the top of the sheet piling, see
the sketch for the detail in Figure 4-79
Figure 4-79 Connection cut-off Figure 4-80 Position of the seepage screens in case of an
screen to the lock floor permeable lock chamber floor
The connection between the side screens and the lock wall is usually obtained by casting part of a single
sheet pile into the concrete wall itself. The lock of this sheet pile then sticks out from the wall and forms
the starting point for the rest of the sheet pile screen.
It must be noted that all the above considerations only apply to locks with impermeable floors. When floors
with filter structures are applied, the seepage screens will have to be positioned under the lock heads as
can be seen in Figure 4-80.
The position of cut-off screens influences the upward groundwater pressure. The best location for a cut-
off screen is at the upstream side of the upper lock head. When the hydraulic gradients are large the
seepage length must be extended further and a second screen must be applied. The best position for this
second screen is at the upstream side of the lower lock head. Especially the lower head benefits from a
reduction in upward pressure because it is not supported by an adjacent lock chamber. When the lock is
constructed in a tidal area and the hydraulic gradient changes direction with the tide it is common to use
two seepage screens, one on each side of the lock, even when the gradients are small.
For proper guidance to entering ships, the angle α must be small. However, a small α means a large distance
between the berthing facilities and the lock itself, which leads to a longer lock cycle and smaller lock
capacities. A good compromise can only be found from practical experience and model studies. In the
Netherlands this has lead to a value of tan(α) = 1:6 for inland waterway locks that are mainly used by self-
propelled cargo ships, not by push convoys combinations.
Ships that leave the lock must not be hindered by waiting ships, so the berthing facilities must be
constructed away from the line through the lock walls (see dashed line in Figure 4-81). It is recommended
to allow for some clearance between this line and the sides of the waiting ships. This will increase the
sailing velocities of the outgoing ships, reduce the locking times and improve the capacity of the lock. The
dimensions of the berthing area ( W x L ) are usually equal to the dimensions of the lock chamber ( w x l ).
Hydraulic Engineering
Faculty of Civil Engineering 121 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
In this way all ships that will enter for the next locking are at the shortest possible distance from the lock.
When a large supply of ships is expected the berthing area can be extended.
Lst = Slowing down length (2,5 times the length of Lc = Length of the lock chamber
the design ship) S = Safety margin in between the waiting areas
W c= Width of the lock chamber and the fairway
Figure 4-81 Design of the lock approach
Locks that are also used by push convoys are usually only marginally wider than the convoy (e.g. lock
chamber width 24 m against a convoy width of 22.80 m). In this case a slightly bent and slowly narrowing
guidance wall is applied to improve safety. It must be understood that a push convoy is difficult to
manoeuvre because of its large mass (a four-unit push convoy weighs 8800 tons, compared to 1350 tons
for a common Europe class vessel).
Berthing facilities near sea locks are usually not constructed as a single continuous area, but as a series
of detached berths. In this way the tugboats, that may be needed to assist large sea-going vessels with
entering or leaving the lock, have more manoeuvring space. In this situation the guidance wall will be a
continuous structure because of its function.
continuous structure. The last requirement shows that additional facilities (e.g. gangways, ladders etc.)
may be needed.
Loads:
For berthing or collision forces a flexible structure would be best because larger displacements dissipate
more kinetic energy. For mooring forces a stiff structure would be the best solution.
So, in a way, the impact forces and the mooring forces require contrary solutions. For large ships this has
lead to the development of separated structures: berthing dolphins to absorb impact forces and mooring
dolphins.
Structural alternatives
A common solution in Europe that satisfies these three observations is depicted in Figure 4-83 below.
Figure 4-83 Steel guard wall Figure 4-84 Guidance walls with floating
girders
This solution consists of a number of vertical steel piles that have been driven into the subsoil to provide
the desired degree of resistance. These piles are connected by one or more horizontal steel girders. The
number of girders depends on the possible water level variations. A hardwood fender is constructed in
front of this girder because wood provides a better material to guide ships than steel, because it is more
flexible. When the water level variations are large the fixed steel girders can be replaced by floating
structures, see Figure 4-84
Sometimes sheet pile walls are used as guidance works. These are very stiff constructions, so to avoid
damage to ships a more flexible structure must be placed in front of the sheet piles, for instance a
framework made of azobé (type of wood).
In the USA approach walls are used quite differently compared to Europe. The vessels, in the USA
generally large push convoys, keep in touch with the approach wall, ‘slide or slip’ along the wall, while they
Hydraulic Engineering
Faculty of Civil Engineering 123 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
are manoeuvring into the lock chamber. In Europe the vessels avoid every contact. The different
procedure is reflected in the layout of lock and approach structures. In Europe the guard wall has an angle
with lock axis, see Figure 4-81, in the USA there is no such angle and the face of the approach wall is
flush with the face of the lock chamber wall.
There is an explanation for the typical manoeuvring procedure in the USA. Often the navigation lock is
part of a weir complex in the river and constructed close to one of the river banks. In the approach zone of
the lock the flow pattern of the water is in the direction of the weir, where water discharges, adjacent to the
lock, see Figure 4-85.
The vessels are ‘pulled’ into this flow and
to maintain course, into the navigation
lock, quite some rudder and propeller
action is required. However, the vessels
can not use their engine power because
the push convoy has to be slowed down to
avoid collision with the lock. The approach
wall is a real guidance structure; it pushes
the convoys in the right direction and
prevents them from ending up in front of
the weir.
Figure 4-86 Floating approach wall; Olmsted Figure 4-87 Nose pier of approach wall during
lock USA construction
Hydraulic Engineering
Faculty of Civil Engineering 124 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
5. References
Other literature:
th
- Handbook of hydraulic resistance, I.E. Idelchik, Begel House Inc., New York, 4 Revised and
augmented edition, 2007
- Fluid-structure interaction in case of waterhammer with cavitation, A.S. Tijsseling, Doctoral thesis
Delft University of Technology, 1993
- Elementary Hydraulics, J.F. Cruise, M.M. Sheriff, V.P. Singh, Thomas Nelson, Student edition,
2007
- Water-resources engineering, D.A. Chin, Pearson Prentice Hall, Upper Saddle River, New Jersey,
nd
2 Edition, 2006
- Pipeline design for water engineers, David Stephenson, Elsevier scientific publishing company,
Amsterdam, 1976
- EAU 2004, Recommendations of the committee for Waterfront Structures Harbours and
th
Waterways, Ernst&Sohn Verlag, Berlin, 8 Edition, 2006 (ISBN 3-433-01666-6)
Internet sites:
www.haringvlietsluizen.nl (October 2005)
www.dubo-centrum.nl/projecten/project.php?recID=103 (Oktober 2005)
www.keringhuis.nl/engels (January 2006)
www.canaux-historiques.com/d2m/ouvrage/montech/fiche_ouvrage/fo_00.html#
www.falkirk-wheel.com
http://en.wikipedia.org/wiki/Falkirk_Wheel
www.pancanal.com/esp/plan/estudios/0260-exec.pdf
www.pancanal.com/esp/plan/estudios/0276-01.pdf
www.pianc.org
Hydraulic Engineering
Faculty of Civil Engineering 125 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Hydraulic Engineering
Faculty of Civil Engineering 126 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Appendices
Hydraulic Engineering
Faculty of Civil Engineering 127 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Hydraulic Engineering
Faculty of Civil Engineering 128 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
CEMT Class I
CEMT Class II
≈ CEMT Class II
CEMT Class Va
CEMT Class Vb
CEMT Class Va
CEMT Class Va
≈ CEMT Class IV
Hydraulic Engineering
Faculty of Civil Engineering 129 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
A2 Water Management
Water shortage and salt water intrusion are two locks, if no further constraints are applied. In special
important issues concerning water ‘resource’ situations, where the impact of the filling/emptying
management. These issues will interfere with lock process on the upstream/downstream waterways is
design to an extend that depends on local conditions. relevant (i.e. waves, surges), locks with water saving
basins can be operated faster than standard locks,
Impact of climate changes has to be considered as an as the amount of water which is exchanged with the
important source of uncertainty for the long term water waterway is smaller.
resource planning.
From water resource management point of view, the
A2.1 Water shortage - Quantity optimisation goal is to find a good balance between
In arid regions, areas with a small water supply or in water consumption, pumping costs and the possible
canals, the water consumption of locks can be an transport of contaminants through the lock.
important optimisation goal. It should be considered
that obviously a climate change is taking place, which A2.2 Salt water intrusion - Quality
might be a relevant factor during the lifetime of the Salt water intrusion in inland waterways by locking
lock. ships in a navigation lock induces large problems
when this water is used for drinking water or to
In canals the water consumption of a lock must be sprinkle agriculture areas. Another problem is that
compensated by pumping stations if no natural water the salt water may penetrate in the soil and replace
supplies for the canal are available. This results in the fresh ground water, which would induce problems
high costs for building the pumping stations, for the vegetation.
maintenance and energy supply which depend on the
amount of consumed water. Salt water intrusion is always accompanied by loss of
fresh water. Because salt water has larger density
If the water on the upper side of the lock is also then fresh water, it naturally enters in the lock
needed for other purposes (e.g. drinking water, chamber and replaces partially the fresh water. The
irrigation), water saving can be very economic, as less loss of fresh water is mainly a problem during the
water has to be transported / cleaned / desalinated. It summer, when the need of fresh water is the highest.
must be considered on which side of the lock the
water quality is better and if exchange must be Salt water intrusion problems not only play a role in
controlled. This must be carefully judged, as the the design of navigation locks between the sea and
implications are not obvious. an inland waterway provides salt water intrusion, but
also for locks between a salted inland navigation way
Especially the water resource management of large and a fresh water storage basin.
locks (lengths > 200 m and/or lift height > 15 m) is not
an easy question to solve. European directives (EEC,
1997) require that the friendliest solution from an The amount of salt water intruding on a fresh water
environmental point of view must always be studied, storage basin by a navigation lock, when no
even without considering economical questions. So preventive measures are taken to separate salt and
when we have to consider a large water head, even if fresh water, depends on the number of navigation
the most feasible technical and economical solution is cycles, the size of the lock and the difference in water
to build a standard lock (without saving system), it is levels (lift height).
mandatory to study other solutions (several locks with
reduced water head or the use of water saving Due to the difference in density of salt and fresh
basins), which might increase significantly the building water, currents in the lock chamber will occur during
and operational costs. the navigation cycle. These currents cause forces on
the ships, which have to be considered.
It must be considered that locks with water saving
basins, lock ladders or twin locks (with water To reduce the salt water intrusion and the loss of
exchange between the locks) show a slower fresh water few solutions can be mentioned:
operational speed than the equivalent standard type of
Hydraulic Engineering
Faculty of Civil Engineering 130 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
- Air-bubble-barrier in the lock head to avoid water for navigation locks without separation of salt
exchange of salt and fresh water as the gates are and fresh water.
opened.
- Movable sill on the locks floor to reduce the water 1. Lock Navigation cycle
depth to a minimum for the ships to be locked. A navigation lock between the sea or a tidal river with
- Systems to remove the salt layer during locking by: salt water and a canal with fresh water will be
i) Leveling and transversal exchange considered in the following. The amount of chlorine in
(Duinkerken, NL), the salt water on the seaside of the navigation lock
ii) Leveling and, transversal and longitudinally will be much higher than in the canal-side (fresh
exchanges, waterside).
- Use of multiple lifts,
- Salt water sump (see P R Cardiff [P.R. 10-02]) Consider the navigation cycle at the moment that the
For the description about these systems see gate at the salt-water side of the lock has been
PIANC’1986 1986 on Locks (Section 12), see opened for quit a long time, so the lock-chamber will
attached CD-ROM Directory A3. be completely filled with salt water having the same
density as the water at the seaside.
Besides technical solutions also management
solutions can be mentioned, such as: The gate at the seaside will close and the emptying
- reducing the opening time of the gates, of the lock-chamber starts, discharging salt water to
- reducing the number of lock cycles, the canal when the water-level of the canal is lower,
- in case a lock is equipped with two lock or filling with fresh water when the water-level of the
chambers, a bigger one and a smaller one, use canal is higher.
the lock chamber which fits the best to the ships
to be locked. Empting the lock chamber will bring an amount of
salt water in the canal, which is mixed with the fresh
The above mentioned technical solutions are very water. The density of the salt water in the lock-
expensive and technically complicated. The chamber will not change.
management solutions are not complicated and do
not increase the building costs or maintenance costs. Filling the lock chamber with fresh water, in case of
higher water level on the canal, the average density
One of the best references about Water quality control of the salt water in the lock chamber will decrease.
at ship locks, Prevention of salt and water exchange
is Kerstma et al (1994) in which a number of projects Opening the gate at the canal-side, the salt water in
are described. the lock-chamber will exchange with the fresh water
in the canal by internal flow, with the final result that
Obviously, for the Panama Canal lock project salt the total lock-chamber-content enters the canal and
water intrusion studies, including the required lands as a rather thin layer on the bottom of the
modelling work, were conducted. These studies were canal. The water in the lock-chamber has turned
critical in discarding the use recycling pumped water, fresh.
of one and two lift locks, and the adoption of three lift
locks with water saving basins. Executive summaries The exchange of salt water will be stopped when the
study can be found in/at: gate at the canal-side closes.
http://www.pancanal.com/esp/plan/estudios/0260-
exec.pdf After closing the gate at the canal-side the leveling of
http://www.pancanal.com/esp/plan/estudios/0276- the lock-chamber starts again, empting fresh water
01.pdf on the sea or tidal river when the water level on the
sea is lower, or filling with salt water when the water
level on the sea is higher.
A2.2.1 Salt water intrusion and loss of fresh
water during the lock navigation cycle Empting the lock chamber will bring an amount of
This section presents the lock navigation cycle and fresh water to the sea. This is a large loss of fresh
the calculation of salt water intrusion and loss of fresh water. The density of the fresh water in the lock-
chamber will not change.
Hydraulic Engineering
Faculty of Civil Engineering 131 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
After filling the lock-chamber the gate at the sea-side A2.2.2 Induced flow in the lock chamber
opens and the total amount of fresh water in the lock- A flow is created in the lock chamber due to
chamber will be pushed away by salt water. The difference in density of salt and fresh water during
exchange of fresh water will be stopped of course the navigation cycle.
when the gate at the sea-side closes.
1. Filling and emptying the lock chamber
Ships in the lock-chamber will decrease the amount of When a fresh-water-lock chamber is filled up with
exchanged salt or fresh water with their water- salt water, the salt water sinks to the bottom of the
displacement tonnage. chamber and the fresh water layer stays above the
salt water (Fig. A1)
2. Calculation of salt water intrusion and loss of
fresh water Filling up a salt-water-lock chamber with fresh water,
The formula to determine the amount of salt water the fresh water flows into as a layer above the salt
entering in the canal at each lock cycle is: water layer.
Vsalt = (hs − z d ).blc .llc − Vs (maximum amount) The water flowing into the lock chamber reflects
against the gates and particularly against the bow
- and stern of the moored ships. Due to this flow and
and the mass of CL - ions is:
its reflection, an internal wave is generated with a
( ρ1 − ρ 2 ) large wavelength.
C = V salt (maximum amount)
1 .4 When emptying the lock chamber there is no wave
generated inside the lock chamber, but only in the
The formula for the amount of fresh water entering in approach channel.
the sea at each navigation cycle is:
with:
3
Vsalt = volume salt water m
3
Vfresh = volume fresh water m
3
Vs = volume displacement of m
ships
-
C = mass of CL - ions kg
hs = water-level of salt water side m
hfr = water-level of fresh water m
side
zd = threshold level of fresh m Fig. A1: Lock filling/emptying - Density flow during
water side filling the fresh-water-lock chamber with salt water
zlc = bottom-level of lock- m (above) or the salt-water-lock chamber with fresh
chamber water (below)
blc = width of lock-chamber m
llc = length of lock-chamber m 2. Exchange of salt and fresh water by opening the
ρ1 = density fresh water kg/m
3 gates
ρ2 = density salt water kg/m
3 As soon as the gates are opened the exchange of
salt and fresh water starts due to the density
Hydraulic Engineering
Faculty of Civil Engineering 132 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
with:
3
Qu = discharge of exchanged water m /s
bd = width of lock m
hbi = water-level of fresh water side m
zd = threshold level of fresh water m
side
zk = bottom level of lock chamber m
Cu = coefficient of discharge of -
exchanged water (= 0.2)
ε = (ρ1- ρ2)/ ρ2 = relative difference -
in density
3
ρ1 = density fresh water kg/m
3
ρ2 = density salt water kg/m
2
g = gravitational acceleration (about m/sec
9.81)
2l k
t1 =
ci
Fig A2: Gate Opening - Density flow during exchange
of salt-water-lock chamber with fresh water
Hydraulic Engineering
Faculty of Civil Engineering 133 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
100a
101
Hydraulic Engineering
Faculty of Civil Engineering 134 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The maximum force on a ship caused by the The fresh water on the salt-water-approach
difference in density is approximately: channel will be as a thin fresh water layer upon the
salt water. This thin fresh water layer flows to the
ε (d .b − d s .bs )
2 2 sea and will be mixed with the salt seawater by
F 'r = .d s − k k wind, ship propellers and so on.
2.l s .C b d k .bk − d s .bs The salt water on the fresh-water-approach
with: channel will take the shape of a thin salt water
layer positioned on the bottom of the approach
F’r = relative longitudinal force - channel. This salt water layer extends over a long
(relative to ship tonnage or distance from the lock into the approach channel.
displacement)
ls = length of the ship m The salt water on the fresh-water-approach
Cb = block coefficient (*) - channel is harmful for the agriculture, environment,
bk = width of the lock chamber m fishery, and so on, and should be removed.
bs = width of the ship m
ds = depth of the ship m To remove this salt water layer the best way is to
dk = water level depth m collect it in a deep sink in the bottom of the
ε = (ρ1- ρ2)/ ρ2 = relative - channel and to flush it away with a discharge
difference in density sluice or pumping station.
Another way is to avoid salt water on the fresh-
(*) The block coefficient (Cb) is the ratio between water-approach channel, as much as possible.
the real ship volume under water and the volume This requires special lock systems (see
of a block equals to length x width x depth of the PIANC’1986 Report, section 12)
ship.
Hydraulic Engineering
Faculty of Civil Engineering 135 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
To estimate the ice formation in locks and canals in the locks and canal, a series of field test were
with ongoing traffic and the need for additional heat carried out in Finland. The tests included full scale
Hydraulic Engineering
Faculty of Civil Engineering 136 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The thermal energy needed to melt the ice is With regards to ice formation, the Finnish Maritime
approximately: Administration carried out a major study on the
Saimaa Canal during 2004 - 2005. As a result of
1.5
E1 = Tw*v *k1*A*b (W/m) where this study this administration created an ice
formation simulation model for the Saimaa Canal.
Tw = temperature difference between the flowing
o
water and ice melting point ( C) The study consisted of field measurements in
v = flow velocity (m/s) different canal ice conditions with different canal
k1 = trough roughness factor heat capacity. These measurements were the basis
1.5 3.5 o
A = constant 4,800 (W*s )/(m * C) in creation of an ice formation simulation model,
b = width of the bottom of the brash ice layer (m) which was used to verify the previous theoretical
k1 = (1+4*h1)*C=1 calculations of the required heat input needed in
h1 = mean thickness of the brash ice layer (m) controlling the ice situation in the canal.
C = equalizing factor (h1/h1max)
h1max = mean maximum thickness or local The simulation consisted of three traffic situations
maximum thickness of the brash ice layer (one, two or four ship passages per day). The
results pointed out that the designed 120 MW heat
The vessel passages also consume the thermal outlet (discharge of warm water with 1 km intervals)
energy when it rotates the warm water melting the is sufficient in controlling the ice situation. During
ice. This energy can be estimated with formula: mild and normal winter vessels with 1A-ice class
could operate almost without icebreaking
E2 = k2*Tw*Q (W/m) where assistance. During severe winters icebreaking
assistance is needed and extreme winters the use
k2 = vessel factor (0.5 – 2.0) of convoys is needed. The simulation model also
o
Q = constant (50 MJ/ C*m a vessel passage) pointed out that short traffic stops effectively reduce
the formation of ice. The model also pointed out
The amount of ice melted between the ice that the melting effect in between the warm water
breakings is approximately:
Hydraulic Engineering
Faculty of Civil Engineering 137 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Hydraulic Engineering
Faculty of Civil Engineering 138 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
To resolve this problem a Naviduct will be built on the intersection between ship- and road traffic. These
functions have to be combined. The Naviduct is an aquaduct which is able to function as navigation lock.
In this way the capacity of the road and waterway will be increased.
Hydraulic Engineering
Faculty of Civil Engineering 139 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
IJsselmeer Markermeer
Hydraulic Engineering
Faculty of Civil Engineering 140 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
A risk analysis has been performed which states that a protection of the lock gates against collision is not
necessary. During periods of frost and ice, it should be able to operate the locks. The design life of the
construction is 100 yrs, the gates and other replaceable elements must be designed cost efficiently.
The level of the gates is at NAP +2.00, the level of lock at NAP +2.65 m. The height of the existing
Houtribdijk is NAP + 6.40 m. A new dike will be constructed at NAP + 4.00 m. At a water level exceeding
NAP+ 0.70 m or at water level differences larger than 1.00 meter all gates will be closed.
A4.3 Design
Excavation works
Costs associated with excavation work (grondverzet) account for a large factor in the budget. For this
reason the lock will be located as much to the North as possible, against the Houtribdijk. The orientation in
East-West direction depends on the chosen steepness of the road (5%). The orientation in North-South
direction is chosen in a way as to limit the length of the breakwater (leidammen) and ensure sufficient
manoeuvring space for the vessels in the waiting and berthing area. This resulted in an orientation which
0
makes an angle of 10 to the north as shown in Figure App3: 4.
Hydraulic Engineering
Faculty of Civil Engineering 141 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Figure App3: 4 Sheetpiles (damwand) around the artificial polder to construct the Naviduct
The design is made in such a way that the road and navigation lock is located in an artificially created
polder. The lowest level, consists of the road, is at an elevation of NAP -10.50 m.
The weak soil layer is excavated to a depth of NAP -11.50 and replaced by sand. The remaining soil layer
with a thickness of 1.50 meter remains to function as a vertical barrier between the different water levels
(capillary height). The artificial polder has sheet piles which act as a barrier in horizontal direction. The
sheet piles are founded in the clay layer. The weak layers near the Houtribdijk are dredged away.
The gates should operate independently. To minimize the width the island between the 2 lock chambers
should be as small as possible. Hence, the hydraulic gate driving machinery has been positioned behind
each other, parallel to the lock axis, as is illustrated in Figure App3: 5.
Hydraulic Engineering
Faculty of Civil Engineering 142 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
The lock head has been designed around the selected gates. A cross section is shown in Figure App3: 6.
Hydraulic Engineering
Faculty of Civil Engineering 143 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
Lock chamber
The lock chamber differs from conventional navigation locks because the lock chamber is constructed
above a road. Demands on the water retention of chamber floor and bottom are therefore high. In addition
to these demands the lock chamber retains soil in the artificial polder.
The slice in the middle of the lock chamber is one big monolithic construction consisting of the lock
chamber, pump room, and road intersection. The pumps are installed for the drainage of the artificial
polder.
Hydraulic Engineering
Faculty of Civil Engineering 144 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
A4.4 Construction
The following construction methods were taken into consideration:
The use of a construction pit was selected since this proved to be the most cost efficient.
Hydraulic Engineering
Faculty of Civil Engineering 145 3/3/2011
Delft University of Technology
CT 3330 Hydraulic Structures Locks
A4.6 As-built
The construction of the Naviduct started in 1999 and was finished in 2003.
Hydraulic Engineering
Faculty of Civil Engineering 146 3/3/2011
Delft University of Technology