Weekly Project Management Status Report Template

Quest Construction is overseeing a 50 km asphalt road construction and widening project in Primland, Virginia that is currently 40% complete. The project is on schedule to be finished by July 2030 despite some weather delays. Expenses amount to 40% of the $32 million budget so far. Risks include further weather issues and potential equipment malfunctions.

Uploaded by

Leo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
85 views5 pages

Weekly Project Management Status Report Template

Quest Construction is overseeing a 50 km asphalt road construction and widening project in Primland, Virginia that is currently 40% complete. The project is on schedule to be finished by July 2030 despite some weather delays. Expenses amount to 40% of the $32 million budget so far. Risks include further weather issues and potential equipment malfunctions.

Uploaded by

Leo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Quest Construction

Asphalt Pavement Project


Status Report

Prepared by

Peter Bun
[email protected]

November 26, 2029


Executive Summary

This report is prepared to outline the progress of the current asphalt pavement
in a road project in Primland, Virginia, set to be completed on July 27, 2030.
The contractor did not encounter major challenges apart from weather
interruptions since it has been raining hard these past few days. The total
actual project progress is around 40% with a total expenses rounding to 40% of
the allocated budget.

The Project

The Project

Quest Construction is currently overseeing the asphalt pavement in road


construction and widening in Primland Virginia. The construction started last
July 27, 2029, and is expected to be completed on July 27, 2030.
 

Scope

The main project objective is to provide improved road access to residents in


Primland, Virginia. The project involves the construction of 50 km improved
rural roads. The project’s major deliverables cover construction completion,
quality inspection, and turnover on the scheduled project completion date.
Milestones

PHASE DESCRIPTION STATUS


Programming and feasibility,
Project Preparation
Design Development, Completed
Phase
Contract Documents
Construction & Construction & inspection
In Progress
Completion Phase of roads

Costs

COSTS BUDGET ACTUAL COSTS TO DATE


Materials &
$2,000,000.00 $ 800,000.00
Equipment Rental
Worker Wages $30,000,000.00 $12,0,000.00
TOTAL $32,000,000.00 $12,800,000.00

Risks

During the project execution, the risks encountered were:

1. Weather interruptions
2. Equipment malfunctions

Action Plan
RISK ACTION ASSIGNED TO
Plan on alternative actions:
Weather interruptions Melony Cortes
working in two shifts
Subject all equipment to repair
Equipment malfunction Melony Cortes
and maintenance
To Use This Documents
The text inside the brackets which is highlighted is meant to be edited with your
text. This is the way you can edit the document as given below:

To Edit Text:
Point the mouse where you want to edit and delete the sample text and then you can
add your text.
You can change the size, font & color of the text in the Main Tab: Home

To Edit Table:
Point the mouse in the table where you want to edit and delete the sample text and
then you can add your text.
You can adjust the row & column size of the table in the Main Tab: Layout

To Edit Chart:
Select the chart which is going to edit and then
In Main tab: Design -> Edit Data
It will open the excel sheet where you can edit the values of the chart