CV=EV-AC=2100-200=100
SV=EV-PV=2100-2400=-300
3 End of period 4
Task Budget % completEV AC PV CV SV
A 400 1 400 300 400 100 0
B 2400 0.5 1200 1000 800 200 400
C 1500 0.33 495 500 600 -5 -105
D 1600 0 0 0 0 0 0
E 900 0 0 0 0 0 0
Total 2095 1800 1800 295 295
End of period 8
Task Budget %completeEV AC PV CV SV
A 400 1 400 300 400 100 0
B 2400 1 2400 2200 2400 200 0
C 1500 1 1500 1500 1500 0 0
D 1600 0.25 400 300 0 100 400
E 900 0.33 297 300 300 -3 -3
F 600 0 0 0 0 0 0
Total 4997 4600 4600 397 397
So CPI=EV/AC =4997/4600=1.086
SPI=EV/PV=4997/4600=1.086
So 1.086 worth of work is planned to date is for each 1 dollar spent . Its under budget
Also schedule index of 1.086 for each 1 dollar spent. So project is ahead of schedule.