20110530125505!2006 09 21 FINAL Ethiopia Biogas Feasibility Report
20110530125505!2006 09 21 FINAL Ethiopia Biogas Feasibility Report
20110530125505!2006 09 21 FINAL Ethiopia Biogas Feasibility Report
Dr Getachew Eshete
Dr. Kai Sonder
Felix ter Heegde
May 2006
0.1 Summary
Rural domestic energy supply in Ethiopia is (virtually) entirely biomass based. In
combination with the increasing pressure of the rural population, this has led to rapid
depletion of natural resources and degradation of the environment in large areas of the
country.
This study researched the extent to which essential conditions for large scale
dissemination of domestic biogas are present. It concludes that there is a significant
technical potential for domestic biogas. In the four studied regions (Amhara, Oromia,
SNNPRS and Tigray) this potential is estimated to be between 1.1 and 3.5 million
households.
But the team also identified important constraints: the low level of disposable income of
most rural households prohibits any significant investment; the scarce availability of
process water endangers proper plant operation; the (very) limited rural dissemination
infrastructure in combination with the scattered population pattern make dissemination
activities laborious and (thus) expensive; the gender imbalance in decision making at
household level will increase the threshold for the investment, and; the low awareness
of alternative energy technology in general and domestic biogas in general will
necessitate a large investment in promotion work.
Clearly, despite its promising features and the significant technical potential,
implementation of a large scale domestic biogas programme will not be “plain sailing”.
The team proposes a pilot domestic biogas programme in four regions over a period of
5 years, aiming to support the construction of 10,000 installations. In addition to the
direct benefits the programme is expected to have, the sizeable pilot will provide better
insights of the exact nature of Ethiopia‟s rural domestic energy sector and dissemination
constraints and allow the programme to adjust its implementation strategy accordingly.
Total programme costs, including all hard and software, have been budgeted to
approximately € 11 million.
ii
Section 2 starts with the study set up. It furthers with the main study findings regarding
installations visited, functionality, economics, operation, dissemination modalities and
lists the organizations active in the field of domestic biogas.
Section 3 addresses the main conditions for large scale dissemination of domestic
biogas, including technical, financial, social and institutional aspects. From a mapping of
Ethiopia‟s livestock data and an interpretation of data regarding the availability of
process water, a first estimate of the technical potential for domestic biogas is offered.
Section 4 presents the lessons learnt and the recommendations based thereon. Some
main programme design considerations –technical design, sizing, costs and benefit of
biogas, subsidy and credit are addressed in more detail. Section 4 ends with a brief
reflection on opportunities of CDM as a co-financing mechanism.
Section 5 drafts the first outline of an activity schedule and budget for a possible pilot of
a large-scale biogas programme in Ethiopia. The section concludes with listing some of
the opportunities and threats of such a programme.
0.2 Acknowledgement
Ethiopia is a large country of great social and geographic variation and domestic energy
–including biogas- is a multifaceted topic. Consequently, for the study our team leaned
heavily on the sympathetic cooperation of a large number of households and
professionals. Everywhere our questions were answered elaborately, where we
overlooked relevant issues our hosts filled us in anyway, and we were provided with a
wealth of background information and documentation.
The team is indebted to all the persons and organizations that took time to assist us and
it was a privilege to have this many knowledgeable and experienced people sharing
their understanding of domestic energy and rural development with us.
Thank you al very much for your contributions and cooperation; it provided the study
with meaning and made doing the study a true pleasure.
Despite all your input, there will likely be errors in the report. Obviously, those are fully
our responsibility.
Addis Abeba,
June 2006.
iii
0.3 Table of content
Section Chapter Title Page
1 Introduction & country background
1 Introduction 2
1.1 Recent history in brief 2
1.2 Current political situation 3
2 Country background 3
2.1 Poverty traps 4
3 Climatic conditions 6
3.1 Rainfall 6
3.2 Drought 6
3.3 Temperature 7
4 Agriculture and animal husbandry 8
4.1 Agriculture 8
4.2 Animal husbandry 10
5 Energy demand & supply, policy and plans 11
5.1 The primary energy resource base 11
5.2 The macro perspective 13
5.3 The micro perspective 15
5.4 The energy sub-sector institutional set-up 17
5.5 Domestic energy in summary 18
6 Biogas 19
6.1 Benefits of domestic biogas 19
6.2 Biogas & Sustainable Development 20
6.3 Biogas & the UN Millennium Development Goals 21
6.4 Biogas & PASDEP 24
6.5 History and current status of domestic biogas in Ethiopia 25
2 Study findings 26
1 Study objectives 27
1.1 Methodologies 27
1.2 Limitations 28
2 Study observations 28
2.1 Types of installations visited 28
2.2 Functionality 29
2.3 Economics 31
2.4 Operation 33
2.5 Dissemination modalities 39
2.6 Policy and strategy 40
2.7 Organizations active in the biogas sector 41
iv
3.3 SNNPRS 55
3.4 Tigray 56
3.5 Summary technical potential 56
4 Design considerations 57
1 Lessons learnt 58
1.1 Technical issues 59
1.2 Operational issues 60
1.3 Economic issues 60
1.4 Dissemination issues 60
1.5 Policy issues 61
2 Recommendations 62
2.1 Sectoral, market oriented approach 62
2.2 Pilot of reasonable size 62
2.3 Investment costs 63
2.4 Technical aspect 63
2.5 Specific recommendations for SNV-Ethiopia 63
3 Some particular considerations 65
3.1 Installation design 65
3.2 Appliances 66
3.3 Plant size 67
3.4 Investment costs 67
3.5 Costs & benefits of domestic biogas 69
3.6 Subsidy 71
3.7 Credit 72
3.8 Biogas & the Clean Development Mechanism 73
v
0.4 List of annexes
0.5 Abbreviations
vi
MFI Micro Finance Institute
MoFED Ministry of Finance and Economic Development
NGO Non Governmental Organization
PPP Public Private Partnership
REF Rural Energy Fund
SME Small and Medium Enterprise
SNNPRS Southern Nations and Nationalities People‟s Regional State
UNDP United Nations Development Programme
(US) $ (United States) Dollar
WB World Bank
WBISPP Woody Biomass Inventory Strategic Planning Project
0.6 References
001 2001 Kellner, C: Biogas Technology. Technical paper developed for the GTZ
Land use planning and resource management project in region (LUPO).
002 April 2001 Kellner, C.: First steps of an Ethiopian Biodigester Standard.
003 May 2004 Eshete, G et al: Final report of the identification study on renewable
energy and energy efficiency in Southern Nations and Nationalities Peoples
Regional State and Ethiopia.
004 January 2005 FAO: Global information and early warning system on food and
agriculture, special report crop and food supply assessment mission to
Ethiopia.
005 CIA world fact book (www.cia.gov/cia/publications/factbook/).
006 January 2005: USDA Production estimates and crop assessment division
007 October 2005: Ministry of Finance and Economic Development. Ethiopia:
Building on Progress: A Plan for Accelerated and Sustained Development to
End Poverty (PASDEP).
008 January 2006 Ministry of Energy and Mines, Ethiopian Rural Energy
Development and Promotion Centre: Indicative dissemination strategies of
biogas energy in Ethiopia (based on technical and socio-economic
assessment), unpublished report.
009 Metaferia Consulting engineers, for the Federal Democratic Republic of
Ethiopia, Ministry of Economic Development and Cooperation Environmental
and social analysis food security project No. ENIBER 2001
010 December 2004, UNESCO: National Water Development Report for Ethiopia.
011 June 2005, Guday Emirie: Early marriage and its effect on girl‟s education in
rural Ethiopia, the case of Mecha woreda in West Gojjam, North Western
Ethiopia, Master Thesis.
012 December 2004, UNESCO et al: National Water Development Report for
Ethiopia.
013 August 1995, Melis Teka Nega: Biogas as Rural Household energy Option –
the Case of Ethiopia, Master Thesis.
014 January 1998, Mulat Demeke et al, Grain Market Research Project:
Determinants of fertilizer use in Ethiopia
vii
0.7 Exchange rates
1 Euro 10.41 Ethiopian Birr
1 Euro 1.19 US Dollar
viii
Report on
the feasibility study of a national programme for
domestic biogas in Ethiopia.
Section 1
Introduction and background
1 Introduction and background Page 2
1
Carol Beckwith and Angela Fisher, African Ark, 1990.
2
Sarah Vaughan, Ethnicity and power in Ethiopia, 2003
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 3
having fought a war with the regime of Mengistu Haile Mariam, the Derg, for over a
decade. As a result, Eritrea became an independent country, and Ethiopia a federation
of reasonably independent regions (the Federal Democratic Republic of Ethiopia).
Last year‟s election in May, however, threatened to change the political climate. The
government, expecting voters to confirm their position, appeared to be surprised by
significant popular support to the opposition. With some delay, the polling results now
seem to be largely accepted, with new voting in a couple of hundred polling stations.
2 Country background.
With a total land area of 1.1 million km2, Ethiopia is about twice the size of France and
the tenth largest country in Africa. It accommodates Africa‟s third biggest population,
currently some 73.1 million people, at a population growth rate of over 2.3 percent per
annum3.
500
-
Eritrea Ethiopia Kenya Somalia Sudan Tanzania Uganda
3
CIA World Fact book
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 4
20%
Ethiopia is one of the least developed 10%
countries; not only in the world, but also in the 0%
region it is scoring amongst the poorest: Eritrea Ethiopia Kenya Somalia Sudan Tanzania Uganda
Over this period, the lion share of ODA was Social dev
5%
Education
3%
allocated to humanitarian and relief aid (33% on Energy
average) against only 6% for agriculture and 7%
Investment in human capital: Poverty and low investment in human capital present
another type of self-perpetuating dynamic. Investing in education may be prohibitive for
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 5
poor households, due both the direct costs, as well as the fact that all members need to
contribute to the family‟s income, including time-consuming tasks such as collecting
water and firewood. Even if returns of education are high, the inability to finance that
initial investment means that there is under-investment. Without significant increases in
productivity it is difficult for capital to be accumulated, so that returns to unskilled labour
are unlikely to grow. Poverty and low education, therefore, reproduce themselves in
future generations.
Low-Risk / Low Return: Small farmers, who constitute the bulk of the population, are
often caught in production of low-risk/low-return food grains. With insufficient cash
funds, and unpredictable outcomes, they cannot afford to take the risk of diversifying
from subsistence food production into potentially higher-return activities (such as
growing cash crops for market), or of spending their limited cash on purchased
agricultural inputs, because if they fail – either because of crop failure, price collapse,
or failure of demand, they will not have either the basic food they would otherwise have
produced, nor the cash to purchase it, and their families will go hungry.
Early-Childhood: Nutrition offers a similar story, with malnutrition very early in life
affecting long-term mental and physical development, and thus limiting lifetime potential
and productivity, and creating a low-income, low-consumption household in the next
generation
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 6
Annual rainfall
3 Climatic conditions.
3.1 Rainfall
The country has a tropical monsoon climate.
Topographic differences –central highlands vs
lowlands- result in significant climatic variety
and three distinct rainfall regimes. In general,
precipitation ranges from 800 – 2000 mm per
annum in the highlands (>1500 m) to less than
200 – 800 mm per annum in the lowlands.
3.2 Drought.
Ethiopia is a country where some 80 percent
of the population depends for its livelihood on
rain-fed agriculture, yet much of the good
topsoil - more than two billion tons a year -
gets blown away or washed down the Blue
Nile River to Egypt. Periodic droughts have
been Ethiopia's lot for hundreds of years. In
recent years droughts are becoming more
frequent and severe. A century ago the country suffered a drought every 10-15 years.
Today they come with alarming regularity every five years or less. Although the drought-
caused famine of 1984-85 remains well known, less serious but nonetheless significant
droughts were observed in 1972-74, 1975-76, 1987, 1988, 1990-91, 1992-93, 1994-95,
1997-98, 2001-02 and 2002-03.
While global climate change may have something to do with increasing the frequency
and intensity of drought in the country, other factors have also contributed to making
Ethiopians more vulnerable to erratic or scarce rainfall. A high population growth rate,
4
FAO crop and food supply assessment mission report, January 2005
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 7
appears to be rising5. 0
1988 1990 1992 1994 1996 1998 2000 2002 2004 2006
3.3 Temperature.
Ethiopia features extremely varied climatic conditions from cool to very cold in the
highlands where most of the population inhabits, to one of the hottest places on earth at
the Dallol Depression.
Most of Ethiopia was supposed to enjoy a tropical climate for its proximity to the
equator, but, due to the fact that most of the country‟s land mass stands over 1,500 m
(4,920 ft), this is not the case.
20 8
rain days
near freezing to 16O Celsius. This is 15 6
5 2
vegetation occurs.
0 0
Woyina Dega (Temperate Zone)-Areas Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Avg MAX temp Avg MIN temp Avg rain days
between 1,500 and 2,600 masl where
temperatures range from 16O Celsius to Gondar temperature and rain
30O Celsius. This is where most of the 35
30
9
8
population lives. 7
temperature oC
25
6
rain days
Qola (Hot Zone)-Areas below 1,500 masl 20 5
15 4
with both tropical and arid conditions 10
3
general term that refers to the extreme Avg MAX temp Avg MIN temp Avg rain days
form of Qola.
Awassa temperature and rain
35 18
30 16
The graphs provide an impression on annual 14
temperature oC
25
12
temperature and rainfall development in three
rain days
20 10
distinct areas. 15 8
6
10
4
5 2
0 0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Avg MAX temp Avg MIN temp Avg rain days
5
December 2004, UNESCO et al National Water Development Report for Ethiopia,
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 8
Division of
agriculture, which contributes 40.1% of the industry
country‟s gross domestic product (GDP), 90% agriculture
of the export earnings and 80% of the services
employment. The role of industry in the
GDP
industry
economy has always been very small. agriculture
Currently, the contribution of industry to GDP is
0% 20% 40% 60% 80% 100%
about 11%, and its share to employment is less
than 5% of the total labor force.
[Mtonnes]
followed by pulses, oil seeds and chat. Crops 150.0 pulses
1,500,000
The average landholding is small; current
estimates mention about 1 ha per holding, and 1,000,000
under Ethiopian farming conditions often
insufficient to sustain the household ref014. The 500,000
The sector is nearly totally dependent on Share of arable land under irrigation
50%
rainfall, with only 2% of the total arable land 45%
6
Source CSA Agricultural Sample Survey 1995/96 in ref 014.
7
CIA World fact Book
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 9
ri
ar
ay
a
a
i
la
ra
iya
uz
al
ra
aw
eb
l
NP
Af
ha
be
gr
um
m
Ha
Ab
D
So
Ti
Am
SN
sub-sector is not only the result of the low
am
ro
re
O
s
G
ul
Di
di
ng
Ad
ha
adoption rate of the many yield enhancing
s
ne
Be
technologies, but also the poor promotion and
marketing schemes, Government policy Jan 28 2006 Ethiopia sees 15.1% increase in agricultural
towards tenure security and agricultural terms production in 2005-06
Addis Ababa - Ethiopian Prime Minister Meles Zenawi says the
of trade (price fluctuations between harvest of country's agricultural production indicates a 15.1 per cent
20% (teff) to over 50% (sorghum) are not increase during the current harvest season and its overall
economy would register a 'double-digit' growth at the end of the
exceptional). current fiscal year ending in June, the local press reported
Saturday.
Chemical fertilizer is recognized as one of the key means to increase agricultural yields.
Fertilizer use has been promoted under the previous as well as the current governments
with distribution systems, extension and credit. For the 1995/96 cropping season, the
average national application was 35 kg/ha for all holdings and 95 kg/ha for fertilizer-
using holdings ref014. This must represent a steep increase for that time, as slightly
earlier documents still mention an average national dosage of 10 kg/ha ref013.
Nevertheless, the application isstill far below the nutrient needs of the heavily cropped
soils.
8
Dr Alemneh Dejene, FAO, The Nexus of natural resources degradation, food security and poverty in the Ethiopian Highlands:
Towards sustainable agriculture and rural development, November 200
9
This rate produces a marginal rate of return of 100%
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 10
Rapidly growing population in the face of limited agricultural productivity, very low rural
incomes, ever-increasing fragmentation of agricultural land and consequent
environmental degradation are some of the major problems from which the nation is
trying to extricate itself.
Dairy production.
Almost 99% of the cattle, sheep and goat population are
indigenous. The current national production of milk from cattle is
about 400 litres for a lactation period, whereas cross-breeds (1%
of the whole population) give 3000 litres over the same period.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 11
Key issues are the availability, the relative cost The National Energy Policy in Ethiopia aims to satisfy the basic
(energy) needs of all households. The energy policy recognizes
of this energy, the sustainability and the the importance of energy as a means for sustainable development.
environmental acceptability when harnessed Key areas include:
Priority development of hydro and traditional energy
for productive use. Except for petroleum, which resources.
is wholly imported, Ethiopia is endowed with Diverse and enhanced biomass based technologies (biogas,
agricultural residue briquetting, ethanol production).
many types of indigenous energy resources. Energy conservation technologies and measures.
Renewable energy sources such as hydro,
Vital to the development of the energy sector are:
solar, wind, etc. are available in reasonable Self-reliance on indigenous resources.
quantities though they remain largely Formulation of conducive sector regulations and directives.
untapped. Ensuring of environmental sustainability.
10
Dr Alemneh Dejene, FAO, The Nexus of natural resources degradation, food security and poverty in the Ethiopian Highlands:
Towards sustainable agriculture and rural development, November 2003
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 12
Wind power: The wind energy potential of the country varies from place to place and
from season to season, as the energy is absolutely seasonal and dependent on the
velocity. In the western part of the country, the average wind speed at 10m a.g.l. is
3.5m/s. In the Rift Valley and eastern part of the country, the average values range
between 3.5-5.5m/s (CESEN, 1986). From this wind speeds an estimated power level of
65W/m^2 and 200W/m^2 can be obtained. In addition, an average wind speed of
6.7m/s, at 10masl was observed in recent wind speed measurement carried out in the
Mekele area. This justifies that the location is suitable for an economic operation of wind
speed turbines (Benjamin, 2004).
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 13
Coal: A number of coal deposit sites have been identified in certain parts of the country.
The total coal deposit of the country is estimated about 178 million tons (Tibebe M.,
Haile Michael F., 2003). The deposit quality varies from high quality to lignite category
with low heating value, high ash content and low quality, but some of them can be
exploited for household and industrial use as alternative source of energy.
700000
Energy consumption
5.2 The macro perspective. 600000
Petroleum
Electricity
The energy sector in Ethiopia is also one of the 500000
Charcoal
Dung
least developed in the world. The country‟s Crop residues
400000
annual energy consumption amounts to ~ Woody biomass
[TJ]
746.000 TJ, equalling 130 GJ per capita per 300000
0
Urban hh Rural hh Agriculture Transport Industries Services
200
150
100
In line with the above, the per capita electric 50
11
World Bank 2002
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 14
Dung Charcoal Electricity Petroleum
8% 1% 1% 5%
for residential use with the main purpose being Transport Industries Services Urban hh
4% 4% 3% 7%
cooking and baking. Agriculture
0%
tons.
Including dead wood as fuel, there is a sustainable biomass supply of some 60.9 million
tons. This suggests there is no overall deficit but that the problem of deficits is local and
not national. The margins, however, are very small, as witnessed by the constinuously
declining forest cover of the country
forest cover
15500
Out of 482 Woredas surveyed, 336 were 15000
y = -140.93x + 295562
12500
problem that cannot be ignored in reforestation 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006
programmes.
12
Aklilu Dalelu (PhD), Rural electrification in Ethiopia: Opportunities and Bottlenecks 2001(?)
13
World Bank ISPP, 2003.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 15
The result is a delicious but very energy-intensive dish. Fuelwood consumption was
reported to be over 700 kg per capita per year (a WB/UNDP assessment from 1984
mentioning 2 kg/cap/day for cooking only ref 013), whereby metads are often fired with
branches, leaves and twigs (BLT) and agricultural residue.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 16
As a result, the cost of domestic energy is high and rapidly increasing. In many parts of
the country dung cake and agricultural residue is (rapidly becoming) a commercial
energy source, traded on markets. At places, air dried dung cake can sell for as much
as ETB 1 per piece of ~ 250 grams and families storing dung cakes for sale are not an
exception in large parts of Orromia, Amhara and Tigray.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 17
The Ministry of Water Resources: Responsible for formulating national sectoral policies
and strategies concerning the protection and utilization of water resources, issuing
permits to construct and operate water works, determining the conditions and methods
required for the optimum allocation and utilization of water that flows across or lies
between more than one regional government. The Ministry of Water Resources has
also responsibilities in the study, design and supervision of medium-large scale
hydropower projects.
The Ministry of Infrastructure: The Ministry was established in 2001, and one of its
responsibilities is to look into the expansion of the energy development in the country
and promote the growth and expansion of the country's electric energy supply. It also
supervises the activities of the Ethiopian Electric Agency and the Ethiopian Electric
Power Corporation.
The Ethiopian Electricity Agency (EEA): The agency was established in 1997.
According to proclamation No. 86/1997, the objective of the Agency is to promote the
development of efficient, reliable high quality and economical electricity services. The
EEA is the government‟s regulatory body ongeneration, transmission, distribution and
sale of electricity are carried out in accordance with the stated proclamation.
The Ethiopian Electric Power Corporation (EEPCO):The Ethiopian Electric Light and
Power Authority (EELPA), the sole Government agency since its establishment in 1956
was responsible for generating, transmission, distribution and sales of electric energy
throughout the country on the principles of commercialization and decentralization of
electricity nationwide until it was restructured and reorganized in 1997 and became a
public company called EEPCo (Ethiopian Electric Power Corporation) with its board of
management designated by government.
The Ethiopia Rural Energy Development and Promotion Centre (EREDPC): Established
in 2002 with the objective to create an enabling environment for the development and
promotion of rural energy resources and technologies. It is thus responsible among
others, to identify the energy resources suitable for the rural areas, study the energy
demand, supply and consumption patterns of the rural areas, evaluate the social,
economic and environmental impacts of using various energy sources and
technologies, raise the awareness of the rural community and provide trainings
concerning the production, distribution, utilization and conservation of energy.
The Rural Electrification Fund (REF): Established in 2003 with the objectives to provide
loans and technical services for rural electrification projects on renewable energy
sources carried out by private operators, cooperatives and local communities as well as
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 18
to encourage the utilization of electricity for production and social welfare purposes in
the rural areas. The Fund is to be operated by the Rural Electrification Board and an
Executive Secretariat. The Secretariat is responsible among others, to review
applications from rural electrification project sponsors and decide upon them based on
the criteria set by the Board, sets out criteria for the selection of Trust Agents, prepare
directives and selection criteria and procedures for the issuance of loans, promote and
support access to and productive use of electricity in the rural areas, as well as facilitate
and co-ordinate the rural electrification programme activities with other rural
development programmes.
As a result:
Fuelwood is over-harvested in many areas, contributing to deforestation of
already ecologically sensitive areas,
Fuelwood and charcoal have been and are rapidly becoming more expensive.
Households (and to a large extend institutions) cope by substituting fuelwood
with dung cake and agricultural residue.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 19
Animal dung and night soil is collected regularly and fed into the biogas plant, this:
reduces pollution: that leads to a cleaner farm environment;
reduces human and animal disease: by improving sanitary conditions related to
bad sanitation and polluted surface water for both the household and the greater
catchment-area, and;
reduces greenhouse gas emissions: depending on the traditional manure
handling, the improved manure management system can significantly reduce
GHG emissions.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 20
reduces fuel expenses: traditional domestic fuels increasingly become part of the
formal economy. Biogas significantly decreases consumption of these traditional
sources;
increases opportunities to use appliances: such as gas lamps and water heaters;
reduces greenhouse gas emissions: from the conventional energy sources;
reduces deforestation: by reducing the demand for firewood;
provides income generation opportunities: by providing an energy source for
technologies and activities such as incubators, kilns, lanterns and cooking flame
that is a new resource or more cost effective than previous sources.
The residue of the anaerobic process - bio-slurry-, is a potent organic fertilizer. When
used in this way it can:
provide a superior organic fertiliser: in terms of available nutrients and soil
texture, increasing agricultural yields with 20-40%.
provide a catalyser for composting other agricultural waste: Applying this practice
increases the amount and quality of organic fertilizer;
improve handling safety: of residue due to the fact that the process of digestion
followed by composting makes handling of the residue much safer from a
hygienic point of view;
reduce chemical fertiliser costs of farmers: by reducing the amount of synthetic
fertiliser used;
reduce greenhouse gas emissions: through avoiding the application and
production of synthetic fertiliser
enables farmers to participate in animal husbandry in areas in which discharge
regulations would otherwise have been prohibitive: anaerobic digestion reduces
odour and environmental load resulting from livestock holding.
These benefits, although not all equally tangible, do not only profit the investor, but have
an impact on the community at meso and macro levels as well. (See also the biogas
tangibility matrix in Section 4.3)
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 21
ways.
Substitution of petroleum products will reduce the countries foreign exchange
demand.
Application of bio-slurry increases the yield and reduces the need` -and
expenses- for synthetic fertilizer.
A vibrant biogas sector creates significant employment and related economic
activities, particularly in rural areas.
Reduced disease (human and animal) can improve productivity.
MDG 1 Eradicate extreme poverty and Biogas and the World Summit on Sustainable Development
hunger. As a follow-up to the Rio Summit of 1992, the World Summit on
Target 1: To halve extreme poverty Sustainable Development was held in Johannesburg in 2002.
Energy was highlighted as a key topic for discussion as it was felt
In general, households who install biogas are that there had not been enough focus on it at the previous summit.
not amongst the poorest of the poor due to the As with the previous Plan of Implementation, waste management,
pollution control and social sustainability were highlighted.
fact that for a biogas plant to function a
household must have a minimum number of The Plan of Implementation states that about two billion people, or
one third of the world's population, presently lack access to
animals that is often more than a very poor electricity or modern energy services and rely on burning firewood
family has. However, the biogas or biomass to meet their cooking and heating needs. Meeting the
energy needs of these people with modern energy services was a
dissemination process and the resulting major issue at the Summit, and governments committed
reduced claim on common ecosystem services themselves to "improving access to reliable, affordable,
economically viable, socially acceptable and environmentally
do affect the livelihood conditions of (very) sound energy services and resources."
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 22
Biogas significantly improves the As part of the implementation of the MDGs, the Millennium
Ecosystem Assessment was released in March 2005. This
sanitary condition of the farm yard and assessment examined the relationship between ecosystems and
its immediate surrounding, lowering the achieving the MDGs. It not only found that not sustainable
ecosystem management and development are imperative for
exposure of household members to reaching the MDGs, but moreover that ecological limits to
harmful infections especially children worldwide growth will affect both developed and developing
countries.
who spend extended periods in the
farm yard. In addition to providing predictions and evidence the assessment
Proper application of bio-slurry will provided a series of proposed responses and interventions. Biogas
programmes have elements that are relevant to each of these
responses and interventions.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 23
Target 9: Integrate the principles of sustainable development into country policies and
program and reverse the loss of environmental resources.
Large scale domestic biogas programmes positively influences national policies
on sustainable development (e.g. agriculture, forestation, poverty reduction)
Biogas programmes usually comply with and support government policies and
programmes that have positive environmental impacts including pollution control,
green house gas emission reduction and forestation
Target 10: Halve the proportion of people without sustainable access to safe drinking
water and basic sanitation.
Biogas reduces fresh water pollution as a result of improved management of
dung.
Connection of the household toilet to the biogas plant significantly improves the
sanitary conditions in the farmyard therefore reducing the risk of water
contamination.
The report urges for progress on 8 major areas, hereunder the relevancy of domestic
biogas regarding improvement in those areas is briefly discussed.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 24
Agriculture: because it still represents the bulk of economic activity, especially in rural
areas, and because the potential to shift to higher-valued crops has not yet been
exploited.
Biogas reduces the workload of the farming household (fuelwood collection, cooking,
cleaning kitchen utensils, weeding of vegetable fields), so increasing the labour
availability for productive agricultural activity.
Bio-slurry, properly applied, is a powerful organic fertilizer, potentially increasing yields
with 10 to 40%. Organic produce fits well into a high-value crop policy.
Much more rapid development of the modern private sector; because there is no other
sustainable way to generate high growth in the long term, nor to create the millions of
off-farm jobs that are needed.
A domestic biogas programme is relatively (non-agricultural, skilled) labour intensive,
providing good quality employment opportunities (see “expected results, section 5.4)
A major expansion of exports, and diversification beyond coffee, which has been
subject to declining prices; in order to fuel growth, to widen the economic base and
reduce susceptibility to shocks, to earn essential foreign exchange, and, in the longer-
term, to reduce the dependency on foreign aid;
Organic produce could be an export commodity. Biogas can replace kerosene for
lightning, thus reducing foreign exchange expenditure.
Infrastructure: to better link markets and producers, to enable business to take place, to
lower the costs of international trade and improve Ethiopia’s competitiveness, and to
allow people easier access to essential services.
No direct link with domestic biogas.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
1 Introduction and background Page 25
Biogas eliminates indoor smoke pollution and improves on-yard sanitary conditions.
Women and children benefit from this improvement disproportional, further improving
the developmental opportunities of women.
Recently, World Vision Ethiopia introduced biogas under its Appropriate Agricultural
Technology Promotion Initiative (AATPI). So far, some 150 plants have been
constructed (or are in the process of being so). In all, the total number of domestic
biogas plants would be in the range of 600 to 700 installations.
Section 2 of the report presents the observations of the study regarding to the visited
biogas installations.
14
EREDPC, Ministry of Energy & Mines, Ethiopia; Indicative dissemination strategies of biogas energy in Ethiopia
15
Christopher Kellner, Bio digester septic tank and bio latrine, construction of standardized systems for utilization and demonstration
16
Dr. Getachew Eshete et al, Identification study on renewable energy and energy efficiency in SNNPRS and Ethiopia.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Report on
the feasibility study of a national programme for
domestic biogas in Ethiopia.
Demolished floating drum installation
Section 2
Study findings.
2 Study findings Page 27
1 Study objectives
The objective of the study is to thoroughly assess the feasibility to set-up and implement
a national biogas programme in Ethiopia17. More specifically, the study will address the
following areas:
- Country background including agricultural & livestock sector, energy demand and
supply, energy policy and plans;
- History of domestic biogas;
- Potential demand for domestic biogas;
- Possible institutional set-up for a national biogas programme, and;
- Outline for a national programme on domestic biogas.
1.1 Methodologies
The following activities and methodologies are proposed:
A. Preparation of a mission to Ethiopia by collecting secondary information,
contacting key respondents and informants in Ethiopia and abroad, and drafting
checklists for biogas plant visits and interviews;
B. Mission to Ethiopia to visit domestic biogas plants constructed in the past, to
meet with key respondents and informants for interview and discussion. The
mission shall include a workshop to discuss with the main stakeholders the roles
of the different actors in Ethiopia and the outline of a possible national biogas
programme;
C. Formulation of the draft study report and submission for comment to
SNV/Ethiopia, members of the Biogas Practice Team (BPT) of SNV, RNE in
Addis Ababa and DGIS/DMW.
D. Submission of the final study report by incorporating the comment from
SNV/Ethiopia, members of the BPT, RNE/Addis Ababa and DGIS/DMW.
1.2 Limitations
The study team necessarily had to be selective in its destinations; the lowlands in the
East and South East, with large migratory cattle herds, and the South-West with its
large forests were not visited as the biogas potential can be expected to be relatively
low in those areas.
Over 4 weeks, the study team travelled large parts of North-West, North and South
Ethiopia, visited many (ex) biogas households, some non-biogas households and
interviewed many organizations that directly or indirectly are involved in domestic
energy and rural development. Even so, in the period available, the team cannot claim
to have a full and in-depth picture of the domestic energy situation in Ethiopia.
17
The ToR for the study is provided as annex 1 to the report
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 28
2 Study observations
The study team travelled some 4000 km over a period of 3 weeks in the North-West, the
North and the South of Ethiopia. The visited
Travel map
regions included Orromia, Amhara, Tigray and
the Southern Nations, Nationalities and
Peoples Regional States (SNNPRS). A brief
description of the 4 regions is provided in
Annex 2.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 29
2.2 Functionality
Overall, 60% of the visited installations were not functioning –i.e. gas could not be
utilized- at the time of the visit. Fixed dome installations (68% functioning) were scoring
significantly better than floating drum installations (16% functioning).
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 30
seem principally operable; we were reported that a severe drought some six
years ago (1998) not only had its toll on the cattle holding (households reporting
that they had to sell of their entire herd of 30 cattle) but also caused drying up of
many water wells, making water-availability “suddenly” a major issue.
In other places too, the large distance to the water source was reported to be the
reason to stop operating the plant, often in relation with children leaving the
house (thus reducing the energy requirement of the household as well as the
“free” labour of the children for fetching water).
The findings of the study team are supported by REDPC technical & socio-economic assessment
100%
the findings of the Ethiopian Rural Energy
Development & Promotion Centre (EREDPC) in
80%
their (unpublished) study report of about half a
year earlier ref 008.
60%
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 31
The REPDC report mentions lack of water; reduced animal holding; abandoned
(resettlement); loss of interest; management, and; minor technical problems as causes
for the installation not functioning.
An even less encouraging report came from the Amhara Mines & Rural Energy and
Promotion Office: of the batch of 54 floating drum biogas plants constructed in the
period 10 to 12 years ago, a report of 2003 claimed none of them was still working.
Also on the 103 installation reported in 1991 by the EEA, Mr. Melis Teka Nega reports:
Almost all of the plants were not working after some time due to19:
Installations not were constructed from with the farmers‟ interest in mind, but
rather with a political motive;
Gas management, every family was cooking at the same time
Labour contribution for feeding the installation.
Biogas plant investment comparision
2.3 Economics
900
Euro
800
2.3.1 Investment costs. 700
600
The reported investment costs for domestic 500
400
biogas plants range from some ETB 6,000 to 300
200
12,000 for fixed dome installations (8 to 20m3). 100
0
Floating drum plants are more expensive, and Ethiopia Nepal Vietnam
A detailed Bill of Quantities from 1995 informs on the costs of a 8 m3 floating drum
installation. In this BoQ the total costs amounted to ETB 8,451 (materials ETB 7,268 +
labour ETB 1,183).
Although the reported investment costs should be taken with care, the conclusion that
biogas plants in Ethiopia are high, both in absolute as well as relative terms, seems
valid.
19
These issues should probably be seen in the context to communal, shared biogas installations.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 32
Low dung production …
2.3.2 Plant size.
In relation with the amount of available dung,
the plant size of the visited installations was
too large. Typical domestic plants would have
a digester volume of at least 8 m3, but more
often sizes of 12 to 20 m3 were observed. Most
households, however, would have only three to
eight up to fifteen heads of cattle. These cattle,
typically, would roam around at fallow land and
collective grazing grounds, would be poorly fed
and (as a result?) rather small.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 33
are used for kerosene lamps as well, none of the biogas appliances or spare parts are
locally available.
The use of non-local materials increases the investment costs. Clay bricks can easily
double in price if transported over larger distances; the metal drums by nature need a
truck to get them on site. Moreover, non-local products, particularly appliances, valves
and taps, aggravate the maintenance problem as replacements, spare parts and repair
knowledge are rarely locally available.
The high investment costs of the observed plants and the high incidence of minor
technical problems leading to dysfunctional installations can both to some extent be
attributed to the use of non-local materials for plant construction and appliances.
The popular view would hold that full subsidies undermine the ownership of the
installation, resulting in the biogas plant not receiving the desired “tender love and care”.
The study team visited a few sites where this could be observed; plants were neglected,
abandoned for seemingly no reason, the smallest investment for repair being avoided.
However, this practice was not the rule; many plants were kept alive despite absence of
any technical back-up system. The study team visited quite a number of installations
that –for their age of 10 to 13 years- had been kept in good working condition.
2.4 Operation
Many (60%!) of the visited installations were not in operation at the time of visiting. The
remaining plants can be divided in very new plants that would work without too many
problems. And older plants (mostly > 10 years) that, against all odds, were kept in
working order by the owners.
It is from this last group that the study team got an impression of how plants were kept
in operation, what farmers would do to get repairs done and, from the first group, where
and when it went wrong.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 34
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 35
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 36
Organic fertilizer …
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 37
2.4.6 Bio-metads.
Although some farmers were supplied with biogas operated metads (baking plates for
injerra) none of the visited households was using this stove as its gas consumption was
claimed to be too high. The design of an appropriate domestic bio-metad is challenging:
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 38
Improved metads (local, Mirte and Lakech) are Possible technical improvements for bio-metads:
currently widely available and strongly
improved burner for better heat distribution,
promoted by multiple actors. Their efficiency aluminium or cast iron plate for better heat transfer,
improvement is significant and these stoves plate of smaller diameter (reducing the diameter from 60 cm
to 50 cm reduced the area to be heated with one-third)
can be fuelled by multiple fuels including dung placing the bio-metad in a “Mirte-like” housing to reduce heat
and agricultural residue, these stoves seem - losses.
for the moment- more appropriate and
economic for the preparation of injerra than (the potential of improved) bio-metads.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 39
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 40
NB:
For “argument‟s sake” the situation is presented dialectically. The reality is not so
black and white; the Bureau of Energy in Awassa, SNNPRS, for instance indicated
that they are increasingly cooperating with manufacturers of the private sector, and
one of the visited households mentioned its contribution to the tune of ETB 4,000 for
the installation
The “Christopher Kellner” approach differs from the above two extremes in scale of
dissemination, and in that the households were not offered financial support, only
technical advice.
Unfortunately, despite policy largely being in place, at the higher “political” level, the
issue seems not to get the required attention and priority. This results in totally
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 41
inadequate funding for even the smallest surveys or dissemination programmes. The
executing bureaux thus are typically seriously resource-limited (project finance,
transport, staffing), resulting more in frustration than implementation.
The interview with Ato Asress, director Ethiopian REDPC, however, gave some
indication that also at central political level the severity of the situation starts to hit
home.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
2 Study findings Page 42
The Centre mainly constructs larger fixed dome installations (up to 200 m3), turn-key, for
the bio-industry around Addis Abeba, but they have been involved in some domestic
installations as well. Selam operates three biogas plants on its own premises.
In general, Selam, over the past 20 years or so, has built a solid reputation on quality
and this shows in their biogas plants.
2.7.5 Biofarm.
Organization directed by Dr. Getachew Tikubet. Biofarm promotes an integrated
approach to biogas, not dissimilar to the Chinese 3 in 1 and 4 in 1 ideas and the
considerations the Carmatec team in Tanzania documented. Biofarm provides technical
services to the World Vision AATPI programme for the construction of domestic biogas
plants. The organization is a bit secretive about the technology they promote. From our
observations, their “Chinese design” is comparable to the “Lupo” design of Christopher
Kellner, with large cylindrical vertical inlet and outlet.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Report on
the feasibility study of a national programme for
domestic biogas in Ethiopia.
Section 3
Potential demand for domestic biogas.
3 Potential demand Page 44
Availability of water required to mix +/- Water availability is very area dependent, and in most parts of Ethiopia
with fresh dung in a 1:1 ratio recurrent droughts have to be taken in consideration.
Sufficient space for biogas plant in ++ Compound space is not an issue in rural areas; farmers have yards of
the compound of potential users reasonable size.
History of proper performing biogas +/- 60% non-functioning is not a good track record, but up to 750 plants nation
installations wide is not a large amount either.
Traditional practice of using of + Traditionally, dung is used as fertilizer. Unfortunately, energy shortage
organic fertilizer increasingly force households to use dung as energy source instead
Scarcity of traditional cooking fuels ++ Fuelwood is scarce to the extent that its use is considered a luxury in large
like firewood parts of the country
Financial
Potential users have access to credit + All visited regions have good, albeit recent, micro credit facilities. There is,
however, no experience yet with biogas credit
Livestock farming is the main source ++ Farming integrates cropping and livestock. Hence, livestock may not be the
of income for potential households main source of income, but it is an indispensable part of it
Role of women in domestic decision- __ Traditionally, domestic decision making is male skewed. The decision for
making process and life an investment in a biogas installation would definitely be within the male
domain.
Biogas plant can be integrated into ++ In view of the integrated farming system, biogas will fit seamlessly in most
normal working routine at the farm situations in the highlands, where cattle are night-stabled.
Social
Awareness of effects of biogas - In view of the low penetration of new technologies in general and biogas in
technology among potential users particular, many farmers may not be very aware
Willingness among potential users to +/- Handling (products of) night soil definitely is a sensitive issue. However,
attach a toilet to the plant there are some good examples.
Political will of the Government to + At REDPC and BoE level, the political will is certainly there. The MoFED
support a national biogas programme and BoFEDs, however, have not been consulted in this detail yet
Institutional
Willingness of (potential) ++ Both from government side (REPDC, BoEs, BoAs) as well as NGO side
stakeholders to get engaged in (UNDP-GEF, Selam, RNE, SNV-Ethiopia) the team met with considerable
biogas programme enthusiasm.
Availability of organizations having + The government‟s agricultural extension network reaches down to kebele
access to potential users level, but habitats are much dispersed.
Score Condition
++ Fully met
+ Met
+/- Doubtful
- Not yet met
-- Falls short
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 45
It is likely that the free grazing practice gradually but increasingly will be replaced by
“cut and carry”, stable feeding of livestock, as the traditional practice may just have to
high a toll on the environment. Parallel, other cattle breeds would be introduced,
improving the situation for biogas.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 46
Proximity to water source (CSA 1998)
more than 15 km 0.7
The 1998 census would indicate that nearly
64% of the rural population live within 1 km 10 to 14 km 0.8
minutes walking). 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0
[%]
This would not quite match the observations of the mission in some of the visited areas
(Amhara, Tigray). In addition, water source yields may reduce significantly during longer
dry periods, forcing water carriers to use lower quality water (not a problem for biogas)
at even longer distances.
Access to safe water would be another proxy Access to safe drinking water
Region rural total
to account for regional variations in water
21
accessibility . The share of the rural Amhara 23% 31%
population thus having access to safe drinking Oromia 23% 30%
water, say 22%, is considerably lower than the SNNPRS 21% 28%
Tigray 26% 34%
share of the rural population living within 30
minutes from a water source. Part of this Source: MoWR - WWDSE 2001
difference may be explained by not all water
sources providing safe drinking water and “access” might be defined more narrow in the
second source
Space: The study team did not visit any farm where the physical space requirement of a
biogas plant could have been a limiting factor. Besides, when fixed dome installations
would be promoted in stead of floating drum plants, the required amount of place will
further reduce.
Biogas & resettlement.
Track record: There are only few domestic
In an attempt to lower the anthropogenic pressure in heavily
biogas plants in Ethiopia. Although their track degraded areas, the previous regime introduced quite rigorous
record is worrying, their impact on the resettlement programmes. Communities were resettled in villages
(often also a new concept) in more prosperous areas, often
reputation of the technology would be limited provided with a wide range of services. Among these services
as the technology as a whole is little known. could be biogas installations.
21
For SNNPR and Tigrai region, a figure on rural accessibility was not available. The share has been calculated assuming 75% of
the share of the total, as is the case for Amhara and Oromia regions, would result in the rural access to safe water.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 47
Many farmers visited by the study team, over Intensive small scale farming in Gurage area
the whole country, had smaller or larger
vegetable gardens on their farm yard. These
farmers used their manure (or bio-slurry in the
case of biogas households) as manure for their
crops. In some areas, however, vegetable
growing is more intensive than others; Gurage,
for instance, is a typical intensive vegetable
growing area, and manure has a high fertilizing
value. In other areas (parts of Amhara and
Tigray), cattle are using common grazing
grounds and manure is less handled by
farmers.
Dairy farm, Addis Abeba
1.2.2 Dairy production: Increasingly, farmers
embark up on dairy production as a
commercial activity. To that extent, dairy
cooperatives with transport / refrigeration
facilities are popping up. The traditional diet of
most (rural) families knows little dairy products
(some butter for cooking, “aib”, the local
cottage cheese and little “urgu” (local yoghurt)
to eat with injerra), promotion aims especially
on increasing urban dairy consumption.
1.2.3 Selling dung-cake: As the efficiency of a biogas stove is easily five times higher
compared with a traditional (dung-cake) stove, contrary to common belief, biogas would
not compete with the commercial value of dung cake as an energy source, as a farmer
would be better off converting the dung to biogas rather than burning it directly.
Additionally, the farmer would reap the fertilizing benefit of bio-slurry
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 48
most of the visited areas is factual, as is its Agricultural residue (50% repl value wood) [ /kg] 0.38 0.04
Dung cake [ /kg] 0.40 0.04
high and rapidly increasing price. So much so Fuelwood [ /kg] 0.75 0.07
that fuelwood and charcoal are gradually Charcoal [ /kg] 1.50 0.14
Kerosene [ /ltr] 3.00 0.29
becoming luxury goods for rural households.
Besides fuelwood, BLT, dung cake and agricultural residue are increasingly becoming
commercial energy sources, traded at markets.
1.2.5 The value of biogas: This value depends directly on the value of the substituted
fuels. The table provides the calculated value of 1 m3 of biogas, based on the fuel price,
the substitution ratio (biogas stoves have a significant higher efficiency than traditional
stoves) and the assumed fuel mix (the share of the substituted fuel in the total energy
supply. The table shows two values; the economic value, taking the full market price of
the substituted fuel into account, Euro
and the financial value, taking substitution economic financial financial
Biogas replacement value Unit ratio fuel mix value share value
only a share of the market price
3
into account. Thus, the financial Agric residue + BLT (50% repl value wood)
Dung cake
[Euro/m gas]
[Euro/m gas]
3
7.06
6.05
15%
15%
0.038
0.035
10%
30%
0.004
0.010
value better allows for the fact Fuelwood [Euro/m gas] 3
3
9.79 68% 0.480 70% 0.336
Charcoal [Euro/m gas] 1.99 1% 0.003 80% 0.002
that rural farmers acquire fuel Kerosene [Euro/m gas]
3
0.63 1% 0.002 100% 0.002
Striking in the results is not only the significant difference of Euro 0.20 between the
economic and the financial value of biogas, but also that the value of biogas is three
times higher in Ethiopia (economic € 0.56, financial € 0.35) as compared with Vietnam
(economic € 0.16, financial € 0.10).
1.2.5 Micro credit: With the micro credit facilities modernizing and extending their
services, credit is becoming a feasible financing option for biogas in many of the visited
areas. Credit terms are not prohibitive, but it has to be taken in mind that there is no
experience with biogas credit yet. Hence, micro financing organizations may require
assistance in covering the risk initially.
In the past, farmers did have a reputation of being reluctant to take loans. Obtaining
credit could be difficult; micro credit facilities were less developed and land could not be
used as collateral. The situation has improved since, but the extent to which this
reluctance may still hamper a biogas credit component would need further study during
the preparation of the implementation document of the programme.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 49
The dominant family structure is characterized by formal and informal power structures
based on the principles of sex, age and relatedness. The gender division of power is
primary, with males, except the very young ones) having power over females. Decisions
regarding education, marriage of children, construction of a house, farm work schedules
of the household members, hiring farm labourers land allocation and the use of farm
inputs are made by the (mostly male) head of the household.
Wives make decisions pertaining to child care, food preparation and household
management. Male dominance is paramount, Injerra basket weaving
but when asked to define who the ultimate
decision maker in family matters is, most
husbands express that both wife and husband
make decisions jointly.
1.3.2 Integration in farming practice: Biogas will easily find its place in the typical
integrated farming set-up of the Ethiopian highlands. Cattle is night stabled, yards allow
enough space for placing an installation, vegetable gardens are often adjacent to the
yards, distances to the kitchen and the stable can mostly be chosen favourable for
biogas.
1.3.3 Awareness on benefits: With the low current penetration of the technology, one
cannot expect wide awareness of the benefits of biogas. Information and promotion,
hence, shall be a significant component in any programme. Biogas benefits, however,
are likely to be very appealing for most households; not only in view of the scarcity of
energy and fertilizing sources, but also from a workload, health and sanitation point of
view.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 50
1.3.5 Health: Biogas installations improve the health situation of families. Most
prominently by eliminating indoor air pollution, the main cause of respiratory diseases,
and in particular for women and small children who are often close to the cooking fire.
Biogas installations further improves the sanitary condition of the farmyard and its direct
environment by feeding animal manure directly to the installation and connecting a toilet
to the plant respectively.
Mortality rates of diseases
14
As such, biogas installations directly contribute 12
to the betterment of the two of Ethiopia‟s three
mortality / 1000 pers
10
main diseases in terms of mortality rate.
8
0
<5
<5
<5
<5
>15
all
all
all
all
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 51
At higher level, particularly regarding the Ministry and Bureaux of Finance and
Economic Development (MoFED / BoFED), further study will be required to gauge the
willingness to co-finance (directly or “in kind”) such a large scale programme. The
BoFED officials visited showed a good understanding of the issues around rural
development, energy and environment.
Indirectly, through the interviews, it transpired that in political circles of the government
the awareness of energy and environment, and hence the concern regarding providing
basic energy services to rural poor households, is very limited indeed.
The private sector does not show great presence in rural Ethiopia. For construction and
maintenance, any programme would have to invest in establishing (initially small and
informal) biogas enterprises. In some areas, linking with Mirte manufacturers or
technicians trained for pump and latrine construction (e.g. Finnida) might be a good
option.
For starting-up, Selam would be a good partner for manufacturing and marketing of
appliances as well as applied research and development. Selam would also –at least
initially- be well placed to provide biogas mason and technician training.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 52
As argued earlier, in view of the cattle stabling customs as well as the poor diet of most
cattle in Ethiopia, households should rather have 4 heads of cattle to ensure sufficient
available manure (>20 kg / day) to produce a reasonable amount of biogas per day (>
1m3 biogas / day). The map indicates that most parts of the studied regions (Amhara,
Oromia, SNNPRS and Tigray) have an average cattle population larger than 4 heads
per household.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 53
3 Technical potential.
To come to a first estimate on the potential for domestic biogas, the number of
households with 4 or more cattle is taken at Woreda level. As substrate, manure of
other stabled animals (donkeys, horses) would do equally well. However, avoiding an
over-optimistic picture, for the calculation only cattle holding is considered.
The availability of manure as substrate for the installation is not the only technical
parameter. Equally important, and much more critical in the Ethiopian context, is the
availability of process water. Practically, in view of the considerable amount of water
that has to be fed to the installation, the water source should be within 20 to 30 minutes
from the farm yard.
3.1 Amhara.
Amhara counts nearly 3.2 million households, out of which 81% keep cattle. Out of
these 2.6 million cattle holdings, 39% are keeping 4 or more cattle.
The country average for proximity to a water source within 20 to 30 minutes is
71%. The high technical potential for domestic biogas in Amhara region thus
would amount to approximately 716 thousand installations.
In rural Amhara 23% of the population has access to safe drinking water; the low
technical potential thus would amount to 232 thousand installations.
Amhara
Cattle % Cattle Cattle Avg cattle cattle holding cattle holding share cattle
Area House holds holdings Cattle population holdings density holding / hh <4 >4 holding >4
Zone [km2] [# of hh] [# of ch] [#of heads] [%] [head/km2] [head/hh] [# of ch] [# of ch] [%]
Awi 6346 175494 137552 638868 78% 101 4.6 0 137552 100%
East Gojam 14186 406823 333321 1257843 82% 89 3.8 207136 126185 38%
North Gondar 45486 462119 375422 1931400 81% 42 5.1 85427 289995 77%
North Shewa (K3) 16077 369828 287843 1018055 78% 63 3.5 240700 47143 16%
North Wollo 12702 324963 253403 910492 78% 72 3.6 187463 65940 26%
South Gondar 14607 407519 336299 1181472 83% 81 3.5 300694 35605 11%
South Wollo 17212 553574 441555 1582857 80% 92 3.6 415106 26449 6%
Wag Hemira 8479 80546 61467 355056 76% 42 5.8 0 61467 100%
West Gojam 13413 413888 347974 1399484 84% 104 4.0 129473 218501 63%
Total Amhara 148509 3194754 2574836 10275527 81% 69 4.0 1565999 1008837 39%
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 54
3.2 Oromia.
Oromia counts over 4.6 million households, out of which 79% keep cattle. Out of these
3.6 million cattle holdings, 78% are keeping 4 or more cattle.
The country average for proximity to a water source within 20 to 30 minutes is
71%. The high technical potential for domestic biogas in Oromia region thus
would amount to approximately 1.978 million installations.
In rural Oromia 23% of the population has access to safe drinking water; the low
technical potential thus would amount to 641 thousand installations.
Oromia
Cattle % Cattle Cattle Avg cattle cattle holding cattle holding share cattle
Area House holds holdings Cattle population holdings density holding / hh <4 >4 holding >4
Zone [km2] [# of hh] [# of ch] [#of heads] [%] [head/km2] [head/hh] [# of ch] [# of ch] [%]
Arsi 23713 573680 480821 2783892 84% 117 5.8 0 480821 100%
Bale 60805 297018 256654 1614990 86% 27 6.3 0 256654 100%
Borena 70604 321428 227715 1732020 71% 25 7.6 0 227715 100%
East Harerghe 23544 406076 338674 975054 83% 41 2.9 338674 0 0%
East Shewa 13893 353342 264953 1416553 75% 102 5.3 20576 244377 92%
East Wellega 22181 295540 229597 1458188 78% 66 6.4 0 229597 100%
Illubabor 16411 220714 158226 794176 72% 48 5.0 0 158226 100%
Jimma 18486 514489 417041 1805867 81% 98 4.3 148888 268153 64%
North Shewa (K4) 11269 269663 222689 1173542 83% 104 5.3 53721 168968 76%
Oromia Zone 4073 78911 60704 326825 77% 80 5.4 0 60704 100%
West Harerghe 17461 309862 261931 994224 85% 57 3.8 150711 111220 42%
West Shewa 21812 554009 449463 2431375 81% 111 5.4 14667 434796 97%
West Wellega 24316 354436 214316 1034513 60% 43 4.8 68448 145868 68%
Hundene 372 15045 11288 34008 75% 92 3.0 11288 0 0%
Total Oromia 328939 4564213 3594072 18575227 79% 56 5.2 806973 2787099 78%
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 55
3.3 SNNPRS.
SNNPRS counts nearly 2.7 million households, out of which 75% keep cattle. Out of
these 2.0 million cattle holdings, 39% are keeping 4 or more cattle.
The country average for proximity to a water source within 20 to 30 minutes is
71%. The high technical potential for domestic biogas in SNNPRS region thus
would amount to approximately 550 thousand installations.
In rural SNNPRS 21% of the population has access to safe drinking water; the
low technical potential thus would amount to 163 thousand installations.
SNNPRS
Cattle % Cattle Cattle Avg cattle cattle holding cattle holding share cattle
Area House holds holdings Cattle population holdings density holding / hh <4 >4 holding >4
Zone [km2] [# of hh] [# of ch] [#of heads] [%] [head/km2] [head/hh] [# of ch] [# of ch] [%]
Amaro Special Woreda 1557 23714 17374 78473 73% 50 4.5 0 17374 100%
Basketo Special Woreda 419 10348 7509 23611 73% 56 3.1 7509 0 0%
Benchi Maji 23159 102783 81521 319902 79% 14 3.9 72986 8535 10%
Burji Special Woreda 1353 7980 6433 32970 81% 24 5.1 0 6433 100%
Dawuro 4380 81637 65541 292664 80% 67 4.5 0 65541 100%
Derashe Special Woreda 1526 23278 12396 66701 53% 44 5.4 0 12396 100%
Gamo Gofa 12153 257901 205707 850291 80% 70 4.1 93563 112144 55%
Gedeo 1356 141168 41506 117356 29% 87 2.8 41506 0 0%
Guraghe 7914 419708 335151 1353983 80% 171 4.0 130601 204550 61%
Hadiya 4026 253305 199648 733814 79% 182 3.7 199648 0 0%
Kaffa 10539 157734 128591 575024 82% 55 4.5 20742 107849 84%
Kembata Alaba Tembaro 2493 193843 144008 472681 74% 190 3.3 144008 0 0%
Konso Special Woreda 2323 36261 22919 103413 63% 45 4.5 0 22919 100%
Konta Special Woreda 2287 17062 13780 52576 81% 23 3.8 13780 0 0%
Shaka 1530 29386 18755 65817 64% 43 3.5 13574 5181 28%
Sidama 6779 528046 404560 1573318 77% 232 3.9 244331 160229 40%
South Omo 23145 91237 60446 1392822 66% 60 23.0 8483 51963 86%
Wolayita 4525 297226 230520 658886 78% 146 2.9 230520 0 0%
Yem Special Woreda 753 16353 13315 51387 81% 68 3.9 13315 0 0%
Total SNNPRS 112217 2688970 2009680 8815689 75% 79 4.4 1234566 775114 39%
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
3 Potential demand Page 56
3.4 Tigray.
Tigray counts nearly 725 thousand households, out of which 77% keep cattle. Out of
these 559 thousand cattle holdings, 44% are keeping 4 or more cattle.
The country average for proximity to a water source within 20 to 30 minutes is
71%. The high technical potential for domestic biogas in Tigray region thus would
amount to approximately 176 thousand installations.
In rural Tigray 21% of the population has access to safe drinking water; the low
technical potential thus would amount to 65 thousand installations.
Tigray
Cattle % Cattle Cattle Avg cattle cattle holding cattle holding share cattle
Area House holds holdings Cattle population holdings density holding / hh <4 >4 holding >4
Zone [km2] [# of hh] [# of ch] [#of heads] [%] [head/km2] [head/hh] [# of ch] [# of ch] [%]
Central Tigray 10327 230761 174810 627831 76% 61 3.6 162010 12800 7%
Southern Tigray 9408 183354 136515 631185 74% 67 4.6 46361 90154 66%
Western Tigray 24652 180952 152793 1081963 84% 44 7.1 20264 132529 87%
Eastern Tigray 5795 129897 95216 324150 73% 56 3.4 82341 12875 14%
Total Tigray 50182 724964 559334 2665129 77% 53 4.8 310976 248358 44%
Country wide, 71% of the rural households live within 20 to 30 minutes walking from a
water source. The “high” technical potential for domestic biogas in the 4 regions hence
is estimated on some 3.5million households.
On average, 23% of the households in the four visited regions have access to safe
water. The “low” technical potential for domestic biogas in the studied area thus would
amount to approximately 1.1 million households.
hh
cattle cattle access to Technical
House Cattle Cattle % Cattle Cattle Avg cattle holding holding share cattle hh water safe potential Technical
Region Area holds holdings population holdings density holding / hh <4 >4 holding >4 < 30 min water HIGH potential LOW
[km2] [# of hh] [# of ch] [#of heads] [%] [head/km2] [head/hh] [# of ch] [# of ch] [%] [%] [# of ch] [# of ch] [# of ch]
Amhara 148509 3194754 2574836 10275527 81% 69 4.0 1587506 1110264 43% 71% 23% 788,287 255,361
Oromia 328939 4564213 3594072 18575227 79% 56 5.2 799379 2787099 78% 71% 23% 1,978,840 641,033
SNNPRS 112217 2688970 2009680 8815689 75% 79 4.4 1213824 758760 38% 71% 21% 538,720 159,340
Tigray 50182 724964 559334 2665129 77% 53 4.8 284879 290733 52% 71% 26% 206,420 75,591
Total study area 639846 11172901 8737922 40331572 78% 63 4.6 3885588 4946856 57% 71% 23% 3,512,268 1,131,324
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Report on
the feasibility study of a national programme for
domestic biogas in Ethiopia.
Section 4
Design
considerations.
Storage jar
4 Design considerations Page 58
1 Lessons learnt.
From the study findings, the following main lessons can be learnt:
1.1.3 In relation with the available dung, most installations are over sized:
See also “1.1.1”, the proper digester size for typical rural Ethiopian households would
be 4 to 6 m3 rather than the often observed 8m3 or larger.
1.1.4 Without proper technical back-up, any plant will fail sooner or later:
However good the initial construction quality, smaller or larger maintenance and
repair requirements will sooner of later hamper proper operation of a biogas
installation when proper (locally available and affordable) technical back-up
installations is not available.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 59
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 60
1.3.3 Micro-finance can play an important role in making domestic biogas affordable:
Most visited biogas installations were constructed in a period when micro-finance
facilities were not well developed. However, currently micro-finance institutions
increasingly adjust lending conditions in such a way that biogas financing becomes a
promising opportunity.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 61
1.5.2 The Bureaux of Energy would seem the best placed coordinating, supervising
and integrating agencies at regional level:
The Bureaux of Energy are mandated to support implementation of a large scale
biogas programme. Most BoEs have experience in smaller biogas projects and in
larger improved cooking stove and metad dissemination projects.
The Bureaux of Energy showed a good and broad understanding of the local
domestic energy issues.
The Bureaux of Energy do not have their own extension network. In a sectoral
approach this may actually be to their advantage; the Bureaux will be “forced” to
work together with other actors in the rural domestic energy arena. Important
actors include the Bureaux of Agriculture and their extension network at Woreda
and Kebele level and (non-) government organizations in the fields of water,
health and sanitation.
1.5.3 To ensure effective participation of the national EREDPC and the regional BoEs,
a significant organizational / institutional support component should be considered:
Although the organizations are mandated and experienced, both national as well as
regional bodies are chronically short of resources of all sorts.
1.5.4 The extension network of the Bureaux of Agriculture would be an asset for a
large scale dissemination programme:
The agricultural extension network is rather dense, and under further development. The
objective is to have one or two extension workers in each Kebele. This apparatus would
offer good opportunities for biogas extension and programme monitoring.
1.5.5 The regional micro-finance institutions can play an important role in a large scale
domestic biogas programme:
The regional micro-finance institutions are developing strongly both in reach and
product variety.
Lending conditions are broadened in such a way that currently biogas financing
could (to a large extent) be accommodated.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 62
2 Recommendations.
From the study findings and lessons learnt, the team suggests the following
recommendations:
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 63
~ 500 plants per Woreda). Selection of the initial programme areas should follow
the finding surveys as mentioned under 2.1.
Construction should take place in batches of 10 to 20 installations within one
smaller area (Kebele, village) to create a good environment for
commercialization, financing and extension.
As a result, the pilot would establish between 500 and 1000 domestic biogas
cores.
The pilot shall provide detailed information and justification for the potential and
opportunity for succession.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 64
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 65
The construction of a floating drum installation is straight forward, with little chance of
error. And for the owner, with the drum clearly indicating the amount of gas available,
the set-up is understandable. However, although some of the visited floating drum
installation showed admirable endurance, its intrinsic setbacks like: low gas pressure
(especially for lamps and longer pipelines but also for discharge of more viscose –more
dry- slurry); cumbersome connection of dome with the gas pipe, with hoses getting
brittle easily; the expensive construction and
transport of the steel dome, would not make it
the design of choice for Ethiopia.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 66
bricks and these bricks have to be trucked–in, a large part of the investment advantage
will be lost.
As the experience with domestic biogas did not establish a vested construction custom
in Ethiopia yet, the study team proposes to introduce the (modified) fixed dome design
that has been used in Nepal successfully for many years 22.
Its design is extremely robust, both in construction as well as operation, allows using
stones as well as bricks for the construction of the round wall, and requires of all fixed
dome designs probably the lowest level of craftsmanship. In addition, as the design has
been used intensively over a long period of time, construction and after sales service
standards and a variety of training material will be readily available.
3.2 Appliances.
Based on the appliances observed during the household visits, significant improvement
can be made:
Selam is developing (currently pilot stage) a promising biogas lamp. If the
expectations are met, this would be an excellent alternative for the current
(copies of) Indian biogas lamps. Alternatively, the Biogas Partnership Nepal
developed a reliable biogas lamp that
could be manufactured in Ethiopia as
well
Many of the observed biogas stoves
would leave room for improvement.
SNV has experience with locally
manufactured stoves (Nepal, Cambodia
and to a lesser extent Vietnam) that
seem appropriate for the Ethiopian
market, and could be manufactured
locally in small batches. Demonstrating the Selam lamp
The quality of the observed gas taps
was not always convincing. SNV has Cambodian biogas stove
experience with simple, robust designs
that can be manufactured locally in
small batches
22
A brief version of the construction manual for this model installation is provided as annex 3
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 67
For a biogas installation to become interesting for the family, it would have to be able to
produce at least around 1 m3 biogas per day. This would require –say- 20 to 30 kg
manure being fed to the installation every day. Hence, a family would need at least the
manure of a herd of 4 to 5 cattle. For such “typical” biogas household, a correctly sized
installation would have a digester volume of 4m3.
The table below provides the relation between digester-size, feeding, water
requirement, cattle holding and gas production, where it should be noted that actual
sizing shall depend on weighing the actual amount of available dung over a longer
period (one week) rather than on the number of cattle. The impression of the mission is
that for typical households, digester sizes of 4 or 6 m3 will suffice.
4 m3 digester 6 m3 digester 8 m3 digester 10 m3 digester
min max min max min max min max
Below the Bill of Quantities for the GGC 2047 model biogas plant constructed in stone.
The similar design in bricks would be approximately 50% more expensive.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 68
Investment costs GGC 2047 biogas plant for Ethiopia for construction in stone [ETB]
3 3 3 3
4 m digester 6 m digester 8 m digester 10 m digester
unit qty costs total qty costs total qty costs total qty costs total
2 Supplied materials
2.1 Cement [bags] 12 720.00 14 840.00 18 1,080.00 21 1,260.00
2.2 Stone, cut [m3] 4 200.00 5 250.00 6 300.00 7 350.00
2.3 Reinforcement rod [kg] 11 110.00 11 110.00 14 140.00 14 140.00
2.4 Fitting material [set price] 605.00 605.00 753.00 753.00
2.5 Appliances [set price] 600.00 600.00 900.00 1,200.00
3 Technical services
3.1 Skilled labour [person days] 2 90.00 2 90.00 2 90.00 2 90.00
3.2 Semi skilled labour [person days] 8 360.00 8 360.00 11 495.00 11 495.00
3.3 Annual maintenance fee [fee per visit] 4 180.00 4 180.00 4 180.00 4 180.00
4 Company fee
4.1 Overhead [person days] 1 45.00 1 45.00 1 45.00 1 45.00
4.2 Risk coverage [share of 2] 5% 111.75 5% 120.25 5% 158.65 5% 185.15
4.3 Company profit [share of 2+3] 20% 573.00 20% 607.00 20% 787.60 20% 893.60
5 Programme fee
5.1 QC contribution fee [fee per visit] 2 50.00 2 50.00 2 50.00 2 50.00
5.2 Participation fee [lump sum] 50.00 50.00 50.00 50.00
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 69
3.5 Costs & benefits of domestic biogas. Investment costs & GDPppp
Despite –possibly- the opportunity to reduce the Investment costs GDPppp capita
investment costs for a domestic installation, the 3500
initial costs are still (very) high, both in relative 3000
2000
[Euro]
The high investment costs of biogas plants in 1500
0
3, chapter 1.2.5) Vietnam Nepal Ethiopia
Reduced pressure for illegal forest encroachment. Reduced chemical fertilizer expenditures.
Reduction drudgery from weeding fields. Increased opportunity for (small-scale) organic
Reduced workload for food-preparation. agriculture.
Reduced soil erosion / degradation. Improved agricultural yields.
Improved opportunity for education. Increased family income.
Reduced risk of erosion and landslides in mountainous Increased employment and income generating
areas. opportunities.
Meso
Improved forest quality and quantity. Opportunity to develop markets for (organic) agricultural
Reduced pollution of the environment as a result of produce.
uncontrolled dumping of animal waste.
23
As mentioned, “formal benefits” can be translated directly in economic gain; one can attribute a price to it. For “Informal b enefits”
this tends to be more complicated and indirect, and they tend to refer more to benefits in the social and environmental domain. This
is not to say that formal benefits should be valued higher, rather that the economic system often poorly allows to value social and
environmental benefits properly.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 70
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 71
IRR
50%
installation appears to be modestly economically IRR5 IRR10
-30%
Because the investment is so sensitive to the -40%
biogas substitution value, and in view of: -50%
the high investment costs in relation with Biogas substitution value [Euro / m 3 biogas]
the per capita GDPppp of the country;
the significant gap between financial and
economic biogas substitution values; IRR sensitivity to subsidy
the significant gap between the internal
IRR
rate of return at micro and macro level, 60%
IRR5 IRR10
The subsidy is proposed to be independent from the installation size. Larger installations
typically would belong to farmers with more cattle. These farmers can be expected to
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 72
contribute more to the investment than smaller farmers. Besides the equity perspective,
also from a technical and economic perspective a flat-rate subsidy would be preferable:
a flat-rate subsidy amount will stimulate plants being properly sized (not too large in
relation to the amount of dung available); this will improve the economics of the plant as
well as the technical functioning.
3.7 Credit.
Credit and savings organizations in Ethiopia seem to develop rapidly; the Association of
Ethiopian Micro Finance Institutions (AEMFI) counted 26 member organizations.
Over the 3 ½ year period between Decembers 2001and June 2005, their number of
clients tripled and the outstanding loan quadrupled. By June 2005, the MFI‟s had over
1.2 million loan clients among them (ranging from ~ 1600 to 126000 clients), with a total
outstanding loan portfolio of nearly ETB 1.5 billion. The average outstanding loan per
client then reached ETB 1,220.
MF development Ethiopia
1,400,000 1,400
According to AEMFI, their typical clients would 1,200,000
# of clients Avg loan / client
1,200
be poor rural households, taking on average a
[ETB/client]
800,000 800
ETB 5,000. Loans are taken to finance
600,000 600
agricultural input, establishment of small
businesses and consumption. 400,000 400
200,000 200
Interest rates are established by the member – MFI‟s themselves, and range from 9 to
24% per annum. Maturity of loans varies from under one year for smaller loans up to 5
years for loans over ETB 5,000. About 40% of the loan is covered by savings, down from
75% in 2001.
The visited regional credit organizations (Amhara, Tigray, Oromia) acted “carefully
positive” on the prospect of extending biogas loans. As biogas is relatively unknown, and
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 73
does not provide direct income (rather savings that are not always easily monetized)
they indicated they may want some sort of an additional guarantee.
Against this institutional back-drop, biogas credit seems a realistic option, although
participating Saving and Credit organizations may need safeguards to protect their
loans. To provide a first indication the effect of a loan on a biogas investment was
calculated with:
a subsidy amount of ETB 1,500;
an interest rate of 12% per annum;
Financing scheme for biogas plant type GGC 2047 built in stone
a loan maturity of 5 years. 4m
3
6m
3
Assuming that the installation would replace Total investment 4,414.75 4,772.25
per cubic meter biogas, and; Annual repayment 608.85 [ETB/annum] 667.79 [ETB/annum]
Monthly repayment 50.74 [ETB/month] 55.65 [ETB/month]
a fuel price of ETB 0.75 per kg of
Financing costs 849.48 [ETB] 931.72 [ETB]
fuelwood,
the monthly savings of ETB 112.50 would easily repay the loan.
According to the experts of the EREPDC, a biogas credit scheme with repayments up to
ETB 1,000 per year would be feasible for farmers with cash crops.
24
“Financing costs” represent the total of the interest costs over the repayment period,
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
4 Design considerations Page 74
In Ethiopia, however:
cattle is largely free grazing and storage of dung under (semi) anaerobic
conditions is not customary, and;
kgCO2eq/pl/yr
Domestic biogas plant GHG reduction
application of chemical fertilizer is hardly 3000
2500
practiced, and in addition substitution of 2000
baseline project
The graph provides the preliminary calculated results of GHG reduction for a typical
Ethiopian biogas household. GHG reduction would tentatively be in the range of 2 tons
CO2 equivalents per installation per year.
Thousands
substitution of fuelwood, assuming a 11,000
reduction
Therefore, one would be well advised to carefully weigh costs and benefits of
developing the programme into a CDM project. Rather, the programme shall from the
start ensure CDM compatibility, especially regarding quality management and
monitoring and evaluation but embark up on CDM registration only once the programme
itself is properly established.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Report on
the feasibility study of a national programme for
domestic biogas in Ethiopia.
Section 5
Outline of the Ethiopia Biogas Programme.
5 Programme outline Page 76
1 Main features.
The Ethiopia Biogas Programme as proposed hereunder intends to lay out a robust
foundation for the establishment of a commercially viable domestic biogas sector.
Salient features of the programme would include:
Financing.
The programme proposes a flat rate subsidy scheme for participating farmers, reducing
the initial investment with ~ 25%. In addition, and key to the long term success, the
programme will support an investment credit facility in cooperation with existing micro-
finance institutions.
Training
The programme will invest significantly in training. On the supply side of the market, to
ensure that necessary dissemination skills are as much as possible available locally.
And on the demand side, to make sure households understand the operation and
maintenance of their plants sufficiently and families apply biogas and bio-slurry to their
maximum advantage.
Study
The programme aims to study and document rural domestic energy practices in general
and biogas user experiences in particular. The study results will be used to direct the
programme and -on the medium term- to justify and direct continuation of a domestic
biogas programme in Ethiopia.
Sectoral approach.
The programme will strongly promote an approach in which Government, non-
government and private sector organizations, in a complementary fashion assume
those programme functions that intrinsically fit to the character of their organization.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 77
3 Programme components.
The focus of the programme shall be the biogas sector as a whole. Sector development
implies the close cooperation of all relevant stakeholders (Government, Non-
Government and private sector) in the sector at all levels (micro and macro). The chart
indicates the main functions in a large-scale domestic biogas programme and its
relations.
25
For the proper application of bio-slurry as organic fertilizer, collection of the slurry would be a prime requirement. Double slurry
pits enable to collect slurry, mix it with other organic material, and leave it for curing for a short period.
26
It is acknowledged that 50% toilet connection in Ethiopia‟s context is a tall order. However, in view of the poor state of sanitation in
rural areas in its health consequences, the programme should be committed to invest significantly in proper promotion. Technically,
the programme will assure that all installations are equipped with a second inlet pipe to ensure attachment of a toilet at a later stage.
27
The assumption is that at the end of the programme 60% of the installations (6000 plants) are constructed with credit assistance.
This credit share will increase from 30% during the first year to 70% in the last programme year.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 78
To support the project‟s purpose, objectives for each of the programme components
have been formulated.
CN Component Objective
1 Promotion & marketing To stimulate demand, informing beneficiaries and stakeholders on the benefits
and costs of domestic biogas.
2 Financing To lower the financial threshold and improve access to credit and repayment
assistance, to facilitate easier access to domestic biogas for all potential
clients, with particular emphasis on the poor, women and other disadvantaged
groups.
3 Construction and After To facilitate the construction of 10000 domestic biogas plants and ensure their
Sales Service continued operation.
4 Quality Management To maximise the effectiveness of the investment made by the biogas owners
and to maintain consumer confidence in domestic biogas technology.
5 Training To provide the skills for business people to run biogas SMEs and for biogas
users to be able to operate their plants effectively
6 Extension To provide the information to allow biogas users to effectively exploit all the
benefits of biogas
7 Institutional Support To maximise the ability of key biogas related institutions to provide the
services and support required by the biogas sector to facilitate access to
domestic biogas and the development of quality biogas products.
8 Monitoring and To identify project progress and impact on stakeholders/other aspects in order
Evaluation to facilitate knowledge transfer.
9 Research and To increase knowledge about domestic biogas issues to maximise
Development effectiveness, quality and service delivery of the biogas programme.
10 Programme management To support, coordinate and supervise the activities driving the development of
(National / Regional) a commercially viable biogas sector.
4 Expected results.
The table shows some of the main expected EBP expected results
results. The detailed overview is provided in
annex 5. Clearly, besides the environmental Biogas plant construction 10,000 [plants]
and energy aspects of domestic biogas,
Energy
significant results can be expected in the Energy production 197,960 [GJ]
socio-economic field and in training. Power installed 33,330 [kW]
Environment
GHG emission reduction 40,400 [t CO2eq]
Fuel substitution
Biomass 59,166 [t biomass]
Kerosene 61 [t]
Socio-economic
Persons reached 60,000 [persons]
Workload reduction (women & children) 2,020 [pers years]
Exposure to indoor air pollution reduced 30,000 [women & children]
Toilets attached 5,000 [toilets]
Productive slurry use 8,000 [households]
Employment generation (direct) 700 [person years]
Training
User training 14,000 [person days]
Professional training 2,741 [person days]
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 79
& Evaluation
Promotion &
Developmen
Managemen
Managemen
Institutional
Constructio
n and A.S.S
Programme
Research &
Investment
Monitoring
marketing
Extension
financing
Training
Support
Quality
t
EREPDC
NBPO
Bureaux of
Energy
RBPO
Bureaux of
Agriculture
Kebele ext
workers
Regional MFIs
Biogas constr.
teams
Selam VTC
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 80
The Ethiopian Rural Energy Promotion and Development Centre will take overall
coordination and supervision responsibility. The Centre will be responsible to develop a
productive rural energy network at national and regional level. The EREPDC ensures
proper cooperation with regional level partners and tunes the (national) programme
strategy with its other rural energy activities and similar activities of other actors.
The National Biogas Programme Office established within the EREPDC (possibly
within the biomass department), will take operational responsibility. The NBPO will
develop construction and after sales service manuals; develop corresponding quality
standards and quality control procedures and training courses; implement quality control
and conduct training. The NBPO will prepare annual and semi annual plans and reports.
Selam Technical and Vocational Centre will, together with the NBPO, implement the
main training components of the programme. To that extent, STVC will provide training
at “Technician” level, for staff of the BoEs and the RBPOs and training at “Construction”
level, for the rural Biogas Construction Teams.
The Bureaux of Energy will have regional coordination and supervision responsibility.
The Bureaux will develop a productive rural energy network at regional, woreda and
kebele level. The BoE ensures proper cooperation with woreda and kebele level
programme partners (Bureaux of Agriculture network, NGOs) and tunes the (regional)
programme with its other rural energy activities and similar activities of other actors.
The Regional Biogas Programme Offices, established within the Bureaux of Energy,
will take operational responsibility at regional level. The RBPOs will implement quality
control, extension and training activities. The Offices will prepare regional annual plans
and reports.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 81
Foundation for this outline is the production forecast. The programme proposes to
support the construction of 10,000 biogas plants over a period of 5 years. Production is
planned in 4 regions: Amhara, Oromia, SNNPRS and Tigray. Tentatively, the production
is evenly divided over the 4 regions. A survey at the start of the programme may
indicate a shift in this division, depending on actual demand and marketing
opportunities.
Initial production will be modest, but is expected to pick up as skills and awareness at
both demand as well as supply side increase. To facilitate effective supervision, it will be
crucial to construct in batches. Hence, for the first year the programme will stimulate to
construct in one Kebele of one Woreda in each
Distribution by years
region in the first year. Regionally, the Region Total 1 2 3 4 5
programme will thereafter gradually develop Amhara 2500 50 200 500 750 1000
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 82
6.1 Subsidy.
As argued earlier, the Ethiopian circumstances would justify an investment subsidy
component. Tentatively, a flat rate subsidy amount of ETB 1,500 (€ 144) is proposed.
Further study should reveal the possibility of a two tier subsidy scheme, with a higher
subsidy level (ETB 2,000) for poorer and/or more remote areas. The subsidy fund
requirement of the programme will thus amount into € 1,441 million.
Annual subs requirement [Euro]
1 2 3 4 5 Total
investment 500
[Euro]
400
300
5.788 million.
Direct investment EBP (inflation correction in farmer investment) [Euro]
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 83
# of plants
6.3 Credit. 4500
The remaining investment will -despite the 4000 Credit Cash
subsidy- still be prohibitive for most rural 3500
3000
farmers. Hence, a proper credit facility will
2500
prove crucial for the success of the programme. 2000 `
1500
In these preliminary calculations it is assumed 1000
that in the first year 30% of the households get 500
0
a loan for the biogas investment. Subsequently,
th 1 2 3 4 5
the credit share shall increase to 70% in the 5
programme year. As a result, at the end of the programme 60% of the participating
households will have constructed their plant with credit assistance.
A “proper credit facility” has for these preliminary calculations been translated in a loan
maturity of 5 years, interest rate of 12% per annum and a one year grace period. Of the
total programme investment principal amount of € 2.631 million, the financing costs 28
will thus result in € 1.149 million.
Investment financing [Euro]
1 2 3 4 5 Total
Loan repayment loan will cover the sanctioned EBP investment credit
Euro
1500000
amount after the 6th year.
1000000
500000
0
1 2 3 4 5 6 7 8 9 10
-500000 year
-1000000
-1500000
28
Financing costs: accumulated interest cost over the entire maturity period.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 84
For that purpose, the government will employ at least two dedicated staff at regional
level and make available proper accommodation. Together with other (part-time) BoE
staff this unit will form the Regional Biogas Programme Office.
Summary Regional Support Budget (total programme, not corrected for inflation) [Euro]
Budget
# of regions: 4 1 2 3 4 5 total
Total Provincial Support Budget 59,467 83,202 159,443 175,586 216,825 694,523
Reg Sup / plant 69.45
Total National Support Budget 273,489 264,174 305,774 323,623 334,266 1,501,326
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 85
Within the national programme budget, a separate reservation has been made to
refurbish existing biogas installations in the programme‟s area op operation. Non- or
poorly functioning biogas plants are detrimental to promotion of the technology. Hence,
the programme will provide support to those households that need assistance in
updating their installation.
1.01 Senior Technical Advisor (EUN) 115,200 96,000 76,800 57,600 38,400 384,000
1.02 Junior Technical Advisor (EUN) - 84,000 70,000 56,000 28,000 238,000
1.11 Senior Technical Advisor (HCN) 16,800 16,800 16,800 16,800 16,800 84,000
1.12 Junior Technical Advisor (HCN) 12,000 12,000 12,000 12,000 12,000 60,000
1.21 Additional advisory services 6,000 6,000 6,000 6,000 6,000 30,000
1.22 Other support expenses 5,000 5,000 5,000 5,000 5,000 25,000
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 86
Application of funds [Euro] [%]
1 Investment
6.7.1 Application of funds. 1a Farmer investment 4,349,028 63%
1b Credit fiancing costs 1,149,649 17%
Investment, for the construction of 10000 1c Investment subsidy 1,440,922 21%
2 Programme support
2a Regional support RBPO 694,523 23%
The remaining 30% (€ 3 million) will be applied 2b National support NBPO 1,501,326 50%
2c Technical assistance 821,000 27%
for programme support. Divided over the 4
participating regions, € 695 thousand will be Total project support 3,016,848 30%
Investment
70%
million, is sourced by the participating farmers a2 Credit financing costs 1,149,649 21%
either directly but more likely indirectly, through Total participating farmers 5,498,676 55%
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 87
In general a biogas programme fits well into the latest insights regarding sustainable
development. Opportunities include access to funding and cooperation with similar
initiatives.
Threats can be defined in the climatic conditions, poverty and agricultural customs and
the political situation in the region.
.
7.1 Opportunities.
The GEF operates in a one-on-one co-financing facility in three steps. Submission for
co-funding of programme identification (PDF A) and formulation (PDF B) and possibly
implementation (PDF C) should be considered.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
5 Programme outline Page 88
7.2 Risks.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 1
Terms of Reference for the feasibility study
4. Time schedule
The mission to Ethiopia shall be completed within a period of three weeks starting mid-March 2006. The
draft report shall be submitted before 30 April 2006. SNV/Ethiopia, members of BPT, RNE/Addis Ababa
and DGIS/DMW will provide within 10 working days comment on the draft report. After that, the final study
report will be presented within five working days.
6. Expected output
Annex 1
Terms of Reference for the feasibility study
The report on the feasibility study shall be well-structured and clearly written in English not exceeding 50
pages excluding annexes and provide informed recommendations on the possibilities to set-up a national
programme on domestic biogas in Ethiopia. Annex I provides a tentative table of contents for the report.
8. Further arrangements
Prior to departure to Ethiopia, the team leader will after consultation with SNV/Ethiopia and RNE/Addis
Ababa come up with an itinerary for the mission. The mission team is free to discuss any matter
concerning the assignment with any institution or individual, but is not authorised to make any official
commitments on behalf of SNV, RNE/Addis Ababa or DGIS/RNE.
9. References
Ethiopia: Building on Progress: A Plan for Accelerated and Sustained Development to End Poverty
(PASDEP). Ministry of Finance and Economic Development. October 2005.
Identification Study on Renewable Energy and Energy Efficiency in SNNPRS and Ethiopia. Dr.
Getachew Eshete et al. May 2004.
Email correspondence with
Mrs Janny C. Poley, First Secretary RNE Horn of Africa Programme
Mr. Rem Neefjes, PC SNV Ethiopia
Mr. Christopher Kellner, Senior Advisor Biogas, SNV Nepal.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 1
Terms of Reference for the feasibility study
Title page
Acknowledgement
Summary
Table of Contents
Abbreviations
1. Introduction and background
- Country background
- Agricultural & livestock sector
- Energy demand and supply, policy and plans
- Safety situation
2. Objective, methodology and limitations
3. History and analysis of domestic biogas
- Link between domestic biogas and the MDGs, national and regional policies of the Government
of Ethiopia
4. Potential demand for domestic biogas
- Current consumption of energy in the rural areas
- Current application of manure
- Climatic conditions
- Availability of water at livestock farms
- Role of women in decision making and livestock keeping
- Most potential areas for domestic biogas in Ethiopia
- Technical potential and benefits of domestic biogas
- Financial and economic potential for domestic biogas
5. Possible institutional set-up for a national biogas programme
- Required functions/services (promotion, operation & maintenance, construction & after sales
service, provision of micro-credit, training, R&D, quality control, extension (use of bio-slurry),
monitoring & evaluation (external), coordination at implementing level, coordination at policy
level)
- Possible providers of the required functions/services and their capacity needs
- Possible role of SNV and supply of advisory services (technical, ID/OD)
- Availability and possible role of other development agencies
6. Outline for a national programme on domestic biogas
- Objectives, output targets and programme duration
- Required tentative budget and possible financing
- Proposed programme management structure
- Required TA
- Assumptions and risks
7. Conclusions and recommendations
8. References
Annexes: - ToR
- Itinerary of the mission
- Contact details of visited organisations and individuals
-
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 2
Short description of the regions in the study area
Unfortunately, the team did only managed to lay hands on part of the full report. As a result, the
information hereunder provided does not have the same level of detail for all four regions
The Amhara Region constitutes ten administrative zones (North Shewa, East Gojam, West Gojam, North
Gonder, South Gonder, North Wollo, South Wollo, Oromia (Kemissie), Awi and Wag Hamra Zones) and
105 Woredas. 48 Woredas are earmarked as food deficit Woredas.
The region is affected by severe land and soil degradation, recurring drought, fragmented farm plots, (0.7
ha/HH,) high population, low literacy, and with poor delivery of research technology and extension
support.
The central highlands of Ethiopia, of which Amhara Region is the major part, under went several crucial
deformations during the tertiary period. This resulted in the appearance of large openings e.g. fissures,
rents and the production of prominent plateau, hills and mountains. Those diversified geological
formations produced complex and mosaic landscapes which made the region a center of diversity and
variability for various biological life and physical structures. The highlands, between the two major
massifs, Tekeze Gorge in the north and Abay Gorge to the south and the Rift valley escarpment in the
east, are an important watershed and source of major national and international rivers.
The high proportion of the younger population combined with the aged (4.8%) poses a very high degree
of dependency. More than 85% of the total population live in the highlands where the climate is mild, the
soils are productive and human and livestock pests and diseases are relatively absent. The majority is
rural with only 12% of the population residing in urban areas.
The Amhara Region has ten major and fairly homogenous agro-ecological zones (AEZs). The major part
of the region (37%) lies within the tepid to moist zone. This agro-ecological zone is predominantly located
in the central part, where there is high potential for crop production. Moisture deficit areas are found in the
hot to warm arid or hot to warm sub-moist agro-ecological zones (Wollo and Gondar zones).
Annex 2
Short description of the regions in the study area
1.4 Soils and Soil Erosion.
There are about twelve distinct soil types in the region. Depressions and flat plains are mainly covered by
black clay soils (Vertisoils). Undulating to gently rolling areas are characterized by dark reddish to brown
colored deep soils (Luvisoils, Nitosoils and Acrisoils). The mountainous and degraded landscapes of most
parts of Wollo and North Gondar are dominated by shallow and stony soils. The major alluvial plains in
the east are predominantly Fluvisoils and Vertisoils with some saline and sodic traces. The highlands of
Amhara suffer from severe soil erosion and degradation.
The regional survey indicated that about 250,800ha is suitable for irrigation and 120,000ha can be
developed by micro-dams and river diversions. At present 15.5% (40,000 ha) has been brought under
irrigation, 97% of these by traditional means.
Prominent friable red and brown clay soils on relatively flat land in Gojam and Awi are potential crop
farming zones and are considered as food self-sufficient areas. The bottom wet lands like Woreta/ Fogera
plains, Chefa-Borkena and Qobbo Valley are crossed by several rivers and are considered as potential
irrigable and rice production areas.
Potable safe water distribution is an unresolved development problem and closely related to gender
issues. Only 10.3% of the population receives clean water and substantial numbers of people walk 5-7
km to fetch water.
1.8 Energy.
Biomass from wood, coal, cow dung and crop residues are the main energy sources, accounting for 99%
of the total fuel needed for domestic use. Alternative energy sources like wind, solar, earth-coal and
methane (bio-gas) gas are under study.
1.9 Wildlife.
There are many endemic mammals and birds in the Region. The Semen Mountain National park is known
for a number of rare wild life including Walya Ibex, Abyssinian Wolf, Chelada Baboon, Minelik bush buck,
Serine birds, etc. Low land animals are widely distributed at Metema and Quara areas and some in Bati
and Woredas bordering the Afar Region. Lake Tana, L.Hayik, Ardibo, May Bara and Gulbo are some of
the lakes (water bodies) that inhabit fish and other aquatic life.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 2
Short description of the regions in the study area
rain-fed, which in some places entails uncertainty due to the erratic nature of the rainfall. The major crop
types include cereals, pulses, oil-crops and tubers. Barley, wheat, teff, maize, sorghum, millet, faba bean,
peas, chickpeas, vetch, lentils, linseed, noug, sesame and oats (wild type) are widely grown in the
different agro-ecological zones of the region.
Cattle constitute 70% of the livestock population, and many of them are highland and 'senga' types. The
Fogera types, around Lake Tana, are potential milk yielder breeds. Sheep (highland sheep with fur) at
Debre Birhan; Amhed Guya and the Menz and Awassi types are potential wool type breeds in the Region.
Equines (horses, mules, sinar donkeys from Metema and camels) are commonly found in the Region.
Hides and skins are mostly used at home, with only small amounts reaching the market. Moreover, there
is no processing plant in the region. Veterinary service is poor in the highlands. Due to limitations in
accessibility, periodic vaccination for epidemics and sporadic diseases is greatly hampered.
Women are responsible for fetching water to the household. In many cases they travel long distances (5-
7km) in search of water.
1.13 Education.
Regional reports indicate that between 40 and 50% of the total population can not read and write. Only
13% of the estimated school age children attend schools. There are 2,506 primary schools, 228 junior
and 76 senior secondary schools.
The primary schools enroll about half a million students, which account for about 18% of the total primary
school age children. The junior and senior secondary schools enroll only 8.3% and 5.4% of the total
population (between 15 and 18 years of age), respectively.
Technical and vocational schools are few, three in number, with a capacity of 700 students at a time.
These institutions train middle level manpower in the fields of mechanics, electricity and commerce.
Community skill training is also given in 114 centers although many of these centers were ruined and
looted during the transition period to the new Government, ten years ago.
There are also three teacher training and three higher training institutes in the region. However, all the
schools and institutes lack adequate facilities, tools, equipment and qualified instructors.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 2
Short description of the regions in the study area
1.15 Cultural Heritage.
There are many historical and cultural sites in the Region that are tourist attractions. The Lalibela rock
hewn churches, Gonder Castles, Mesela Mariam and Ankober Palaces, Tisesat Fals and the islands in
Lake Tana are the major cultural heritage sites. Limalimo and Tekeze gorges, Ras Dashen and Semien
Park, Wofwasha (birds), Gussa-ecology (Menez) and Dessie-Bati areas are also tourist attractions.
1.16 Income.
Average annual income per household is Birr 1,500 (for a household of 4.3 persons) and per capita
income is Birr 350. About 32% of the households are without oxen. The average land holding in the
highlands and the lowlands is 0.70 ha and 1.75 ha, respectively.
The region is divided into five administrative zones (Western, Central, Eastern, Mekele and Southern
Zones). It has 35 Woredas, 603 development centers (Tabias) and 2,272 kushets. Tabias are the main
development centers, which are the basic units of the administrative structure.
Tigrai exhibits three distinct topographical zones; the central highlands, the north- western lowlands and
the eastern lowlands. The central highlands are an extension of the central highlands of the country with
an elevation of between 1,500 and 3,200masl, the highest peak being 3,900masl. As this ecological zone
is safe from malaria and most other diseases, population density is very high, which through time led to
degradation of the natural resources. The northwestern lowlands are sparsely populated and have soils
that are less eroded and exploited. Close to the Sudanese border, elevation is as low as 500masl.
Malaria and livestock diseases are more prevalent in this zone. The eastern escarpment falls steeply from
the plateau of 2,900masl to the depressions in the Afar Region.
Seventy eight percent of the population of the 15-64 age groups is economically active and 1,226,970
persons are employed in various sectors of the economy. The rate of unemployment for the total
population of the region, by sex, is 1.5% and 1.7% for males and females, respectively. Fertility rate is
5.4% for the region. Estimated infant mortality rate is 123/ 1000 births and life expectancy is 49 years.
The larger proportion of the population is concentrated in the highlands, mainly in the eastern part. The
western lowlands are sparsely populated. The settlement pattern is in scattered villages with a limited
number of houses in each village. The pattern poses problems to provide services like health, schools,
water supply, electricity and communications. There is also lack of well-developed rural centers, small
and middle sized towns, which can perform necessary functions for the rural hinterland.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 2
Short description of the regions in the study area
just south of Mekele and southward along the eastern part of Tigrai highlands, the short rains prevail,
which last 45 to 65 days.
The mean annual rainfall and the length of the growing period increases considerably when one moves
from lower to higher altitudes and from east to west. The length of the growing period varies from 120
days in the western part to 90 days along the Eastern Escarpments and eastern low lands (TRBIMPP,
1997/98).
The mean temperature in the lowlands of Tigrai is 250c. In the eastern part, along the foot slopes of the
great escarpment, separating the lowlands from the highlands, the temperature ranges from 25 to 280c.
Also, in the extreme western part of theregion, where altitude falls below 1000masl and along the Tekeze
0 0
River, mean temperature is about 25 c. Temperature of 15 to 18 c is restricted to the ridges of the
highlands, which run west east from Inda Silassie to Adigrat, and the upper slopes of the escarpment.
According to TAFP's 1996 survey, there are four main agro-ecological zones identified in the region.
These include:
hot to warm arid lowlands (found mainly in the eastern part of the region below 1,400 masl);
hot to warm semi-arid lowlands and plateau remnants (found on the extreme western of the region
between 500-1600 masl);
hot-to warm sub-moist lowland and plateau remnants (found in the south-western part of the region
and along the western part of the eastern escarpment); and
tepid to cool sub-moist low to high altitude, which occupies the central and north western part of the
region with altitude varying from 1000 to 3000masl.
Soil and water conservation activities have included planting trees around gullies to stabilize the check
dams. The most significant biological conservation measures accomplished include the establishment of
area closures. In the region, excluding the southern zone, about 143,016 hectares of uncultivated and
overgrazed hillsides are enclosed (TFAP, 1996).
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 2
Short description of the regions in the study area
The long history of intense human settlement has left an extremely degraded landscape. Most of the
climax vegetation, especially on the highlands, has been transformed to grass and shrubs vegetation.
However, there is an indication from the remnant vegetation that the highland areas, above 2,000m, were
covered by Podocarpus gracilior, Olea africana, Cord/a africana and highland Acacia of various types.
The lower valleys and the western lowlands were covered with deciduous woodlands and shrub-lands
mostly dominated by species like Acacia spp., Boswellia spp., etc. At present, severe fuel wood scarcity
prevails in almost all areas of the region, more in the highlands than in the lowlands, and better in
localities close to forest degraded wood lands compared to the predominantly clear agricultural
landscapes.
The region has a total livestock population of 2,533,047 TLU. Of the total livestock population, 3,040,712,
1,465,693 and 935,337 are cattle, goats and sheep, respectively. Equines are important pack animals in
transporting input and output to rural and urban markets. They are also important in human transport
(horses & mules). Among the equines, donkeys stand first in quantity with a total number of 303,405
followed by mules (10,417) and horses (5,110). There are also camels (13,661) and poultry (3,765,276).
The region produces significant amounts of good quality honey from 164,580 colonies of beehives (ILCA
1990).
2.11 Education.
According to the Bureau of Education (1999/2000), there were about 289,319 students from grade 1 to
grade 6 in governmental and 9,503 students in non- governmental schools. In addition to this, there were
about 27,131 students from grade 7 to 8 in government and 1,713 in non-governmental schools.
Similarly, the number of students from grade 9 to grade 12 in governmental and non-governmental
schools was 16,213 and 546, respectively. Moreover, there are about 7 colleges/universities in the region
enrolling 1,663 students (BETR 1999). Besides this normal educational program, there is a program of
literacy for the adult population. So far, 12 rounds of literacy campaigns have been undertaken and
136,587 males and 74,520 females have participated in these rounds (BETR 1999/2000).
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 2
Short description of the regions in the study area
2.13 Cultural Heritage.
There are a number of cultural heritages that are very much impressive to both national and international
visitors. These include, among others, the obelisks of Axum, the churches of Debre Damo and Abrha
Woatsebha, and the historical mosque of Negash.
The topography of Oromia includes high and rugged mountain ranges, undulating
and rolling plateaus, panoramic gorges and deep incised river valleys and rolling plains. The altitude
ranges from about 500 masl. in the Rift Valley to about 4,200masl at Batu Mountain, the highest peak in
the region. Over three fourths (75.9%) of the region lies between 1,000 and 2,500 masl.; 17% below
1000 masl. and the remaining 7.1 % fall in altitudes above 2,500 masl.
Thirty percent of the land of the region is estimated to have a slope gradient of below 0.5%, which
includes the low plains, river and rift valley floors. Five percent of the landmass of the region, having
slope gradient of above 15%, is characterized by severe erosion risks. About 65% of the region is
potentially utilizable from the viewpoint of good surface drainage and low risks to soil erosion.
Highland Oromia attracts heavy precipitation particularly in the summer from moisture-laden southwest
tropical monsoon winds that cross the Atlantic Ocean. Over a quarter of the region receives 800-1200mm
of rainfall (mean annual), while its arid lowlands and wet highlands receive mean annual of less than
800mm and over 1,600mm, respectively. In these areas, especially in the arid and semi arid portion of the
region, rainfall variability is so high that it seriously affects crop production. Late onset and early cessation
of rains causes heavy damages on crop and livestock production. It is estimated that, in the highlands,
rainfall can reduce production by 50% while in the lowlands the reduction could be as high as 70 to 90%
of the normal average.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 2
Short description of the regions in the study area
the region. Almost half of the regional surface cover is Cenozoic basalts and sediments, while 28.8% is of
old Mesozoic sedimentary rock cover.
Soils of volcanic origin dominate the central high plateau of the region. The soils include Cambisols,
Phaeozems, Luvisols and Vertisols. Except the Vertisols, which are constrained by poor drainage, the
others are mostly utilized for cropping. Other major soil units of significant coverage include Acrisols and
Nitosols, both characterizing the western section of the western sub region and the northern Borena area.
Soils of arid climate, gypsic soils, occur in the rift valley system and the lowlands of eastern sub region.
3.7 Wildlife.
The region is home for various types of wildlife. There are a number of national parks (Awash, Bale
Mountains and Abjata Shala), sanctuaries (Babile and Yavelo), game reserves (Bale and Awash West)
and controlled hunting areas (Borena, Bale, Chercher / Arba Gugu, Segen and Awash West) covering
some 97,667km2.
Water born and water related diseases are the major health problems of the region. Among these,
malaria, helementhiasis and diarrhoea dominate. Malaria is the most prevalent health problem of the
region. It occurs in all the areas below 2000 masl, and was the first amongst the top ten diseases
registered in several health centers of the region, in the year 2000. The major types of malaria parasites
commonly found in Oromia regional state are Plasmodium vivax and Plasmodium falciparium.
Other intestinal parasites are the ones mainly associated with poor quality of drinking water, unsanitary
living environment and poor personal hygiene, which are common in the region. The major intestinal
parasites frequently encountered are Amoebae, Ascaris, Gardia & tapeworm. Upper respiratory tract
infections, Pneumonia, Subcutaneous tissue infections and skin infections are also common in the region.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 2
Short description of the regions in the study area
3.11 Education.
Though education services have been improving over the last six years, still most of the population has
no access to education facilities. Enrolment rates in primary schools (1-8) are only 52% and only 22.4%
of the population are able to read and write.
The existing road net work is mostly concentrated in the more productive zones of the central and
Western parts of the region, which are assumed to be areas of high economic importance. The poor
network in drought prone areas makes delivery of food aid extremely difficult and farmers obliged to carry
their produce to market places by pack animals or humans. This severely constrains the total farm
production that can be marketed and adds substantially to the cost of farm inputs and prices of other
consumption
The SNNPR occupies about 113,539 km 2 and accounts for about 10% the total area of the country. There
is a wide variation of altitude in the region, which ranges from about 380masl at Lake Turkana to about
4,210masl at Mount Guge in North Omo.
Administratively, the SNNPR is divided into 12 Zones and 77 Woredas. Seven of the woredas are Special
Woredas, which directly report to the regional government.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 2
Short description of the regions in the study area
4.4 Farming System and Crop Production.
The agricultural production of the region includes both food crops and cash crops. Root crops such as
cassava, yam, taro, and sweet potato are predominantly found in the Woina Dega agro-climatic zone.
Cash crops such as coffee, cotton, and spices occupy an important place of the region's economy.
The region has an estimated population of 7.7 million cattle, 2.2 million sheep, 2 million goats and 1.3
million equines, approximately 1.14 animals per person.
The Agricultural Bureau of the region has aims at increasing productivity per unit of land, while minimizing
the dependency on rainfall by shifting towards water harvesting and irrigation development. It also
focuses on the introduction of high yielding, disease and pest resistant crops.
Pneumonia, helminthiasis (intestinal parasites), upper respiratory tract infections, dysentery and infection
of skin and subcutaneous tissue are among the main causes of outpatient visits. The majority of the
health problems are water related diseases that are transmitted by drinking contaminated water, or due to
lack of safe water for personal hygiene or through aquatic insects that depend on water for their breeding.
The top five causes of deaths (as recorded in 1999/2000) are malaria (19.5%), TB (15.0%) pneumonia
(15.8%), accidents (5.2%) and tetanus (3.2%). Gastro-enteritis and colitis, meningitis, dysentery, chronic
rheumatic heart disease, malnutrition and anemia are also among the causes of deaths in the region.
Malaria is by far the most important health problem in the region. It is well recorded that areas below
2,000m altitude are malarious, and short-lived transmission occurs even above 2,000m where the
microclimate is favorable. Most parts of the 12 administrative zones and the 7 special Woredas of the
region have endemic malaria transmission. Many Woredas of the region are also annually affected by
epidemic of the disease. For example, about 146,100 people living in 101 Kebeles in 25 Woredas were
affected by a malaria epidemic in 1999/2000. The entire 32 'Chronic food deficit' Woredas of the region
are known to be endemic for malaria.
Public health infrastructure of the region includes 12 hospitals (10 governmental and
2 non-governmental), 95 health centres (91 governmental and 4 non-governmental),366 clinics (310
governmental and 56 non-governmental), and 263 health posts. In addition, there are 109 private clinics
and 91 other governmental clinics (other than the regional health bureau). Furthermore, there are 31
pharmacies, 43 drug shops and 478 rural drug vendors in the region. In 1999/2000 there were 2,814
health personnel including 215 physicians, 792 nurses, 133 sanitarians, 10 pharmacists, 30 health
officers, 1447 health assistants, 41 pharmacy technicians, 104 laboratory technicians, 6 biologists and 23
X-ray technicians.
The Regional Rural Road Authority has recruited a consulting firm to carry out a regional master plan
study for road networking and prioritize future road construction and maintenance programs to effectively
utilize the resources.
Of the 32 chronic food deficit Woredas considered in this study, 25 Woredas have all weather road
network while the remaining 7 Woredas (Kemba, Zala, Ubamale, Dita Deramalo, Selamago, Maenit,
Surma and Dizi) do not have reliable all weather roads. The Woredas located in Wolayita and Gamo Gofa
zones have relatively good road networks.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
CONSTRUCTION MANUAL
FOR
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
Introduction:
The success or failure of any biogas plant mainly depends upon the quality of
construction works. To come to a successfully constructed biogas plant, the mason
should not only respect the dimensions as indicated on the drawing but also follow the
correct construction method. Hereunder, in a step by step fashion, the right construction
method of the 2047 design GGC model bigots plant is given.
The table below gives some relevant data about these six different sizes of biogas
plants.
A biogas plant consists of five main structures or components. The required quantity
of dung and water is mixed in the inlet tank and this mix in the form of slurry is
allowed to be digested inside the digester. The gas produced in the digester is
collected in the dome, called as the gas holder. The digested slurry flows to the
outlet tank from the digester through the manhole. The slurry then flows through the
overflow opening to the compost pit where it is collected and composted. The gas is
supplied to the point of application through the pipeline.
Before deciding the size of plant, it is necessary to collect dung for several days to
determine what is the average daily dung production. The amount of dung daily
available helps in determining the capacity of the plant.
If a plant is underfed, the gas production will be low. In this case, the pressure of the
gas might not be sufficient to displace the slurry in the outlet chamber. This means
that the amount of slurry fed into the digester is more than the amount of slurry
thrown out from the outlet. This will cause the slurry level to rise in the digester, gas
holder and it may eventually enter to the gas pipe and sometimes to the gas stove
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
and lamp while opening the main valve. Therefore, the slurry should always be fed
according tot he prescribed amount as indicated in the above table.
2. Construction Materials:
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
The following points should be kept in mind when deciding on a site for biogas plant
construction:
For proper functioning of the plant, the right temperature has to be maintained in
the digester. Therefore, a sunny site has to be selected.
To make plant operation easy and to avoid wastage of raw materials specially
the dung, the plant must be as close as possible to the stable (cattle-shed) and
water source. If the nearest water source is at a distance of more than 20
minutes walk, the burden of fetching water becomes too much and no plant
should be installed in such places.
If longer gas-pipe is used the cost will be increased as the pipe is expensive.
Furthermore, longer pipe increases the risk of gas leakage due to more joints in
it. The main valve has to be opened and closed before and after use. Therefore,
the plant should be as close as possible to the point of use so that the above
problems are eliminated.
The edge of the foundation of the plant should be at least two metres away from
the house or any other building to avoid risk of damages.
The plant should be at least 10 metres away from the well or any other under-
ground water sources to protect water from pollution.
Sufficient space for compost pits should be available.
When a suitable site is selected, a small peg has to be stuck in the ground at the
centre spot of the digester. A cord has to be attached to this peg with the length
indicated on the drawing under dimension “C”. Now this cord is the radius of the
digester pit and the circumference can be decided by moving the edge of the cord
on circular fashion. The pit depth is indicated on the drawing under dimension “E”.
The excavation work should only be started after deciding the location of manhole
and outlet tank. The pit walls should be as vertical as possible and, most important,
the pit bottom must be levelled and the earth must be untouched.
While digging, excavated soil should be thrown at least one foot away from the lay-
out, so that it does not fall inside the pit when the construction work is in progress.
After digging the pit, a suitable arrangement must be made for the inlet pipe(s).
If because of hard rock or under ground water, the right depth cannot be achieved,
the pit has to be made as deep as possible, while after completion of the structure
some protective measures have to be constructed so that the walls of outlet and
dome is supported well from outside. (see chapter 10)
5. Construction of Round-wall
At the centre of the pit, a straight rod or pipe (the 0.5” GI gas-pipe) must be placed in
an exact vertical position. At ground-level, a heavy pole or pipe has to be placed
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
horizontally over the centre of the pit. The vertical pipe can now be secured to the
horizontal pipe or pole. After securing, the vertical pipe has again to be checked
whether it is still in the right position.
A string or wire can now be attached to the vertical pipe. The length of this wire can
be found on the drawing under the dimension “F”. One cm has to be added to this
length to allow space for plastering. Every brick or stone which is laid in the round-
wall has to be exactly F + 1 cm away from the vertical pipe.
After deciding the radius of digester, the round-wall is started to be constructed. The
first row of bricks must be positioned on their sides so that a 4.5” high 9” wide base
is made. It is essential that first row is placed on a firm, untouched and level soil.
The next rows of bricks can be positioned on their lengths so that the wall thickness
becomes 4.5”. It is not necessary to make pillars in the wall but the backfilling
between wall and pit-side must be compacted with great care. This backfilling has to
be done in the morning before starting the construction work. Earth should be well
compacted by adding water and gentle ramming all along the circumference of the
digester. Poor compaction will lead to cracks in round-wall and dome.
If stone is used for the construction of round-wall, the wall should rest against the pit-
side as it is difficult to have proper backfilling because of the irregular shape of the
outside of the stone wall. The cement mortar used can be 1 cement - 4 sand to 1
cement - 6 sand depending on the quality of the sand.
The height of the round-wall can be found on the drawing under dimension “H” when
measured from the finished floor. The dung inlet pipe and toilet pipe must be placed
in position when the round-wall is 35 cm high. To reduce the risk of blockage, the
inlet pipe(s) must be placed as vertical as practically possible. Exactly to the
opposite of the dung inlet pipe, a 60 cm wide opening must be left in the round-wall
which acts as manhole. The digested slurry also flows out to the outlet tank through
this opening. The inlet pipe from the toilet should be placed as close as possible with
the dung inlet pipe with a maximum distance of 45 degrees from the dung inlet on
the dung inlet-centre manhole line (hartline).
When the round-wall has reached the correct height, the inside must be plastered
with a smooth layer of cement mortar with a mix of 1 cement - 3 sand. The digester
floor can be made from bricks or small stones with plaster in cement mortar.
6. Dome Construction:
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
On the vertical centre pipe, a mark has to be made at a distance “J”, as given in
the drawing, from the finished floor. The compacted earth has to reach this level.
The vertical pipe can now be removed by pulling it upwards. It has to be replaced
by a shorter 0.5” dia. pipe, approx. 0.5 metres length in the earth exactly at the
same spot. Now the template should be used to make the shape of the dome.
The top of the round-wall must be clean when the template is in use. The
template can be checked by making sure the top is horizontal and the side
exactly vertical. Furthermore, the part of the template that touches the round-wall
must be in the same position all over the round-wall.
It is important that the earth of the mould is well compacted. If the earth is further
compressed after casting the dome, by its own weight and that of the concrete, it
can lead to cracks in the dome. When the earth mould has the exact shape of the
template, a thin layer of find sand has to be spread on the mould-top by gently
patting it on the surface. Any excess sand or soil that falls on the round-wall has
to be removed. The earth used for the mould has to be damp to prevent dry earth
from soaking up water from freshly concrete.
Before starting the casting work, enough manpower and construction materials
like sand, gravel, cement and water has to be collected on the site. The casting
has to be done as quickly as possible and without interruptions as this will
negatively affect the quality of the cast. A constant, adequate supply of concrete
(mix: 1 cement, 3 sand, 3 gravel) must be made for the mason. No concrete
older than 30 minutes should be used.
A special care should be taken to maintain the thickness of dome while casting,
i.e. the thickness; in and near the edges should be more than the thickness in the
centre. for 6, 8, 10 & 15 cubic metres plants, the thickness in the edge should be
25 cm whereas thickness in the centre should be 7 cm. Similarly, for 4 and 20
cubic metres plats, the thickness in the centre should be 7 & 9 cm respectively
and the edge should be 22 and 28 cm respectively.
The small pipe on the top of the mould must be left in place till the main gas pipe
is installed. This is to make sure that the main gas pipe is exactly in the centre.
Already during the casting, the concrete has to be protected against strong
sunlight by covering it with jute bags or straw mats. This protection has to be left
in place for at least one week. The day after the casting, the turret must be made.
Any delays can lead to leakage between main gas pipe and dome. Also from the day
after the casting onwards, the dome has to be sprinkled with water 3 to 4 times a
day which is known as „curing‟. After approximately one week, depending on the
temperature, the earth of the mould can be removed through the manhole. When all
earth is removed, the inside of the dome, has to be thoroughly cleaned with a brush
and clean water.
On the clean surface the following plaster coats have to be applied to make the
dome gas-tight.
a) Cement - water flush.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
b) 10 mm layer, 1 cement - 2 sand, plaster.
c) 5 mm layer, 1 cement - 1 sand, punning.
d) Cement/acrylic emulsion paint coating, 1.5 paint - 20 cement.
e) Cement/acrylic emulsion paint coating, 1 paint - 2 cement.
A plaster coat must be at least one day old before the next layer can be put on.
When a layer of plaster is applied, the work must be executed with the greatest care
and without interruptions. The well - functioning of the plant is very much depending
on the gas tightness of dome.
To construct the outlet tank, excavation has to be done just behind the manhole. The
level of excavation can be measured from the digester floor by taking the dimension
“I” minus the thickness of the digester floor. The earth behind the manhole and
under the outlet floor has to be very well compacted otherwise cracks will occur.
The inside dimensions of the outlet can be found on the drawing under A, B and
D. The distance from the digester floor to the outlet floor is given by the
dimension “I”.
It is important that these dimensions should be accurate as they determine the
useful capacity of the gas holder. For the same reason the outlet floor and the
top of the walls have to be in level. The walls have to be vertical and finished with
a smooth layer of cement plaster (mix: 1 cement - 3 sand). On the outside, the
walls have to be supported with sufficient earth body upto the overflow level. This
again is to avoid cracks.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
men without great difficulty.
The surface on which the slabs are cast, has to be flat and clean. Special care has
to be taken for the compaction of the concrete, as small holes will expose, the steel
reinforcement to corrosive vapour coming from the slurry in the outlet and will cause
the corrosion which may ultimately lead to the slab collapse. Hence, if holes are
formed in the slab these should be blocked with plaster layer. The outlet cover slabs
are essential to protect people and animals from falling inside and to avoid
excessive vaporization of the slurry in dry season.
For all slabs:
1. Thickness : 3” (7.5 cm)
2. Cover : 1” (2.5 cm)
3. C/C spacing (longitudinal) : 6” (15 cm)
4. C/C spacing (cross sectional) : 1‟ (30 cm)
5. Concrete ratio (cement:sand:gravel) : 1:2:4
6. Curing period : One week
Note: Casting should be done on a levelled surface and plastic sheets or empty cement bags should be used as bed sheets.
The inlet pit is constructed to mix dung and water. This can be constructed with or
without a mixing device. Installation of mixing device is preferable not only because
it makes plant operation easier for the user but also because it improves the quality
of mix. When a mixer is installed it has to be firmly attached to the structure, easy to
operate, effective in the mixing process and steel parts in contact with the dung are
to be galvanised.
The top of the structure should not be more than one metre high nor less than 50 cm
from the ground level and both inside and outside of the pit has to be covered with a
smooth layer of plaster (mix: 1 cement - 3 sand).
The bottom of the tank, must be at least 5 cm above the outlet overflow level. The
position of the inlet pipe in the floor must be such that pole or rod can enter through
it without obstructions. For the same reason the inlet pipe must be without bends.
Even though mixing devices is not installed, the inlet pit should be round in shape as
this is more economical material-wise and easier for hand mixing.
In case of toilet attachment to the plant it is better to construct without siphon or trap
as the pan with siphon needs more water which may result excess water inside the
digester. It is also not possible to de-block the pipe when the toilet has a trap. The
toilet should not be farther than 45 degree from the hartline. Additionally, the toilet
pan level should be at least 15 cm above the outlet overflow level.
9. Lay-out of Pipeline:
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
The gas pipe conveying the gas from
the plant to users point is vulnerable for
damages by people, domestic animals
and rodents. Therefore, only light quality
galvanised iron pipe should be used
which must be, where possible, buried 1
foot below ground level. Fittings in the
pipeline must be sealed with zinc putty
and Teflon tape. Any other sealing
agent, like grease, paint only, soap etc.
must not be allowed. To reduce the risk of leakage, the use of fittings, specially
The biogas coming from the digester is saturated with water vapour. This water
vapour will condense at the walls of the pipeline. If this condensed water is not
removed regularly, it will ultimately clog the pipeline. Hence, a water drain has to be
placed in the pipeline. The position of the water drain should be inclined below the
lowest point of the pipeline so that water will flow by gravity to the trap. Water can be
removed by opening the drain. As
this has to be done periodically the
drain must be well accessible and
protected in a well-maintained drain
pit.
As soon as there is gas production, all joints and taps must be checked for leakage
by applying a thick soap solution. If there is leakage the foam will either move or
break.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
Compost pits are an integral of the biogas plant: no plant is complete without them. a
minimum of 2 compost pits must be dug near to the outlet overflow in such a way
that the slurry can run freely into the pits. Enough earth body must remain however,
at least 1 metre, between the pits and the outlet chamber to avoid cracking of the
chamber walls. The total volume of the compost pits must be at least equal to the
plant volume.
To make a potent and easy to use as fertiliser, the compost pits should be filled with
agricultural residues together with the slurry from the plant.
The earth coming from digging the compost pits can be used for backfilling of the
inlet and outlet chamber and for top filling over the dome.
For proper
insulation during the
cold season and as
counter-weight
against the gas
pressure inside, a
minimum top filling
40 cm compacted
earth is required on
the dome. If e.g. because of high ground water table, the plant is not positioned
deep enough, the top filling will be prone to erosion due to wind and rain. In these
cases, proper protection, i.e. with a dry stone circular wall, has to be applied.
Notes:
1. Length and width mentioned in the above table can be changed according to the
space available without changing the volume of the pits.
2. If possible Length, Width should be doubled.
3. Depth of the pit should not exceed 1 metre (100 cm) due to safety reason.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
If the concerned mason and plumber strictly follow the above described instructions
during the construction phase, the complete plant will be of high quality. Hence, the
plant owner will be benefited ultimately from the investment and positive return will
be achieved as per the expectations. This again will persuade his relative and
neighbours to install a biogas plant as well, while a poorly constructed plant will do
harm to the reputation of biogas technology.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 3
GGC 2047 construction manual
3
Dome templates 4 6 8 & 10 M
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 4
Expected results
Biogas plant construction annual [# of plants/yr] 200 800 2000 3000 4000 10000 [plants]
cumulative [# of plants] 200 1000 3000 6000 10000
Energy
Energy production 9.80 [GJ/plant/yr] 1960 9800 29400 58800 98000 197,960 [GJ]
Power installed (nett) 1.65 [kW th/plant] 330 1650 4950 9900 16500 33,330 [kW]
Environment
GHG emission reduction 2 [tons CO2 eq/plant/yr] 400 2000 6000 12000 20000 40,400 [t CO2eq]
Fuel substitution
Biomass
Agricultural residue 0.45 [tons agric res/plant/yr] 90.6 453 1359 2718 4530 9,151 [t]
Dung cake 0.63 [tons dungcake/plant/yr] 125.6 628 1884 3768 6280 12,686 [t]
Fuelwood 1.76 [tons fuelwood/plant/yr] 351.6 1758 5274 10548 17580 35,512 [t]
Charcoal 0.01 [tons charcoal/plant/yr] 1.8 9 27 54 90 1,818 [t]
Total biomass 2.93 [tons biomass/plant/yr] 585.8 2929 8787 17574 29290 59,166 [t biomass]
Fossil
Kerosene 0.003 [tons/plant/yr] 0.6 3 9 18 30 61 [t]
Socio-economic
Persons reached (female) 3 [pers/biogas hh] 600 2400 6000 9000 12000 30,000 [women]
Persons reached (male) 3 [pers/biogas hh] 600 2400 6000 9000 12000 30,000 [man]
Workload reduction (women & children) 0.1 [pers-year/plant/yr] 20 100 300 600 1000 2,020 [pers years]
Exposure to indoor air pollution reduced (women &3chidren)
[pers/biogas hh] 600 2400 6000 9000 12000 30,000 [women & children]
Toilets attached 50% [connection rate] 100 400 1000 1500 2000 5,000 [toilets]
Productive surry use 80% [inclusion rate] 160 640 1600 2400 3200 8,000 [households]
Employment generation (direct) 0.07 [pers-year/plant] 14 56 140 210 280 700 [person years]
Training
User training
Pre construction training (female) 0.2 [pers-day/plant] 40 160 400 600 800 2,000 [person days]
Pre construction training (male) 0.3 [pers-day/plant] 60 240 600 900 1200 3,000 [person days]
Post construction training (female) 0.4 [pers-day/plant] 80 320 800 1200 1600 4,000 [person days]
Post construction training (male) 0.1 [pers-day/plant] 20 80 200 300 400 1,000 [person days]
Bio-slurry extension (female) 0.2 [pers-day/plant] 40 160 400 600 800 2,000 [person days]
Bio-slurry extension (male) 0.2 [pers-day/plant] 40 160 400 600 800 2,000 [person days]
Total User Training 1.4 [pers-day/plant] 280 1120 2800 4200 5600 14,000 [person days]
Professional training
Project management & administration 0.003 [pers-day/plant] 1 3 7 10 13 33 [person days]
Biogas technology 0.054 [pers-day/plant] 11 43 108 162 216 540 [person days]
Biogas technology refresher 0.027 [pers-day/plant] 5 21 53 80 107 267 [person days]
Biogas construction 0.090 [pers-day/plant] 18 72 180 270 360 900 [person days]
Biogas construction refresher 0.053 [pers-day/plant] 11 43 107 160 213 533 [person days]
Operation check 0.040 [pers-day/plant] 8 32 80 120 160 400 [person days]
Biogas extension 0.007 [pers-day/plant] 1 5 14 20 27 68 [person days]
Total professional training 0.274 [pers-day/plant] 55 219 548 822 1096 2,741 [person days]
Annex 5
Outline activity schedule and budget
1 Production planning
Production per Region / Woreda per year
Distribution by years
Region Woreda Total 1 2 3 4 5
Distribution by years
Region Province Total 1 2 3 4 5
Distribution by years
Region Province Total 1 2 3 4 5
Distribution by years
Region Province Total 1 2 3 4 5
Distribution by years
Region Total 1 2 3 4 5
Distribution by years
1 2 3 4 5
3 Direct investment.
Investment costs / plant [Euro]
1 2 3 4 5 AVG
700
600
500
[Euro]
400
300
200
100
0
1 2 3 4 5
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 5
Outline activity schedule and budget
4 Investment credit.
Investment costs / plant [Euro]
1 2 3 4 5
3,780,798
1500000
1.1 Region / Woreda - level prom cpgn # of cpgn 1 3 5 5 5 19 1,000 1,000 3,000 5,000 5,000 5,000 19,000
1.2 Biogas awareness wsp (25 pers) # of wsps 4 16 40 60 80 200 100 400 1,600 4,000 6,000 8,000 20,000
1.3 Hh assessment & registration # of hh 50 200 500 750 1000 2500 1 50 200 500 750 1,000 2,500
[control %]
2.1 Annual operation check 100% 50 250 750 1500 2500 5050 1.00 50 250 750 1,500 2,500 5,050
2.2 Plant control & acceptance 100% 50 200 500 750 1000 2500 5.00 250 1,000 2,500 3,750 5,000 12,500
2.3 QC completed 10% 5 20 50 75 100 250 6.00 30 120 300 450 600 1,500
2.4 QC under construction 5% 3 10 25 38 50 125 10.00 25 100 250 375 500 1,250
2.4 Q administration # of reports 108 480 1325 2363 3650 7925 0.50 54 240 663 1,181 1,825 3,963
3.21 Biogas mason refresher wsp (20 pers) # of trg crs 2 6 14 16 38 400 - 800 2,400 5,600 6,400 15,200
3.4 User trg pre-cons (25 pers) # of trg crs 2 8 20 30 40 100 100 200 800 2,000 3,000 4,000 10,000
3.4 User trg op & maint (25 pers) # of trg crs 2 8 20 30 40 100 100 200 800 2,000 3,000 4,000 10,000
4.1 Demo slurry plots # of plots 10 10 10 10 10 50 30 300 300 300 300 300 1,500
4.2 Slurry applicaltion wsps (10 hh) # of wsps 10 25 40 50 125 100 - 1,000 2,500 4,000 5,000 12,500
4.3 Demo 3 in 1 & 4 in 1 plants # of plants 10 10 500 - - 5,000 - - 5,000
4.4 3 in 1 & 4 in 1 plant wsp (15 pers) # of wsps 5 5 10 200 - - - 1,000 1,000 2,000
4.5 3 in 1 & 4 in 1 plant follow up visit/plant 10 10 20 10 - - - 100 100 200
Summary Regional Support Budget (total programme, not corrected for inflation) [Euro]
Budget
# of regions: 4 1 2 3 4 5 total
Total Provincial Support Budget 59,467 83,202 159,443 175,586 216,825 694,523
Reg Sup / plant 69.45
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 5
Outline activity schedule and budget
6 National support budget
1.01
1.02 Dev & repr prom material ls/year 1 1 1 1 1 5 4,500.00 4,500 4,500 4,500 4,500 4,500 22,500
1.03 EBP PR material ls/year 1 1 1 1 1 5 2,500.00 2,500 2,500 2,500 2,500 2,500 12,500
1.04 Promotion activities ls/year 1 1 1 1 1 5 7,500.00 7,500 7,500 7,500 7,500 7,500 37,500
- - - - - -
1.11 Assessment survey existing plants survey 4 4 8 500.00 2,000 - 2,000 - - 4,000
1.12 Refurbishment support exisitng plants ls/plant 10 40 100 150 200 500 300.00 3,000 12,000 30,000 45,000 60,000 150,000
2.01 Subsidy transfer & administration # of transfers 200 800 2000 3000 4000 10000 2.00 400 1,600 4,000 6,000 8,000 20,000
2.11 Auditing # of audits 1 1 1 1 1 5 3,000.00 3,000 3,000 3,000 3,000 3,000 15,000
2.12 Financial monitoring # of regions 8 8 8 8 8 40 500.00 4,000 4,000 4,000 4,000 4,000 20,000
3.01 Biogas business development strategy survey 1 1 2 3,000.00 - 3,000 - - 3,000 6,000
3.02 Biogas business dev seminar (50pers) # of seminar 6 6 6 18 1,500.00 - 9,000 9,000 9,000 - 27,000
3.03 BCT assessment & coaching # of BCT 20 20 20 60 500.00 - 10,000 10,000 10,000 - 30,000
3.11 BCT Association support # of assoc 4 4 4 12 250.00 - - 1,000 1,000 1,000 3,000
[control %]
4.01 QCE completed 2% 20 30 40 60 80 230 50.00 1,000 1,500 2,000 3,000 4,000 11,500
4.02 QCE under construction 1% 10 15 20 30 40 115 75.00 750 1,125 1,500 2,250 3,000 8,625
4.03 Q administration # of reports 460 1965 5360 9540 14720 32045 0.20 92 393 1,072 1,908 2,944 6,409
6.01 Bio-slurry application study study 1 1 1 3 4,000.00 4,000 - 4,000 - 4,000 12,000
6.02 Dev bio-slurry manual ls/year 1 1 2 500.00 - 500 - 500 - 1,000
6.03 3 in 1 and 4 in 1 prom mat dev ls/year 1 1 2 750.00 750 - 750 - - 1,500
6.04 Print & distrib ext material ls/plant 200 800 2000 3000 4000 10000 1.25 250 1,000 2,500 3,750 5,000 12,500
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 5
Outline activity schedule and budget
7.01 Biogas Advisory Board establishment study 1 1 2 1,500.00 1,500 - - - 1,500 3,000
7.02 BAB support ls/yr 1 1 1 1 1 5 1,250.00 1,250 1,250 1,250 1,250 1,250 6,250
7.03 Training & staff development facility ls/region/yr 4 4 4 4 4 20 4,000.00 16,000 16,000 16,000 16,000 16,000 80,000
7.04 Infrastructure improvement facility ls/region/yr 4 4 4 4 4 20 3,000.00 12,000 12,000 12,000 12,000 12,000 60,000
Total research & development 32,250 29,250 29,250 29,250 32,250 152,250
8.11 Biogas & environmental impact study 1 1 2 4,000.00 - - 4,000 - 4,000 8,000
8.12 Biogas & gender study 1 1 1 3 6,000.00 6,000 - 6,000 - 6,000 18,000
8.21 External project progress evaluation evaluation 1 1 2 8,000.00 - 8,000 - 8,000 - 16,000
8.22 External final project evaluation evaluation 1 1 20,000.00
8.21 MSc / BSc study support ls/study 8 8 8 8 8 40 1,000.00 8,000 8,000 8,000 8,000 8,000 40,000
Total research & development 23,965 9,360 11,025 12,100 9,800 66,250
10.11 Coordinator pers month 12 12 12 12 12 60 750.00 9,000 9,000 9,000 9,000 9,000 45,000
10.12 Administrator pers month 12 12 12 12 12 60 600.00 7,200 7,200 7,200 7,200 7,200 36,000
10.13 IT / GIS systems officer pers month 12 12 12 12 12 60 450.00 5,400 5,400 5,400 5,400 5,400 27,000
10.14 Promotion & marketing officer pers month 6 12 12 12 12 54 300.00 1,800 3,600 3,600 3,600 3,600 16,200
10.15 Chief Biogas Engineer pers month 12 12 12 12 12 60 600.00 7,200 7,200 7,200 7,200 7,200 36,000
10.16 Biogas Engineer pers month 12 24 24 36 36 132 350.00 4,200 8,400 8,400 12,600 12,600 46,200
10.41 Other programme expenses ls/month 12 12 12 12 12 60 1,000.00 12,000 12,000 12,000 12,000 12,000 60,000
10.42 Utilities ls/month 12 12 12 12 12 60 500.00 6,000 6,000 6,000 6,000 6,000 30,000
10.43 Office expenses ls/month 12 12 12 12 12 60 500.00 6,000 6,000 6,000 6,000 6,000 30,000
10.44 Office furniture ls 0 8,000 750 2,000 1,000 1,000 12,750
10.45 Office equipment ls 0 20,000 1,000 10,000 1,000 1,000 33,000
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 5
Outline activity schedule and budget
Total National Support Budget 273,489 264,174 305,774 323,623 334,266 1,501,326
Promotion &
marketing
15%
Finance
4%
Construction &
a.s.s
5%
Project
management
36%
Quality assurance
3%
Training
11%
Research &
development Extension
5% 2%
Monitoring &
evaluation Institutional support
8% 11%
7 Technical assistance.
1.01 Senior Technical Advisor (EUN) pers month 12 10 8 6 4 40 9,600.00 115,200 96,000 76,800 57,600 38,400 384,000
1.02 Junior Technical Advisor (EUN) pers month 12 10 8 4 34 7,000.00 - 84,000 70,000 56,000 28,000 238,000
1.11 Senior Technical Advisor (HCN) pers month 12 12 12 12 12 60 1,400.00 16,800 16,800 16,800 16,800 16,800 84,000
1.12 Junior Technical Advisor (HCN) pers month 12 12 12 12 12 60 1,000.00 12,000 12,000 12,000 12,000 12,000 60,000
1.21 Additonal advisory services pers month 3 3 3 3 3 15 2,000.00 6,000 6,000 6,000 6,000 6,000 30,000
1.22 Other support expenses ls/yr 1 1 1 1 1 5 5,000.00 5,000 5,000 5,000 5,000 5,000 25,000
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Annex 5
Outline activity schedule and budget
8 Summary
1a Farmer investment 71,182 304,726 814,316 1,304,161 1,854,644 4,349,028 434.90 44%
1b Credit financing costs 9,331 53,259 177,903 341,902 567,255 1,149,649 114.96 12%
1c Investment subsidy 28,818 115,274 288,184 432,277 576,369 1,440,922 144.09 14%
2a Regional support (RBPO) 59,467 83,202 159,443 175,586 216,825 694,523 69.45 7%
2b National support (NBPO) 273,489 264,174 305,774 323,623 334,266 1,501,326 150.13 15%
2c Technical assistance 155,000 219,800 186,600 153,400 106,200 821,000 82.10 8%
Total project 597,287 1,040,434 1,932,219 2,730,949 3,655,558 9,956,447 995.64 100%
1 Investment
1a Farmer investment 4,349,028 63% 434.90
1b Credit fiancing costs 1,149,649 17% 114.96
1c Investment subsidy 1,440,922 21% 144.09
2 Programme support
2a Regional support RBPO 694,523 23% 69.45
2b National support NBPO 1,501,326 50% 150.13
2c Technical assistance 821,000 27% 82.10
a Farmers
a1 Farmer investment 4,349,028 79% 434.90
a2 Credit financing costs 1,149,649 21% 114.96
c SNV
d1 Technical assistance 821,000 82.10
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Addendum
Comments on draft study report by the EREDPC
The study team, through SNV Ethiopia, requested Ethiopia Rural Energy Development
and Promotion Centre (EREDPC), a key actor in the development and promotion of
rural domestic energy technology, for comments on the draft report.
These comments, from Mr. Kitane Workneh, Biomass Technology Study &
Development Team Leader, dated 26 June 2006, unfortunately only reached the study
team after the completion and submission of the final report.
Although part of the comments have been taken care of in the final report, in this
addendum a brief reaction on the comments.
Within the available time it was not possible to thoroughly visit entire Ethiopia. The
South-western / western areas of the country were excluded as the forest coverage in
these areas –in general- was believed to be such that the population would have
relatively easy access to (non-commercial) fuelwood. The team‟s assessment, hence,
was that promotion of domestic biogas would have less potential in these areas.
Nevertheless, here too deforestation looms as an environmental threat which could
indeed be mitigated by a domestic biogas programme.
It is very well possible that at the time of construction installations were actually sized
correctly. The observations of the team, however, indicate that in relation with the
current daily available cattle manure, most of the installations are too large.
Addendum
Comments on draft study report by the EREDPC
4 Biogas Appliances: All RTPC (Rural Technology Promotion
Centers) are producing their own Cooking stove and Biogas Lamps,
which is over looked by the team.
Noted.
Correct; in the draft report “Mirte” and “Lakech” were confused. In the final report this
has been corrected.
Selam Technical and Vocational Centre (STVC) is suggested as a well placed central
institution for initial R&D and training, particularly when a programme –as
recommended- would introduce uniform construction, design and quality standards.
Obviously, the outreach of STVC will be limited; with their experience, RTPCs can –and
should- play an important role in training, supervision and quality control at regional /
local level.
Noted and agreed. The biogas programme in Nepal actually proposes a distance limit of
20 minutes for water collection. In view of the generally large distances that Ethiopian
households have to travel for water and fuel, I thought it might be acceptable to suggest
slightly larger distances. Clearly, shorter distances are preferable.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Addendum
Comments on draft study report by the EREDPC
Agreed, the suggested equal distribution was solely intended as a first approach.
Factual potential and demand should be the actual key for distribution. The report
proposes regional-level studies to improve the insights in this matter.
Based on our field observations and backed up by population and livestock data, for
most of the households the amount of daily available dung would justify installations
with a digester volume of 4 to 6 m3. As also argued in the report, this amount of manure
will not fully satisfy the domestic energy requirement. The construction cost / volume
ratio is indeed higher for smaller installations, but the construction cost / gas production
ratio for a certain amount of feeding is optimal for the smallest feasible (correct
hydraulic retention time) size. Clearly, proper sizing shall be based on the actual
available feeding, and should be established in-situ.
Firstly, to stimulate the ownership awereness, the suggested subsidy levels are based
on the assumption that farmers make a significant own investment in the installation. In
case the programme would support polyethene installations, subsidy levels
consequently should be lowered. More importantly however, the track record –at least in
Asia- of polyethylene plants, in terms of durability and “operationability”, is not
encouraging. Despite the lower investment, in the service-context of rural Ethiopia, this
technology would not be the preferred option.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Addendum
Comments on draft study report by the EREDPC
and clearly stated as this is a core process for the success of
the biogas program.
In the final report, to which the outline budget is annexed, more detail is provided. In
brief technical training is proposed for masons –private biogas constructors- and
technicians –regional government staff. Training on operation and maintenance is
proposed for –in particular female- biogas owners. Further training is proposed in the
field of business management for small construction and manufacturing enterprises and
ToT (Training of trainers) for regional staff. A programme implantation document coud
provide further detail.
Noted, see also reply on comment 6. I suggest working out implementation details in the
programme implementation document.
Correct, and the omission is regretted. The report should have proposed a guarantee
arrangement similar to the ones used in the Asian biogas programmes (Nepal, Vietnam,
Cambodia, Bangladesh). In outline, these programmes charge a guarantee fee –directly
or indirectly- from the farmer. The programme manages this fund, and finances service
visits and guarantee cases from this fund.
The mandate of the study pertained specifically to domestic biogas. Although the team
visited WCDO head office in Addis Abeba and one project site in Awassa (and
appreciated their activities), it was not felt prudent to elaborate on this beyond
Report on the feasibility study of a national programme for domestic biogas in Ethiopia
Addendum
Comments on draft study report by the EREDPC
mentioning them in chapter 2.7.6 of section 2. However, during the formulation of the
programme implementation document –and later on during the actual implementation
for that matter- cooperation with WCDO can be considered.
Report on the feasibility study of a national programme for domestic biogas in Ethiopia