Updated 2016 IRR - 31 March 2021
Updated 2016 IRR - 31 March 2021
Updated 2016 IRR - 31 March 2021
25
The 2016 Revised Implementing Rules and Regulations
This Updated 2016 Revised Implementing Rules and Regulations, 2 hereinafter called the
IRR, is promulgated pursuant to Section 75 of Republic Act No. (R.A.) 9184, otherwise
known as the “Government Procurement Reform Act,” for the purpose of prescribing the
necessary rules and regulations for the modernization, standardization, and regulation of the
procurement activities of the Government of the Philippines (GoP).(a)
The provisions of this IRR are in line with the commitment of the GoP to promote good
governance and its effort to adhere to the principles of transparency, accountability, equity,
efficiency, and economy in its procurement process. It is the policy of the GoP that
procurement of Goods, Infrastructure Projects and Consulting Services shall be competitive
and transparent, and therefore shall undergo competitive bidding, except as provided in
Rule XVI of this IRR.(a)
d) System of accountability where both the public officials directly or indirectly involved
in the procurement process as well as in the implementation of procurement
contracts and the private parties that deal with GoP are, when warranted by
circumstances, investigated and held liable for their actions relative thereto.
2
The 2016 revised IRR was approved by the Government Procurement Policy Board (GPPB) through its Resolution 13-2016,
dated 9 August 2016, and published in the Official Gazette on 29 August 2016. It took effect sixty (60) days after its
publication or on 28 October 2016.
26
The 2016 Revised Implementing Rules and Regulations
4.1 This IRR shall apply to all procurement of any branch, agency, department, bureau,
office, or instrumentality of the GoP, including government-owned and/or -controlled
corporations (GOCCs), government financial institutions (GFIs), state universities and
colleges (SUCs), and local government units (LGUs).
4.2 Any Treaty or International or Executive Agreement to which the GoP is a signatory
affecting the subject matter of the Act and this IRR shall be observed. In case of
conflict between the terms of the Treaty or International or Executive Agreement
and this IRR, the former shall prevail.
The GoP negotiating panels shall, as its default position, adhere to R.A. 9184 and this
IRR, or at the very least, selection through competitive bidding, in all Foreign-funded
Procurement. If the Treaty or International or Executive Agreement states otherwise,
then the negotiating panel shall ensure that the reasons for the adoption of a
different rule or method of procurement are clearly reflected in the records of
discussion.(a)
b) Acquisition of real property which shall be governed by R.A. 10752 3, entitled “An
Act Facilitating the Acquisition of Right-Of-Way Site or Location for National
Government Infrastructure Projects,” and other applicable laws, rules and
regulations; and
4.5 The following are not procurement activities under R.A. 9184 and this IRR:
3
Repealed R.A. No. 8974.
27
The 2016 Revised Implementing Rules and Regulations
e) Joint Venture under the revised NEDA Guidelines (GOCC and Private Entities),
and Joint Venture Agreements by LGU with Private entities; and
For purposes of this IRR, the following terms or words and phrases shall mean or be
understood as follows:
a) Act . Refers to R.A. 9184, entitled “An Act Providing for the Modernization,
Standardization and Regulation of the Procurement Activities of the Government and
for other Purposes,” otherwise known as the Government Procurement Reform Act.
b) Approved Budget for the Contract (ABC). Refers to the budget for the contract
duly approved by the HoPE, as provided for in the General Appropriations Act (GAA),
continuing, and automatic appropriations, in the case of national government
agencies (NGAs); the corporate budget for the contract approved by the governing
board, pursuant to Executive Order (E.O). No. 518, s. 1979, in the case of GOCCs
and GFIs, and R.A. 8292 in the case of SUCs; the budget approved by the
Sanggunian through an appropriations ordinance in the case of LGUs. For multi-year
contracts, for which a Multi-Year Obligational Authority (MYOA) or an equivalent
document is required, the ABC shall be that incorporated in the project cost reflected
in the MYOA or equivalent document.
For Foreign-funded Procurement, the ABC refers to the cost estimate prepared by
the Procuring Entity and approved by the foreign government/foreign or international
financing institution as specified in the Treaty or International or Executive
Agreement.(a)
e) Bidding Docum ents. Refer to the documents issued by the Procuring Entity as the
basis for bids, furnishing all information necessary for a prospective bidder to
28
The 2016 Revised Implementing Rules and Regulations
prepare a bid for the Goods, Infrastructure Projects and/or Consulting Services
required by the Procuring Entity. (5.f)
f) Bids and Aw ards Com m ittee (BAC) . Refers to the Committee established in
accordance with Rule V of this IRR. (5.c)
g) Com m on-Use Supplies and Equipm ent (CSE). Refer to those goods, materials
and equipment that are used in the day-to-day operations of Procuring Entities in the
performance of their functions. For the purpose of this IRR, CSE shall be those
included in the Electronic Catalogue of the PhilGEPS. (a)
i) Consulting Services. Refer to services for infrastructure projects and other types
of projects or activities of the GoP requiring adequate external technical and
professional expertise that are beyond the capability and/or capacity of the GoP to
undertake such as, but not limited to: (i) advisory and review services; (ii) pre-
investment or feasibility studies; (iii) design; (iv) construction supervision; (v)
management and related services; and (vi) other technical services or special
studies. General principles on Consulting Services are provided for in Annex “B” of
this IRR.
j) Dom estic Bidder. Refers to any person or entity offering unmanufactured articles,
materials or supplies of the growth or production of the Philippines, or manufactured
articles, materials, or supplies manufactured or to be manufactured in the Philippines
substantially from articles, materials, or supplies of the growth, production, or
manufacture, as the case may be, of the Philippines.
k) Dom estic Entity . Refers to an individual or a sole proprietor who is a citizen of the
Philippines or a partnership, corporation, cooperative, or association duly organized
under the laws of the Philippines and of which at least seventy five percent (75%) of
the interest or outstanding capital stock belongs to citizens of the Philippines,
habitually established in business and habitually engaged in the manufacture or sale
of the merchandise covered by his bid, and the business has been in existence for at
least five (5) consecutive years prior to the advertisement and/or posting of the
Invitation to Bid. 4
l) Ex ecutive Agreem ents . Refer to International Agreements except that they do not
require legislative ratification.
m) Ex pendable Supplies. Refer to articles which are normally consumed in use within
one (1) year or converted in the process of manufacture or construction, or those
having a life expectancy of more than one (1) year but which shall have decreased
substantially in value after being put to use for only one (1) year (e.g., medicines,
stationery, fuel, and spare parts).
4
Preference to domestic entities, provided for under Commonwealth Act 138, dated 7 November 1936, which has been
expressly repealed by R.A. No. 10667, The Philippine Competition Act of 2015, shall no longer be applied.
29
The 2016 Revised Implementing Rules and Regulations
n) Foreign Bid. Refers to any offer of articles, materials or supplies not manufactured
or not to be manufactured in the Philippines, substantially from articles, materials, or
supplies of the growth, production, or manufacture, as the case may be, of the
Philippines.
p) Foreign Grants . Refer to grants with no repayment obligations and are provided in
monetary form, goods, works, and consultancy services, among others.
q) Foreign Loans . Refer to loans, credits, and indebtedness with private foreign banks
or with foreign governments, agencies, or instrumentalities of such foreign
governments, foreign financial institutions, or other international organizations with
whom, or belonging to countries with which, the Philippines has diplomatic relations,
as may be necessary and upon such terms and conditions as may be agreed upon, to
enable the GoP to finance, either directly or through any government office, agency
or instrumentality or any government-owned and controlled corporation, industrial,
agricultural or other economic development purposes or projects authorized by law.
r) Goods. Refer to all items, supplies, materials and general support services, except
Consulting Services and infrastructure projects, which may be needed in the
transaction of public businesses or in the pursuit of any government undertaking,
project or activity, whether in the nature of equipment, furniture, stationery,
materials for construction, or personal property of any kind, including non-personal
or contractual services, such as, the repair and maintenance of equipment and
furniture, as well as trucking, hauling, janitorial, security, and related or analogous
services, as well as procurement of materials and supplies provided by the Procuring
Entity for such services. The term “related” or “analogous services” shall include, but
is not limited to, lease of office space, media advertisements, health maintenance
services, and other services essential to the operation of the Procuring Entity. (a)
s) Governm ent P rocurem ent Policy Board (GPPB) . Refers to the Body created in
accordance with Rule XX of this IRR.
t) Head of the Procuring Entity (HoPE). Refers to: (i) the head of the agency or
body, or his duly authorized official, for NGAs and the constitutional commissions or
offices, and other branches of government; (ii) the governing board or its duly
authorized official, for GOCCs, GFIs and SUCs; or (iii) the local chief executive, for
LGUs: Provided, however, That in an agency, department, or office where the
procurement is decentralized, the head of each decentralized unit shall be considered
as the HoPE, subject to the limitations and authority delegated by the head of the
agency, department, or office.(a)
30
The 2016 Revised Implementing Rules and Regulations
w) Non-ex pendable Supplies . Refer to articles which are not consumed in use and
ordinarily retain their original identity during the period of use, whose serviceable life
is more than one (1) year and which add to the assets of the GoP (e.g., furniture,
fixtures, transport and other equipment). For this IRR, the term non-expendable
supplies shall include semi-expendable property. (a)
z) Portal . Refers to a website that integrates a wide variety of contents for the purpose
of attracting and aggregating multiple users together in a central virtual space.
aa) Procurem ent. Refers to the acquisition of goods, consulting services, and the
contracting for infrastructure projects by the Procuring Entity. In case of projects
involving mixed procurements, the nature of the procurement, i.e., Goods,
Infrastructure Projects or Consulting Services, shall be determined based on the
primary purpose of the contract. Procurement shall also include the lease of goods
and real estate. With respect to real property, its procurement shall be governed by
the provisions of R.A. 10752 and other applicable laws, rules and regulations. (a)
cc) Treaties . Refer to international agreements entered into by the GoP which require
legislative ratification after executive concurrence.
dd) Universal or Com m ercial Bank s . Refer to universal or commercial banks duly
authorized under R.A. 8791, otherwise known as “The General Banking Act of 2000.”
31
The 2016 Revised Implementing Rules and Regulations
manuals, standard Bidding Documents, and forms, including those to be used for
major procurement like drugs and textbooks. (a)
6.2 Procuring Entities are mandated to use the Generic Procurement Manuals (GPMs),
Philippine Bidding Documents (PBDs), and other standard forms issued by the GPPB.
However, whenever necessary, to suit the particular needs of the Procuring Entity,
modifications may be made, particularly for major and specialized procurement,
subject to the approval of the GPPB. (a)
7.1. All procurement shall be within the approved budget of the Procuring Entity and
should be meticulously and judiciously planned by the Procuring Entity. Consistent
with government fiscal discipline measures, only those considered crucial to the
efficient discharge of governmental functions shall be included in the Annual
Procurement Plan (APP). For purposes of this IRR, a procurement project shall be
considered crucial to the efficient discharge of governmental functions if it is required
for the day-to-day operations or is in pursuit of the principal mandate of the
Procuring Entity concerned. The APP shall include provisions for foreseeable
emergencies based on historical records. In the case of Infrastructure Projects, the
APP shall consider the appropriate timing/phasing of related project activities, such
as, engineering design and acquisition of right-of-way site or location, to
reduce/lower project costs. (a)
7.3. The APP shall be formulated and revised only in accordance with the following
guidelines:
7.3.1. Upon issuance of the budget call in the case of NGAs, SUCs, Constitutional
Commissions or Offices, or similar document for GOCCs, GFIs and LGUs, the
Procuring Entity shall prepare its indicative APP for the succeeding calendar
year to support its proposed budget taking into consideration the budget
framework for that year in order to reflect its priorities and objectives.(a)
7.3.2. In the preparation of the indicative APP, the end-user or implementing units
of the Procuring Entity shall formulate their respective Project Procurement
Management Plans (PPMPs) for their different programs, activities, and
projects (PAPs). The PPMP shall include:
32
The 2016 Revised Implementing Rules and Regulations
e) the time schedule for each procurement activity and for the contract
implementation; and
7.3.3. In order to hasten project implementation, Procuring Entities which may not
have the proficiency or capability to undertake a particular procurement, as
determined by the HoPE concerned, may outsource the procurement tasks
by:
7.3.4. The PPMPs shall then be submitted to the Procuring Entity’s Budget Office for
evaluation in order to ensure consistency with the Procuring Entity's budget
proposal and compliance with existing budgeting rules. The PPMPs included in
the budget proposal shall be forwarded to the BAC Secretariat for
6
As amended by GPPB Resolution No. 21-2017, dated 30 May 2017, published in the Philippine Daily Inquirer on 20 November
2017.
33
The 2016 Revised Implementing Rules and Regulations
consolidation into an indicative APP, and to the BAC for final recommendation
of the appropriate procurement modality. For this purpose, the indicative APP
shall include the following:
c) Method of Procurement;
e) Source of funds;
7.3.5. As soon as the GAA, corporate budget, or appropriation ordinance, as the case
may be, becomes final, the end-user or implementing units shall revise and
adjust the PPMPs to reflect the budgetary allocation for their respective PAPs.
The revised PPMPs shall be submitted to the BAC, through its Secretariat, for
the final recommendation of the methods of procurement. The indicative APP
shall then be revised and approved in accordance with Section 7.2 of this IRR.
The APP shall be submitted to the GPPB on or before the end of January of
the budget year, and shall be posted in accordance with E.O. 662, series of
2007, as amended. (a)
7.4. Changes to the individual PPMPs and the consolidated APP may be undertaken every
six (6) months or as often as may be required by the HoPE. The respective end-user
or implementing units of the Procuring Entity shall be responsible for the changes to
the PPMPs, while the BAC Secretariat shall be responsible for the consolidation of
these PPMPs into an APP, which shall be subject to the approval of the HoPE.
Changes in the APP, if any, for the budget year shall be submitted to the GPPB in
July of the current budget year, and in January of the following budget year. (a)
7.5. Except for procurement projects undertaken through early procurement activities
(EPA), the ABC as reflected in the approved APP shall be at all times consistent with
the appropriations for the project authorized in the GAA, continuing, and automatic
appropriations, the corporate budget, and the appropriations ordinance, as the case
may be. 8 (a)
For EPA, the posted ABC may be higher than the approved budget as long as the
contract price to be awarded is within the amount authorized in the GAA, reenacted
7
Refer to Appendix 2 for the Annual Procurement Plan (APP) format.
8
As amended by GPPB Resolution No. 14-2019, dated 17 July 2019, published in the Official Gazette on 26 August 2019.
34
The 2016 Revised Implementing Rules and Regulations
Procuring Entities are encouraged to undertake EPA to ensure the timely delivery of
goods, implementation of infrastructure projects and rendition of consultancy
services. The conduct of EPA for nationally-funded procurement projects may
commence as early as the submission of the NEP to Congress, usually in July. No
EPA may be conducted without an indicative APP duly approved by the HoPE and the
MYCA issued by the DBM, in the case of multi-year projects. This will facilitate the
awarding of procurement contracts upon approval and effectivity of their respective
funding sources or the reenactment of the previous year’s budget which constitutes
the current year’s authorized budget, when authorized by the Constitution, law or
rules. 11 (a)
For EPA, the indicative APP shall be based on the ABC in the proposed national
budget submitted by the President to Congress; for GOCCs, on budget levels as
proposed to the governing board; for LGUs, on budget levels as proposed in the
executive budget submitted to the Sanggunian; and for foreign-assisted projects
(FAPS), on the document issued by the foreign donor or financing institution
explicitly stating that a loan is to be made available to the Philippines or any of its
agencies or instrumentalities with borrowing authority.(n) 12
No award of contract shall be made until the approval and effectivity of the GAA,
corporate budget, appropriations ordinance or the loan agreement in the case of
FAPs. 13 (a)
9
Ibid.
10
Ibid.
11
Ibid.
12
Ibid.
13
Ibid.
14
Ibid.
15
As amended by GPPB Resolution No. 27-2019, dated 10 December 2019, published in the Official Gazette on 30 December
2019.
35
The 2016 Revised Implementing Rules and Regulations
8.1.2. To take advantage of the significant built-in efficiencies of the PhilGEPS and
the volume discounts inherent in bulk purchasing, all Procuring Entities shall
utilize the PhilGEPS for the procurement of Common-Use Supplies in
accordance with the rules and procedures to be established by the GPPB.
With regard to the procurement of non-common use items, Infrastructure
Projects, and Consulting Services, agencies may hire service providers
through competitive bidding to undertake their electronic procurement:
Provided, however, That these service providers meet the following minimum
requirements:
a) Comply with the provisions of the Act and this IRR, and R.A. 8792,
otherwise known as the “Electronic Commerce Act;”
b) Linked to the PhilGEPS, particularly with regard to the posting of all bid
opportunities and awards;
d) Ensure that the BAC shall have complete control of the bidding process,
and that the BAC’s sole authority to open bids is strictly observed;
f) Must provide for the use of electronic signatures and other current
electronic authentication devices;
36
The 2016 Revised Implementing Rules and Regulations
i) Electronic payment facilities, if used, shall comply with all laws, rules and
regulations issued by the Government.
8.1.3. The GPPB shall determine and certify compliance with the above
requirements. However, the GPPB may delegate this task to technically
capable agencies/offices/units of the Government.
a) The PhilGEPS shall have a centralized electronic bulletin board for posting
procurement opportunities, notices, awards and reasons for award. All
Procuring Entities are required to post all procurement opportunities,
results of bidding and related information in the PhilGEPS bulletin board.
b) Procuring Entities shall post the Invitation to Bid for Goods and
Infrastructure Projects or the Request for Expression of Interest for
Consulting Services, in the electronic bulletin board in accordance with
Section 21 of this IRR.
d) The PhilGEPS shall deny registration to or exclude from the registry any
party that is found to have willfully misrepresented any of the information
provided in the application for registration or who is in the “blacklist” of
the Government or any of its Procuring Entities in accordance with Section
69.4 of this IRR, including foreign government/foreign or international
financing institution whose blacklisting rules have been recognized by the
GPPB.
37
The 2016 Revised Implementing Rules and Regulations
c) Procuring Entities without internet access may avail of the PhilGEPS Public
Access Terminals which shall be installed at DBM-designated locations in
the provinces and in Metro Manila: Provided, however, That they shall
comply with Section 8.3 of this IRR.
d) The Electronic Catalogue may also feature non-common use items that
may be procured directly and without competitive bidding by Procuring
Entities from suppliers through the PhilGEPS Virtual Store: Provided,
however, That for an item to be carried in the Electronic Catalogue for
this purpose, the supplier thereof must have been determined as the
Lowest Calculated Responsive Bidder in a previous bidding conducted by
DBM-PS or by a Procuring Entity for DBM-PS: Provided, further, That such
item will be featured in the Electronic Catalogue for a maximum period of
six (6) months unless another supplier offers a price lower by at least five
percent (5%) and such supplier is determined by the DBM-PS or by the
Procuring Entity that conducted the previous bidding for DBM-PS to meet
the eligibility and bidding requirements for the item, in which case the
item from the latter supplier will be that featured in the Electronic
Catalogue for the remainder of the six (6)-month period.
The PhilGEPS shall also feature a Virtual Store, Electronic Payment, Electronic
Bid Submission, and such other features as may be developed in the future.
38
The 2016 Revised Implementing Rules and Regulations
The PhilGEPS may have a feature that will enable the ordering of
common-use and non-common use items online called a virtual
store. The virtual store shall be open only to registered Procuring
Entities and may not be accessed by suppliers.
8.3.1. All Procuring Entities are mandated to fully use the PhilGEPS in accordance
with the policies, rules, regulations, and procedures adopted by the GPPB and
embodied in this IRR. In this connection, all Procuring Entities shall register
with the PhilGEPS and shall undertake measures to ensure their access to an
on-line network to facilitate the open, speedy and efficient on-line
transmission, conveyance and use of electronic data messages or electronic
documents. The DBM-PS shall assist Procuring Entities to ensure their on-line
connectivity and help in training their personnel responsible for the operation
of the PhilGEPS from their terminals.
16
Refer to Appendix 3 for the Guidelines for Electronic Bidding (E-Bidding).
39
The 2016 Revised Implementing Rules and Regulations
8.3.2. The rules and regulations governing the manual method of procurement shall
apply whenever the rules in this Section are silent. Further, the GPPB is
authorized to approve changes in the procurement process to adapt to
improvements in modern technology, provided that such modifications are
consistent with the provisions of Section 3 of the Act and this IRR.
8.4.2. Requests for clarification from bidders may be sent electronically to the BAC.
To be binding on bidders, clarifications and amendments to the Invitation to
Bid/Request for Expression of Interest and to the Bidding Documents shall be
in the form of Supplemental/Bid Bulletins which shall be posted in the
PhilGEPS bulletin board.
8.5. Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
8.5.2. All bidders shall upload and maintain in PhilGEPS a current and updated file of
the following Class “A” eligibility documents under Sections 23.1(a) and
24.1(a): 17
a) Registration Certificate;
c) Tax Clearance;
17
Informing all procuring entities on the deferment of the implementation of the mandatory submission of PhilGEPS Certificate
of Registration and Membership through GPPB Circular No. 07-2017, dated 31 July 2017, published in the Philippine Daily
Inquirer on 18 August 2017.
40
The 2016 Revised Implementing Rules and Regulations
A Contracting Party refers to a State that has joined the Apostille Convention,
whether or not the Convention has entered into force for that State. 20 (n)
https://www.hcch.net/en/instruments/conventions/authorities1/?cid=41. 21 (n)
8.5.3. Registered bidders determined to be eligible may submit their bids at any
time before the closing date specified in the Bidding Documents. The
PhilGEPS shall bar all incoming bids after such prescribed date and time. (a)
8.5.4. The PhilGEPS shall have a feature that allows the electronic submission of
eligibility requirements and bids.
8.5.5. Upon receipt of a bid, the PhilGEPS shall generate and send a message to the
bidder acknowledging such receipt.
18
As of 14 May 2019, Austria, Finland, Germany and Greece.
19
As amended by GPPB Resolution No. 13-2019, dated 23 May 2019, published in the Official Gazette on 26 August 2019.
20
Ibid.
21
Ibid.
22
Refer to Appendix 4 for the Guidelines for the Use of the Government of the Philippines – Official Merchants Registry (GoP-
OMR).
41
The 2016 Revised Implementing Rules and Regulations
8.6.1. The BAC shall have the sole authority to open the bids.
8.6.2. Only the financial proposals of bidders whose technical proposals meet the
minimum technical requirements shall be opened or decrypted.
d) Any other act that breaches or violates the security, integrity, and
confidentiality of the PhilGEPS.
8.7. Observers
The PhilGEPS shall allow observers, duly authorized by the BAC, to monitor the
procurement proceedings on-line: Provided, however, That such observers do not
have any direct or indirect interest in the contract to be bid as prescribed in Section
13 of this IRR.
The PhilGEPS shall incorporate the following features, which shall be periodically upgraded
to keep abreast with developments in technology:
42
The 2016 Revised Implementing Rules and Regulations
b) Integrity – The PhilGEPS shall ensure that no person, including the system
administrators and chairperson and members of the BAC, shall be able to alter the
contents of bids submitted through the system or read the same ahead of the
stipulated time for the decryption or opening of bids. For this purpose, bids submitted
through the PhilGEPS shall be sealed through electronic keys. The authenticity of
messages and documents submitted through the PhilGEPS shall also be ensured by
the use of electronic signatures.
c) Confidentiality – The PhilGEPS shall ensure the privacy of parties transacting with it.
For this purpose, no electronic message or document sent through the system shall be
divulged to third parties unless such electronic message or document was sent after
the sender was informed that the same will be made publicly available. The PhilGEPS
shall protect the intellectual property rights over documents, including technical
designs, submitted in response to Invitations to Bid.
d) Audit Trail – The PhilGEPS shall include a feature that provides for an audit trail for on-
line transactions, and allows the Commission on Audit (COA) to verify the security and
integrity of the system at any time.
All procurement shall be done through competitive bidding, except as provided in Rule XVI
of this IRR.
43
The 2016 Revised Implementing Rules and Regulations
11.1.2 However, to expedite the procurement process for practical intents and
purposes, the HoPE may create separate BACs where the number and
complexity of the items to be procured shall so warrant. The BACs may be
organized either according to: (a) geographical location of PMO or end-user
or implementing units of the Procuring Entity; or (b) nature of procurement.
Similar committees for decentralized and lower level offices may also be
formed when deemed necessary by the HoPE.
11.2.1 The HoPE shall designate at least five (5) but not more than seven (7)
members to the BAC of unquestionable integrity and procurement
proficiency.
11.2.2 The BAC for NGAs, departments, bureaus, offices, or instrumentalities of the
GoP, including the judicial and legislative branches, constitutional
commissions, SUCs, GOCCs, and GFIs shall be composed of the following:
Regular Members:
Provisional Members:
44
The 2016 Revised Implementing Rules and Regulations
1. The BAC for Local Government Units shall be composed of the following:
i. One representative each from the regular offices under the Office
of the Local Chief Executive such as, but not limited to, the
following: Office of the Administrator, Budget Office, Legal Office,
Engineering Office, General Services Offices; and
b) For Barangays:
i. The BAC shall be composed of at least five (5), but not more than
seven (7) regular members of the Sangguniang Barangay, except
the Punong Barangay.
ii. The Punong Barangay, being the Local Chief Executive, shall
designate the Chairperson, Vice-Chairperson, and members of the
BAC.(a)
2. The HoPE may designate alternate BAC members, who shall have the
same qualifications as that of the members originally designated under
Section 11.2.2 of this IRR. The alternate members shall attend meetings
of the BAC and receive the proportionate honoraria, whenever the
original members are absent. The alternate members shall have the
same term as the original members. (a)
4. Unless sooner removed for a cause, the members of the BAC shall have
a fixed term of one (1) year reckoned from the date of appointment,
renewable at the discretion of the HoPE. Upon expiration of the terms of
the current members, they shall continue to exercise their functions until
new BAC members are designated. In case of resignation, retirement,
separation, transfer, re-assignment, removal, or death, the replacement
shall serve only for the unexpired term: Provided, however, That in case
of leave or suspension, the replacement shall serve only for the duration
of the leave or suspension. For justifiable causes, a member shall be
suspended or removed by the HoPE.
45
The 2016 Revised Implementing Rules and Regulations
v. Evaluation of Bids;
To the extent possible, the BAC in central offices shall render necessary assistance to
its regional or lower office BACs to facilitate the conduct of procurement from pre-
procurement conference to the post-qualification stage. (a)
12.2 The BAC shall be responsible for ensuring that the Procuring Entity abides by the
standards set forth by the Act and this IRR, and it shall prepare a Procurement
Monitoring Report (PMR) in the form prescribed by the GPPB. 23 The PMR shall cover
all procurement activities specified in the APP, whether ongoing and completed, from
the holding of the pre-procurement conference to the issuance of notice of award
and the approval of the contract, including the standard and actual time for each
major procurement activity. The PMR shall be approved and submitted by the HoPE
to the GPPB in electronic format 24 within fourteen (14) calendar days after the end of
each semester. The PMR shall likewise be posted in accordance with E.O. 662, s.
2007, as amended. (a)
12.3 Quorum
23
Refer to Appendix 5 for the Procurement Monitoring Report (PMR) Format.
24
As amended by GPPB Resolution No. 11-2020, dated 20 May 2020, published in the Philippine Daily Inquirer on 27 May
2020.
46
The 2016 Revised Implementing Rules and Regulations
A majority of the total BAC composition as designated by the HoPE shall constitute a
quorum for the transaction of business, provided that the presence of the
Chairperson or Vice-Chairperson shall be required.
For purposes of determining a quorum, a member of the BAC, which include the
Chairperson or the Vice-Chairperson, may be present, either in person or face-to-
face through videoconferencing, webcasting or similar technology for procuring
entities with such technology. 25 (n)
12.4 Meetings
The Chairperson or, in his absence, the Vice-Chairperson, shall preside at all
meetings of the BAC. Meetings of the BAC may be conducted electronically for
procuring entities with videoconferencing, webcasting, or similar technology
capability. The decision of at least a majority of those present, either in person, face-
to-face through videoconferencing, webcasting or similar technology, or a
combination thereof, at a meeting at which there is quorum shall be valid and
binding as an act of the BAC: Provided, however, That the Chairperson or, in his
absence, the Vice-Chairperson, shall vote only in case of a tie. 26 (a)
1. At least one (1) shall come from a duly recognized private group in a sector
or discipline relevant to the procurement at hand, for example:
25
As amended by GPPB Resolution No. 24-2018, dated 4 December 2018, published in the Official Gazette on 26 August 2019.
26
Ibid.
27
As amended by GPPB Circular No. 01-2021, dated 4 March 2021, published in the Philippine Star on 15 March 2021.
47
The 2016 Revised Implementing Rules and Regulations
13.2 The observers shall come from an organization duly registered with the Securities
and Exchange Commission (SEC) or the Cooperative Development Authority (CDA),
and should meet the following criteria:
13.3 Observers shall be invited at least five (5) calendar days before the date of the
procurement stage/activity. The absence of observers will not nullify the BAC
proceedings: Provided, That they have been duly invited in writing. The Procuring
Entities should ensure that the invitation is received at least five (5) calendar days
before each procurement activity. In the event that a procurement activity has to
be postponed, the observers shall be notified immediately of the change in
schedule. (a)
b) To submit their report to the Procuring Entity and furnish a copy to the GPPB
and Office of the Ombudsman/Resident Ombudsman. If no report is
submitted by the observer within seven (7) calendar days after each
procurement activity, then it is presumed that the bidding activity conducted
by the BAC followed the correct procedure; and
13.5 Observers shall be allowed access to or be provided with the following documents
free of charge upon their request: (a) minutes of BAC meetings; (b) abstract of
Bids; (c) post-qualification summary report; (d) APP and related PPMP; and (e)
opened proposals. In all instances, observers shall be required to enter into a
confidentiality agreement with the concerned Procuring Entity in accordance with
the form prescribed by the GPPB. 28(a)
28
Confidentiality Agreement based on the 2014 Procurement Observer’s Guide. Refer to Appendix 6 for the Confidentiality
Agreement Format.
48
The 2016 Revised Implementing Rules and Regulations
b) Organize and make all necessary arrangements for BAC and the TWG meetings
and conferences;
d) Take custody of procurement documents and other records and ensure that all
procurements undertaken by the Procuring Entity are properly documented;
i) Consolidate PPMPs from various units of the Procuring Entity to make them
available for review as indicated in Section 7 of this IRR and prepare the APP;
and
j) Act as the central channel of communications for the BAC with end-user or
implementing units, PMOs, other units of the line agency, other government
agencies, providers of goods, infrastructure projects, and consulting services,
observers, and the general public. (a)
14.2 In case of an existing ad hoc Secretariat, the HoPE shall assign full-time support staff
to their BAC Secretariat. The head of the Secretariat in central offices shall be at
least a fifth (5th) ranking permanent employee or, if not available, a permanent
employee of lower rank; or shall be at least a third (3rd) ranking permanent
employee in bureaus, regional offices and sub-regional/ district offices, or if not
available, a permanent employee of lower rank. In addition to integrity, Heads of
Procuring Entities shall consider procurement proficiency as a factor in designating
the head of the Secretariat and Procurement Unit. (a)
14.3 To expedite the procurement process, the HoPE shall ensure that the members of
the BAC, its Secretariat and TWG, shall give utmost priority to BAC assignments over
all other duties and responsibilities, until the requirements for the said assignments
at hand are completed. (a)
The Procuring Entity may grant payment of honoraria to the BAC members in an amount not
to exceed twenty five percent (25%) of their respective basic monthly salary subject to
availability of funds. For this purpose, the DBM shall promulgate the necessary guidelines. 29
The Procuring Entity may also grant payment of honoraria to the BAC Secretariat and the
TWG members, subject to the relevant rules of the DBM.
29
Refer to Appendix 7 for the Guidelines on the Grant of Honoraria to Government Personnel Involved in Government
Procurement.
49
The 2016 Revised Implementing Rules and Regulations
The GPPB shall establish a sustained training program to develop the capability of the BACs,
BAC Secretariats, TWGs, and the Procurement Units of Procuring Entities, and
professionalize the same.
The HoPE shall ensure that the BAC, its Secretariat and TWG members, including other
relevant procurement personnel are sent to attend procurement training or capacity
development program. Within six (6) months upon designation, the BAC, its Secretariat and
TWG members should have satisfactorily completed such training or program conducted,
authorized or accredited by the GPPB through its Technical Support Office. 30
The HoPE is encouraged to attend similar procurement training and capacity development
activities. (a)
17.1 The Bidding Documents shall be prepared by the Procuring Entity following the
standard forms and manuals prescribed by the GPPB. 31 The Bidding Documents shall
include the following:
a) ABC;
c) Eligibility Requirements;
30
Refer to GPPB Circular No. 07-2018 dated 4 September 2018. Integrated in the 2016 updated IRR of R.A. No. 9184 as
Appendix 29.
31
Refer to GPPP Circular No. 04-2020 dated 16 September 2020, published in the Philippine Star on 26 September 2020.
50
The 2016 Revised Implementing Rules and Regulations
17.2 The specifications and other terms in the Bidding Documents shall reflect the
necessary specifications required to meet the needs of the Procuring Entity in clear
and unambiguous terms.
In mixed procurements, the Procuring Entity shall specify in the Bidding Documents
the requirements, criteria and other conditions of the bidding procedures and of the
ensuing contract as applicable to each component of the project. In the preparation
of Bidding Documents, the Procuring Entity shall ensure compliance with existing
laws, rules and regulations, especially those concerning licenses and permits required
for the project, in accordance with Section 34.2 of this IRR. (a)
17.3 To provide prospective bidders ample time to examine the Bidding Documents and to
prepare their respective bids, the concerned BAC shall make the Bidding Documents
available from the time the Invitation to Bid / Request for Expression of Interest is
first advertised/posted until the deadline for the submission and receipt of bids.(a)
17.4 Bidders may be asked to pay a fee to recover the cost for the preparation and
development of the Bidding Documents pursuant to the Guidelines on the Sale of
Bidding Documents. 32 The Procuring Entity shall post the complete Bidding
Documents at its website and the PhilGEPS website from the time the Invitation to
Bid/Request for Expression of Interest is advertised. Bidding Documents may be
downloaded from any of the said websites: Provided, That upon submission of their
bids, the bidders shall pay the applicable fee, if required. The Bidding Documents
may also be secured from the BAC Secretariat upon payment of the corresponding
fee, if required. (a)
17.5 Bidding Documents Fee may be refunded in accordance with the aforementioned
Guidelines based on the grounds provided for under Section 41 of the Act and this
IRR. (n)
No bidding and award of contract for Infrastructure Projects shall be made unless the
detailed engineering investigations, surveys and designs, for the project have been
sufficiently carried out and duly approved in accordance with the standards and
specifications prescribed by the HoPE concerned or his duly authorized
representative, pursuant to the recommendation of the end-user or implementing
unit and in accordance with the provisions of Annex “A” 33 of this IRR. In case of
projects with pending acquisition of right-of-way site or location, the procurement
process may commence, but no award of contract shall be made until an authority or
permit to enter is issued by the property owner; or a notarized deed of sale or deed
of donation is executed in favor of the government; or a writ of possession is issued
by a court of competent jurisdiction, as the case may be.
The exception is in case of design and build scheme, wherein the bidders shall be
allowed to submit its preliminary engineering designs as part of its bid. The
procedures for the procurement and contract implementation of Infrastructure
Projects using a design and build scheme shall be in accordance with the provisions
of Annex “G” 34 of this IRR. (a)
32
Refer to Appendix 8 for the Guidelines on the Sale of Bidding Documents.
33
Detailed Engineering for the Procurement of Infrastructure Projects.
34
Guidelines for the Procurement and Implementation of Contracts for Design and Build Infrastructure Projects.
51
The 2016 Revised Implementing Rules and Regulations
This Section shall also apply to the goods component of Infrastructure Projects and
Consulting Services. (a)
In all stages of the preparation of the Bidding Documents, the Procuring Entity shall ensure
equal access to information. Prior to their official release to prospective bidders, no aspect
or part of the Bidding Documents shall be divulged or released to any prospective bidder or
person having direct or indirect interest in the project to be procured, or to any party,
except those officially authorized in the handling of the documents. (a)
However, in procurements involving and affecting national security, the disclosure of the
specific components of the procurement documents, such as, the technical specifications,
requirements and components, shall be dependent upon the HoPE having due regard to the
nature, classification, sensitivity and confidentiality of the relevant documents vis-à-vis the
purpose and reason for the request. 35 (n)
a) Confirm the description and scope of the contract, the ABC, and contract
duration;
b) Ensure that the procurement is in accordance with the PPMP and APP;
35
As amended by GPPB Resolution No. 21-2017, dated 30 May 2017, published in the Philippine Daily Inquirer on 20 November
2017.
36
As amended by GPPB Resolution No. 14-2019, dated 17 July 2019, published in the Official Gazette on 26 August 2019.
52
The 2016 Revised Implementing Rules and Regulations
d) Review, modify and agree on the criteria for eligibility screening, evaluation,
and post-qualification;
20.2 The holding of a pre-procurement conference may not be required for small
procurements, i.e., procurement of Goods costing Two Million Pesos (₱2,000,000.00)
and below, procurement of Infrastructure Projects costing Five Million Pesos
(₱5,000,000.00) and below, and procurement of Consulting Services costing One
Million Pesos (₱1,000,000.00) and below.
i) Goods, the name of the contract to be bid and a brief description of the
goods to be procured;
ii) Infrastructure Projects, the name and location of the contract to be bid,
the project background and other relevant information regarding the
proposed contract works, including a brief description of the type, size,
major items, and other important or relevant features of the works; and
b) The name of the project, identification and number of lots or items specific to
the bidding, as well as the basis of evaluation of the project, lots, or items,
where applicable;
c) A general statement on the criteria to be used by the Procuring Entity for the
eligibility check, the short listing of prospective bidders, in the case of the
53
The 2016 Revised Implementing Rules and Regulations
d) The date, time and place of the deadline for the submission and receipt of the
eligibility requirements, the pre-bid conference if any, the submission and
receipt of bids, and the opening of bids;
g) The place, time and website where the Bidding Documents may be secured or
downloaded, and, where required, the price of the Bidding Documents, in
accordance with Section 17.4 of this IRR;
i) The name, address, telephone number, facsimile number, e-mail and website
addresses of the concerned Procuring Entity, as well as its designated contact
person; and
k) For electronic bid submission, the Invitation to Bid, including the Bidding
Documents shall clearly state whether the PE shall allow the submission and
receipt of bids through electronic means. 37
21.2 Advertising and Posting of the Invitation to Bid/Request for Expression of Interest
21.2.1 Except as otherwise provided in Section 54.2 of this IRR and for the
procurement of common-use goods and supplies, the Invitation to
Bid/Request for Expression of Interest shall be:
Procuring Entities that cannot post its opportunities in the PhilGEPS for
justifiable reasons shall continue to publish its advertisements in a newspaper
of general nationwide circulation. (a)
21.2.2 If the Procuring Entity will allow electronic bid submission, the highest
official managing the Information Technology system of the agency shall
issue a Certification based on the prescribed form of the GPPB. 38
37
As amended by GPPB Resolution No. 09-2020, dated 7 May 2020, published in the Philippine Daily Inquirer on 15 May 2020.
54
The 2016 Revised Implementing Rules and Regulations
22.2 The pre-bid conference shall be held at least twelve (12) calendar days before the
deadline for the submission and receipt of bids, but not earlier than seven (7)
calendar days from the PhilGEPS posting of the Invitation to Bid or Bidding
Documents and in the case of Consulting Services, from the determination of the
shortlisted consultants. If the Procuring Entity determines that, by reason of the
method, nature, or complexity of the contract to be bid or when international
participation will be more advantageous to the GoP, a longer period for the
preparation of bids is necessary, the pre-bid conference shall be held at least thirty
(30) calendar days before the deadline for the submission and receipt of bids.(a)
22.3 The pre-bid conference shall discuss, clarify and explain, among other things, the
eligibility requirements and the technical and financial components of the contract to
be bid including questions and clarifications raised by the prospective bidders before
and during the Pre-Bid Conference.
22.4 The minutes of the pre-bid conference shall be recorded and prepared not later than
five (5) calendar days after the pre-bid conference, and shall be made available to
prospective bidders not later than five (5) days upon written request. 40 (a)
Decisions of the BAC amending any provision of the Bidding Documents shall be
issued in writing through a Supplemental/Bid Bulletin at least seven (7) calendar
days before the deadline for the submission and receipt of bids. (a)
38
As amended by GPPB Resolution No. 12-2020, dated 20 May 2020, published in the Philippine Daily Inquirer on 30 May
2020.
39
As amended by GPPB Resolution No. 09-2020, dated 7 May 2020, published in the Philippine Daily Inquirer on 15 May 2020.
40
As amended by GPPB Resolution No. 04-2021, dated 4 March 2021, published in the Philippine Star on 15 March 2021.
55
The 2016 Revised Implementing Rules and Regulations
22.5.1 Requests for clarification(s) on any part of the Bidding Documents or for
an interpretation must be in writing and submitted to the BAC of the
Procuring Entity concerned at least ten (10) calendar days before the
deadline set for the submission and receipt of bids. The BAC shall
respond to the said request by issuing a Supplemental/Bid Bulletin, duly
signed by the BAC Chairperson, to be made available to all those who
have properly secured the Bidding Documents, at least seven (7)
calendar days before the deadline for the submission and receipt of bids.
(a)
22.5.3 Any Supplemental/Bid Bulletin issued by the BAC shall also be posted in
the PhilGEPS, the website of the Procuring Entity concerned, if available,
and at any conspicuous place within the premises of the Procuring Entity.
It shall be the responsibility of all those who have properly secured the
Bidding Documents to inquire and secure Supplemental/Bid Bulletins that
may be issued by the BAC. However, bidders who have submitted bids
before the issuance of the Supplemental/Bid Bulletin must be informed
and allowed to modify or withdraw their bids in accordance with Section
26 of this IRR. (a)
Legal Documents
56
The 2016 Revised Implementing Rules and Regulations
iii) Tax clearance per E.O. 398, s. 2005, as finally reviewed and approved by
the Bureau of Internal Revenue (BIR).
Technical Documents
iv) Statement of the bidder of all its ongoing government and private
contracts, including contracts awarded but not yet started, if any, whether
similar or not similar in nature and complexity to the contract to be bid.
All of the above statements shall include all information required in the
PBDs prescribed by the GPPB.
Financial Documents
vii) The bidder’s audited financial statements, showing, among others, the
bidder’s total and current assets and liabilities, stamped “received” by the
BIR or its duly accredited and authorized institutions, for the preceding
calendar year which should not be earlier than two (2) years from the
date of bid submission.(a)
For Goods, valid joint venture agreement (JVA), in case the joint venture is
already in existence. In the absence of a JVA, duly notarized statements from
all the potential joint venture partners should be included in the bid, stating
that they will enter into and abide by the provisions of the JVA in the event that
the bid is successful. Failure to enter into a joint venture in the event of a
contract award shall be ground for the forfeiture of the bid security.
Each partner of the joint venture shall submit their respective PhilGEPS
Certificates of Registration in accordance with Section 8.5.2 of this IRR. The
submission of technical and financial eligibility documents by any of the joint
venture partners constitutes compliance: Provided, That the partner responsible
to submit the NFCC shall likewise submit the Statement of all of its ongoing
contracts and Audited Financial Statements. (a)
57
The 2016 Revised Implementing Rules and Regulations
23.2 In case of foreign bidders, the eligibility requirements or statements, the bids, and all
other documents to be submitted to the BAC must be in English. If the eligibility
requirements or statements, the bids, and all other documents submitted to the BAC
are in foreign language other than English, it must be accompanied by a translation
of the documents in English. The documents shall be translated by the relevant
foreign government agency, the foreign government agency authorized to translate
documents, or a registered translator in the foreign bidder’s country; and shall be
authenticated by the appropriate Philippine foreign service establishment/post or the
equivalent office having jurisdiction over the foreign bidder’s affairs in the
Philippines.(a)
However, for Contracting Parties to the Apostille Convention, the documents shall
be authenticated through an apostille by the Competent Authority, as defined in
Section 8.5.2 paragraph 4 of the 2016 revised IRR of RA No. 9184, except for
countries 41 identified by the DFA that will still require legalization (red ribbon) by
the relevant Embassy or Consulate. (n) 42
23.3 To facilitate determination of eligibility, the BAC of a Procuring Entity shall use the
contents of the PhilGEPS electronic registry of manufacturers, suppliers,
distributors, contractors, and/or consultants, in accordance with Section 8.5.2 of
this IRR. (23.4a)
41
As of 14 May 2019, Austria, Finland, Germany and Greece.
42
As amended by GPPB Resolution No. 13-2019, dated 23 May 2019, published in the Official Gazette on 26 August 2019.
58
The 2016 Revised Implementing Rules and Regulations
23.4.1.3 The bidder must have completed, within the period specified in
the Invitation to Bid, an SLCC that is similar to the contract to
be bid, and whose value, adjusted to current prices using the
Philippine Statistics Authority (PSA) consumer price indices,
must be at least fifty percent (50%) of the ABC. However, in
the case of Expendable Supplies, said SLCC must be at least
twenty five percent (25%) of the ABC.
For this purpose, the similar contracts mentioned under (a) and
(b) above must have been completed within the period
specified in the Invitation to Bid. The Procuring Entity may
clarify in the Bidding Documents the definition or description of
what it considers to be a similar project. (23.5.1.3a)
43
Refer to Appendix 9 for the Guidelines in the Determination of Eligibility of Foreign Suppliers, Contractors, and Consultants to
Participate in Government Procurement Projects.
59
The 2016 Revised Implementing Rules and Regulations
44
As amended by GPPB Resolution No. 06-2019, dated 8 March 2019, published in the Philippine Daily Inquirer on 17 May
2019.
45
Ibid.
46
Ibid.
47
Ibid.
60
The 2016 Revised Implementing Rules and Regulations
23.4.2.3 In accordance with R.A. 4566, entitled “An Act Creating the
Philippine Licensing Board for Contractors, Prescribing its
Powers, Duties and Functions, Providing Funds Therefor, and
for Other Purposes,” the persons/entities enumerated in
Section 23.4.2.1 of this IRR may participate in competitive
bidding if he has been issued a license by the PCAB to engage
or act as a contractor.(23.5.2.3a)
23.4.2.4 The bidder must have completed an SLCC that is similar to the
contract to be bid, and whose value, adjusted to current prices
using the PSA consumer price indices, must be at least fifty
percent (50%) of the ABC to be bid: Provided, however, That
contractors under Small A and Small B categories without
similar experience on the contract to be bid may be allowed to
bid if the cost of such contract is not more than the Allowable
Range of Contract Cost (ARCC) of their registration based on
the guidelines as prescribed by the PCAB.
48
Ibid.
61
The 2016 Revised Implementing Rules and Regulations
23.5 GOCCs may be eligible to participate in Competitive Bidding only if they can
establish that they (a) are legally and financially autonomous, (b) operate under
commercial law, and (c) are not attached agencies of the Procuring Entity. The
GPPB shall promulgate the necessary guidelines for this provision. (23.6)
23.6 Notwithstanding the eligibility of a bidder, the Procuring Entity concerned reserves
the right to review the qualifications of the bidder at any stage of the procurement
process if the Procuring Entity has reasonable grounds to believe that a
misrepresentation has been made by the said bidder, or that there has been a
change in the bidder’s capability to undertake the project from the time it submitted
its eligibility requirements. Should such review uncover any misrepresentation made
in the eligibility requirements, statements or documents, or any changes in the
situation of the bidder which will affect the capability of the bidder to undertake the
project so that it fails the eligibility criteria, the Procuring Entity shall consider the
said bidder as ineligible and shall disqualify it from obtaining an award or contract,
in accordance with Rules XXI, XXII, and XXIII of this IRR.(23.7a)
Section 24. Eligibility Requirements and Short Listing for Consulting Services
24.1 For purposes of determining the eligibility and short list of bidders in accordance with
Sections 24.4 and 24.5 of this IRR, only the following documents shall be required by
the BAC, using the forms prescribed in the Bidding Documents:
Legal Documents
i) Registration certificate from SEC, DTI for sole proprietorship, or CDA for
cooperatives.
62
The 2016 Revised Implementing Rules and Regulations
iii) Tax clearance per E.O. 398, s. 2005, as finally reviewed and approved by
the BIR.
Technical Documents
iv) Statement of the bidder of all its ongoing and completed government
and private contracts, including contracts awarded but not yet started, if
any, whether similar or not similar in nature and complexity to the
contract to be bid, within the relevant period as provided in the Bidding
Documents. The statement shall include all information required in the
PBDs prescribed by the GPPB.(a)
Financial Document
24.2 In the case of foreign consultants, the eligibility requirements or statements, the
bids, and all other documents to be submitted to the BAC must be in English. If the
eligibility requirements or statements, the bids, and all other documents submitted to
the BAC are in foreign language other than English, it must be accompanied by a
63
The 2016 Revised Implementing Rules and Regulations
However, for Contracting Parties to the Apostille Convention, the documents shall be
authenticated through an apostille by the Competent Authority, as defined in Section
8.5.2 paragraph 4 of the 2016 revised IRR of RA No. 9184, except for countries 49
identified by the DFA that will still require legalization (red ribbon) by the relevant
Embassy or Consulate. 50 (n)
24.3.2 When the types and fields of consulting services in which the foregoing
persons/entities wish to engage involve the practice of professions
regulated by law, those who will actually perform the services shall be
Filipino citizens and registered professionals authorized by the
appropriate regulatory body to practice those professions and allied
professions.
49
As of 14 May 2019, Austria, Finland, Germany and Greece.
50
As amended by GPPB Resolution No. 13-2019, dated 23 May 2019, published in the Official Gazette on 26 August 2019
64
The 2016 Revised Implementing Rules and Regulations
24.4.2 Subject to the short listing of consultants as provided in this IRR, the
determination of eligibility of consultants shall be based on the evaluation
of the eligibility documents prescribed above in accordance with the
procedures provided in Section 30.1 of this IRR.
24.4.4 Should there be any change in the original Bidding Documents prior to
the conduct of eligibility checking and shortlisting, the BAC shall issue
supplemental/bid bulletin for such purpose at least seven (7) calendar
days before the deadline for the submission of eligibility documents,
subject to the provisions of Section 22.5.3 of this IRR.(n)
24.5.1 With respect to a particular contract for Consulting Services to be bid, the
concerned Procuring Entity shall only consider for short listing those
consultants whose contracts, as identified in the eligibility documents
submitted for registration, are similar in nature and complexity to the
contract to be bid, based on the Request for Expression of Interest.
24.5.2 The BAC shall draw up the short list of consultants from those who have
been determined as eligible in accordance with the provisions of this IRR.
The number of short listed consultants, which shall be determined in the
pre-procurement conference, shall consist of three (3) to seven (7)
consultants, with five (5) as the preferable number. Should only one (1)
or less than the required number apply for eligibility and short listing,
pass the eligibility check, and/or pass the minimum score required in the
short listing, the BAC shall consider the same. The shortlisted bidders
shall then be required to pay the fee for the Bidding Documents, if
applicable, subject to the provisions of Section 17.4 of this IRR. (a)
24.5.3 The BAC shall specify in the Request for Expression of Interest the set of
criteria and rating system for short listing of consultants to be used for
the particular contract to be bid, which shall consider the following,
among others:
65
The 2016 Revised Implementing Rules and Regulations
principal and key staff, including the times when employed by other
consultants;
24.5.4 The BAC shall recommend the short list of consultants to the HoPE for
consideration and approval. The entire process of eligibility check and
short listing shall not exceed twenty (20) calendar days.
24.6 GOCCs may be eligible to participate in Competitive Bidding only if they can
establish that they (a) are legally and financially autonomous, (b) operate under
commercial law, and (c) are not attached agencies of the Procuring Entity. The
GPPB shall promulgate the necessary guidelines for this provision.
24.7 Notwithstanding the eligibility of a consultant and/or inclusion in the short list of
consultants, the Procuring Entity concerned reserves the right to review his
qualifications at any stage of the procurement process if it has reasonable grounds
to believe that a misrepresentation has been made by the said consultant, or that
there has been a change in the consultant’s capability to undertake the project from
the time he submitted his eligibility requirements. Should such review uncover any
misrepresentation made in the eligibility requirements, statements or documents, or
any changes in the situation of the consultant which will affect the capability of the
consultant to undertake the project so that the consultant fails the preset eligibility
criteria, the Procuring Entity shall consider the said consultant as ineligible and shall
disqualify him from submitting a bid or from obtaining an award or contract, in
accordance with Rules XXI, XXII, and XXIII of this IRR.
25.2 The first envelope shall contain the following technical information/documents, at the
least:
66
The 2016 Revised Implementing Rules and Regulations
vi) Bid security in the prescribed form, amount and validity period;
viii) Omnibus Sworn Statement in accordance with Section 25.3 of this IRR;
and
v) NFCC Computation;
vii) Bid security in the prescribed form, amount and validity period;
(3) List of contractor’s major equipment units, which are owned, leased,
and/or under purchase agreements, supported by proof of ownership
or certification of availability of equipment from the equipment
lessor/vendor for the duration of the project, as the case may be; and
52
As amended by GPPB Resolution No. 21-2017, dated 30 May 2017, published in the Philippine Daily Inquirer on 20 November
2017.
67
The 2016 Revised Implementing Rules and Regulations
ix) Omnibus Sworn Statement in accordance with Section 25.3 of this IRR;
i) The bid security in the prescribed form, amount and validity period;
iv) Approach, work plan, and schedule: Provided, however, That for
architectural design, submission of architectural plans and designs shall
not be required during the consultant’s selection process;
vi) Omnibus Sworn Statement in accordance with Section 25.3 of this IRR.(a)
25.3 The Omnibus Sworn Statement executed by the bidder, or its duly authorized
representative, shall contain the following:
(a) The signatory is the duly authorized representative of the prospective bidder,
and granted full power and authority to do, execute and perform any and all
acts necessary to participate, submit the bid, and to sign and execute the
ensuing contract accompanied by the duly notarized Special Power of Attorney,
Board/Partnership Resolution, or Secretary’s Certificate, whichever is
applicable;
(b) It is not “blacklisted” or barred from bidding by the GoP or any of its agencies,
offices, corporations, or LGUs, including foreign government/foreign or
international financing institution whose blacklisting rules have been recognized
by the GPPB; by itself or by relation, membership, association, affiliation, or
controlling interest with another blacklisted person or entity as defined and
provided for in the Uniform Guidelines on Blacklisting; 53 (a)
(d) It is authorizing the HoPE or his duly authorized representative/s to verify all
the documents submitted;
(e) It complies with the disclosure provision under Section 47 of the Act and this
IRR, in relation to other provisions of R.A. 3019;
53
As amended by GPPB Resolution 16-2020, dated 16 September 2020, published in the Philippine Star on 26 September 2020.
68
The 2016 Revised Implementing Rules and Regulations
(h) It did not give or pay, directly or indirectly, any commission, amount, fee, or
any form of consideration, pecuniary or otherwise, to any person or official,
personnel or representative of the government in relation to any procurement
project or activity; and [25.2(a)(iv), 25.2(b)(iv), 25.2(c)(iv)a]
(i) In case advance payment was made or given , failure to perform or deliver any
of the obligations and undertakings in the contract shall be sufficient grounds
to constitute criminal liability for swindling (estafa) or the commission of fraud
with unfaithfulness or abuse of confidence through misappropriating or
converting any payment received by a person or entity under an obligation
involving the duty to deliver certain goods or services, to the prejudice of the
public and the government of the Philippines pursuant to Article 315 of Act No.
3815 s. 1930, as amended, or the Revised Penal Code. 54(n)
25.4 The second envelope shall contain the financial information/documents as specified
in the PBDs.
25.5 Bids shall be received by the BAC on the date, time, and place specified in the
Invitation to Bid/Request for Expression of Interest. The following periods from the
last day of posting of the Invitation to Bid/Request for Expression of Interest up to
the submission and receipt of bids shall be observed:
ABC
Period
(in Philippine currency)
Fifty (50) million and below 50 calendar days
Above fifty (50) million 65 calendar days
25.6 Bids, including the eligibility requirements under Section 23.1 of this IRR, submitted
after the deadline shall not be accepted by the BAC. The BAC shall record in the
minutes of bid submission and opening, the bidder’s name, its representative and
the time the late bid was submitted or in case of online or electronic bid
submission, generate a Bid receipt page for the official time of late submission
which can be saved or printed by the bidder. 55(a)
25.7 To ensure transparency and accurate representation of the bid submission, the BAC
Secretariat shall notify in writing all bidders whose bids it has received through its
PhilGEPS-registered physical address or official e-mail address. The notice shall be
issued within seven (7) calendar days from the date of the bid opening. (n)
25.8 The original copy of the bid form shall be typed or written in ink and shall be signed
by the bidder or its duly authorized representative. (n)
54
Issued by GPPB Resolution 16-2020, dated 16 September 2020, published in the Philippine Star on 26 September 2020.
55
As amended by GPPB Resolution No. 09-2020, dated 7 May 2020, published in the Philippine Daily Inquirer on 15 May 2020.
69
The 2016 Revised Implementing Rules and Regulations
protected, 56 shall be rejected. However, bid envelopes that are not properly sealed
and marked or not properly compressed and password-protected, 57 as required in
the Bidding Documents, shall be accepted, provided that the bidder or its duly
authorized representative shall acknowledge such condition of the bid as submitted.
The BAC shall assume no responsibility for the misplacement of the contents of the
improperly sealed or marked bid, or improperly compressed or password-protected
folder, 58 or for its premature opening. (n)
For online or electronic bid submission, where a bidder modifies its Bid, it shall not
be allowed to retrieve its original Bid, but shall only be allowed to send another Bid
equally secured and properly identified. In the case of electronic submission, to be
labelled as a “modification,” of the one previously submitted. The time indicated in
the latest Bid receipt page generated shall be the official time of submission. Bids
submitted after the deadline shall not be accepted. 60(a)
26.2 A bidder may, through a letter, withdraw its bid before the deadline for the receipt of
bids. Withdrawal of bids after the applicable deadline shall be subject to appropriate
sanctions as prescribed in this IRR. A bidder may also express its intention not to
participate in the bidding through a letter which should reach and be stamped
received by the BAC before the deadline for the receipt of bids. A bidder that
withdraws its bid shall not be permitted to submit another bid, directly or indirectly,
for the same contract.
27.1 All bids shall be accompanied by a bid security, payable to the Procuring Entity
concerned as a guarantee that the successful bidder shall, within ten (10) calendar
days from receipt of the notice of award, enter into contract with the Procuring Entity
and furnish the performance security required in Section 39 of this IRR, except when
Section 37.1 of this IRR allows a longer period. Failure to enclose the required bid
security in the form and amount prescribed herein shall automatically disqualify the
bid concerned.
27.2 The bidder shall submit a Bid Securing Declaration, or any form of Bid Security, in an
amount not less than the required percentage of the ABC in accordance with the
following schedule:(a)
70
The 2016 Revised Implementing Rules and Regulations
27.3 The bid security shall be denominated in Philippine Pesos and posted in favor of the
Procuring Entity.
27.4 Without prejudice to the provisions of the Act and this IRR on the forfeiture of bid
securities, bid securities shall be returned only after the bidder with the Lowest
Calculated Responsive Bid (LCRB) or Highest Rated Responsive Bid (HRRB), as the
case may be, has signed the contract and furnished the performance security,
except to those declared by the BAC as failed or post-disqualified in accordance
with this IRR, upon submission of a written waiver of their right to file a request for
reconsideration and/or protest.
27.5 A Bid Securing Declaration is an undertaking which states, among others, that the
bidder shall enter into contract with the Procuring Entity and furnish the required
performance security within ten (10) calendar days, as indicated in the Bidding
Documents, from receipt of the Notice of Award, and commits to pay the
corresponding amount as fine and be automatically disqualified from bidding of any
procurement contract of any Procuring Entity for a period of time, upon receipt of
the Blacklisting Order, 61 in the event it violates any of the conditions stated therein
as required in the guidelines 62 issued by the GPPB.(a)
27.6 In no case shall the bid security be returned later than the expiration of the bid
validity period indicated in the Bidding Documents, unless it has been extended in
accordance with Section 28.2 of this IRR. (a)
61
As amended by GPPB Resolution 16-2020, dated 16 September 2020, published in the Philippine Star on 26 September 2020.
62
Refer to Appendix 10 for the Guidelines on the Use of Bid Securing Declaration as amended by GPPB Resolution 16-2020,
dated 16 September 2020, published in the Philippine Star on 26 September 2020.
71
The 2016 Revised Implementing Rules and Regulations
28.1. Bids and bid securities shall be valid for a reasonable period as determined by the
HoPE concerned, which shall be indicated in the Bidding Documents, but in no case
shall the period exceed one hundred twenty (120) calendar days from the date of
the opening of bids.
28.2. Should it become necessary to extend the validity of the bids and bid securities
beyond one hundred twenty (120) calendar days, the Procuring Entity concerned
shall request in writing all those who submitted bids for such extension before the
expiration date therefor. Bidders, however, shall have the right to refuse to grant
such extension without forfeiting their bid security.
The BAC shall open the bids immediately after the deadline for the submission and receipt of
bids. The time, date, and place of the opening of bids shall be specified in the Bidding
Documents.
For electronic bid submission, the passwords for accessing the Bidding Documents will be
disclosed by the Bidders only during the actual bid opening which may be done in person or
face-to-face through videoconferencing, webcasting or similar technology. 63(a)
In case the bids cannot be opened as scheduled due to justifiable reasons, the BAC shall
take custody of the bids submitted and reschedule the opening of bids on the next working
day or at the soonest possible time through the issuance of a Notice of Postponement to be
posted in the PhilGEPS website and the website of the Procuring Entity concerned.
The bidders or their duly authorized representatives may attend the opening of bids. The
BAC shall ensure the integrity, security, and confidentiality of all submitted bids. The
abstract of bids as read and the minutes of the bid opening shall be made available to the
public upon written request and payment of a specified fee to recover cost of materials. (a)
Receipt of the scanned copies of the first bid envelope with the required forms
prescribed in this IRR, which are for online or electronic bid submission, shall be
63
As amended by GPPB Resolution No. 09-2020, dated 7 May 2020, published in the Philippine Daily Inquirer on 15 May 2020.
72
The 2016 Revised Implementing Rules and Regulations
considered as compliant with the requirements of the said bid submission, subject to
the submission of the original copies of the following:
i) bid securing declaration or other forms of bid security excluding cash, and
ii) the omnibus sworn statement.
These forms shall be submitted by the bidder to and duly received by the BAC
concerned during the post-qualification stage.
The non-submission of these forms on the set period shall render the bid submission
as non-compliant and shall result in the post-disqualification of the bid. 64
30.2 Immediately after determining compliance with the requirements in the first
envelope, the BAC shall forthwith open the second bid envelope of each remaining
eligible bidder whose first bid envelope was rated “passed.” The second envelope of
each complying bidder shall be opened within the same day, except as provided
under Section 33 of this IRR. In case any of the requirements in the second envelope
of a particular bid is missing, incomplete or patently insufficient, and/or if the
submitted total bid price exceeds the ABC, the BAC shall rate the bid concerned as
“failed.” Only bids that are determined to contain all the bid requirements for both
components shall be rated “passed” and shall immediately be considered for
evaluation and comparison. (a)
Receipt of the scanned copies of the second bid envelope with the required forms
such as the duly-signed bid form, price schedules, or other forms prescribed in this
IRR, for electronic or online bid submission, shall be considered as compliant with
the requirements of the said bid submission. 65
30.3 For the procurement of Goods where, due to the nature of the requirements of the
project, the required technical specifications/requirements of the contract cannot be
precisely defined in advance of bidding, or where the problem of technically unequal
bids is likely to occur, a two (2)-stage bidding procedure may be employed. In these
cases, the Procuring Entity concerned shall prepare the Bidding Documents, including
the technical specification in the form of performance criteria only. Under this
procedure, prospective bidders shall be requested at the first stage to submit their
respective eligibility requirements if needed, and initial technical proposals only (no
price tenders). The concerned BAC shall then evaluate the technical merits of the
proposals received from eligible bidders vis-à-vis the required performance
standards. A meeting/discussion shall then be held by the BAC with those eligible
bidders whose technical tenders meet the minimum required standards stipulated in
the Bidding Documents for purposes of drawing up the final revised technical
specifications/requirements of the contract. Once the final revised technical
specifications are completed and duly approved by the concerned BAC, copies of the
same shall be issued to all the bidders identified in the first stage who shall then be
required to submit their revised technical tenders, including their price proposals in
two (2) separate sealed envelopes in accordance with this IRR, at a specified
deadline, after which time no more bids shall be received. The concerned BAC shall
then proceed in accordance with the procedure prescribed in this IRR.
30.4 For the procurement of Consulting Services, the detailed implementation of the
procedure specified in this Section shall be as provided in Section 33 of this IRR.
64
As amended by GPPB Resolution 16-2020, dated 16 September 2020, published in the Philippine Star on 26 September 2020.
65
Ibid
73
The 2016 Revised Implementing Rules and Regulations
31.2 For Foreign-funded Procurement, the ABC shall be applied as the ceiling: Provided,
That the following conditions are met:
b) The Procuring Entity has procedures in place to ensure that the ABC is based on
recent estimates made by the engineer or the responsible unit of the Procuring
Entity and that the estimates are based on adequate detailed engineering (in the
case of Infrastructure Projects) and reflect the quality, supervision and risk and
inflationary factors, as well as prevailing market prices, associated with the types
of Goods or Infrastructure Projects to be procured.
c) The Procuring Entity has trained cost estimators on estimating prices and
analyzing bid variances. In the case of Infrastructure Projects, the Procuring
Entity must also have trained quantity surveyors.
d) The Procuring Entity has established a system to monitor and report bid prices
relative to ABC and engineer’s/Procuring Entity’s estimate.
e) The Procuring Entity has established a monitoring and evaluation system for
contract implementation to provide a feedback on actual total costs of Goods and
Infrastructure Projects.
Section 32. Bid Evaluation for the Procurement of Goods and Infrastructure
Projects
32.1 Members of the BAC, its staff and personnel, Secretariat and TWG, as well as
Observers, are prohibited from making or accepting any communication with any
bidder regarding the evaluation of their bids until the issuance of the Notice of
Award. However, the BAC, through its Secretariat, may ask in writing the bidder for a
clarification of its bid. All responses to requests for clarification shall be in writing.(a)
32.2 For the procurement of Goods and Infrastructure Projects, the BAC shall evaluate the
financial component of the bids to determine the Lowest Calculated Bid using the
following steps:
32.2.1 The BAC shall immediately conduct a detailed evaluation of all bids using
non-discretionary criteria in considering the following:
74
The 2016 Revised Implementing Rules and Regulations
32.2.2 The BAC shall evaluate all bids on an equal footing to ensure fair and
competitive bid comparison. For this purpose, all bidders shall be required
to include the cost of all taxes, such as, but not limited to, value added
tax (VAT), income tax, local taxes, and other fiscal levies and duties
which shall be itemized in the bid form and reflected in the detailed
estimates. Such bids, including said taxes, shall be the basis for bid
evaluation and comparison.
32.2.3 In case of discrepancies between: (a) bid prices in figures and in words,
the latter shall prevail; (b) total price per item and unit price for the item
as extended or multiplied by the quantity of that item, the latter shall
prevail; (c) stated total price and the actual sum of prices of component
items, the latter shall prevail; (d) unit cost in the detailed estimate and
unit cost in the bill of quantities, the latter shall prevail.
32.2.4 Bids shall then be ranked in the ascending order of their total calculated
bid prices, as evaluated and corrected for computational errors, and other
bid modifications, to identify the Lowest Calculated Bid. Total calculated
bid prices, as evaluated and corrected for computational errors, and other
bid modifications, which exceed the ABC shall be disqualified.
32.3 After all bids have been received, opened, examined, evaluated, and ranked, the
BAC shall prepare the corresponding Abstract of Bids. All members of the BAC shall
sign the Abstract of Bids and attach thereto all the bids with their corresponding bid
securities and the minutes or proceedings of the bidding. The Abstract of Bids shall
contain the following:
c) Names of bidders and their corresponding calculated bid prices arranged from
lowest to highest, the amount of bid security and the name of the issuing
entity.
32.4 The entire evaluation process for the procurement of Goods and Infrastructure
Projects shall be completed within seven (7) calendar days from the deadline for
receipt of proposals. (a)
75
The 2016 Revised Implementing Rules and Regulations
Section 33. Bid Evaluation of Short Listed Bidders for Consulting Services
33.1 From submission and receipt of bids until the approval by the HoPE of the ranking of
short listed bidders, those that have submitted their bids are prohibited from making
any communication with any BAC member, including its staff and personnel, as well
as its Secretariat and TWG, regarding matters connected to their bids. However, the
BAC, through its Secretariat, may ask in writing the bidder for a clarification of its
bid. All responses to requests for clarification shall be in writing.
33.2 The purpose of bid evaluation is to determine the Highest Rated Bid using the
following steps:
33.2.1 The BAC shall conduct a detailed evaluation of bids using either of the
following evaluation procedures as specified in the Bidding Documents:
ii) After receipt of bids, the technical proposals shall first be opened
and evaluated, in accordance with Section 33.2.2 of this IRR. The
BAC shall rank the consultants in descending order based on the
numerical ratings of their technical proposals and identify the
Highest Rated Bid: Provided, however, That the Highest Rated Bid
shall pass the minimum score indicated in the Bidding Documents.
iv) After approval by the HoPE of the Highest Rated Bid, its financial
proposal shall then be opened. The BAC shall, within three (3)
calendar days, notify and invite the consultant with the Highest
Rated Bid for the opening of financial proposal for the purpose of
conducting negotiations with the said consultant. In the letter of
notification, the BAC shall inform the consultant of the issues in
the technical proposal the BAC may wish to clarify during
negotiations.
76
The 2016 Revised Implementing Rules and Regulations
iv) After approval by the HoPE of the Highest Rated Bid, the BAC
shall, within three (3) calendar days, notify and invite the
consultant with the Highest Rated Bid for negotiation in
accordance with Section 33.2.5 of this IRR, except for the
financial proposal under item (e) thereof. (a)
77
The 2016 Revised Implementing Rules and Regulations
33.2.4 All participating short listed consultants shall be furnished the results
(ranking and total scores only) of the evaluation after the approval by the
HoPE of the ranking. Said results shall also be posted in the PhilGEPS and
the website of the Procuring Entity, whenever available, for a period of
not less than seven (7) calendar days.
Except for meritorious reasons, negotiations with any one consultant shall
be completed within ten (10) calendar days.
33.2.6 Total calculated bid prices, as evaluated and corrected for minor
arithmetical corrections, such as computational errors, which exceed the
ABC shall not be considered.
33.3 There should be no replacement of key personnel before the awarding of contract,
except for justifiable reason as may be determined by the BAC, such as, illness,
death, or resignation provided it is duly supported by relevant certificates, or any
delay caused by the Procuring Entity. The BAC shall immediately consider
negotiation with the next ranked consultant if unjustifiable replacement of
personnel by the first ranked firm is made. Once the contract has been awarded, no
replacement shall be allowed by the HoPE until after fifty percent (50%) of the
78
The 2016 Revised Implementing Rules and Regulations
personnel’s man-months have been served, except for justifiable reasons, subject
to appropriate sanctions as prescribed in the PBDs. (a)
33.4 The entire evaluation process, including the submission of the results thereof to the
HoPE for approval, shall be completed in not more than twenty-one (21) calendar
days after the deadline for receipt of proposals. The proposal with the highest score
shall be identified as the Highest Rated Bid.
RULE X – POST-QUALIFICATION
34.2 Within five (5) calendar days from receipt by the bidder of the notice from the BAC
that the bidder has the Lowest Calculated Bid or Highest Rated Bid, the bidder shall
submit to the BAC its latest income and business tax returns, and other appropriate
licenses and permits required by law and stated in the Bidding Documents.
34.3 The post-qualification shall verify, validate, and ascertain all statements made and
documents submitted by the bidder with the Lowest Calculated Bid/Highest Rated
Bid, using non-discretionary criteria, as stated in the Bidding Documents. These
criteria shall consider, but shall not be limited to, the following:
79
The 2016 Revised Implementing Rules and Regulations
If the BAC verifies any of these deficiencies to be due to the bidder's fault
or negligence, the BAC shall disqualify the bidder from the award, for the
procurement of Goods.
iv) Ascertainment of the authenticity of the bid security and its correctness as
to type, amount, form and wording, and validity period, as required in the
Bidding Documents.
80
The 2016 Revised Implementing Rules and Regulations
of Credit in the amount specified and over the period stipulated in the Bidding
Documents, or the bidder’s NFCC to ensure that the bidder can sustain the
operating cash flow of the transaction. (a)
34.4 If the BAC determines that the bidder with the Lowest Calculated Bid/Highest Rated
Bid passes all the criteria for post-qualification, it shall declare the said bid as the
LCRB or HRRB 66, and recommend to the HoPE the award of contract to the said
bidder at its submitted bid price or its calculated bid price, whichever is lower or, in
the case of quality-based evaluation procedure, submitted bid price or its
negotiated price, whichever is lower.
34.5 If, however, the BAC determines that the bidder with the Lowest Calculated
Bid/Highest Rated Bid fails the criteria for post-qualification, it shall immediately
notify the said bidder in writing of its post-disqualification and the grounds for it.
34.6 Immediately after the BAC has notified the first bidder of its post-disqualification,
and notwithstanding any pending request for reconsideration thereof, the BAC shall
initiate and complete the same post-qualification process on the bidder with the
second Lowest Calculated Bid/Highest Rated Bid. If the second bidder passes the
post-qualification, and provided that the request for reconsideration of the first
bidder has been denied, the second bidder shall be post-qualified as the bidder with
the LCRB or HRRB.
34.7 If the second bidder, however, fails the post-qualification, the procedure for post-
qualification shall be repeated for the bidder with the next Lowest Calculated
Bid/Highest Rated Bid, and so on until the LCRB or HRRB, as the case may be, is
determined for award, subject to Section 37 of this IRR.
34.8 The post-qualification process shall be completed in not more than twelve (12)
calendar days from the determination of the Lowest Calculated Bid/Highest Rated
Bid. In exceptional cases, the post-qualification period may be extended by the
HoPE, but in no case shall the aggregate period exceed forty-five (45) calendar
days for Goods and Infrastructure Projects, or thirty (30) calendar days in
Consulting Services.
c) All bids fail to comply with all the bid requirements or fail post-qualification, or,
in the case of Consulting Services, there is no successful negotiation; or
66
In case of a tie among bidders, refer to Appendix 11 for the Tie-Breaking Method.
81
The 2016 Revised Implementing Rules and Regulations
d) The bidder with the LCRB, HRRB, SCRB or SRRB refuses, without justifiable
cause, to accept the award of contract, and no award is made in accordance
with Section 40 of the Act and this IRR.
35.2 In order to determine the reason for the failed bidding, the BAC shall conduct a
mandatory review and evaluation of the terms, conditions, and specifications in the
Bidding Documents, including its cost estimates.
35.3 Based on its findings, the BAC shall revise the terms, conditions, and specifications,
and if necessary, adjust the ABC, subject to the required approvals, and conduct a
re-bidding with re-advertisement and/or posting, as provided for in Section 21.2 of
this IRR.
35.4 All bidders who have initially responded to the Invitation to Bid/Request for
Expression of Interest and have been declared eligible or short listed in the previous
biddings shall be allowed to submit new bids. The BAC shall observe the same
process and set the new periods according to the same rules followed during the
previous bidding(s).
35.5 Should there occur a second failure of bidding, the Procuring Entity may resort to
negotiated procurement as provided for in Section 53.1 of this IRR.
35.6 Without prejudice to Sec. 35.1 hereof, the BAC is authorized, upon consultation with
the end-user unit, to cancel or terminate the conduct of procurement activities, for
any justifiable reason, such as but not limited to: 67
c) the source of funds for the project has been withheld or reduced through no
fault of the PE; or 70
a) If after advertisement, only one prospective bidder applies for eligibility check, in
accordance with the provisions of this IRR, and it meets the eligibility requirements or
criteria, after which it submits a bid which is found to be responsive to the bidding
requirements;
b) If after advertisement, more than one prospective bidder applies for eligibility check, in
accordance with the provisions of this IRR, but only one bidder meets the eligibility
67
As amended by GPPB Resolution No. 09-2020, dated 7 May 2020, published in the Philippine Daily Inquirer on 15 May 2020.
68
Ibid.
69
Ibid.
70
Ibid.
71
Ibid.
82
The 2016 Revised Implementing Rules and Regulations
c) If after the eligibility check, more than one bidder meets the eligibility requirements,
but only one bidder submits a bid, and its bid is found to be responsive to the bidding
requirements.
In all instances, the Procuring Entity shall ensure that the ABC reflects the most
advantageous prevailing price for the Government. (a)
To facilitate the approval of the award, the BAC shall submit the
following supporting documents to the HoPE:
b) Abstract of Bids;
Within three (3) calendar days from the issuance of the resolution
recommending award of the contract, the BAC shall notify all other
bidders, in writing, of its recommendation. (a)
37.1.2 Within a period not exceeding fifteen (15) calendar days from the
determination by the BAC of the bidder with the LCRB, HRRB, SCRB, or
SRRB, and the recommendation to award the contract, the HoPE or his
duly authorized representative shall approve or disapprove the said
recommendation. (a)
37.1.3 In case of approval, the HoPE shall immediately issue the Notice of
Award to the bidder with the LCRB, HRRB, SCRB or SRRB.
83
The 2016 Revised Implementing Rules and Regulations
A request for reconsideration may be filed by the bidder with the HoPE
within three (3) calendar days from receipt of the notice of disapproval.
The HoPE shall resolve with finality the request for reconsideration within
seven (7) calendar days from the filing thereof and furnish the bidder a
copy of the resolution immediately from its promulgation. In no case shall
the request for reconsideration stay or delay the bidding process.
However, the request for reconsideration must first be resolved before
any award is made. (a)
37.1.4 Within ten (10) days from receipt of by the winning bidder of the Notice
of Award, the following conditions should be complied before the contract
may be awarded:(a)
ii) ii) A valid PCAB license and registration for the type and cost
of the contract to be bid for foreign bidders in Infrastructure
Projects, when the Treaty or International or Executive
Agreement expressly allows submission of such license and
registration as a pre-condition to the Notice of Award; or(a)
37.1.5 Contract award shall be made within the bid validity period provided in
Section 28 of this IRR.
37.1.6 The BAC, through the Secretariat, shall post, within three (3) calendar
days from its issuance, the Notice of Award in the PhilGEPS, the website
72
As amended by GPPB Resolution No. 36-2017, dated 7 November 2017, published in the Philippine Daily Inquirer on 24 April
2018.
84
The 2016 Revised Implementing Rules and Regulations
of the Procuring Entity, if any, and any conspicuous place in the premises
of the Procuring Entity.
37.2.2 The Procuring Entity shall enter into contract with the winning bidder
within the same ten (10) day period provided that all the documentary
requirements are complied with.
a) Contract Agreement;
b) Bidding Documents;
d) Performance Security;
When further approval of higher authority is required, the approving authority for
the contract or his duly authorized representative shall be given a maximum of
twenty (20) calendar days from receipt thereof to approve or disapprove it. In the
case of GOCCs, the concerned board or its duly authorized representative shall be
given a maximum of thirty (30) calendar days from receipt thereof to approve or
disapprove it. (a)
37.4.2 The Procuring Entity, through the BAC Secretariat, shall post a copy of
the Notice to Proceed and the approved contract in the PhilGEPS and the
85
The 2016 Revised Implementing Rules and Regulations
website of the Procuring Entity, if any, within fifteen (15) calendar days
from the issuance of the Notice to Proceed.
For purposes of this section, the term “jury duty” shall be understood to mean a
state by which the members give utmost priority to BAC assignment over all the
other duties and responsibilities until the requirements for the said assignments at
hand are completed.
38.2 The maximum periods and the recommended earliest possible time for action on
specific procurement activities are provided for in Annex “C” 73 of this IRR. In case
the deadline for each activity falls on a non-working day (i.e. Saturday and Sunday),
legal holiday, or special non-working holiday, or other nonworking days duly declared
by the President, Governor, Mayor or other Government Official authorized to make
such declaration, the deadline shall be the next working day. 74 (a)
38.3 If no action on the contract is taken by the HoPE or the appropriate approving
authority within the periods specified in this IRR, the contract concerned shall be
deemed approved: Provided, however, That where further approval by the Office of
the President is required, the contract shall not be deemed approved unless and until
the Office of the President gives actual approval to the contract concerned.
a. For Early Procurement Activities, pending approval and effectivity of the GAA,
corporate budget or appropriations ordinance, or the loan agreement in the case
of FAPs; and 77
The period of action on procurement activities which has been tolled or suspended
shall begin to run again once the basis of such tolling or suspension no longer
73
Recommended Earliest Possible Time and Maximum Period Allowed For the Procurement of Goods, Infrastructure Projects,
and Consulting Services.
74
As amended by GPPB Resolution No. 36-2017, dated 7 November 2017, published in the Philippine Daily Inquirer on 24 April
2018.
75
As amended by GPPB Resolution No. 21-2017, dated 30 May 2017, published in the Philippine Daily Inquirer on 20 November
2017.
76
As amended by GPPB Resolution No. 09-2020, dated 7 May 2020, published in the Philippine Daily Inquirer on 15 May 2020.
77
Ibid.
78
Ibid.
86
The 2016 Revised Implementing Rules and Regulations
exists, such as upon the approval and effectivity of the GAA, reenacted budget,
appropriations ordinance, corporate budget or loan agreement, as the case may be,
or upon lifting of the suspension of the conduct of procurement activities. 79
The period of action on procurement activities shall not commence anew but rather,
grants the PE the balance of the remaining period available for the conduct of
procurement activities which has been tolled or suspended. 80(a)
39.1 To guarantee the faithful performance by the winning bidder of its obligations under
the contract in accordance with the Bidding Documents, it shall post a performance
security prior to the signing of the contract. 81
39.2 The performance security shall be in an amount not less than the required
percentage of the total contract price in accordance with the following schedule: (a)
Amount of Performance
Security
Form of Performance Security (Not less than the required
percentage of the Total
Contract Price)
a) Cash or cashier’s/manager’s check issued by a
Universal or Commercial Bank.
79
Ibid.
80
Ibid.
81
During a State of Calamity, or Implementation of Community Quarantine or Similar Restrictions, GPPB Resolution No. 09-
2020, dated 7 May 2020, published in the Philippine Daily Inquirer on 15 May 2020 provides that procuring entities are allowed
to accept:
xxx
6.4 Performance Securing Declaration (PSD) in lieu of a performance security to guarantee the winning bidder’s faithful
performance of obligations under the contract, subject to the following:
a. Similar to the PSD used in Framework Agreement, such declaration shall state, among others, that the winning
bidder shall be blacklisted from being qualified to participate in any government procurement activity for one (1) year,
in case of first offense or two (2) years, if with prior similar offense, in the event it violates any of the conditions stated
in the contract. A copy of the PSD form is attached hereto as Annex “A”;
b. An unnotarized PSD may be accepted, subject to submission of a notarized PSD before payment, unless the same is
replaced with a performance security in the prescribed form, as stated below; and
c. The end-user may require the winning bidder to replace the submitted PSD with a performance security in any of the
prescribed forms under Section 39.2 of the 2016 revised IRR of RA No. 9184 upon lifting of the State of Calamity, or
community quarantine or similar restrictions, as the case may be.
87
The 2016 Revised Implementing Rules and Regulations
Amount of Performance
Security
Form of Performance Security (Not less than the required
percentage of the Total
Contract Price)
c) Surety bond callable upon demand issued by a
surety or insurance company duly certified by
Thirty percent (30%)
the Insurance Commission as authorized to
issue such security.
39.3 The performance security shall be denominated in Philippine Pesos and posted in
favor of the Procuring Entity, which shall be forfeited in the event it is established
that the winning bidder is in default in any of its obligations under the contract.
39.4 The performance security shall remain valid until issuance by the Procuring Entity of
the Certificate of Final Acceptance.
39.5 The performance security may be released by the Procuring Entity after the
issuance of the Certificate of Final Acceptance, subject to the following conditions:
a) Procuring Entity has no claims filed against the contract awardee or the surety
company;
b) It has no claims for labor and materials filed against the contractor; and
39.6 For the procurement of Infrastructure Projects, the winning bidder shall post an
additional performance security following the schedule above to cover any
cumulative increase of more than ten percent (10%) over the original value of the
contract as a result of amendments to order or change orders, extra work orders
and supplemental agreements, as the case may be. The winning bidder shall cause
the extension of the validity of the Performance Security to cover approved contract
time extensions.
39.7 In case of a reduction in the contract value, or, in the case of procurement of
Infrastructure Projects, for partially completed works under the contract which are
usable and accepted by the GoP, and the use of which, in the judgment of the
implementing agency or the Procuring Entity, will not affect the structural integrity
of the entire project, the said agency or Procuring Entity shall allow a proportional
reduction in the original performance security: Provided, That any such reduction is
more than ten percent (10%) and that the aggregate of such reductions is not
more than fifty percent (50%) of the original Performance Security.
Section 40. Failure to Enter into Contract and Post Performance Security
40.1 If the bidder with the LCRB, HRRB, SCRB or SRRB fails, refuses or is unable to
submit the documents required under Section 37.1 of this IRR or to make good its
bid by entering into a contract with the Procuring Entity or post the required
Performance Security within the period stipulated in this IRR or in the Bidding
Documents, the bid security shall be forfeited and the appropriate sanctions provided
in this IRR and existing laws shall be imposed, except where such failure, refusal or
inability is through no fault of the said bidder.
88
The 2016 Revised Implementing Rules and Regulations
40.2 In the case of the failure, refusal or inability of the bidder with LCRB or HRRB to
submit the documents required under Section 37.1 of this IRR or to enter into
contract and post the required Performance Security, as provided in this Section, the
BAC shall disqualify the said bidder, and shall initiate and complete the post-
qualification process on the bidder with the second Lowest Calculated Bid/Highest
Rated Bid: Provided, however, That in the case of Consulting Services, the second
Highest Rated Bid has successfully undergone the negotiation stage in accordance
with Section 33.2.5 of this IRR. This procedure shall be repeated until the LCRB or
HRRB is determined for award. However, if no bidder passes post-qualification, the
BAC shall declare the bidding a failure and conduct a re-bidding with re-
advertisement. Should there occur another failure of bidding after the conduct of the
contract’s re-bidding, the Procuring Entity concerned may enter into a negotiated
procurement.
40.3 In the case of failure, refusal or inability of the bidder with the SCRB or SRRB to
submit the documents required under Section 37.1 of this IRR or to enter into
contract and post the required Performance Security, as provided in this Section, the
BAC shall disqualify the said bidder, and shall declare the bidding a failure and
conduct a re-bidding with re-advertisement and/or posting, as provided for in
Sections 21 and 25 of this IRR. Should there occur another failure of bidding after
the conduct of the contract’s re-bidding, the Procuring Entity concerned may enter
into a negotiated procurement.
b) If the BAC is found to have failed in following the prescribed bidding procedures; or
c) For any justifiable and reasonable ground where the award of the contract will not
redound to the benefit of the GoP, as follows: (i) if the physical and economic
conditions have significantly changed so as to render the project no longer
economically, financially, or technically feasible, as determined by the HoPE; (ii) if the
project is no longer necessary as determined by the HoPE; or (iii) if the source of
funds for the project has been withheld or reduced through no fault of the Procuring
Entity.(a)
89
The 2016 Revised Implementing Rules and Regulations
42.3 The contract implementation guidelines for the procurement of consulting services
are provided for in Annex “F” of this IRR.
42.4 The contract termination guidelines as provided for in Annex “I” of this IRR. (n)
42.5 No incentive bonus, in whatever form or for whatever purpose, shall be allowed. (42.4)
42.6 Procuring Entities may cause the issuance of the letter of credit in favor of foreign
suppliers: Provided, That the letter of credit shall be issued by a Government
Servicing Bank: Provided, further, that the cost for the opening of letter of credit
shall be for the account of the foreign supplier and must be stated in the Bidding
Documents: Provided, finally, That payment shall be charged against the letter of
credit only after delivery and acceptance of the goods as certified by the Procuring
Entity.(a) 82
43.1.2 The Procuring Entity shall give preference to materials and supplies
produced, made and manufactured in the Philippines, subject to the
conditions herein below specified. The award shall be made to the lowest
Domestic Bidder, provided his bid is not more than fifteen percent (15%)
in excess of the lowest Foreign Bid. (a)
43.1.3 A Domestic Bidder can only claim preference if it secures from the DTI a
certification that the articles forming part of its bid are substantially
composed of articles, materials, or supplies grown, produced, or
manufactured in the Philippines. (43.1.4)
43.2.1 The preference shall be applied when the lowest Foreign Bid is lower
than the lowest bid offered by a Domestic Bidder. The Procuring Entity
shall ensure that both bids are responsive to the minimum requirements
as specified in the Bidding Documents. (a)
43.2.2 For evaluation purposes, the lowest Foreign Bid shall be increased by
fifteen percent (15%).
82
As amended by GPPB Resolution No. 12-2019, dated 22 April 2019, published in the Official Gazette on 26 August 2019.
90
The 2016 Revised Implementing Rules and Regulations
43.2.3 In the event that the lowest bid offered by a Domestic Bidder does not
exceed the lowest Foreign Bid as increased, the Procuring Entity shall
award the contract to the Domestic Bidder at the amount of the lowest
Foreign Bid. (a)
43.2.4 If the Domestic Bidder refuses to accept the award of contract at the
amount of the Foreign Bid within two (2) calendar days from receipt of
written advice from the BAC, the Procuring Entity shall award the
contract to the bidder offering the Foreign Bid.
Priority programs and infrastructure projects funded out of the annual GAA which are
intended for implementation within the province shall be subject to the same competitive
bidding and to the procurement processes prescribed in this IRR. For purposes of this
Section, Engineering District infrastructure projects and priority programs fully funded by the
Government and identified in consultation with the concerned members of Congress, shall
constitute “provincial projects” and shall be governed by this Section.
The lease of construction and office equipment, including computers, communication and
information technology equipment, are subject to the same competitive bidding and to the
processes prescribed under the Act and this IRR. Lease may also cover lease purchases or
lease-to-own and similar variations.
47.1 All bids shall be accompanied by a sworn affidavit of the bidder that it is not related
to the HoPE, members of the BAC, the TWG, and the BAC Secretariat, the head of
the PMO or the end-user or implementing unit, and the project consultants, by
consanguinity or affinity up to the third civil degree. Failure to comply with the
aforementioned provision shall be a ground for the automatic disqualification of the
91
The 2016 Revised Implementing Rules and Regulations
bid in consonance with Section 30 of this IRR. For this reason, relation to the
aforementioned persons within the third civil degree of consanguinity or affinity
shall automatically disqualify the bidder from participating in the procurement of
contracts of the Procuring Entity notwithstanding the act of such persons inhibiting
themselves from the procurement process. On the part of the bidder, this provision
shall apply to the following persons:
e) If the bidder is a joint venture, the provisions of items (a), (b), (c), or (d) of
this Section shall correspondingly apply to each of the members of the said
joint venture, as may be appropriate. (a)
47.2 All bidders also found to have conflicting interests with each other shall be
disqualified to participate in the procurement at hand, without prejudice to the
imposition of appropriate administrative, civil, and criminal sanctions. A bidder may
be considered to have conflicting interests with another bidder in any of the events
described in paragraphs (a) through (c) below and a general conflict of interest in
any of the circumstances set out in paragraphs (d) through (j) below:
b) A bidder receives or has received any direct or indirect subsidy from any other
bidder;
c) A bidder has the same legal representative as that of another bidder for
purposes of this bid;
d) A bidder has a relationship, directly or through third parties, that puts them in
a position to have access to information about or influence on the bid of
another bidder or influence the decisions of the Procuring Entity regarding
this bidding process. This will include a firm or an organization who lends, or
temporarily seconds, its personnel to firms or organizations which are
engaged in consulting services for the preparation related to procurement for
or implementation of the project if the personnel would be involved in any
capacity on the same project;
e) A bidder submits more than one bid in this bidding process. However, this
does not limit the participation of subcontractors in more than one bid;
92
The 2016 Revised Implementing Rules and Regulations
48.2 In accordance with Section 10 of this IRR, as a general rule, the Procuring Entities
shall adopt competitive bidding as the general method of procurement and shall see
to it that the procurement program allows sufficient lead time for such competitive
bidding. Alternative methods of procurement shall be resorted to only in highly
exceptional cases provided for in this Rule.
48.3 The method of procurement to be used shall be as indicated in the approved APP. If
the original method of procurement recommended in the APP was competitive
bidding but cannot be ultimately pursued, the BAC, through a resolution, shall justify
93
The 2016 Revised Implementing Rules and Regulations
49.3 The pre-selection shall be based upon the capability and resources of the bidders to
perform the contract taking into account their experience and past performance on
similar contracts, capabilities with respect to personnel equipment or manufacturing
facilities, and financial position. Pre-selection shall be done in accordance with the
following procedures provided in the GPMs.
The BAC of the concerned Procuring Entity shall directly invite all the suppliers or
consultants appearing in the pre-selected list. All other procedures for competitive
bidding shall be undertaken, except for the advertisement of Invitation to
Bid/Request for Expression of Interest under Section 21.2.1 of this IRR.
a) Procurement of Goods of proprietary nature which can be obtained only from the
proprietary source, i.e. when patents, trade secrets, and copyrights prohibit others
from manufacturing the same item;
83
Refer to Appendix 12 for the Pre-Selection Procedure in the Conduct of Limited Source Bidding.
94
The 2016 Revised Implementing Rules and Regulations
c) Those sold by an exclusive dealer or manufacturer which does not have sub-dealers
selling at lower prices and for which no suitable substitute can be obtained at more
advantageous terms to the GoP.
Repeat Order, when provided for in the APP, is a method of procurement of Goods from the
previous winning bidder, whenever there is a need to replenish goods procured under a
contract previously awarded through Competitive Bidding. Repeat orders shall likewise be
subject to the following conditions:
a) Unit prices of the repeat order must be the same as or lower than those in the original
contract: Provided, That such prices are still the most advantageous to the GoP after
price verification;
b) The repeat order will not result in splitting of contracts, requisitions, or purchase
orders, as provided for in Section 54.1 of this IRR;
c) Except in cases duly approved by the GPPB, the repeat orders shall be availed of only
within six (6) months from the date of the Notice to Proceed arising from the original
contract: Provided, That there has been a partial delivery, inspection and acceptance
of the goods within the same 6-month period; and
d) Repeat orders shall not exceed twenty-five percent (25%) of the quantity of each item
in the original contract. In order not to exceed the 25% threshold, the goods under
the original contract must be:
i. Quantifiable
ii. Divisible; and
iii. Consisting of at least four (4) units per item. (a)
52.1 Shopping is a method of procurement of Goods whereby the Procuring Entity simply
requests for the submission of price quotations for readily available off-the-shelf
goods or ordinary/regular equipment to be procured directly from suppliers of known
qualifications. This method of procurement shall be employed in any of the following
cases:
84
Consolidated Guidelines for the Alternative Methods of Procurement.
95
The 2016 Revised Implementing Rules and Regulations
52.2 The phrase “ordinary or regular office supplies” shall be understood to include those
supplies, commodities, or materials which are necessary in the transaction of official
businesses, and consumed in the day-to-day operations.
However, office supplies shall not include services such as repair and maintenance of
equipment and furniture, as well as trucking, hauling, janitorial, security, and related
or analogous services. (a)
52.3 Under Section 52.1 (b) of this IRR, at least three (3) price quotations from bona fide
suppliers shall be obtained.
52.4 The thresholds prescribed in Annex “H” of this IRR shall be subject to a periodic
review by the GPPB. For this purpose, the GPPB shall be authorized to increase or
decrease the said amount in order to reflect changes in economic conditions and for
other justifiable reasons.
53.1 Tw o Failed Biddings . Where there has been failure of competitive bidding or
Limited Source Bidding for the second time as provided in Section 35 of the Act and
this IRR. (a)
53.2 Em ergency Cases . In case of imminent danger to life or property during a state of
calamity, or when time is of the essence arising from natural or man-made calamities
or other causes where immediate action is necessary to prevent damage to or loss of
life or property, or to restore vital public services, infrastructure facilities and other
public utilities.
The instances or situations where the foregoing conditions may be applied include
the provision of immediate response and initial recovery steps to avoid loss of life,
injury, disease and other negative effects on human, physical, mental and social
well-being, together with damage to property, destruction of assets, loss of services,
social and economic disruption and environmental degradation. 85(a)
In the case of Infrastructure Projects, the Procuring Entity has the option to
undertake the project through negotiated procurement or by administration or, in
high security risk areas, through the AFP 86.
85
As amended by GPPB Resolution No. 03-2020, dated 9 March 2020, published in the Philippine Daily Inquirer on 13 March
2020.
86
Refer to Appendix 13 for the Guidelines on Implementation of Infrastructure Projects Undertaken by the AFP Corps of
Engineers.
96
The 2016 Revised Implementing Rules and Regulations
97
The 2016 Revised Implementing Rules and Regulations
consultants shall, at the most, be on a six month basis, renewable at the option of
the appointing HoPE, but in no case shall exceed the term of the latter.
53.9 Sm all Value Procurem ent . Procurement of Goods, Infrastructure Projects and
Consulting Services, where the amount involved does not exceed the threshold
prescribed in Annex "H" of this IRR: Provided, That in case of Goods, the
procurement does not fall under shopping in Section 52 of this IRR. (a)
87
As amended by GPPB Resolution No. 23-2018, dated 4 December 2018, published in the Official Gazette on 26 August 2019.
88
As amended by GPPB Resolution No. 23-2018, dated 4 December 2018, published in the Official Gazette on 26 August 2019.
89
Ibid.
90
Ibid.
91
Ibid.
92
Ibid.
93
Ibid.
94
Ibid.
95
Ibid.
96
Ibid.
98
The 2016 Revised Implementing Rules and Regulations
53.10 Lease of R eal Property and Venue . Lease of real property and venue for official
use, subject to Annex “H” of this IRR. (a)
53.14 Direct R etail Purchase of Petroleum Fuel, Oil and Lubricant (POL)
Products and Airline Tickets. Where Goods and Services are required by a
Procuring Entity for the efficient discharge of its principal mandate, governmental
functions, or day-today operations, direct retail purchase of (i) petroleum fuel, oil
and lubricant (POL) products; and (ii) airline tickets may be made by end-users
delegated to procure the same from identified direct suppliers or service
providers. 98 (n)
Section 54. Terms and Conditions for the use of Alternative Methods
54.2 For alternative methods of procurement, the Procuring Entity may dispense with the
advertisement in the newspaper and posting requirement as prescribed in Section
21.2.1 of this IRR.
97
Refer to Appendix 14 for the Guidelines on Non-Governmental Organization Participation in Public Procurement.
98
As amended by GPPB Resolution No. 24-2019, dated 30 October 2019, published in the Official Gazette on 30 December
2019.
99
The 2016 Revised Implementing Rules and Regulations
For the following modalities, however, the BAC, through its Secretariat, shall post the
invitation or request for submission of price quotations/proposals in the PhilGEPS
website, the website of the Procuring Entity concerned, if available, and at any
conspicuous place reserved for this purpose in the premises of the Procuring Entity
for a period of at least three (3) calendar days:
2. Section 52.1(b) Shopping for ordinary office supplies and equipment not available
in DBM-PS (for ABC above Fifty Thousand Pesos (₱50,000.00));
4. Section 53.9 Small Value Procurement (For ABC above Fifty Thousand Pesos
(₱50,000.00)); and
54.3 In all instances of alternative methods of procurement, the BAC, through the
Secretariat, shall post, for information purposes, the notice of award, contract or
purchase order, including notice to proceed if necessary, in the PhilGEPS website,
the website of the Procuring Entity concerned, if available, and at any conspicuous
place reserved for this purpose in the premises of the Procuring Entity, except for
contracts with ABC of Fifty Thousand Pesos (₱50,000.00) and below.(a)
54.4 Except for Limited Source Bidding under Section 49 of this IRR, submission of bid
securities may be dispensed with.
Performance and/or warranty securities are required for the following alternative
methods of procurement, in accordance with Sections 39 and 62 of this IRR:
100
The 2016 Revised Implementing Rules and Regulations
Small Value Procurement Procuring Entity may require Procuring Entity may require
PS depending on the nature WS depending on the nature
of the procurement project. of the procurement project.
However, for Infrastructure In no case shall WS be
Projects, PS is required. required in the procurement
of Consulting Services.
b. Section 52.1 (b) - Shopping for Ordinary Office Supplies and Equipment not
available in DBM-PS
c. Section 53.3 - Take Over of Contracts (Only for New Bidders, if any.)
For purposes of Limited Source Bidding under Section 49 and Two Failed Biddings
under Section 53.1, the BAC shall require the submission of a certificate of PhilGEPS
registration in accordance with Section 8.5.2 of this IRR. (a)
54.7 The specific terms, conditions and documentary requirements, including the
limitations and restrictions, for the application of each of the alternative methods
mentioned in this article shall be provided for in Annex "H" of this IRR and guidelines
specifically issued for this purpose. (n)
101
The 2016 Revised Implementing Rules and Regulations
If a failed bidder signifies his intent to file a request for reconsideration, the BAC
shall keep the bid envelopes of the said failed bidder unopened and/or duly sealed
until such time that the request for reconsideration has been resolved. (a)
55.2 In the event that the request for reconsideration is denied, decisions of the BAC may
be protested in writing to the HoPE: Provided, however, That a prior request for
reconsideration should have been filed by the party concerned in accordance with
the preceding Section, and the same has been resolved.
55.3 The protest must be filed within seven (7) calendar days from receipt by the party
concerned of the resolution of the BAC denying its request for reconsideration. A
protest shall be made by filing a verified position paper with the HoPE concerned,
accompanied by the payment of a non-refundable protest fee, which shall be paid in
cash in accordance with the following schedule:(a)
55.4 The verified position paper shall contain the following information:
g) Such other matters and information pertinent and relevant to the proper
resolution of the protest.
The position paper is verified by an affidavit that the affiant has read and
understood the contents thereof and that the allegations therein are true and
correct of his personal knowledge or based on authentic records. An unverified
position paper shall be considered unsigned, produces no legal effect, and results to
the outright dismissal of the protest.
a) he has not theretofore commenced any action or filed any claim involving the
same issues in any court, tribunal or quasi-judicial agency and, to the best of
his knowledge, no such other action or claim is pending therein;
102
The 2016 Revised Implementing Rules and Regulations
c) if he should thereafter learn that the same or similar action or claim has been
filed or is pending, he shall report that fact within five (5) days therefrom to the
HoPE wherein his protest is filed.
Failure to comply with the foregoing requirements shall not be curable by mere
amendment of the verified position paper.
The protests shall be resolved strictly on the basis of records of the BAC. The HoPE shall
resolve the protest within seven (7) calendar days from receipt thereof. Subject to the
provisions of existing laws on the authority of Department Secretaries and the heads of
agencies, branches, constitutional commissions, or instrumentalities of the GoP to approve
contracts, the decisions of the HoPE concerned shall be final up to the limit of his contract
approving authority. With respect to LGUs, the decision of the local chief executive shall be
final. (a)
In no case shall any protest taken from any decision treated in this Rule stay or delay the
bidding process: Provided, however, That protests must first be resolved before any award
is made.
58.2 This provision is without prejudice to any law conferring on the Supreme Court the
sole jurisdiction to issue temporary restraining orders and injunctions relating to
Infrastructure Projects of the GoP.
58.3 The head of the BAC Secretariat of the Procuring Entity concerned shall ensure that
the GPPB shall be furnished a copy of the cases filed in accordance with this Section.
103
The 2016 Revised Implementing Rules and Regulations
59.2 Any and all disputes arising from the implementation of a contract covered by the
Act and this IRR shall be submitted to arbitration in the Philippines according to the
provisions of R.A. 876, otherwise known as the "Arbitration Law" and R.A. 9285,
otherwise known as the “Alternative Dispute Resolution Act of 2004”: Provided,
however, That disputes that are within the competence of the Construction Industry
Arbitration Commission to resolve shall be referred thereto. The process of
arbitration shall be incorporated as a provision in the contract that will be executed
pursuant to the provisions of the Act and this IRR: Provided, further, That by mutual
agreement, the parties may agree in writing to resort to other alternative modes of
dispute resolution.
The arbitral award and any decision rendered in accordance with the foregoing Section shall
be appealable by way of a petition for review to the Court of Appeals. The petition shall
raise pure questions of law and shall be governed by the Rules of Court.
61.2 In cases where the cost of the awarded contract is affected by any applicable new
laws, ordinances, regulations, or other acts of the GoP, promulgated after the date of
bid opening, a contract price adjustment shall be made or appropriate relief shall be
applied on a no loss-no gain basis.(17a)
61.3 Any request for price escalation under extraordinary circumstances shall be
submitted by the concerned entity to the National Economic and Development
Authority (NEDA) with the endorsement of the Procuring Entity. The burden of
proving the occurrence of extraordinary circumstances that will allow for price
escalation shall rest with the entity requesting for such escalation. NEDA shall only
respond to such request after receiving the proof and the necessary documentation.
For purposes of this Section, “extraordinary circumstances” shall refer to events that
may be determined by the NEDA in accordance with the Civil Code of the Philippines,
and upon the recommendation of the Procuring Entity concerned.
61.4 All contracts shall be denominated and payable in Philippine currency, and this shall
be stated in the Bidding Documents: Provided, however, That subject to the
99
Refer to Appendix 15 for the Guidelines for Contract Price Escalation.
104
The 2016 Revised Implementing Rules and Regulations
guidelines 100 issued by the GPPB, the Procuring Entity may provide in the Bidding
Documents that obligations may be paid in foreign currency, which shall be accepted
or tradeable by the Bangko Sentral ng Pilipinas; 101 Provided, further, That should the
Procuring Entity receive bids denominated in foreign currency, the same shall be
converted to Philippine currency based on the exchange rate prevailing on the day of
the bid opening for purposes of bid comparison and evaluation.(a)
62.1 For the procurement of Goods, in order to assure that manufacturing defects shall be
corrected by the supplier, a warranty security shall be required from the contract
awardee for a minimum period of three (3) months, in the case of Expendable
Supplies, or a minimum period of one (1) year, in the case of Non-expendable
Supplies, after acceptance by the Procuring Entity of the delivered supplies.
The obligation for the warranty shall be covered by either retention money in an
amount equivalent to at least one percent (1%) but not to exceed five percent (5%)
of every progress payment, or a special bank guarantee equivalent to at least one
percent (1%) but not to exceed five percent (5%) of the total contract price. The
said amounts shall only be released after the lapse of the warranty period or, in the
case of Expendable Supplies, after consumption thereof: Provided, however, That
the supplies delivered are free from patent and latent defects and all the conditions
imposed under the contract have been fully met. (a)
62.2 For the procurement of Infrastructure Projects, the following warranties shall be
made:
62.2.2 One (1) year from project completion up to final acceptance or the
defects liability period.
62.2.2.1 The contractor shall undertake the repair works, at his own
expense, of any damage to the infrastructure on account of
the use of materials of inferior quality, within ninety (90)
days from the time the HoPE has issued an order to
undertake repair. In case of failure or refusal to comply with
this mandate, the Procuring Entity shall undertake such
repair works and shall be entitled to full reimbursement of
expenses incurred therein upon demand.
100
Refer to Appendix 16 for the Guidelines on Procurements Involving Foreign-Denominated Bids, Contract Prices, and
Payment Using Letters of Credit.
101
As amended by GPPB Resolution No. 15-2020, dated 28 July 2020, published in the Official Gazette on 21 September 2020.
105
The 2016 Revised Implementing Rules and Regulations
106
The 2016 Revised Implementing Rules and Regulations
107
The 2016 Revised Implementing Rules and Regulations
Amount of Warranty
Security
Form of Warranty Security (Not less than the required
percentage of the Total
Contract Price)
a) Cash or Letter of Credit issued
by a Universal or Commercial
Bank: Provided, however, That
the Letter of Credit shall be
confirmed or authenticated by a
Universal or Commercial Bank,
if issued by a foreign bank. Five percent (5%)
For biddings conducted by
LGUs, the Letter of Credit may
be issued by other banks
certified by the BSP as
authorized to issue such
financial instrument. (a)
b) Bank guarantee confirmed by a
Universal or Commercial Bank.
108
The 2016 Revised Implementing Rules and Regulations
c) To prepare a generic procurement manual and the standard bidding forms for
procurement;
d) To ensure the proper implementation by Procuring Entities of the Act, this IRR
and all other relevant rules and regulations pertaining to public procurement;
The GPPB shall create a Technical Support Office (TSO) which shall provide support
in the performance of its duties and responsibilities specified in the Act and this
IRR. The TSO shall be an attached agency of the DBM and shall be under its
administrative supervision for general oversight and for budgeting purposes.
The GPPB shall determine the TSO’s organizational structure and staffing, subject
to DBM approval. The TSO shall be headed by an Executive Director and supported
by Deputy Executive Directors, of good moral character, unquestionable integrity,
and known probity, to be appointed by the President of the Republic of the
Philippines. 102(a)
All other employees of the TSO shall be appointed by its Executive Director. 103 (a)
63.3 The TSO shall provide research, technical and administrative support to the GPPB,
including:
102
As amended by GPPB Resolution No. 17-2019, dated 17 July 2019, published in the Philippine Daily Inquirer on 26 July
2019.
103
Ibid.
109
The 2016 Revised Implementing Rules and Regulations
e) Monitoring the compliance to the Act and assisting Procuring Entities improve
their compliance;
g) Secretariat support.
63.4 In addition to the powers granted under the Act and this IRR, the GPPB shall
absorb all the powers, functions and responsibilities of the Procurement Policy
Board created under E.O. 359, s. 1989. All functions related to procurement policy-
making of the Infrastructure Committee of the NEDA Board are transferred to the
GPPB.
The GPPB shall be composed of the Secretary of the Department of Budget and
Management, as Chairperson, the Director-General of NEDA, as Alternate Chairperson, with
the following as Members; the Secretaries of the Departments of Public Works and
Highways, Finance, Trade and Industry, Health, National Defense, Education, Interior and
Local Government, Science and Technology, Transportation, Information and
Communications Technology, and Energy, or their duly authorized representatives, and a
representative from the private sector to be appointed by the President upon the
recommendation of the GPPB. The GPPB may invite representatives from the COA or from
relevant Government agencies and private sectors to serve as resource persons.
a) Opening any sealed bid including but not limited to Bids that may have been
submitted through the electronic system and any and all documents required to
be sealed or divulging their contents, prior to the appointed time for the public
opening of Bids or other documents.
b) Delaying, without justifiable cause, the screening for eligibility, opening of bids,
evaluation and post evaluation of bids, and awarding of contracts beyond the
prescribed periods of action provided for in this IRR.
104
Pursuant to Section 10(h) of RA No. 11363 or “An Act Establishing the Philippine Space Development and Utilization Policy
and Creating The Philippine Space Agency, and for Other Purposes” approved on 8 August 2019, the Director-General of the
Philippine Space Agency shall serve as a member of the Government Procurement Policy Board (GPPB) as established by
Republic Act No. 9184.
110
The 2016 Revised Implementing Rules and Regulations
e) Abuse by the HoPE of his power to reject any and all bids as mentioned under
Section 41 of the Act and this IRR, with manifest preference to any bidder who
is closely related to him in accordance with Section 47 of the Act and this IRR.
When any of the foregoing acts is done in collusion with private individuals, the
private individuals shall likewise be liable for the offense.
In addition, the public officer involved shall also suffer the penalty of temporary
disqualification from public office, while the private individual shall be permanently
disqualified from transacting business with the Government.
65.2 Private individuals who commit any of the following acts, and any public officer who
conspires with them, shall upon conviction, suffer the penalty of imprisonment of
not less than six (6) years and one (1) day but not more than fifteen (15) years:
a) When two or more bidders agree and submit different bids as bona fide
bidders, all the while knowing that the bid(s) of one or more of them was so
much higher than the other that the latter could not be honestly accepted and
that the contract will surely be awarded to the pre-arranged lowest bid.
b) When a bidder maliciously submits different bids through two or more persons,
corporations, partnerships or any other business entity in which he has an
interest, to create the appearance of competition that does not in fact exist so
as to be adjudged as the winning bidder.
c) When two or more bidders enter into an agreement which calls upon one or
more of them to refrain from bidding for procurement contracts, or which
requires one or more of them to withdraw Bids already submitted, in order to
secure an undue advantage to any one of them.
In addition, the public officer persons involved shall also suffer the penalty of
temporary or perpetual disqualification from public office and the private individual
shall be permanently disqualified from transacting business with the Government.
65.3 Private individuals who commit any of the following acts, and any public officer
conspiring with them, shall upon conviction, suffer the penalty of imprisonment of
not less than six (6) years and one (1) day but not more than fifteen (15) years:
111
The 2016 Revised Implementing Rules and Regulations
b) Submitting Bidding Documents of whatever kind and nature that contain false
information or falsified documents or conceal such information in the Bidding
Documents, in order to influence the outcome of the competitive bidding.
65.4 It is understood that the above penalties and offenses shall cover all types of
procurement whether done manually or electronically.
65.5 When the bidder is a juridical entity, criminal liability and the accessory penalties
shall be imposed on its directors, officers or employees who actually commit any of
the foregoing acts. If a person previously held liable or found guilty under the
provisions of the Act and this IRR has a controlling interest in a prospective bidder-
entity, the said bidder-entity shall be disqualified to participate in any procurement
activity being conducted by the Government.
Jurisdiction over the offenses defined under this Rule shall belong to the appropriate courts,
according to laws existing at the time of the commission of the offenses.
All contracts executed in accordance with the Act and this IRR shall contain a provision on
liquidated damages which shall be payable by the contractor in case of breach thereof. For
the procurement of Goods, Infrastructure Projects and Consulting Services, the amount of
the liquidated damages shall be at least equal to one-tenth of one percent (0.001) of the
cost of the unperformed portion for every day of delay. Once the cumulative amount of
liquidated damages reaches ten percent (10%) of the amount of the contract, the Procuring
Entity may rescind or terminate the contract, without prejudice to other courses of action
and remedies available under the circumstances. (a)
112
The 2016 Revised Implementing Rules and Regulations
69.1 In addition to the provisions of Rules XXI and XXII of this IRR, the HoPE, subject to
the authority delegated to the BAC, if any, shall impose on bidders or prospective
bidders, the administrative penalty of suspension for one (1) year for the first
offense, and suspension of two (2) years for the second offense from participating in
the competitive bidding process, as well as disqualification from further participating
in the competitive bidding being undertaken by the Procuring Entity concerned,
where applicable, for the following violations:
a) Submission of eligibility requirements containing false information or falsified
documents.
c) Allowing the use of one’s name, or using the name of another for purposes of
competitive bidding.
i) All other acts that tend to defeat the purpose of the competitive bidding, such
as habitually withdrawing from bidding, submitting late Bids or patently
insufficient bid, for at least three (3) times within a year, except for valid
reasons.
69.2 In addition to the penalty of suspension, the bid security or the performance
security posted by the concerned bidder or prospective bidder shall also be
forfeited.
69.3 The HoPE may delegate to the BAC the authority to impose the aforementioned
administrative penalties.
113
The 2016 Revised Implementing Rules and Regulations
The HoPE may preventively suspend any member of the Technical Working Group or the
Secretariat, or the BAC, if there are strong reasons or prima facie evidence showing that the
officials or employees concerned are guilty of the charges filed against them under Rules
XXI and XXII of this IRR, or for dishonesty as defined by the Civil Service Laws. For
uniformed personnel of the AFP, the substantive and procedural due process under its
justice system shall be applied. In all cases, due process as mandated by the Constitution
and Civil Service laws, rules and regulations, shall be strictly observed.
All the members of the BAC are hereby authorized to engage the services of private lawyers
or external counsel immediately upon receipt of Court Notice that a civil or criminal action,
suit or proceeding is filed against them in connection with the lawful performance of their
official functions and duties as BAC members. The lawyer's fee shall be part of the
indemnification package for the BAC members, subject to the provisions of Section 73 of the
Act and this IRR. For purposes of this Rule, the BAC members shall be understood to include
its support staff, such as the members of the TWG and the BAC Secretariat.
73.1 The GPPB shall establish an equitable indemnification package 106 for public officials
providing services in and for the BAC, which may be in the form of free legal
assistance, liability insurance, and other forms of protection and indemnification for
all reasonable fees, costs, and expenses incurred by such persons in connection with
any administrative, civil or criminal action, suit or proceeding to which they may be,
or have been made, a party, by reason of the lawful performance of their official
functions and duties, unless they are finally adjudged in such action or proceeding to
be liable for gross negligence or misconduct or grave abuse of discretion, or
otherwise held liable or guilty of the complaints or charges.In the event of a
settlement or compromise, indemnification shall be confined only on matters covered
by the settlement, for which the Procuring Entity had been advised by counsel, that,
105
Refer to Appendix 17 for the Uniform Guidelines for Blacklisting of Manufacturers, Suppliers, Distributors, Contractors, and
Consultants.
106
Refer to Appendix 18 for the Guidelines for Legal Assistance and Indemnification of Bids and Awards Committee (BAC)
Members and its Support Staff.
114
The 2016 Revised Implementing Rules and Regulations
74.1 As the need arises, this IRR may be amended by the GPPB.Any amendment to this
IRR shall be applicable to all procurement activities, the advertisement or invitation
of which were issued after the date of effectivity of the said amendment.
The Act repeals E.O. 40, entitled “Consolidating Procurement Rules and Procedures for All
National Government Agencies, Government-Owned or -Controlled Corporations and/or
Government Financial Institutions, and Requiring the Use of the Government Electronic
Procurement System;” E.O. 262, s. 2000, entitled "Amending E.O. 302, s. 1996, entitled
"Providing Polices, Guidelines, Rules and Regulations for the Procurement of Goods/
Supplies by the National Government" and Sec. Three (3) of E.O. 201, s. 2000, entitled
"Providing Additional Policies and Guidelines in the Procurement of Goods/Supplies by the
National Government;" E.O. 302, s. 1996, entitled "Providing Policies, Guidelines, Rules and
Regulations for the Procurement of Goods/Supplies by the National Government" and
Presidential Decree No. 1594 (P.D. 1594), dated June 11, 1978, entitled “Prescribing
Policies, Guidelines, Rules and Regulations for Government Infrastructure Contracts;" and
the relevant provisions of R.A. 7898 dated February 23, 1995, entitled “An Act Providing for
the Modernization of the Armed Forces of the Philippines and for Other Purposes.” This law
amends Title Six, Book Two of R.A. 7160, otherwise known as the “Local Government Code
of 1991," and, in furtherance thereto, Chapter Five, Title One, Book One of the same law;
the relevant provisions of E.O. 164, s. 1987, entitled "Providing Additional Guidelines in the
Processing and Approval of Contracts of the National Government." Any other law,
presidential decree or issuance, executive order, letter of instruction, administrative order,
proclamation, charter, rule or regulation and/or parts thereof contrary to or inconsistent with
the provisions of the Act is hereby repealed, modified or amended accordingly.
This IRR repeals Memorandum Order No. 119 dated 18 September 2003, otherwise known
as the “Implementing Rules and Regulations Part A”: GPPB Resolution 03-2009 dated 22
July 2009, otherwise known as the Revised Implementing Rules and Regulations; and
relevant portions of E.O. 301, s. 1987 entitled “Decentralizing Actions on Government
Negotiated Contracts, Lease Contracts and Records Disposal.” Any other issuance, executive
order, administrative order, proclamation, charter, rule or regulation and/or parts thereof
contrary to or inconsistent with the provisions of this IRR is hereby repealed, modified or
amended accordingly.
115
The 2016 Revised Implementing Rules and Regulations
If any provision in this IRR, or application of such provision to any circumstance, is declared
invalid or unconstitutional, the other provisions not affected thereby shall remain valid and
subsisting.
77.1 In all procurement activities, if the advertisement or invitation for bids was issued
prior to the effectivity of the Act, the provisions of E.O. 40 and its IRR, P.D. 1594
and its IRR, R.A. 7160 and its IRR, or other applicable laws, as the case may be,
shall govern.
77.2 In cases where the advertisements or invitations for bids were issued before the
effectivity of this IRR, Procuring Entities may continue adopting the procurement
procedures, rules, and regulations provided in the Revised IRR of 2009 or other
applicable laws, as the case may be. (a)
This IRR shall take effect sixty (60) calendar days after its publication in the Official Gazette
or in a newspaper of general nationwide circulation and upon filing with the University of the
Philippines Law Center of three (3) certified copies of this IRR. (a)
116
The 2016 Revised Implementing Rules and Regulations – Annex “A”
ANNEX “A”
DETAILED ENGINEERING FOR THE PROCUREMENT OF INFRASTRUCTURE
PROJECTS
1. Detailed engineering shall proceed only on the basis of the feasibility or preliminary
engineering study made which establishes the technical viability of the project and
conformance to land use and zoning guidelines prescribed by existing laws. The
findings contained in the feasibility study, if undertaken for the project, shall be
examined. If, in the course of this exercise, it is found that changes would be
desirable in the design standards of principal features, as proposed, specific
recommendations for such changes shall be supported by detailed justifications,
including their effects on the cost, and (if necessary) the economic justification.
a) Survey
b) Site Investigation
3. Work under detailed engineering shall include, but not necessarily be limited to, the
following:
117
The 2016 Revised Implementing Rules and Regulations – Annex “A”
c) Contract Plans – The following plans shall be prepared for each construction
contract in accordance with guidelines and standards adopted by the procuring
entity concerned, incorporating at least the following:
vi) Other details which may be required by the head of the agency
f) Unit Prices – These shall be prepared for each contract using costs based on
reasonable approved current prices as projected over the proposed
construction period, divided into local and foreign exchange costs, as the case
may be.
g) Approved Budget for the Contract – the ABC to be bid shall be prepared by
official(s) duly designated by the Head of the Procuring Entity concerned or by
his duly authorized official. It shall be approved by the Head of the Procuring
Entity or his duly designated official.
Since the contracts are fixed price contracts, the ABC to be bid shall provide for
the projected movements of construction costs over the construction period
118
The 2016 Revised Implementing Rules and Regulations – Annex “A”
considering the projected inflation and foreign exchange rates as issued by the
Development Budget Coordination Committee (DBCC). It shall also show the
local and foreign currency requirements, as the case may be.
The ABC to be bid shall specify for each major work item, such as earthwork,
roadwork, and massive concreting, the components for equipment rentals,
fuel, labor, materials and overhead, including the cost of the approved
construction safety and health program and warranty premium.
k) Warranty Period – Likewise, the Bidding Documents shall specify the type of
project and the corresponding warranty period required by the procuring
entity.
119
The 2016 Revised Implementing Rules and Regulations – Annex “A”
life cycle costs of the projects without sacrificing the quality and integrity of the
structure, while maintaining its essential function, performance, and safety.
4. For projects to be implemented by phases, the Procuring Entity shall ensure that there
is a clear delineation of work for each phase, which must be usable, and structurally
sound. It shall also ensure the conduct of the detailed engineering activities for each
phase as provided for in Item 2 of this Guidelines. (n)
6. The above rules shall apply to the implementation of infrastructure projects under
normal or ordinary conditions. However, under emergency or extraordinary cases
involving major calamities and disasters as declared by the President where time is of
the essence to save lives and properties and restore damaged infrastructures, detailed
engineering works shall be conducted in accordance with the guidelines and
procedures, as prescribed by the head of the appropriate infrastructure agency and
approved by the Infrastructure Committee of the National Economic and Development
Authority Board, to enable quick response to said cases, while maintaining the safety
and integrity of the structure.
120
The 2016 Revised Implementing Rules and Regulations – Annex “B”
ANNEX “B”
GENERAL PRINCIPLES ON CONSULTING SERVICES
1. Definition
The services of consultants may be engaged by any procuring entity for government
projects or related activities of such magnitude and/or scope as would require a level
of expertise or attention beyond the optimum in-house capability of the procuring
entity concerned and consistent with the Government’s policy not to compete with the
private sector.
3. Independence of Consultants
4. Hiring of Consultants
4.1 Consultants shall be hired on the basis of their proven expertise, experience and
capability. Under certain conditions provided herein, cost may be included as a
factor in the selection of consultants. In order to manifest trust and confidence in
and promote the development of Filipino consultancy, Filipino consultants shall be
hired whenever the services required for the project are within the expertise and
capability of Filipino consultants: Provided, however, That in the event Filipino
consultants do not have the sufficient expertise and capability to render the services
required under the project, as determined by the Head of the Procuring Entity,
foreign consultants may be hired.
4.3 In the hiring of foreign consultants, all pertinent laws and regulations of the
Philippines shall be followed.
4.4 Technology and knowledge transfer to the procuring entity shall be required in the
provision of consulting services, where applicable.
5. Organization of Consultants 107
121
The 2016 Revised Implementing Rules and Regulations – Annex “B”
The services to be provided by consultants can be divided into six (6) broad
categories, namely: (a) advisory and review services; (b) pre-investment or feasibility
studies; (c) design; (d) construction supervision; (e) management and related
services; and (f) other technical services or special studies.
6.1. Advisory and Review Services. These services include advice on particular
projects or problems. These will include advice on and review of, among
others, planning, design and other professional services, as well as
management, production, inspection, testing and quality control. They also
include such services as appearances before commissions, boards or other
judicial bodies to give evidence or otherwise submit professional opinions.
6.2. Pre-Investment or Feasibility Studies. These are the studies which normally
precede decisions to go (or not to go) forward with specific projects. These
studies may have as their objectives:
6.3. Design. This type of services normally consists of three (3) phases:
122
The 2016 Revised Implementing Rules and Regulations – Annex “B”
a) Pre-Design Phase – establishes the general size and scope of the project
and its location on the site. The services include but are not limited to
reconnaissance, topographical and other engineering and land surveys,
soils investigations, preparation of preliminary architectural/engineering
designs, layouts, outline specifications, preliminary cost estimates and
specific recommendations prior to actual design;
6.5. Management and Related Services. These may include the following:
123
The 2016 Revised Implementing Rules and Regulations – Annex “B”
6.6. Other Technical Services or Special Studies. The Technical Services may
include the following:
The Special Studies may include the following and other studies not covered
under any of the services and studies described above:
a) Soils investigation;
e) Parcellary surveys;
124
The 2016 Revised Implementing Rules and Regulations – Annex “B”
n) Housing;
o) Interior design;
q) Landscaping;
125
The 2016 Revised Implementing Rules and Regulations – Annex “C”
ANNEX “C”
RECOMMENDED EARLIEST POSSIBLE TIME AND MAXIMUM PERIOD ALLOWED
FOR THE PROCUREMENT OF GOODS AND SERVICES
Maximum
Minimum Operational Operational
Calendar
Calendar Timeline Timeline
Procurement Days Conditions /
Section Days (Recommended (Maximum
Activity Allowed Remarks
Recommended Earliest Period
for
for Activity Possible Time) Allowed)
Activity
Optional for ABC of
Pre-Procurement Whenever
20 1 CD Day 0 0 ₱2,000,000.00 and
Conference necessary
below
Advertisement / Start of Availability
21.2.1 Posting of 7 CDs Days 1 to 7 7 CDs Day 1 to 7 of Bidding
Invitation to Bid Documents
• Optional for ABC
below
₱1,000,000.00
• Not Earlier than 7
CDs from
Whenever
22.2 Pre-Bid Conference 1 CD Day 8 Day 8 to 40 Advertisement /
necessary
Posting
• 12 CDs before
Deadline of
Submission and
Receipt of Bids
Deadline of
Last day of
Submission and
25.5 1 CD Day 20 45 CDs Day 52 Availability of
Receipt of Bids /
Bidding Documents
Bid Opening
32.4 Bid Evaluation 1 CD Day 21 7 CDs Day 53 to 59
The bidder must
submit all Post-
Qualification
Requirements
Post-Qualification Day 60 to
34.8 2 CDs 108 Day 22 to 23 45 CDs within 5 CDs from
104
receipt of notice as
bidder with LCB in
accordance with
Sec. 34.2.
Approval of
Resolution/Issuanc Day 105 to
37.1.2 1 CD Day 24 15 CDs
e of Notice of 119
Award
Contract
Day 120 to
37.2.1 Preparation and 1 CD Day 25 10 CDs
129
Signing
Approval of
20 or 30
37.3 contract by higher 1CD If necessary.
CDs
authority
Issuance of Notice Day 130 to
37.4.1 1 CD Day 26 7 CDs
to Proceed 136
TOTAL TIME Excluding Approval
26 CDs 136 CDs of Higher Authority,
if applicable.
108
One (1) Calendar day is allotted for the BAC to notify the Bidder that it has the Lowest Calculated Bid (LCB).
126
The 2016 Revised Implementing Rules and Regulations – Annex “C”
RECOMMENDED EARLIEST POSSIBLE TIME AND MAXIMUM PERIOD ALLOWED
FOR THE PROCUREMENT OF INFRASTRUCTURE PROJECTS
109
For Infrastructure Projects ₱50,000,000.00 and below.
110
For Infrastructure Projects above ₱50,000,000.00.
111
One (1) Calendar day is allotted for the BAC to notify the Bidder that it has the Lowest Calculated Bid (LCB).
127
The 2016 Revised Implementing Rules and Regulations – Annex “C”
RECOMMENDED EARLIEST POSSIBLE TIME AND MAXIMUM PERIOD ALLOWED
FOR THE PROCUREMENT OF CONSULTING SERVICES
112
One (1) Calendar day is allotted for the BAC to notify the Bidder that it has the Highest Rated Bid (HRB).
128
The 2016 Revised Implementing Rules and Regulations – Annex “D”
ANNEX “D”
CONTRACT IMPLEMENTATION GUIDELINES FOR THE PROCUREMENT OF GOODS,
SUPPLIES AND MATERIALS
1. Amendment to Order
1.1. Subject to the conditions set forth below, amendments to order may be issued at
any time by the procuring entity concerned. If any such order increases or
decreases the cost of, or the time required for executing any part of the work
under the original contract, an equitable adjustment in contract price and/or
delivery schedule shall be mutually agreed upon between the parties concerned,
and the contract modified in writing.
c) place of delivery.
1.3. An amendment to order may also be issued by the concerned procuring entity
where there are additional items needed and necessary for the protection of the
goods, which were not included in the original contract. Payments for these
additional items shall be based on the unit prices in the original contract for items
of goods similar to those in the original contract. If the contract does not contain
any rate applicable to the additional items, then suitable prices shall mutually be
agreed upon between the parties. Request for payment by the supplier for any
additional items shall be accompanied by a statement with the approved
supporting forms, giving a detailed accounting and record of amount for which it
claims payment. The contract time shall likewise be extended if the acquisition of
such additional items so warrants.
1.4. Under no circumstances shall a supplier proceed to commence work under any
amendment to order unless the same has been approved by the Head of the
Procuring Entity concerned or his duly authorized representative. As an exception
to the rule, the Regional Director/Head concerned may authorize the immediate
start of work under any amendment to order in the event of emergencies to
avoid detriment to public service, or damage to life and/or property or when time
is of the essence: Provided, however, That the same is valid only on items up to
the point where the cumulative increase in the contract cost which has not yet
been duly fully approved by the Head of the Procuring Entity concerned or his
duly authorized representative does not exceed five percent (5%) of the original
contract cost: Provided, further, That the corresponding amendment to order
shall immediately be prepared and submitted for approval to the Head of the
Procuring Entity concerned or his duly authorized representative. For an
amendment to order involving a cumulative amount exceeding five percent (5%)
of the original contract price, no work thereon shall be commenced unless the
129
The 2016 Revised Implementing Rules and Regulations – Annex “D”
same has been approved by the Head of Procuring Entity concerned or his duly
authorized representative: Provided, That, the said cumulative amount does not
exceed ten percent (10%) of the original contract price.
2. Suspension of Work
2.1 The procuring entity may suspend the work wholly or partly by written order for a
certain period of time, as it deems necessary due to force majeure or any fortuitous
events as defined in the contract. The supplier shall take all reasonable steps to
minimize the costs allocable to the work covered by such order during work
stoppage.
2.2 Before the suspension order expires, the procuring entity concerned shall either lift
such order or terminate the work covered by the same. If the suspension order is
lifted, or if the period of the order expires, the supplier shall have the right to resume
work. Appropriate adjustments shall be made in the delivery or contract schedule, or
contract price, or both, and the contract shall be modified accordingly.
3. Liquidated Damages
3.1 When the supplier fails to satisfactorily deliver goods under the contract within the
specified delivery schedule, inclusive of duly granted time extensions, if any, the
supplier shall be liable for damages for the delay and shall pay the procuring entity
liquidated damages, not by way of penalty, an amount equal to one-tenth (1/10) of
one percent (1%) of the cost of the delayed goods scheduled for delivery for every
day of delay until such goods are finally delivered and accepted by the procuring
entity concerned.The procuring entity need not prove that it has incurred actual
damages to be entitled to liquidated damages. Such amount shall be deducted from
any money due or which may become due to the supplier, or collected from any
securities or warranties posted by the supplier, whichever is convenient to the
procuring entity concerned. In case the total sum of liquidated damages reaches ten
percent (10%) of the total contract price, the procuring entity concerned may
rescind the contract and impose appropriate sanctions over and above the liquidated
damages to be paid. 113
4. Advance Payment
4.1 In accordance with Presidential Decree 1445, advance payment shall be made only
after prior approval of the President, and shall not exceed fifteen percent (15%) of
the contract amount, unless otherwise directed by the President; Provided, however,
that for cases mentioned under 4.3, 4.4, and 4.5 of these guidelines, no prior
approval by the President shall be necessary.All progress payments shall first be
charged against the advance payment until the latter has been fully exhausted,
unless otherwise approved by the President.
4.3 A single advance payment not to exceed fifty percent (50%) of the contract amount
shall be allowed for contracts entered into by a procuring entity for the following
services where requirement of down payment is a standard industry practice:
a) Hotel and restaurant services;
113
As amended by GPPB Resolution No. 02-2020, dated 27 February 2020, published in the Philippine Star on 22 April 2020.
130
The 2016 Revised Implementing Rules and Regulations – Annex “D”
4.4 Advance payment not to exceed fifteen percent (15%) of the contract amount,
unless otherwise directed by the President, shall also be allowed for procurement of
goods required to address contingencies arising from natural or man-made calamities
in areas where a “State of Calamity” has been declared by appropriate authorities.
The rules and regulations for the other aspects of contract implementation shall be
included in the manuals to be issued by the GPPB, such as, but not limited to, the
following:
a) Incidental Services;
b) Spare Parts;
c) Delays in the Supplier’s Performance;
d) Purchaser’s Responsibilities;
e) Prices;
f) Payment;
g) Taxes and Duties;
h) Subcontracts;
i) Standards;
j) Packing;
k) Insurance;
l) Transportation;
m) Inspections and Tests;
n) Patent Rights;
o) Limitations of Liability;
p) Termination for Default;
q) Termination for Insolvency;
r) Termination for Convenience; and
s) Assignment.
131
The 2016 Revised Implementing Rules and Regulations – Annex “E”
ANNEX “E”
CONTRACT IMPLEMENTATION GUIDELINES FOR THE PROCUREMENT OF
INFRASTRUCTURE PROJECTS
1.1. Variation Orders may be issued by the procuring entity to cover any
increase/decrease in quantities, including the introduction of new work items that
are not included in the original contract or reclassification of work items that are
either due to change of plans, design or alignment to suit actual field conditions
resulting in disparity between the preconstruction plans used for purposes of
bidding and the "as staked plans" or construction drawings prepared after a joint
survey by the contractor and the Government after award of the contract,
provided that the cumulative amount of the positive or additive Variation Order
does not exceed ten percent (10%) of the original contract price. The
addition/deletion of works under Variation Orders should be within the general
scope of the project as bid and awarded. The scope of works shall not be
reduced so as to accommodate a positive Variation Order. A Variation Order may
either be in the form of either a change order or extra work order.
1.2. A Change Order may be issued by the implementing official to cover any
increase/decrease in quantities of original work items in the contract.
1.3. An Extra Work Order may be issued by the implementing official to cover the
introduction of new work necessary for the completion, improvement or
protection of the project which was not included as items of work in the original
contract, such as, where there are subsurface or latent physical conditions at the
site differing materially from those indicated in the contract, or where there are
duly unknown physical conditions at the site of an unusual nature differing
materially from those ordinarily encountered and generally recognized as
inherent in the work or character provided for in the contract.
1.4. Any cumulative positive Variation Order beyond ten percent (10%) of the original
contract price shall be subject of another contract to be bid out if the works are
separable from the original contract. In exceptional cases where it is urgently
necessary to complete the original scope of work, the Head of the Procuring
Entity may authorize a positive variation order that will make the cumulative
value of the positive Variation Orders go beyond ten percent (10%) but not more
than twenty percent (20%) of the original contract price, subject to the
guidelines to be determined by the GPPB: Provided, however, That appropriate
sanctions shall be imposed on the designer, consultant or official responsible for
the original detailed engineering design which failed to consider the Variation
Order beyond ten percent (10%).
1.5. In claiming for any Variation Order, the contractor shall, within seven (7)
calendar days after such work has been commenced pursuant to Item 3.2
hereof; or, within twenty eight (28) calendar days after the circumstances or
reasons justifying a claim for extra cost shall have occurred, deliver a notice
giving full and detailed particulars of any extra cost in order that it may be
investigated at that time. Failure to provide either of such notices in the time
stipulated shall constitute a waiver by the contractor for any claim. The
preparation and submission of Variation Orders are as follows:
132
The 2016 Revised Implementing Rules and Regulations – Annex “E”
b) The Head of the Procuring Entity or his duly authorized representative upon
receipt of the proposed Change Order or Extra Work Order shall
immediately instruct the appropriate technical staff or office of the
procuring entity to conduct an on-the-spot investigation to verify the need
for the work to be prosecuted and to review the proposed plan, and prices
of the work involved.
c) The technical staff of appropriate office of the procuring entity shall submit
a report of their findings and recommendations, together with the
supporting documents, to the Head of the Procuring Entity or his duly
authorized representative for consideration.
e) The timeframe for the processing of Variation Orders from the preparation
up to the approval by the procuring entity concerned shall not exceed thirty
(30) calendar days.
2.1. For Variation Orders, the contractor shall be paid for additional work items whose
unit prices shall be derived based on the following:
133
The 2016 Revised Implementing Rules and Regulations – Annex “E”
then be combined with the mark-up factor (i.e., taxes and profit) used by
the contractor in his bid to determine the unit price of the new work item.
2.2. Request for payment by the contractor for any extra work shall be accompanied
by a statement, with the approved supporting forms, giving a detailed accounting
and record of amount for which he claims payment. Said request for payment
shall be included with the contractor's statement for progress payment.
3.1. Under no circumstances shall a contractor proceed to commence work under any
Change Order or Extra Work Order unless it has been approved by the Head of
the Procuring Entity or his duly authorized representative.
3.2. However, under any of the following conditions, the procuring entity’s
representative/Project Engineer may, subject to the availability of funds and
within the limits of his delegated authority, allow the immediate start of work
under any Change Order or Extra Work Order:
Provided, however, That such approval is valid on work done up to the point
where the cumulative increase in value of work on the project which has not yet
been duly fully approved does not exceed five percent (5%) of the adjusted
original contract price;
Provided, further, That immediately after the start of work, the corresponding
Change Order or Extra Work Order shall be prepared and submitted for approval
in accordance with the above rules herein set. Payments for works satisfactorily
accomplished on any Change Order or Extra Work Order may be made only after
approval of the same by the Head of the Procuring Entity or his duly authorized
representative.
Provided, finally, That for a Change Order or Extra Work Order involving a
cumulative amount exceeding five percent (5%) of the original contract price, no
work thereon may be commenced unless said Change Order or Extra Work Order
has been approved by the Head of the Procuring Entity or his duly authorized
representative.
4. ADVANCE PAYMENT
4.1. The procuring entity shall, upon a written request of the contractor which shall
be submitted as a contract document, make an advance payment to the
contractor in an amount not exceeding fifteen percent (15%) of the total contract
price, to be made in lump sum or, at the most, two installments according to a
schedule specified in the Instructions to Bidders and other relevant Tender
Documents.
134
The 2016 Revised Implementing Rules and Regulations – Annex “E”
4.2. The advance payment shall be made only upon the submission to and
acceptance by the procuring entity of an irrevocable standby letter of credit of
equivalent value from a commercial bank, a bank guarantee or a surety bond
callable upon demand, issued by a surety or insurance company duly licensed by
the Insurance Commission and confirmed by the procuring entity.
4.3. The advance payment shall be repaid by the contractor by deducting fifteen
percent (15%) from his periodic progress payments a percentage equal to the
percentage of the total contract price used for the advance payment.
4.4. The contractor may reduce his standby letter of credit or guarantee instrument
by the amounts refunded by the Monthly Certificates in the advance payment.
5. PROGRESS PAYMENT
5.1. Once a month, the contractor may submit a statement of work accomplished
(SWA) or progress billing and corresponding request for progress payment for
work accomplished. The SWA should show the amounts which the contractor
considers itself to be entitled to up to the end of the month, to cover (a) the
cumulative value of the works it executed to date, based on the items in the Bill
of Quantities, and (b) adjustments made for approved variation orders executed.
Alternatively, the Procuring Entity may require in the Bidding Documents that
statement of work accomplished or progress billing and the corresponding
request for progress payment may only be submitted upon actual completion of
the infrastructure project or a specific portion, segment, milestone or phase
thereof. 114(a)
5.2. The procuring entity’s representative/project engineer shall check the contractor’s
SWA and certify the amount to be paid to the contractor as progress payment.
Except as otherwise stipulated in the Instruction to Bidders, materials and
equipment delivered on the site but not completely put in place shall not be
included for payment. 115 (a)
5.3. The procuring entity shall deduct the following from the certified gross amounts
to be paid to the contractor as progress payment:
6. RETENTION MONEY
6.1. Progress payments are subject to retention of ten percent (10%) referred to as
the "retention money." Such retention shall be based on the total amount due to
the contractor prior to any deduction and shall be retained from every progress
payment until fifty percent (50%) of the value of works, as determined by the
114
As amended by GPPB Resolution No. 07-2018, dated 18 May 2018, published in the Official Gazette on 20 August 2018.
115
Ibid.
116
Ibid.
135
The 2016 Revised Implementing Rules and Regulations – Annex “E”
procuring entity, are completed. If, after fifty percent (50%) completion, the
work is satisfactorily done and on schedule, no additional retention shall be
made; otherwise, the ten percent (10%) retention shall be imposed.
6.2. The total "retention money" shall be due for release upon final acceptance of the
works. The contractor may, however, request the substitution of the retention
money for each progress billing with irrevocable standby letters of credit of from
a commercial bank, bank guarantees or surety bonds callable on demand, of
amounts equivalent to the retention money substituted for and acceptable to
Government, provided that the project is on schedule and is satisfactorily
undertaken. Otherwise, the ten percent (10%) retention shall be made. Said
irrevocable standby letters of credit, bank guarantees and/or surety bonds, to be
posted in favor of the Government shall be valid for a duration to be determined
by the concerned implementing office/agency or procuring entity and will answer
for the purpose for which the ten percent (10%) retention is intended, i.e., to
cover uncorrected discovered defects and third party liabilities.
7. CONTRACT COMPLETION
Once the project reaches an accomplishment of ninety-five (95%) of the total contract
amount, the procuring entity may create an inspectorate team to make preliminary
inspection and submit a punch-list to the contractor in preparation for the final
turnover of the project. Said punch-list will contain, among others, the remaining
works, work deficiencies for necessary corrections, and the specific duration/time to
fully complete the project considering the approved remaining contract time. This,
however, shall not preclude the procuring entity's claim for liquidated damages.
The Procuring Entity shall ensure the timely implementation of infrastructure projects
by monitoring the performance of the contractors. 118
When the contractor incurs negative slippage during the contract duration, the
Procuring Entity shall implement the calibrated measures provided under GPPB Circular
No. 03-2019 dated 8 March 2019, entitled “Guidance on Contract Termination due to
Fifteen Percent (15%) Negative Slippage by the Contractor in Infrastructure
Projects.” 119
9. LIQUIDATED DAMAGES
9.1. Once the contract duration expires, including any time extension duly granted,
and 120 the contractor refuses or fails to satisfactorily complete the work, the
Procuring Entity shall impose upon the contractor in default liquidated damages.
Liquidated damage is an amount equal 121 to at least one tenth (1/10) of one (1)
percent of the cost of the unperformed portion of the works for every day of
delay.
117
As amended by GPPB Resolution No. 02-2020, dated 27 February 2020, published in the Philippine Star on 22 April 2020.
118
Ibid.
119
Ibid.
120
Ibid.
121
Ibid.
136
The 2016 Revised Implementing Rules and Regulations – Annex “E”
9.2. In computing for liquidated damages, the Procuring Entity determines the
usability of the project. 122 A project or a portion thereof may be deemed usable
when it starts to provide the desired benefits as certified by the targeted end-
users and the concerned Procuring Entity.
9.3. To be entitled to such liquidated damages, the Procuring Entity does not have to
prove that it has incurred actual damages. Such amount shall be deducted from
any money due or which may become due the contractor under the contract or
collect such liquidated damages from the retention money or other securities
posted by the contractor, or a combination thereof, 123 whichever is convenient to
the Procuring Entity.
9.4. In case the total sum of liquidated damages reaches ten percent (10%) of the
total contract price, the Procuring Entity has the following options: 124
9.4.2. Allow the contractor to continue the works without prejudice to the
continued imposition of liquidated damages until the works have been
completed. This does not, however, preclude the Procuring Entity in
resorting to Termination of Contract under Annex I of the 2016
revised IRR of RA No. 9184. 126
10.1. The procuring entity shall have the authority to suspend the work wholly or partly
by written order for such period as may be deemed necessary, due to force
majeure or any fortuitous events or for failure on the part of the contractor to
correct bad conditions which are unsafe for workers or for the general public, to
carry out valid orders given by the procuring entity or to perform any provisions
of the contract, or due to adjustment of plans to suit field conditions as found
necessary during construction. The contractor shall immediately comply with
such order to suspend the work wholly or partly.
10.2. The contractor or its duly authorized representative shall have the right to
suspend work operation on any or all projects/activities along the critical path of
activities after fifteen (15) calendar days from date of receipt of written notice
from the contractor to the district engineer/regional director/consultant or
equivalent official, as the case may be, due to the following:
122
Ibid.
123
Ibid.
124
Ibid.
125
Ibid.
126
Ibid.
137
The 2016 Revised Implementing Rules and Regulations – Annex “E”
e. Delay in the payment of contractor's claim for progress billing beyond forty-
five (45) calendar days from the time the contractor's claim has been
certified to by the procuring entity’s authorized representative that the
documents are complete unless there are justifiable reasons thereof which
shall be communicated in writing to the contractor.
10.3. In case of total suspension, or suspension of activities along the critical path,
which is not due to any fault of the contractor, the elapsed time between the
effective order of suspending operation and the order to resume work shall be
allowed the contractor by adjusting the contract time accordingly.
11.1. Should the amount of additional work of any kind or other special circumstances
of any kind whatsoever occur such as to fairly entitle the contractor to an
extension of contract time, the procuring entity shall determine the amount of
such extension; provided that the procuring entity is not bound to take into
account any claim for an extension of time unless the contractor has, prior to
the expiration of the contract time and within thirty (30) calendar days after
such work has been commenced or after the circumstances leading to such
claim have arisen, delivered to the procuring entity notices in order that it could
have investigated them at that time. Failure to provide such notice shall
constitute a waiver by the contractor of any claim. Upon receipt of full and
detailed particulars, the procuring entity shall examine the facts and extent of
the delay and shall extend the contract time completing the contract work when,
in the procuring entity's opinion, the findings of facts justify an extension.
11.2. No extension of contract time shall be granted the contractor due to (a) ordinary
unfavorable weather conditions and (b) inexcusable failure or negligence of
contractor to provide the required equipment, supplies or materials.
11.3. Extension of contract time may be granted only when the affected activities fall
within the critical path of the PERT/CPM network.
11.4. No extension of contract time shall be granted when the reason given to support
the request for extension was already considered in the determination of the
original contract time during the conduct of detailed engineering and in the
preparation of the contract documents as agreed upon by the parties before
contract perfection.
138
The 2016 Revised Implementing Rules and Regulations – Annex “E”
12.1. To help ensure the quality of materials being used in infrastructure projects, the
Bureau of Research and Standards (BRS) of the DPWH, Department of Science
and Technology (DOST), or Department of Trade and Industry (DTI) shall
accredit, in accordance with industry guidelines, the testing laboratories whose
services are engaged or to be engaged in infrastructure projects. All
government infrastructure project owners must accept results of material test(s)
coming only from DOST/BRS accredited laboratories.
139
The 2016 Revised Implementing Rules and Regulations – Annex “E”
For project types which do not have specific CPES Guidelines, the Procuring
Entities concerned may formulate and adopt their own implementing Guidelines
specific to their needs provided the NEDA-INFRACOM poses no objections to
their adoption, and provided further that said Guidelines are made known to all
prospective bidders.
All Procuring Entities implementing CPES shall submit the results of their
performance evaluation to the CIAP on a monthly basis or as often as
necessary. The procuring entity’s CPES-IU shall likewise develop and maintain a
databank and disseminate the CPES reports to the concerned units/departments
within the procuring entity and to other interested users.
The CIAP shall consolidate all of the CPES evaluation results received and shall
disseminate the same to all Procuring Entities concerned. The CPES rating and
other information shall be used by the concerned government agencies for the
following purposes: (a) pre-qualification/eligibility screening of constructors; (b)
awarding of contracts; (c) project monitoring and control; (d) issuance of
Certificate of Completion; (e) policy formulation/review; (f) industry planning;
(g) granting of Incentives/Awards, and, in adopting measure to further improve
performance of contractors in the prosecution of government projects.
The rules and regulations for the other aspects of contract implementation shall be
included in the manuals to be issued by the GPPB, such as, but not limited to, the
following:
a) Sub-contracting;
b) Interference with Traffic and Adjoining Properties;
c) Clearance of Project Site of Obstruction;
d) Inspection and Testing;
e) Daywork;
f) Measurement of Works; and
g) Other Implementation Aspects.
140
The 2016 Revised Implementing Rules and Regulations – Annex “F”
ANNEX “F”
CONTRACT IMPLEMENTATION GUIDELINES FOR THE PROCUREMENT OF
CONSULTING SERVICES
The Government, as it considers fair and reasonable, may allow advance payment to
the Consultant in the amount which shall not exceed fifteen percent (15%) of the
contract amount to cover the cost of mobilization, subject to the posting of an
irrevocable standby letter of credit issued by an entity acceptable to the agency and of
an amount equal to the advance payment. The advance payment shall be repaid by
the Consultant by deducting from his progress payments such sum as agreed upon
during the contract negotiations until fully liquidated within the duration of the
contract.
All Consultancy contracts shall be fixed price contracts. Any extension of contract time
shall not involve any additional cost.
The rules and regulations for the other aspects of contract implementation shall be
included in the manuals to be issued by the GPPB.
141
The 2016 Revised Implementing Rules and Regulations – Annex “G”
ANNEX “G”
GUIDELINES FOR THE PROCUREMENT AND IMPLEMENTATION OF CONTRACTS
FOR DESIGN AND BUILD INFRASTRUCTURE PROJECTS
These guidelines shall govern the procurement and implementation of contracts for
design and build infrastructure projects and shall supplement applicable provisions of
Republic Act No. 9184 (RA 9184) and its Revised Implementing Rules and Regulations
(IRR) in particular Section 17.6 and Annex E.
2. PURPOSE
These guidelines are formulated to determine the conditions for the use of the design
and build scheme for infrastructure projects and the procedures for the
implementation thereof.
3. GUIDING PRINCIPLES
The procuring entity, prior to resorting to the design and build scheme, should
consider the following advantages and disadvantages of said scheme:
3.1. Advantages:
a) Since both design and construction are in the hands of the contractor, there
is a single point of responsibility for quality, cost, and schedule adherence,
including the risks related to design. This precludes buck-passing and
finger-pointing between the designer and the builder.
b) Because design and construction periods can overlap, the total design and
construction time, as well as the final project cost, will be significantly
reduced.
d) The procuring entity does not need to spend much time and money in
seeing to it that the work is done by the contractor exactly as indicated by
the design documents prepared by the designer, and in coordinating and
arbitrating between separate design and construction contracts.
3.2. Disadvantages:
a) Procuring Entities should, however, take into account that in utilizing the
design and build scheme for a particular project, contractors are given too
much discretion in determining the project cost and there is difficulty in
predicting its final cost until the actual commencement of construction.
142
The 2016 Revised Implementing Rules and Regulations – Annex “G”
4. DEFINITION OF TERMS
a. Approved Budget for the Contract (ABC). This shall be a lump sum amount
that shall cover the cost of design and construction works (at the option of the
procuring entity) based on the conceptual design and performance specifications
and in accordance with applicable provisions of the law or agency guidelines.
The ABC shall be calculated based on either the approximate quantities of work
of the conceptual design, from standardized designs or from cost records of
previous projects of similar kind.
b. Bidding Documents for Design and Build Scheme. These shall basically be
similar to the Bidding Documents for infrastructure projects and shall also
include the performance specifications and parameters to be followed by the
design and build contractors and the method for allocation of risks for the design
and build contract, among others.
c. Conceptual Design. This shall describe the general idea of the procuring entity
with regard to the completed facility and shall identify the scope or physical
components and structures, specific outputs and requirements of the structures
and proposed methods of construction, where necessary.
d. Design and Build Projects. This refers to infrastructure projects where the
procuring entity awards a single contract for the architectural/engineering design
and construction to a single firm, partnership, corporation, joint venture or
consortium.
143
The 2016 Revised Implementing Rules and Regulations – Annex “G”
location, and identify existing and future right-of-way limits and construction
easements associated with the procuring entity’s conceptual design.
5.1. The Design and Build scheme shall be applied under any of the following cases:
a. For flagship, priority and fast track projects that need to be completed on a
tight completion schedule, as included in the Medium-Term Public
Investment Program (MTPIP) for national projects and in the Regional
Development Investment Plan (RDIP) for regional and provincial projects;
5.2. All design and build projects shall be included in the Annual Procurement Plan
(APP) of the procuring entity concerned and shall be subject to prior approval
by the Head of the Procuring Entity or his/her duly authorized representative.
The procuring entity may create a Design and Build Committee (DBC) composed of
highly technical personnel experienced in the field of architecture, engineering and
construction in the particular type of project to be bid. The DBC shall assist the project
management office (PMO) in the preparation of the conceptual design and
performance specifications and parameters, review of detailed engineering design and
supervision of the project. It shall, likewise, assist the Bids and Awards Committee
(BAC) and the Technical Working Group (TWG) in the evaluation of technical proposals
in accordance with the criteria set in the Bidding Documents.
No bidding and award of design and build contracts shall be made unless the required
preliminary design and construction studies have been sufficiently carried out and duly
144
The 2016 Revised Implementing Rules and Regulations – Annex “G”
approved by the Head of the Procuring Entity that shall include, among others, the
following:
i. Project Description
v. Preliminary Investigations
ix. Minimum requirements for a Construction Safety and Health Program for the
project being considered
The above data are for reference only. The procuring entity does not guarantee that
these data are fully correct, up to date, and applicable to the project at hand. The
contractor is responsible for the accuracy and applicability of all data, including the
above, that it will use in its design and build proposal and services.
The acquisition of right-of-way and the conduct of eminent domain proceedings shall
still be the responsibility of the procuring entity, which shall include a preliminary
budget for this purpose.
8.1. Upon award of the design and build contract, the winning bidder shall be
responsible for the preparation and submission of all necessary detailed
engineering investigations, surveys and designs in accordance with the
provisions of Annex “A” of this IRR (with the exception of the Bidding
Documents and the ABC).
8.2. The procuring entity shall ensure that all the necessary schedules with regard
to the submission, confirmation and approval of the detailed engineering design
and the details of the construction methods and procedures shall be included in
the contract documents.
8.3. The procuring entity shall review, order rectification, and approve or disapprove
– for implementation only - the submitted plans within these schedules. All
instructions for rectification shall be in writing stating the reasons for such
rectification. The design and build contractor shall be solely responsible for the
145
The 2016 Revised Implementing Rules and Regulations – Annex “G”
9. ELIGIBILITY REQUIREMENTS
9.1. The eligibility requirements for Design and Build infrastructure projects shall
comply with the applicable provisions of Sections 23 to 24 of IRR.
9.2. A modified set of requirements integrating eligibility documents and criteria for
infrastructure projects and consulting services shall be adopted, as follows:
The prospective bidder shall submit all the required Class “A” and Class
“B” documents for infrastructure projects and the following:
146
The 2016 Revised Implementing Rules and Regulations – Annex “G”
10.1. In the submission of bids, the first envelope (Technical Proposal) shall contain
all the required documents for infrastructure projects under Section 25.2(b) of
the IRR of R.A 9184 and the following additional documents:
10.2. The second envelope (Financial Proposal) shall contain all the required
documents for infrastructure projects under Section 25.3 of the IRR of R.A
9184 and the following additional documents:
i. Lump sum bid prices, which shall include the detailed engineering cost,
in the prescribed Bid Form;
ii. Detailed estimates including a summary sheet indicating the unit prices
of construction materials, labor rates and equipment rentals used in
coming up with the bid; and
For the detailed evaluation of the design and build proposals a two-step procedure
shall be adopted by the BAC, which may be undertaken with the assistance of the
DBC.
147
The 2016 Revised Implementing Rules and Regulations – Annex “G”
i. The first step of the evaluation shall involve the review of the
preliminary conceptual designs and track record submitted by the
contractor as indicated in the Bidding Documents using a non-
discretionary “pass/fail” criteria that involve compliance with the
following requirements:
Only those bids that passed the above criteria shall be subjected to the
second step of evaluation.
The BAC shall open the financial proposal of each “passed” bidder and shall
evaluate it using non-discretionary criteria - including arithmetical corrections
for computational errors - as stated in the Bidding Documents, and thus
determine the correct total calculated bid prices. The BAC shall automatically
disqualify any total calculated bid price which exceeds the ABC. The total
calculated bid prices (not exceeding the ABC) shall be ranked, in ascending
order, from lowest to highest. The bid with the lowest total calculated bid
price shall be identified as the Lowest Calculated Bid (LCB).
12.1. The LCB shall be subject to post-qualification in accordance with Section 34,
Rule X of this IRR to determine its responsiveness to the eligibility and bid
requirements. If after post-qualification the Lowest Calculated Bid is
determined to be post-qualified it shall be considered the Lowest Calculated
and Responsive Bid (LCRB) and the contract shall be awarded to the bidder.
In case of post-disqualification of the LCB, the procedure under Section 34
shall also be followed.
148
The 2016 Revised Implementing Rules and Regulations – Annex “G”
12.2. The Head of the Procuring Entity shall approve or disapprove the
recommendations of the BAC within a period not exceeding fifteen (15)
calendar days from the determination and declaration by the BAC of the
LCRB.
12.3. The Head of the Procuring Entity concerned shall award the contract to the
said bidder pursuant to the provisions of Section 37, Rule XI of this IRR.
13.1. No works shall commence unless the contractor has submitted the required
documentary requirements and the procuring entity has given written
approval. Work execution shall be in accordance with reviewed and approved
documents.
13.2. The contractor shall be responsible for obtaining all necessary information as
to risks, contingencies and other circumstances which may affect the works
and shall prepare and submit all necessary documents specified by the
procuring entity to meet all regulatory approvals as specified in the contract
documents.
13.3. The Contractor shall submit a detailed program of work within fourteen (14)
calendar days after the issuance of the Notice to Proceed for approval by the
procuring entity that shall include, among others:
ii. Periods for review of specific outputs and any other submissions and
approvals;
vi. List of equipment required on site for each major stage of the work;
and
vii. Description of the quality control system to be utilized for the project.
149
The 2016 Revised Implementing Rules and Regulations – Annex “G”
ii. Provided that the contractor suffers delay and/or incurs costs due to
changes or errors in the procuring entity’s performance specifications
and parameters, he shall be entitled to either one of the following:
13.6. The contract documents shall include the manner and schedule of payment
specifying the estimated contract amount and installments in which the
contract price will be paid.
13.7. The contractor shall be entitled to advance payment subject to the provisions
of Section 4 of Annex “E”.
13.8. The procuring entity shall define the quality control procedures for the design
and construction in accordance with agency guidelines and shall issue the
proper certificates of acceptance for sections of the works or the whole of the
works as provided for in the contract documents.
13.9. The contractor shall provide all necessary equipment, personnel, instruments,
documents and others to carry out specified tests.
13.10. All design and build projects shall have a minimum Defects Liability Period of
one (1) year after contract completion or as provided for in the contract
documents. This is without prejudice, however, to the liabilities imposed upon
the engineer/architect who drew up the plans and specification for a building
sanctioned under Article 1723 of the New Civil Code of the Philippines.
13.11. The contractor shall be held liable for design and structural defects and/or
failure of the completed project within the warranty periods specified in
Section 62.2.3.2 of the IRR.
150
The 2016 Revised Implementing Rules and Regulations – Annex “G”
In the implementation of these guidelines, the GPPB may issue additional guidelines
or introduce modifications thereto through the amendment of its specific provisions
as the need arises, as well as, formulate, approve and disseminate standard Bidding
Documents, forms and evaluation documents, whenever necessary.
151
The 2016 Revised Implementing Rules and Regulations – Annex “H”
ANNEX “H”
CONSOLIDATED GUIDELINES FOR THE ALTERNATIVE METHODS OF
PROCUREMENT
I. POLICY STATEMENT
II. PURPOSE
III. SCOPE
This Guidelines shall apply to the national government, its branches, constitutional
offices, departments, bureaus, offices and agencies, including state universities and
colleges, government-owned and/or -controlled corporations, government financial
institutions, and local government units.
B. Limited Source Bidding under Section 49, Negotiated Procurement under Sections
53.8 (Defense Cooperation Agreement), 53.11 (NGO Participation), 53.12
(Community Participation), and 53.13 (UN Agencies).
152
The 2016 Revised Implementing Rules and Regulations – Annex “H”
the appropriate End-User or relevant office, as the case may be, shall justify and
recommend through a BAC Resolution such change in the mode of procurement
to be approved by the HOPE. The changes must be reflected in the APP and
submitted to the GPPB in accordance with Section 7.4 of the IRR of R.A. 9184.
For the following alternative methods, however, the BAC, through its Secretariat,
shall post the procurement opportunity [e.g., Request for Quotation (RFQ) or
Request for Proposal (RFP)] in the Philippine Government Electronic Procurement
System (PhilGEPS) website, the website of the Procuring Entity concerned, if
available, and at any conspicuous place reserved for this purpose in the premises
of the Procuring Entity for a period of at least three (3) calendar days:
127
Section 54.1, IRR of R.A. No. 9184.
128
Section 54.2, IRR of R.A. No. 9184.
153
The 2016 Revised Implementing Rules and Regulations – Annex “H”
3) Section 53.9 – Small Value Procurement, for projects with ABC above
Fifty Thousand Pesos (₱50,000.00);
3) Section 53.3 – Take Over of Contracts (Only for New Bidders, if any.);
129
As amended by GPPB Resolution No. 05-2020, dated 20 March 2020, published in the Philippine Daily Inquirer on 24 March
2020.
130
Section 54.6, IRR of R.A. No. 9184.
131
Section 18, R.A. No. 9184 and its IRR.
154
The 2016 Revised Implementing Rules and Regulations – Annex “H”
For Shopping under Section 52.1(a) due to the urgent nature of the attendant
circumstances, the BAC and the HOPE through a Resolution and issuance for the
purpose, 132 respectively, may delegate to specific officials, personnel, committee
or office in the Procuring Entity the conduct of Shopping and award of contract to
efficiently and expeditiously deal with the emergency sought to be addressed. (a)
For Negotiated Procurement under Section 53.14, the BAC and the HOPE through
a Resolution and issuance for the purpose, respectively, shall delegate to specific
officials, personnel, committee or office in the Procuring Entity the conduct of
Direct Retail Purchase to efficiently and expeditiously deal with the pressing need
sought to be addressed. (n)
For Negotiated Procurement under Emergency Cases under Section 53.2, the
HoPE, through an issuance for the purpose, may delegate to either the BAC or the
End-user unit or any other appropriate bureau, committee, support or procuring
unit the authority to directly negotiate with a legally, technically, and financially
capable supplier, contractor, or consultant. 133
The HoPE may also delegate the awarding of contract under Negotiated
Procurement (Emergency Cases) under Section 53.2 to any official of the
procuring entity except to the BAC Chairperson or members pursuant to Section
11.2.5 of the 2016 revised IRR of RA No. 9184 and other associated issuances or
to any other official where there exists conflict of interest, such as those to whom
the HoPE has delegated the authority to directly negotiate under the foregoing
modality. 134
For record and monitoring purposes, all awards shall be immediately reported
with all supporting documents to the HOPE, through the BAC, to ensure
compliance with all the conditions and requirements provided for under R.A. 9184,
its IRR and related guidelines.
K. Mandatory Review. The BAC shall conduct a mandatory review and evaluation
of the terms, conditions, specifications, cost estimates in the RFQ or RFP, if none
or less than the required number of quotations or proposals are received, despite
the extension of deadline for the third time.
132
As amended by GPPB Resolution No. 24-2019, dated 30 October 2019, published in the Official Gazette on 30 December
2019.
133
As amended by GPPB Resolution No. 03-2020, dated 9 March 2020, published in the Philippine Daily Inquirer on 13 March
2020.
134
Ibid.
155
The 2016 Revised Implementing Rules and Regulations – Annex “H”
Based on its findings, the BAC may revise the terms and conditions and
specifications, and if necessary, adjust the ABC, subject to the required approvals,
and repeat the procurement process.
a. The BAC shall recommend to the HOPE the award of contract. Within a
period not exceeding fifteen (15) calendar days from receipt, the HOPE
shall approve or disapprove the BAC’s recommendation. In case of
approval, the HOPE shall immediately issue the NOA to the Supplier,
Contractor or Consultant. In the event the HOPE shall disapprove the
recommendation, such disapproval shall be based only on valid,
reasonable, and justifiable grounds to be expressed in writing, addressed
to the BAC.
c. The HOPE or his duly authorized representative shall issue the NTP, if
necessary, and a copy of the approved contract to the Supplier,
Contractor or Consultant within three (3) calendar days from the date of
approval of the contract by the appropriate government approving
authority.
135
Section 54.3, IRR of R.A. No. 9184.
136
Sections 54.4 and 54.5, IRR of R.A. No. 9184.
156
The 2016 Revised Implementing Rules and Regulations – Annex “H”
V. SPECIFIC GUIDELINES
137
Section 50, R.A. No. 9184 and its IRR.
157
The 2016 Revised Implementing Rules and Regulations – Annex “H”
To justify the need to procure through the Direct Contracting method, the End-
User should conduct a survey of the industry and determine the supply source. In
all cases where Direct Contracting is contemplated, the survey must be
conducted prior to the commencement of the procurement process. Moreover,
the End-User must justify the necessity for an item that may only be procured
through Direct Contracting, and it must be able to prove that there is no suitable
substitute in the market that can be obtained at more advantageous terms.
2. Procedure
a) The BAC shall prepare the RFQ or pro-forma invoice together with the
terms and conditions of sale, and shall send the same to the identified
direct supplier.
c) The BAC shall recommend to the HOPE the award of contract in favor of
the supplier. Award of contract shall be made in accordance with Section
IV(L) of this Guidelines.
158
The 2016 Revised Implementing Rules and Regulations – Annex “H”
b) Unit prices must be the same as or lower than those in the original
contract, provided that such prices are still the most advantageous to the
government after price verification;
d) Except in cases duly approved by the GPPB, repeat orders shall be availed
of only within six (6) months from the date of the NTP arising from the
original contract, provided that there has been a partial delivery, inspection
and acceptance of the goods within the same period;
e) Repeat orders shall not exceed twenty-five percent (25%) of the quantity of
each item in the original contract. In order not to exceed the 25%
threshold, the goods under the original contract must be:
i. Quantifiable;
ii. Divisible; and
iii. Consisting of at least four (4) units per item.
2. Procedure
b) When all the conditions are present, the BAC shall recommend to the HOPE
the award of contract through Repeat Order. Award of contract shall be
made in accordance with Section IV(L) of this Guidelines.
C. SHOPP I N G 139
159
The 2016 Revised Implementing Rules and Regulations – Annex “H”
2. Procedure
160
The 2016 Revised Implementing Rules and Regulations – Annex “H”
ii. The BAC shall immediately prepare the RFQ, indicating the
specifications, quantity, ABC, and other terms and conditions of the
contract.
iii. The RFQ may be sent directly to the supplier of known technical,
legal and financial qualifications. Due to the attendant circumstances
and the urgency of the procurement, the supplier shall immediately
respond to the RFQ and signify its technical, legal and financial
capability to supply and deliver the goods to be procured. Posting of
the RFQ may be dispensed with.
iv. The BAC shall immediately validate the technical, legal and financial
capability of the supplier to supply and deliver the goods by
requiring the submission of relevant documents or through other
verifiable means to prove the capability of the Supplier.
ii. The BAC shall prepare the RFQ, indicating the specifications,
quantity, ABC, and other terms and conditions of the contract.
iii. Except for those with ABCs equal to Fifty Thousand Pesos (₱
50,000.00) and below, RFQs shall be posted for a period of at least
three (3) calendar days in the PhilGEPS website, website of the
Procuring Entity, if available, and at any conspicuous place reserved
for this purpose in the premises of the Procuring Entity.
iv. The BAC shall send the RFQs to at least three (3) suppliers of known
qualifications, and at least three (3) price quotations must be
obtained. This, notwithstanding, those who responded through any
of the required postings shall be allowed to participate.
161
The 2016 Revised Implementing Rules and Regulations – Annex “H”
vi. Upon receipt of at least three (3) quotations within the prescribed
deadline, the BAC shall prepare an Abstract of Quotations setting
forth the names of those who responded to the RFQ, their
corresponding price quotations, and the lowest calculated quotation
submitted.
vii. The BAC shall validate the technical, legal and financial capability of
the supplier to supply and deliver the goods.
iii. All bids fail to comply with all the bid requirements or fail post-
qualification, or, in the case of consulting services, there is no
successful negotiation; or
iv.
The bidder with the Lowest/Single Calculated Responsive Bid or
Highest/Single Rated Responsive Bid refuses, without justifiable
cause, to accept the award of contract, and no award is made in
accordance with Section 40 of RA 9184 and its IRR.
b) Procedures
140
Section 53, R.A. No. 9184 and its IRR.
141
Section 53.1, IRR of R.A. No. 9184.
162
The 2016 Revised Implementing Rules and Regulations – Annex “H”
ii. The BAC shall invite at least three (3) suppliers, contractors or
consultants, including those disqualified in previous biddings for the
project, for negotiations to ensure effective competition. This,
notwithstanding, those who responded through any of the required
postings shall be allowed to participate. Even if only one (1) bidder
should respond to such invitation or posting, the BAC shall proceed
with the negotiation subject to the rules prescribed hereunder.
iv. Following completion of the negotiations, the BAC shall request all
suppliers, contractors, or consultants in the proceedings to submit,
on a specified date, a best offer based on the final technical and
financial requirements. Pursuant to Section IV(G) of this Guidelines,
the Procuring Entity shall require the submission of a Certificate of
PhilGEPS Registration in accordance with Section 8.5.2 of the IRR of
RA 9184.
142
Section 53.2, IRR of R.A. No. 9184.
163
The 2016 Revised Implementing Rules and Regulations – Annex “H”
The BAC or the End-user unit or any other appropriate bureau, committee,
support or procuring unit shall recommend to the HoPE any revision of the
Annual Procurement Plan (APP) to cover the Procurement Project that will be
resorting to Negotiated Procurement (Emergency Cases) under Section 53.2
of the 2016 revised IRR subject to the validation by the appropriate office in
the Procuring Entity that there are funds in the budget to cover for the
same. 144
The proposed APP revision(s) may only be approved by the HoPE upon its
confirmation of the existence and veracity of the ground(s) relied upon in
resorting to Negotiated Procurement (Emergency Cases) under Section 53.2
of the 2016 revised IRR. 145
b) Procedure
143
As amended by GPPB Resolution No. 03-2020, dated 9 March 2020, published in the Philippine Daily Inquirer on 13 March
2020.
144
Ibid.
145
Ibid.
146
Section 16, R.A. No. 10121.
147
As amended by GPPB Resolution No. 03-2020, dated 9 March 2020, published in the Philippine Daily Inquirer on 13 March
2020.
164
The 2016 Revised Implementing Rules and Regulations – Annex “H”
ii. The BAC or the End-user unit or any other appropriate bureau,
committee, support or procuring unit shall recommend to the HoPE
any revision of the Annual Procurement Plan (APP) to cover the
Procurement Project that will be subject to Negotiated Procurement
(Emergency Cases) under Section 53.2 of the 2016 revised IRR
subject to the validation by the appropriate office in the Procuring
Entity that there are funds in the budget to cover for the same. 148
iii. The HoPE may delegate to either the BAC or the End-user unit or
any other appropriate bureau, committee, support or procuring unit
the authority to directly negotiate with a legally, technically, and
financially capable supplier, contractor, or consultant for
procurement undertaken through any of the allowable instances of
Negotiated Procurement (Emergency Cases) under Section 53.2 of
the 2016 revised IRR. 149
b) Procedure
i. The BAC shall post-qualify and negotiate with the second lowest
calculated/highest rated bidder for the project under consideration
at the said bidder’s own original bid price, applicable to the
remaining works to be done. Authority to negotiate contracts for
148
Ibid.
149
Ibid.
150
Ibid.
151
Section 53.3, IRR of R.A. No. 9184.
165
The 2016 Revised Implementing Rules and Regulations – Annex “H”
ii. If negotiation fails, then the BAC shall post-qualify and negotiate
with the next lowest calculated/highest rated bidder at the said
bidder’s own original bid price.
iii. If the negotiation fails another time, the process is repeated until all
the bidders from the previous bidding have been considered.
iv. If the negotiation fails and there is no bidder left from the previous
bidding or if the original awardee is a Single Calculated Responsive
Bidder/Single Rated Responsive Bidder, the BAC may either invite at
least three (3) suppliers/contractors/consultants to submit their bids,
or resort to any other appropriate alternative method of
procurement.
iv. In determining the SLCC, NFCC and PCAB license, the sum of the
value of the remaining works for the existing contract and the ABC
of the contiguous or adjacent work shall be considered;
vi. The ABC of the contiguous or adjacent work involved does not
exceed the contract amount of the ongoing project;
152
Section 53.4, IRR of R.A. No. 9184.
166
The 2016 Revised Implementing Rules and Regulations – Annex “H”
viii. Negotiations for the procurement are commenced before the expiry
of the original contract.
If there is a necessity to introduce new items which are related to the scope
of work of the original contract, the Procuring Entity shall ensure that the unit
prices of the new items are equal to or lower than the prevailing market
prices.
b) Procedure
i. The BAC shall negotiate with the contractor or consultant for the
ongoing infrastructure project or consulting services (e.g., scope of
work or terms of reference, unit price and other terms and
conditions of the contract).
153
Section 53.5, IRR of R.A. No. 9184.
154
Refer to Appendix 20 for the Guidelines on the Procurement of Printing Services.
167
The 2016 Revised Implementing Rules and Regulations – Annex “H”
ii. Servicing Agency has the mandate to deliver the goods and services
required to be procured or to undertake the infrastructure project or
consultancy required by the Procuring Agency;
iv. Servicing Agency owns or has access to the necessary tools and
equipment required for the project;
c) Procedure
i. The End-User unit shall justify to the BAC that the resort to Agency-
to-Agency is more efficient and economical to the government.
ii. It shall likewise secure a certificate from the relevant officer of the
Servicing Agency that the latter complies with all the foregoing
conditions.
168
The 2016 Revised Implementing Rules and Regulations – Annex “H”
To justify the need to procure through this negotiated modality, the End-User
shall conduct a market study and determine the probable sources. This study
should confirm that the supplier, contractor or consultant could undertake the
project at more advantageous terms. In all cases, the market study must be
conducted prior to the commencement of the procurement process.
b) Procedure
ii. Upon successful negotiation, the BAC shall recommend the award of
contract to the HOPE in accordance with Section (IV)(L) of this
Guidelines.
169
The 2016 Revised Implementing Rules and Regulations – Annex “H”
ii. The term of the individual consultant shall, at the most, be on a six
(6) month basis, renewable at the option of the appointing HOPE,
but in no case shall exceed the term of the latter.
b) Procedure
i. The End-User Unit shall justify to the BAC the engagement of the
individual in accordance with the conditions set forth in this Section.
ii. The BAC shall undertake the negotiation with the individual
consultant based on the Terms of Reference prepared by the End-
User. Considering the nature of the consultancy work, the
negotiations need not be elaborate, it is enough that the BAC has
validated that the individual is legally, technically and financially
capable to undertake and fulfill the consultancy work based on the
Terms of Reference.
iii. The BAC shall recommend to the HOPE the award of contract to the
individual consultant. Award of contract shall be made in accordance
with Section (IV)(L) of this Guidelines.
157
Section 53.9, IRR of R.A. No. 9184.
170
The 2016 Revised Implementing Rules and Regulations – Annex “H”
b) Procedure
i. The End-User shall submit a request for SVP to the BAC, which
indicates the technical specifications, scope of work, terms of
reference, ABC and other terms and conditions.
ii. The BAC shall prepare and send the RFQs/RFPs to at least three (3)
suppliers, contractors or consultants of known qualifications. This,
notwithstanding, those who responded through any of the required
postings shall be allowed to participate. Receipt of at least one (1)
quotation is sufficient to proceed with the evaluation thereof.
iii. Except for those with ABCs equal to Fifty Thousand Pesos (₱
50,000.00) and below, RFQs shall be posted for a period of three (3)
calendar days in the PhilGEPS website, website of the Procuring
Entity, if available, and at any conspicuous place reserved for this
purpose in the premises of the Procuring Entity.
vi. The BAC shall recommend to the HOPE the award of contract in
favor of the supplier or contractor with the Single or Lowest
Calculated and Responsive Quotation (for goods or infrastructure
projects), or consultant with the Single or Highest Rated and
Responsive Proposal (for consulting services). In case of approval,
the HOPE shall immediately enter into contract with the said
supplier, contractor or consultant.
158
Section 53.10, IRR of R.A. No. 9184.
171
The 2016 Revised Implementing Rules and Regulations – Annex “H”
b) Policy Considerations
ii. Location
The ABC shall be set using the midpoint of the range obtained from
the results of the market analysis on the prevailing lease rates for
real property or venue within the vicinity of the selected location
complying with the criteria and technical specifications of the End-
User Unit. In no case shall the rental rates, including additional
172
The 2016 Revised Implementing Rules and Regulations – Annex “H”
Rental rates should also be within the prevailing market rates for
lease of real property or venue with the same or similar condition or
classification and located within the vicinity. Rental rate refers to
the amount paid by the Lessee for the use and/or occupancy of the
privately-owned real property to the Lessor, where payment is
usually made on a monthly basis.
i. Real Property
b) The real property being offered by the Lessor with the Single or
Lowest Calculated Quotation shall be rated in accordance with
the technical specifications and the reasonableness of its price
quotation shall be determined in accordance with the
methodology prescribed in Appendix B.
159
As amended by GPPB Resolution No. 09-2020, dated 7 May 2020, published in the Philippine Daily Inquirer on 15 May 2020.
160
Ibid.
173
The 2016 Revised Implementing Rules and Regulations – Annex “H”
ii. Venue
a) The BAC shall send the RFQ to at least three (3) venues within
the vicinity of the selected location. Receipt of at least one (1)
quotation is sufficient to proceed with the evaluation thereof.
161
As amended by GPPB Resolution No. 06-2018, dated 18 May 2018, published in the Official Gazette on 20 August 2019.
174
The 2016 Revised Implementing Rules and Regulations – Annex “H”
10. DI R ECT R ETAI L PUR CHASE OF P ETR OLEUM FUEL, OI L AND LUBR I CAN T
(POL) PR ODUCTS AN D AI R LI NE TI CK ETS 162
b. Definition. Where Goods and Services are required by a Procuring Entity for
the efficient discharge of its principal mandate, governmental functions, or
day-to-day operations, direct retail purchase of POL products and airline
tickets may be made by end-users delegated to procure the same from
identified direct suppliers or service providers. (n) 165
162
As amended by GPPB Resolution No. 24-2019, dated 30 October 2019, published in the Official Gazette on 30 December
2019.
163
Ibid.
164
Ibid.
165
Ibid.
166
Ibid.
167
Ibid.
168
Ibid.
169
Ibid.
170
As amended by GPPB Resolution No. 24-2019, dated 30 October 2019, published in the Official Gazette on 30 December
2019.
175
The 2016 Revised Implementing Rules and Regulations – Annex “H”
d. Procedure.
ii. Taking into account the usual trade and business practices being
observed in the industry and the requirements and other reasonable
considerations identified by the end-user, direct retail purchase of
the required POL products or airline tickets shall be carried out in
accordance with pertinent accounting principles and practices as
well as of sound management and fiscal administration provided
that they do not contravene existing laws and regulations applicable
to financial transactions.(n) 171
171
Ibid.
172
GPPB Resolution 09-2009, dated 23 November 2009.
173
GPPB Resolution 18-2007, dated 31 May 2007.
174
GPPB Resolution 08-2009, dated 3 November 2009.
176
The 2016 Revised Implementing Rules and Regulations – Annex “H”
Any other guidelines, administrative order, office order, rule or regulation and/or parts
thereof contrary to or inconsistent with the provisions of the Consolidated Guidelines are
hereby repealed, modified or amended accordingly.
This Consolidated Guidelines for Alternative Methods of Procurement shall take effect sixty
(60) calendar days after its publication in the Official Gazette or in a newspaper of general
nationwide circulation and upon filing with the University of the Philippines Law Center of
three (3) copies of this Annex “H”.
177
The 2016 Revised Implementing Rules and Regulations – Annex “H”
ANNEX “H”
APPENDIX A
DOCUMENTARY REQUIREMENT
ALTERNATIVE METHODS OF PROCUREMENT
I. This Appendix prescribes for the documents that the BAC shall require from suppliers,
contractors and consultants for Alternative Methods of Procurement, except for Repeat
Order, Shopping under Section 52.1(a), and Negotiated Procurement under Sections
53.1 (Two-Failed Biddings), and 53.5 (Agency-to-Agency) of the IRR of RA 9184.
II. The BAC shall indicate in the RFQ or RFP at what stage of the procurement process
these requirements must be submitted, i.e., submission of offer/s, evaluation of
offer/s, or 175 before issuance of Notice of Award. (a)
Professional
License Income/
Mayor’s/ PhilGEPS PCAB Omnibus
Alternative /Curriculum NFCC Business
Business Reg. License Sworn
Modality Vitae (Infra.) Tax
Permit Number (Infra.) Statement
(Consulting Return
Services)
I. Direct
For ABCs
Contracting
above
[Section 50]
P500K
II. Shopping
[Sec 52.1(b)]
III.
Negotiated
Procurement
A.
Emergency For
For ABCs For ABCs
Cases ABCs
above above
[(Section above
P500K P500K 176
53.2)] P500K
B. Take-Over
of Contracts
(Section
53.3.2; for
new bidders)
C. Adjacent/
Contiguous
(Section
53.4)
D. Scientific,
Scholarly or
Artistic
Work, For ABCs
Exclusive above
Technology P500K
and Media
Services
175
As amended by GPPB Resolution No. 36-2017, dated 7 November 2017, published in the Philippine Daily Inquirer on 24 April
2018.
176
As amended by GPPB Resolution No. 21-2017, dated 30 May 2017, published in the Philippine Daily Inquirer on 20
November 2017.
178
The 2016 Revised Implementing Rules and Regulations – Annex “H”
Professional
License Income/
Mayor’s/ PhilGEPS PCAB Omnibus
Alternative /Curriculum NFCC Business
Business Reg. License Sworn
Modality Vitae (Infra.) Tax
Permit Number (Infra.) Statement
(Consulting Return
Services)
(Section
53.6)
E. Highly
Technical
Consultant
(Section
53.7)
F. Small
Value
For ABCs For ABCs
Procurement
above above
(Section
P500K P50K
53.9)
G. Lease of
Real
Except Except Except
Property or
for gov’t for gov’t for gov’t
Venue
agencies agencies agencies
(Section
as lessors as lessors as lessors
53.10)
*For individuals engaged under Sec. 53.6, 53.7 and 53.9 of the IRR of RA No. 9184, only the BIR
Certificate of Registration shall be submitted in lieu of DTI Registration and Mayor’s Permit.
** Requirements under Section 53.6 of the IRR of RA No. 9184 will not apply to artists such as singer,
performer, poet, writer, painter and sculptor who are not engaged in business. (n)
*** For methods of procurement requiring Mayor’s Permit and PhilGEPS Registration Number,
Certificate of Platinum Membership may be submitted in lieu of the said documents. (n)
III. Procuring Entities already maintaining an updated file of any of the bidder’s above-
mentioned requirements, whether through the PhilGEPS Certificate of Registration
and Membership or its own records, may no longer require its re-submission.
179
The 2016 Revised Implementing Rules and Regulations – Annex “H”
ANNEX “H”
APPENDIX B
DOCUMENTARY REQUIREMENT
ALTERNATIVE METHODS OF PROCUREMENT
WEIGHT
RATING FACTORS RATING
(%)
180
The 2016 Revised Implementing Rules and Regulations – Annex “H”
WEIGHT
RATING FACTORS RATING
(%)
e. Firefighting equipment (6)
4. Other requirements
a. Maintenance (5)
b. Attractiveness (5)
100
1. The reasonableness of rental rates may be determined using any of the following
methods.
This method uses the following formula and a depreciation rate determined
after meticulous ocular inspection of the actual condition of the real property:
181
The 2016 Revised Implementing Rules and Regulations – Annex “H”
1.1.2. Reproduction Cost refers to the estimated total cost of replacing the
real property with the same utility.
1.1.3. Capitalization Rate refers to the interest rate on the cost or value of
the property.
1.1.4. Rentable Area refers to the total area of the real property in square
meters being occupied or to be occupied by the Lessee less the
common area like lobby, stairway, elevator hall, common comfort
room, machine room for air conditioner, and other areas of common
use by the public or upper floor occupants.
1.1.5. Factor Value refers to the rating factor where locations and site
conditions, neighborhood data and real property structural condition,
functionality, facilities and other requirements, including free services
and facilities offered by the Lessor are considered. The rating factors
and its corresponding weights are provided in Table A of this
Appendix.
182
The 2016 Revised Implementing Rules and Regulations – Annex “H”
2. If the price quotation of the prospective Lessor does not exceed the computed
monthly rental or is within the prevailing market rates, the rental rate offered may be
regarded as reasonable, and its quotation may then be considered for award.
183
The 2016 Revised Implementing Rules and Regulations – Annex “H”
184
The 2016 Revised Implementing Rules and Regulations – Annex “H”
I. Availability X (.5) =
II. Location and Site Condition X (.1) =
III. Neighborhood Data X (.05) =
185
The 2016 Revised Implementing Rules and Regulations – Annex “H”
Note: Weight of each rating factor may be changed as long as total weight per classification is
equivalent to 100. Figures in parenthesis are samples. Procuring Entity must determine
passing rate before inviting bids from Lessors. A bid is determined to be responsive if it is
equal to or higher than the passing rate.
186
The 2016 Revised Implementing Rules and Regulations – Annex “I”
ANNEX “I”
GUIDELINES ON TERMINATION OF CONTRACTS
5. Head of the Procuring Entity refers to: (i) the head of the agency or his duly
authorized official, for national government agencies; (ii) the governing board or
its duly authorized official, for government-owned and/or controlled corporations;
or (iii) the local chief executive, for local government units. Provided, that in a
department, office or agency where the procurement is decentralized, the Head
of each decentralized unit shall be considered as the Head of the Procuring Entity
subject to the limitations and authority delegated by the head of the department,
office or agency.
7. Termination in Part means the termination of a part but not all, of the work
that has not been completed and accepted under a contract.
8. Termination in Whole means the termination of all of the work that has not
been completed and accepted under a contract.
187
The 2016 Revised Implementing Rules and Regulations – Annex “I”
9. Show Cause refers to a notice which the Procuring Entity is required to issue
prior to terminating a contract. The purpose of a show cause notice is to enable
the contractor to present its position why the contract should not be terminated.
10. Verified Report refers to the report submitted by the Implementing Unit to the
Head of the Procuring Entity setting forth its findings as to the existence of
grounds or causes for termination and explicitly stating its recommendation for
the issuance of a Notice to Terminate.
The following are ground for termination of contract for default:(a) 177
a) Pursuant to Sec. 68 of the 2016 revised IRR, the Procuring Entity may
terminate the contract when outside of force majeure, the Supplier fails
to deliver or perform any or all of the Goods within the period(s)
specified in the contract, or within any extension thereof granted by the
Procuring Entity pursuant to a request made by the Supplier prior to the
delay, and such failure amounts to at least ten percent (10%) of the
contract price;(a) 178
b) Pursuant to Sec. 68 of the 2016 revised IRR, the Procuring Entity may
terminate the contract when, as a result of force majeure, the Supplier
is unable to deliver or perform any or all of the Goods, amounting to at
least ten percent (10%) of the contract price, for a period of not less
than sixty (60) calendar days after receipt of the notice from the
Procuring Entity stating that the circumstance of force majeure is
deemed to have ceased; or(a) 179
c) The Procuring Entity shall terminate the contract when the Supplier fails
to perform any other obligation under the Contract. 180 (a)
The Procuring Entity shall terminate a contract for default when any of the
following conditions attend its implementation:
a) Due to the Contractor’s fault and while the project is on-going, it has
incurred negative slippage of fifteen percent (15%) or more in
accordance with Presidential Decree 1870;
177
As amended by GPPB Resolution No. 07-2019, dated 8 March 2019, published in the Philippine Daily Inquirer on 4 May
2019.
178
Ibid.
179
Ibid.
180
Ibid.
188
The 2016 Revised Implementing Rules and Regulations – Annex “I”
b) Due to the Contractor’s fault and after the contract time has expired, it
has incurred a negative slippage of ten percent (10%) or more in the
completion of the work; or
c) The Contractor:
ii. does not actually have on the project site the minimum essential
equipment listed on the Bid necessary to prosecute the Works in
accordance with the approved work plan and equipment
deployment schedule as required for the project;
iii. does not execute the Works in accordance with the contract or
persistently or flagrantly neglects to carry out its obligations under
the contract;
The Procuring Entity shall terminate a contract for default when any of the
following conditions attend its implementation:
c) The Consultant fails to perform any other obligation under the contract.
The Procuring Entity may terminate the Contract, in whole or in part, at any time
for its convenience. The Head of the Procuring Entity may terminate a contract
for the convenience of the Government if he has determined the existence of
conditions that make Project Implementation economically, financially or
technically impractical and/or unnecessary, such as, but not limited to, fortuitous
event(s) or changes in law and national government policies.
189
The 2016 Revised Implementing Rules and Regulations – Annex “I”
The Procuring Entity may terminate the contract in case it is determined prima
facie that the Supplier/Contractor/Consultant has engaged, before or during the
implementation of the contract, in unlawful deeds and behaviors relative to
contract acquisition and implementation. Unlawful acts include, but are not
limited to, the following:
E. Termination by Contractor/Consultant
The Contractor may terminate its contract with the Procuring Entity if the
works are completely stopped for a continuous period of at least sixty (60)
calendar days through no fault of its own, due to any of the following
reasons:
b) The prosecution of the work is disrupted by the adverse peace and order
situation, as certified by the Armed Forces of the Philippines Provincial
Commander and approved by the Secretary of National Defense.
The Consultant may terminate its agreement with the Procuring Entity if the
latter is in material breach of its obligations pursuant to the contract and has
not remedied the same within sixty (60) calendar days following its receipt of
the Consultant’s notice specifying such breach.
190
The 2016 Revised Implementing Rules and Regulations – Annex “I”
a) that the contract is being terminated for any of the ground(s) afore-
mentioned, and a statement of the acts that constitute the ground(s)
constituting the same;
3. Show Cause. Within a period of seven (7) calendar days from receipt of the
Notice of Termination, the Supplier/Contractor/Consultant shall submit to the
Head of the Procuring Entity a verified position paper stating why the contract
should not be terminated.
5. Decision. Within a non-extendible period of ten (10) calendar days from receipt
of the verified position paper, the Head of the Procuring Entity shall decide
whether or not to terminate the contract. It shall serve a written notice to the
Supplier/Contractor/Consultant of its decision and, unless otherwise provided, the
Contract is deemed terminated from receipt of the
Supplier/Contractor/Consultant of the notice of decision. The termination shall
only be based on the ground(s) stated in the Notice to Terminate.
191
The 2016 Revised Implementing Rules and Regulations – Annex “I”
a) to have any portion delivered or performed and paid at the contract terms
and prices; and/or
b) to cancel the remainder and pay to the Supplier an agreed amount for
partially completed or performed goods and for materials and parts
previously procured by the Supplier.
If the Supplier suffers loss in its initial performance of the terminated contract,
such as purchase of raw materials for goods specially manufactured for the
Procuring Entity which cannot be sold in open market, it shall be allowed to
recover partially from the contract, on a quantum meruit basis. Before
recovery may be made, the fact of loss must be established under oath by the
Supplier to the satisfaction of the Procuring Entity before recovery may be
made.
V. AMENDMENTS
192
Appendix of the Handbook on Government Procurement
APPENDIX
GP PB Guidelines
and Other I ssuances
193
Revised Guidelines for the Implementation of Infrastructure Appendix 1
Projects By Administration
APPENDIX 1
REVISED GUIDELINES FOR THE IMPLEMENTATION OF INFRASTRUCTURE
PROJECTS BY ADMINISTRATION
These guidelines shall provide rules for the implementation of projects “by
administration” by all Departments, Bureaus, Offices and Agencies of the National
Government (NGA), Government-Owned and/or Controlled Corporations (GOCCs),
Government Financing Institutions (GFIs), State Universities and Colleges (SUCs), and
Local Government Units (LGUs).
Projects undertaken “by administration” by the Armed Forces of the Philippines Corps
of Engineers (AFPCOE) shall be governed by the guidelines issued by the GPPB
through Resolution 09-2005 dated 28 April 2005.
For purposes of these guidelines, the following terms shall be defined as follows:
2.3 Job-Contractor refers to a person or entity who carries out, under his own
responsibility, supervision and control, the performance or completion of a
specific job, service or work which has been farmed out by another for the
latter’s benefit.
2.5 Labor-only Contractor refers to a person or entity that engages in the supply
of workers/laborers to an employer but does not have substantial capital or
investment in the form of tools, equipment, machineries, work premises,
among others, and the workers recruited and placed perform activities directly
related to the principal business of the employer.
2.6 Pakyaw refers to a system of hiring a labor group for the performance of a
specific work and/or service incidental to the implementation of an
infrastructure project by administration whereby tools and materials are
furnished by the implementing agency. For the specific work/service output, a
lump-sum payment is made either through the group leader or divided among
the pakyaw workers and disbursed using a payroll system.
2.7 Semi-skilled Work/Job refers to a work/job which needs some skills but
does not require doing the more complex work duties. Semi-skilled jobs may
require alertness and close attention to watching machine processes; or
inspecting, testing or otherwise looking for irregularities; or tending or guarding
equipment, property, materials, or persons against loss, damage or injury; or
194
Revised Guidelines for the Implementation of Infrastructure Appendix 1
Projects By Administration
other types of activities which are similarly less complex than skilled work, but
more complex than unskilled work. A job may be classified as semi-skilled
where coordination and dexterity are necessary, as when hands or feet must be
moved quickly to do repetitive tasks.
2.8 Skilled Work/Job refers to work that requires qualifications in which a person
uses judgment to determine the machine and manual operations in order to
obtain the proper form, quality, or quantity of material to be produced. Skilled
work may require laying out work estimating quality, determining the suitability
and needed quantities of materials, making precise measurements, reading
blueprints or other specifications, or making necessary computations or
mechanical adjustments to control or regulate the work.
2.9 Unskilled Work/Job refers to work which needs little or no judgment that
can be learned on the job in a short period of time. The job may or may not
require considerable strength.
The Department of Public Works and Highways shall validate the track record
and capability of the LGUs, as implementing agencies for nationally funded
projects. 183
181
Amended through GPPB Resolution No. 20-2020, dated October 22, 2020, published in the Philippine Star on December 22,
2020
182
ibid
183
ibid
184
ibid.
185
ibid
195
Revised Guidelines for the Implementation of Infrastructure Appendix 1
Projects By Administration
3.5 Procurement of tools and construction equipment shall be subject to the rules
on public bidding.
3.6 For projects funded by the National Government and implemented by a Local
Government Unit, the latter shall be required to post the necessary warranty
security in accordance with Section 62 of RA 9184 and its IRR. 186
4.1 Pakyaw labor shall be drawn from the vicinity of the project, or Pakyaw labor
groups belong to various Barangay Associations contiguous to the project site.
Unskilled labor should be drawn from the Barangay where the project is
located; semi-skilled labor shall be recruited within the municipality, preferably
within the Barangay; skilled labor shall be recruited within the province but
preferably within the Barangay/Municipality.
4.2 The formation of Pakyaw Groups should actively involve the Barangay leaders
and the community. A Project Facilitator (PF) shall be appointed by the
implementing agency to assist in the organization of the Pakyaw Groups and in
the preparation of the Pakyaw Contracts. The PF shall, for purposes of
informing the community of the project and of organizing pakyaw groups, shall
convene community meetings, with the assistance of the Barangay
Chairperson/s. The PF shall cause the registration of all unemployed or
underemployed members of the community who are interested to join Pakyaw
groups being formed for the project.
4.3 The Pakyaw workers should be formed into groups of workers based on the
lump sum works. In case of competitive selection, pakyaw groups which were
not selected for a particular lump sum work may choose to compete for other
works requiring pakyaw groups.
4.4 Where there is competition for the award of Pakyaw works, the pakyaw labor
contract shall be awarded through competitive selection with at least three (3)
Pakyaw Groups participating. There is deemed to be a competition for the
award of pakyaw contracts when the number of laborers who registered during
the community meeting is more than what is reasonably needed for the lump
sum work required under the project. The competitive selection shall be done
on a “per-output” basis. And the winner(s) shall be determined based on what
group(s) undertake(s) to deliver the desired output at the lowest rate, either
per item of output or per lump sum work, within the required period.
4.5 For purposes of Item 4.4 hereof, the number of members per group shall be
determined by the Project Facilitator to ensure that at least three Pakyaw
Groups are organized for the competitive selection. The determination by the
Project Facilitator of the number of members per Pakyaw Group shall be
186
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
196
Revised Guidelines for the Implementation of Infrastructure Appendix 1
Projects By Administration
4.6 A Group Leader shall be elected from among the members of the group who
shall be the signatory to the Pakyaw Contract and any other documents
pertaining to the work on behalf of the Pakyaw Group. He may be replaced at
any time by the group through an election for that purpose, after due notice to
the Project Facilitator and the Barangay Chairperson. Any such replacement
shall not invalidate any previous Pakyaw Contract.
4.8 The amount of a pakyaw labor contract per project shall not exceed Five
Hundred Thousand Pesos (₱ 500,000.00) per pakyaw group.
This set of guidelines repeals GPPB Resolution 13-2005 approving and adopting the
Guidelines for the Implementation of Infrastructure Projects through Negotiated
Procurement under Sec. 54.2 (d) of IRR 187 of RA 9184 and by Administration.
6.0 Effectivity
These Guidelines or any amendments hereto shall take effect fifteen (15) days after
publication in the Official Gazette or in a newspaper of general nationwide circulation
and upon filing with the University of the Philippines Law Center of three (3) certified
copies of these guidelines. 188
187
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
188
Issued through GPPB Resolution 18-2006, dated 06 December 2006, published in the Official Gazette on 09 April 2007.
197
Preparation of the Annual Procurement Plan Appendix 2
APPENDIX 2
GPPB CIRCULAR 08-2015
PREPARATION OF THE ANNUAL PROCUREMENT PLAN (APP)
1.0 Purpose
1.1. This Circular 189 is being issued to reiterate the requirement of preparing the
APP and inform all procuring entities to prepare the APP in the format approved
by the GPPB.
1.2. The accurate preparation of the APP fosters meticulous and judicious
procurement planning at the agency level.
1.3. This is also being issued to clarify that the APP-Common-Use Supplies and
Equipment (APP-CSE), which is to be submitted to the Department of Budget
and Management – Procurement Service (DBM-PS) on or before 15 November
of every year pursuant to Administrative Order (AO) No. 17 Series of 2012, and
DBM Circular Letter No. 2013-14, for the purpose of determining the quarterly
cash requirements for common supplies, materials, and equipment of the
agency and for the over-all management of the central procurement of
common-use supplies and equipment by the DBM-PS, is different from the APP
prescribed by Republic Act (R.A.) No. 9184 and its associated issuances.
2.0 Scope
All Departments, Bureaus, Offices and Agencies of the National Government including
State Universities and Colleges, Government Owned and/or Controlled Corporations,
Government Financial Institutions, and Local Government Units.
3.1. Section 7 of R.A. No. 9184 and its revised Implementing Rules and Regulations
(IRR) mandates the preparation of the APP which should include procurements
considered crucial to the efficient discharge of governmental functions.
3.2. On 30 March 2015, the Office of the President issued Administrative Order No.
46 Series of 2015 which included the submission of the APP to the GPPB-TSO
within the first month of the year, and for those who have not submitted, to
comply before the end of April, as one of the measures to speed up the
procurement procedures.
4.1. Per GPPB Resolution No. 20-2015, 190 the GPPB approved the revised format of
the APP (attached as Annex “A”), to be used by all procuring entities where all
of their procurement activities for the year, including the requirements in its
APP-CSE are reflected.
189
Issued on 16 July 2015.
190
Format of the PMR was amended through GPPB Resolution No. 14-2019 dated 17 July 2019 to reflect Early Procurement
Activities (EPA), published in the Official Gazette on 26 August 2019.
198
Preparation of the Annual Procurement Plan Appendix 2
199
Preparation of the Annual Procurement Plan Appendix 2
Annex A
200
Guidelines for Electronic Bidding Appendix 3
APPENDIX 3
GUIDELINES FOR ELECTRONIC BIDDING (E-BIDDING)
These Guidelines are formulated to provide rules and procedures that shall apply to
all branches, constitutional commissions and offices, agencies, departments,
bureaus, offices, and instrumentalities of the Government, including government-
owned and/or controlled corporations (“GOCCs”), government financial institutions
(“GFIs”), state universities and colleges (“SUCs”) and local government units
(“LGUs”) in the procurement of goods, infrastructure projects and consulting services
through electronic means utilizing the PhilGEPS.
3.1. For purposes of these Guidelines, the following terms, or words and phrases
shall mean or be understood as follows:
3.1.2. Bid Notice Creator – refers to a member of the Bids and Awards
Committee (BAC) or its Secretariat specifically designated by the BAC
to be responsible for creating the electronic Bid Notices/Supplements,
or by the Head of the Procuring Entity in creating notices of award.
201
Guidelines for Electronic Bidding Appendix 3
3.1.12. Portable Document Format (PDF) – refers to a file format that has
captured all the elements of a printed document as an electronic
image that can be viewed, navigated, printed, copied but cannot be
edited or changed.
3.1.14. Response Forms – refers to technical and financial forms that are
editable and can be populated with information.
202
Guidelines for Electronic Bidding Appendix 3
3.2. Terms, words, and phrases used in these Guidelines shall have the same
meaning as those that are defined in RA 9184 and RA 8792, otherwise known
as the Electronic Commerce Act, and their respective Implementing Rules and
Regulations, and the Guidelines for the Use of the Government of the
Philippines – Official Merchants Registry (GoP-OMR).
4.1. All Procuring Entities are mandated to fully use the PhilGEPS in accordance
with RA 9184 and its IRR, and the policies, guidelines, and circulars issued by
the GPPB.
4.2. All Procuring Entities shall register with the PhilGEPS and shall undertake
measures to ensure their access to the on-line network in order to facilitate
open, speedy and efficient on-line transmission, conveyance and use of
electronic data messages or electronic documents. Further, the PhilGEPS shall
assist procuring entities ensure their on-line connectivity and provide training
for their personnel responsible for the operation of the system from their
terminals.
4.3. The rules and regulations governing the manual method of procurement shall
apply whenever the rules in these Guidelines are silent.
4.4. The Invitation to Bid, including the Bidding Documents shall clearly state
whether Electronic Bidding is available for the procurement opportunity.
4.5. The provisions under Section 13 of the IRR on Observers shall apply without
prejudice to full compliance with the requirement under Section 8.7 of the
IRR.
4.6. Only bidders who pay the Bid Document Fee shall be allowed to participate in
the e-bidding activities and submit a bid.
4.8. PhilGEPS must establish a user help desk or a call center which offers
centralized customer service (telephone- based service, live chat, e-mails)
and support functions that will both cater to procuring entities and Registered
Merchants to effectively and efficiently address issues and problems during
their procurement operations.
4.9. PhilGEPS and/or the Procuring Entity must provide Online Bidders common
access points to the Internet to enable them to submit electronic bids.
4.10. Prospective bidders, who submit their bids electronically, shall not be allowed
to submit bids manually. Any bid modifications shall likewise be submitted
electronically, provided that this is done before the deadline for submission
and receipt of electronic bids.
203
Guidelines for Electronic Bidding Appendix 3
4.11. These guidelines shall also apply when procuring entities resort to any of the
Alternative Modes of Procurement specifically Shopping under Section 52.1(b)
and Negotiated Procurement under Section 53.1 (two-failed biddings) and
Section 53.9 (small value procurement), subject to the prior approval of the
Head of the Procuring Entity in order to promote economy and efficiency, and
whenever justified by the conditions provided in RA 9184 and its IRR.
5.1. Procuring Entities, through their respective Bid Notice Creators, shall create
an electronic Invitation to Bid in accordance with the contents provided for
under Section 21.1 of the IRR of RA 9184 to provide prospective bidders
sufficient information for the contract to be bid (“Bid Notices”) using the
electronic bid facility under PhilGEPS. Only Bid Notices that have been
verified and approved by the Bid Notice Approver shall be posted in the
PhilGEPS Electronic Bulletin Board.
5.2. Procuring Entities shall upload a complete set of bidding documents in the
PhilGEPS website which will be available from the time the Bid Notice is
posted, and which PDF version can be downloaded free of charge by
Registered Merchants until the deadline for the submission and receipt of
bids.
5.3. Registered Merchants who have set their bid-match profiles shall
automatically be notified through electronic mail (e-mail) and/or through the
Registered Merchant’s respective PhilGEPS “Pending Task” page of posted Bid
Notices.
5.4. Only Registered Merchants who pay the Bid Document Fee through the Bid
Payment Modality shall be allowed to download complete bidding documents
and bid response forms.
6.1. For contracts to be bid where the conduct of Pre-Bid Conference is required
under Section 22 of the IRR, the same procedure governing the manual
method will also apply.
6.2. Procuring Entities with videoconferencing capabilities may conduct their pre-
bidding conferences electronically provided that their Registered Merchants
shall also have similar capabilities and facilities.
6.3. During the conduct of the Pre-Bid Conference, Registered Merchants may
send requests for clarification through the PhilGEPS online facility, which shall
be read during the meeting and shall form part of the minutes, unless the
Procuring Entity has previously decided that only those who have purchased
the Bidding Documents shall be allowed to participate in the pre-bid
conference and raise or submit written queries or clarifications.
204
Guidelines for Electronic Bidding Appendix 3
Merchants through the PhilGEPS Electronic Bulletin Board not later than three
(3) calendar days after the pre-bid conference.
6.5. Requests for clarification(s) on any part of the Bidding Documents or for an
interpretation must be in writing and submitted to the BAC of the procuring
entity concerned, either electronically through PhilGEPS or otherwise, at least
ten (10) calendar days before the deadline set for the submission and receipt
of bids.
6.6. Only Bid Bulletins/Supplements approved by the Bid Notice Approver shall be
posted in the PhilGEPS at least seven (7) calendar days before the deadline
for the submission and receipt of bids. PhilGEPS shall automatically notify
through e-mail all Registered Merchants who have downloaded the bidding
documents and paid the Bid Document Fee.
7.2. Only a Certified Member with the appropriate classification can avail of the
PhilGEPS advance eligibility submission by uploading their electronic
documents to the PhilGEPS document library, which can be accessed for
current or future procurements.
8.1. On-line Bidders may submit their eligibility requirements to the Procuring
Entity through the e-bidding facility of PhilGEPS.
8.2.1. In case of joint venture, each partner of the joint venture must: (i) be
registered in the PhilGEPS, (ii) secure Certified Membership Status,
and (iii) electronically send their respective eligibility documents.
8.2.2. The joint venture partners must identify and designate the Primary
and Secondary Partner(s).
8.2.3. Before the PhilGEPS will accept submissions of technical and financial
proposals from the Primary Partner, there must be a confirmation
from the Secondary Partner(s) as to existence of, or agreement to
enter into, a joint venture.
205
Guidelines for Electronic Bidding Appendix 3
8.3. On-line Bidders, or the Primary Partner in the case of Joint Ventures, shall
electronically submit their bids through the Bidder’s On-line Nominee, at any
time before the closing date and time specified in the bidding documents.
8.4. The actual time of bid submission of an On-line Bidder shall be the time
indicated on the PhilGEPS Server when the bidder clicks the “Submit” button
which shall be automatically recorded by PhilGEPS. Upon receipt of a bid, the
PhilGEPS shall automatically generate a bid receipt page that can be printed
by the on-line bidder. This contains the recorded “submission time” which
shall be considered as the Official Submission Time of the bidder.
8.5. An On-line Bidder may modify its bid at any time before the closing date and
time for the submission and receipt of bids.
8.6. An On-line Bidder may withdraw its bid before the deadline for the
submission and receipt of bids.
8.7. The PhilGEPS shall bar all incoming bids after the closing date and time.
9.1. On-line bidders may submit the bid security in cash through the PhilGEPS
electronic payment facility.
9.2. In case of other forms of bid security, the on-line bidder shall prepare and
submit a scanned copy of the bid security together with the electronic bid.
However, the original bid security must be submitted to the BAC concerned
before the end of business hours on the day of bid submission, a failure of
which shall automatically render the bid submission as non-compliant.
9.3. If the on-line bidder sends the original bid security through registered mail or
private courier, the indicated date of receipt by the postal service or private
courier shall be considered as the date of submission to the BAC concerned,
without prejudice to any verifications during post-qualification.
10.1. In case of system failure, the rules provided for in Annex 1 shall
automatically apply regarding extension of the bid closing date.
11.1. Upon receipt of manually-filed bids, the Bid Opener, before the Bid Opening,
but immediately after the deadline for submission of bids, shall record and
input into PhilGEPS E-bidding module the date and time each of the bid was
manually received, including the name of the bidder’s authorized
representative.
11.2. The BAC shall open the bids immediately after the deadline for submission
and receipt of bids, and on the bid opening date.
206
Guidelines for Electronic Bidding Appendix 3
11.3. Before the decryption of electronic bids, the Bid Opener must first login to
PhilGEPS and only then can BAC members input their respective USER IDs
and PASSWORDS, provided however, that PhilGEPS decryption will not take
place unless all the members present and logging-in constitute quorum.
11.4. The Bid Opener shall publicly open the first bid envelopes of bidders who
submitted bids manually to determine each bidder’s compliance with the
documents required to be submitted for eligibility, that is, legal, technical
and financial eligibility documents; and for the technical requirements. For
this purpose, the BAC shall check the submitted documents of each bidder
against a checklist of required documents to ascertain if they are all present,
using a non-discretionary “pass/fail” criterion. If a bidder submits the
required document, it shall be rated “passed” for that particular requirement.
In this regard, bids that fail to include any requirement or are incomplete or
patently insufficient shall be considered as “failed”. Otherwise, the BAC shall
rate the bidder “passed” in relation to the eligibility and technical documents
in the first envelope.
11.5. After all the manually submitted first envelopes of bidders were opened, and
the results and findings were encoded in the PhilGEPS Preliminary
Examination Report facility, the Bid Opener shall thereafter proceed to
decrypt the electronic First Bid Envelopes submitted by the On-line Bidders
to determine each bidder’s compliance with the required eligibility and
technical documents following the steps and procedures outlined in Section
11.4 hereof. Thereafter, the Bid Opener shall input the findings and results
into the PhilGEPS’ Preliminary Examination Report facility.
11.6. Immediately after determining compliance with the requirements in the first
envelope, the Bid Opener shall forthwith open the manually submitted
second bid envelope of each eligible bidder whose first bid envelope was
rated “passed.” The second envelope of each complying bidder shall be
opened within the same day.
11.7. After all the manually submitted second envelopes of bidders were opened,
and the results and findings were encoded in the PhilGEPS Preliminary
Examination Report facility, the Bid Opener shall thereafter proceed to
decrypt the electronic Second Bid Envelopes of each On-line Bidders whose
electronic first bid envelope was rated “passed” to determine each bidder’s
compliance with the required financial documents following the steps and
procedures outlined in Section 11.6 hereof.
Only bids that are determined to contain all the bid requirements for both
components shall be rated “passed” and shall immediately be considered for
evaluation and comparison.
11.9. PhilGEPS shall automatically send an electronic mail to all bidders who failed
207
Guidelines for Electronic Bidding Appendix 3
12.1. The BAC shall immediately conduct a detailed evaluation of all bids using
non-discretionary criteria in considering the following:
12.2. The BAC shall evaluate all bids on an equal footing to ensure fair and
competitive bid comparison. For this purpose, all bidders shall be required
to include the cost of all taxes, such as, but not limited to, value added tax
(VAT), income tax, local taxes, and other fiscal levies and duties which shall
be itemized in the bid form and reflected in the detailed estimates. Such
bids, including said taxes, shall be the basis for bid evaluation and
comparison.
12.3. In case of discrepancies between: (a) bid prices in figures and in words, the
latter shall prevail; (b) total price of the item and unit price of the item as
extended or multiplied by the quantity of that item, the latter shall prevail;
(c) stated total price and the actual sum of prices of component items, the
latter shall prevail; (d) unit cost in the detailed estimate and unit cost in the
bill of quantities, the latter shall prevail.
12.4. Bids shall then be ranked in the ascending order of their total calculated bid
prices, as evaluated and corrected for computational errors, and other bid
modifications, to identify the Lowest Calculated Bid. Total calculated bid
prices, as evaluated and corrected for computational errors, and other bid
modifications, which exceed the ABC shall be disqualified.
12.5. After all bids have been received, opened, examined, evaluated, and ranked,
the BAC shall prepare the corresponding Abstract of Bids. All members of
the BAC shall sign the Abstract of Bids and attach thereto all the bids with
their corresponding bid securities and the minutes or proceedings of the
bidding. The Abstract of Bids shall contain the following:
208
Guidelines for Electronic Bidding Appendix 3
12.6. After conducting the detailed evaluation of all bids using non-discretionary
criterion, the Bid Opener shall input and record the results of the evaluation
into the PhilGEPS’ Evaluation Summary Report facility.
12.7. The PhilGEPS shall automatically rank the bidders in ascending order based
on their total calculated bid prices to identify the LCB as evaluated and
corrected for computational errors, and other bid modifications. Total
calculated bid prices, as evaluated and corrected for computational errors,
and other bid modifications, which exceed the ABC shall be disqualified.
After all bids have been received, opened, examined, evaluated, and ranked,
the system shall thereafter generate the Abstract of Bids in the form of
PhilGEPS Evaluation Summary Report.
12.8. The BAC shall manually prepare a Resolution whether approving or denying
the Abstract of Bids generated by the system. However, after the BAC
Resolution approving the Abstract of Bids is uploaded in the PhilGEPS, an
electronic message shall be automatically sent to all bidders who participated
informing them that the Abstract of Bids is available for downloading.
Consulting Services
12.9. To determine the Highest Rated Bid (HRB), the BAC shall immediately
conduct a detailed evaluation of all bids using the steps provided for under
Section 33 of the IRR of RA 9184.
12.10. After conducting the detailed evaluation of all bids using non-discretionary
criteria, the Bid Opener shall input and record the results of the evaluation
into the PhilGEPS’ Summary Report facility.
12.11. The PhilGEPS shall automatically rank the bidders in descending order
based on their total score to identify the HRB. After all bids have been
received, opened, examined, evaluated, and ranked, the system shall
thereafter generate the Abstract of Bids.
12.12. The BAC shall manually prepare a Resolution whether approving or denying
the Abstract of Bids generated by the system. However, after the BAC
209
Guidelines for Electronic Bidding Appendix 3
13.1 The Lowest Calculated Bid (“LCB”)/Highest Rated Bid (“HRB”) shall undergo
post-qualification pursuant to Rule X of the IRR in order to determine
whether the bidder concerned complies with and is responsive to all the
requirements and conditions as specified in the Bidding Documents.
13.2 Within one (1) day after the approval of the Abstract of Bids, the bidder with
the LCB/HRB should be notified through electronic mail that the bidder shall
undergo post-qualification and submit the post-qualification requirements
within three (3) calendar days as provided for under Section 34.2 of the IRR.
13.3 If the BAC determines that the bidder with the LCB/HRB passes all the
criteria for post-qualification, it shall declare the said bid as the Lowest
Calculated Responsive Bid (LCRB)/ Highest Rated Responsive Bid (HRRB),
and recommend to the Head of the Procuring Entity the award of contract to
the said bidder at its submitted bid price or its calculated bid price,
whichever is lower or, in the case of quality-based evaluation procedure,
submitted bid price or its negotiated price, whichever is lower.
13.4 If, however, the BAC determines that the bidder with the LCB/HRB fails the
criteria for post-qualification, it shall immediately notify the said bidder
electronically in writing of its post-disqualification and the grounds for it.
13.5 Immediately after the BAC has electronically notified the first bidder of its
post-disqualification, and notwithstanding any pending request for
reconsideration thereof, the BAC shall initiate and complete the same post-
qualification process on the bidder with the second LCB/HRB. If the second
bidder passes the post-qualification, and provided that the request for
reconsideration of the first bidder has been denied, the second bidder shall
be post-qualified as the bidder with the LCRB/HRRB.
13.6 If the second bidder, however, fails the post-qualification, the procedure for
post-qualification shall be repeated for the bidder with the next LCB/HRB,
and so on until the LCRB or HRRB, as the case may be, is determined for
award, subject to Section 37 of the IRR.
13.7 The post-qualification process shall be completed in not more than seven (7)
calendar days from the determination of the LCB/HRB. In exceptional cases,
the post-qualification period may be extended by the Head of the Procuring
Entity, but in no case shall the aggregate period exceed thirty (30) calendar
days.
13.8 The BAC or its Bid Opener shall record and encode the post-qualification
results of manually submitted documents in the PhilGEPS. For electronic
documents submitted online, the BAC or its Bid Opener shall decrypt the
documents and the results recorded automatically.
210
Guidelines for Electronic Bidding Appendix 3
13.9 After recording the post-qualification summary and uploading the BAC
resolution declaring the bidder with the LCRB/HRRB in the PhilGEPS, an
electronic message shall be automatically sent to all bidders who participated
informing them that the Notice of LCRB/HRRB is available for downloading.
14.0 AWARD
14.1 The BAC shall recommend to the Head of the Procuring Entity the award of
contract to the bidder with the LCRB/HRRB or the Single Calculated/Rated
Responsive Bid after the post-qualification process has been completed.
To facilitate the approval of the award, the BAC shall submit the following
supporting documents to the Head of the Procuring Entity:
b) Abstract of Bids;
14.2 In case of approval, the Head of the Procuring Entity (HOPE) shall
immediately issue the Notice of Award to the bidder with the LCRB/HRRB.
In the event the Head of the Procuring Entity shall disapprove such
recommendation, such disapproval shall be based only on valid, reasonable,
and justifiable grounds to be expressed in writing, copy furnished the BAC.
14.3 Upon approval by the HOPE of the BAC recommendation to award the
contract to the LCRB/HRRB, the Notice of Award (“NOA”) shall be created by
the Bid Notice Creator in the PhilGEPS upon instruction of the HOPE,
provided however, that the NOA shall only be created and issued to the
LCRB/HRRB if no request for reconsideration or protest is received by, or
inputted in PhilGEPS.
14.4 Upon issuance of the NOA to the LCRB/HRRB, an electronic message shall
be automatically sent to all bidders who participated informing them of the
results of the bidding process.
14.5 Notwithstanding the issuance of the Notice of Award, the award of the
contract shall be subject to the following conditions:
211
Guidelines for Electronic Bidding Appendix 3
i) Valid JVA, if applicable, within ten (10) calendar days from receipt
by the bidder of the notice from the BAC that the bidder has the
LCRB or HRRB, as the case may be; or
14.6 Contract award shall be made within the bid validity period provided in
Section 28 of the IRR.
14.7 The BAC, through the Secretariat, shall post, within three (3) calendar days
from its issuance, the Notice of Award in the PhilGEPS, the website of the
procuring entity, if any, and any conspicuous place in the premises of the
procuring entity.
14.8 After the contract signing and submission of the Performance Bond, the Bid
Notice Creator shall update the “proceed date” and the “contract start and
end dates” and upload a copy of the Notice to Proceed and approved
Contract in the PhilGEPS.
16.0 EFFECTIVITY
These Guidelines shall take effect fifteen (15) calendar days after its publication in
the Official Gazette or in a newspaper of general nationwide circulation. 191
191
Issued through GPPB Resolution 23-2013, dated 30 July 2013, and published in The Daily Tribune on 03 November 2014.
212
Guidelines for Electronic Bidding Appendix 3
Annex 1
213
Guidelines for the use of the GOP-OMR Appendix 4
APPENDIX 4
GUIDELINES FOR THE USE OF THE GOVERNMENT OF THE PHILIPPINES -
OFFICIAL MERCHANTS REGISTRY (GoP-OMR)
These Guidelines shall govern the general procedures for the use of the Government
of the Philippines-Official Merchants Registry (“GoP-OMR”), the electronic database
developed and maintained by PhilGEPS pursuant to Section 8.2.2 of the Revised IRR
of R.A. 9184.
3.1. For purposes of these Guidelines, the following terms, or words and phrases
shall mean or be understood as follows:
3.2. Terms, words, and phrases used in these Guidelines shall have the same
meaning as those that are defined in R.A. 9184 and its Revised Implementing
Rules and Regulations.
4.1 The GoP-OMR shall be the centralized electronic database of merchants for
purposes of government electronic procurement.
4.2 The PhilGEPS office shall not determine the eligibility of merchants. The
PhilGEPS office’s evaluation of the eligibility requirements shall be for the sole
214
Guidelines for the use of the GOP-OMR Appendix 4
4.4 The determination of the eligibility of merchants, whether registered with the
GoP-OMR or not, shall remain with the Bids and Awards Committee (BAC).
The BAC’s determination of validity of the eligibility requirements shall be
conclusive to enable the merchant to participate in the public bidding process.
5.1 The PhilGEPS office shall develop and implement the necessary procedures for
the registration and membership of merchants in the GoP-OMR.
5.2 Subject to Section 6, the procedures for registration of merchants shall prescribe
the following requirements:
5.2.2 an account number with a bank duly licensed by the Bangko Sentral
ng Pilipinas (BSP), which shall be used to facilitate financial
transactions such as, but not limited to, the payment of fees;
charges; bid, performance, and warranty securities; and similar
costs;
5.2.3 a secure e-mail address, which shall be used for all communications
between the BAC and the PE;
5.2.5 eligibility requirements as provided in R.A. 9184 and its Revised IRR;
and,
5.4 The PhilGEPS office shall receive and process all applications for registration,
and shall have the sole power to approve or disapprove any application in
accordance with its registration procedures, subject to existing laws, rules
and regulations, and these Guidelines.
215
Guidelines for the use of the GOP-OMR Appendix 4
5.5 Approval of the application shall amount to the registration of the merchant in
the GoP-OMR. Disapproval shall prevent the registration of the merchant in
the GoP-OMR until such time that it satisfactorily complies with the
requirements.
5.6 The PhilGEPS office shall deny registration to or exclude from the GoP-OMR
any merchant (a) that is found to have willfully misrepresented any of the
information provided in the application for registration, or (b) that is in the
“blacklist” of a PE. For this purpose, exclusion from the registry shall result in
the cancellation of the merchant’s account in the PhilGEPS website.
5.6.1 This exclusionary rule also applies to any merchant that has been
subjected to the blacklisting rules of foreign governments, and
foreign or international financing institutions, if such rules have been
recognized by the Government Procurement Policy Board (GPPB).
5.6.2 The PE shall immediately notify the PhilGEPS office and the GPPB
regarding its “blacklisting” of a merchant by forwarding a copy of
the Blacklisting Order to PhilGEPS and GPPB. Upon receipt of the
Blacklisting Order, the PhilGEPS office shall exclude the merchant
from the GoP-OMR.
6.1 The PhilGEPS office shall develop a merchants’ membership classification that
will define the extent of a merchant’s access to and use of the PhilGEPS
website, and include the rules and procedures for acquiring, maintaining,
relinquishing, changing, or renewing a membership status in the registration
procedure mentioned in Section 5.1 hereof.
6.2 Merchants shall have the option to choose its membership classification based
on the categories provided by the PhilGEPS office. Merchants shall be entitled
to a Certificate of Registration and Membership depending on the chosen
classification and payment of the corresponding membership fee determined
by the PhilGEPS office.
6.3 A Certificate of Registration and Membership shall be valid and effective for a
period of one (1) year from the date of issuance as indicated therein. This
Certificate may be renewed; provided , that the merchant maintains its
records in the GoP-OMR current and updated at least once a year or more
frequently as may be necessary; provided further , that the merchant’s
failure to maintain its records current and updated shall result in the
downgrading of the merchant’s membership classification in accordance with
the procedures of the PhilGEPS office, notwithstanding the fact that the one-
year validity of the Certificate of Membership has not yet expired.
7.1 The following rules shall apply only to electronic registries that
simultaneously allow submission and/or recording/entry of eligibility
requirements with registration:
7.2 All existing electronic merchant registries used and maintained by PEs shall
be integrated into the GoP-OMR. Upon integration, the PE shall henceforth
216
Guidelines for the use of the GOP-OMR Appendix 4
use the GoP-OMR for government procurement purposes, and shall cease
using the prior registry.
7.3 The PE shall coordinate with the PhilGEPS office to determine whether the
existing registry is compatible with the GoP-OMR.
7.4 After a finding of compatibility, the PE shall integrate its registry with the
GoP-OMR.
If the registries are incompatible, the PE shall cease using its registry and use the
GoP-OMR. The PE shall be given sufficient amount of time to effect the shutdown of
its electronic registry and the shift to the use of the GoP-OMR. The PE and the
PhilGEPS office shall coordinate with each other for this purpose.
PEs that maintain manual registries shall be encouraged to shift to the use of the
GoP-OMR. If the PE decides to retain the use of its manual registry, it may do so;
provided, however, that when the PE shifts to an electronic registry, it shall use the
facilities of the GoP-OMR. After the shift, the PE shall henceforth use the GoP-OMR
for government procurement purposes.
10.0 AMENDMENTS
11.0 EFFECTIVITY
These Guidelines shall take effect fifteen (15) days after its publication in the Official
Gazette or in a newspaper of general nationwide circulation, and upon filing with the
University of the Philippines Law Center of three (3) certified copies of these
guidelines. 192
192
Issued through GPPB Resolution 12-2012, dated 1 June 2012, and published in The Daily Tribune on 28 December 2012.
217
Procurement Monitoring Report Format Appendix 5
APPENDIX 5
GPPB CIRCULAR 03-2015
PROCUREMENT MONITORING REPORT (PMR) FORMAT
1.0 Purpose
This Circular 193 is being issued to remind the Procuring Entities of the requirement on
the submission of the PMR for every semester in accordance with Section 12.2 of the
IRR of RA 9184.
2.0 Coverage
The 2012 Country Procurement Assessment Report (CPAR) noted that the
results of the APCPI yield a 41% compliance rate for the preparation of PMRs
among the pilot agencies, and a lower rate of 18% for the posting of these
reports at the agency websites.
4.2 Pursuant to Sections 12.1of the IRR of RA 9184, PMR shall be approved and
submitted by the HOPE to the GPPB in printed and electronic format 194 within
fourteen (14) calendar days after the end of each semester.
193
Issued on 20 March 2015.
194
Format of the PMR was amended through GPPB Resolution No. 14-2019, dated 17 July 2019, to reflect Early Procurement
Activities (EPA), published in the Official Gazette on 26 August 2019.
218
Procurement Monitoring Report Format Appendix 5
219
Confidentiality Agreement Format Appendix 6
APPENDIX 6
CONFIDENTIALITY AGREEMENT FORMAT
___________________________________
(First party’s details)
and
___________________________________
(Second party’s details)
1. As used in this Agreement, “confidential information” shall mean all information and
materials including, without limitation, market analyses, cost estimates, technical
specifications, evaluation criteria and results, and any documentation, analyses,
compilations, forecasts, studies or other procurement-related documents prepared
based on any of the foregoing that is provided by the party disclosing (“Disclosing
Party”) to the party receiving (“Receiving Party”) information under this Agreement,
whether oral, written, or in any other medium.
2. The Receiving Party shall maintain the secrecy of the Disclosing Party’s Confidential
Information and shall exert all reasonable efforts to preserve the confidentiality of
such information, including, but not limited to, the implementation of reasonable
physical security measures and operating procedures.
3. The Receiving Party agrees that at all times and notwithstanding any termination or
expiration of this Agreement, it will hold in strict confidence and not disclose to any
third party all Confidential Information received from the Disclosing Party, except as
approved in writing by the latter. The receiving party shall be prohibited from using
the Confidential Information for purposes other than compliance with its obligations
as an Observer under Republic At 9184 and its Implementing Rules and Regulations.
4. Access to Confidential Information of the Disclosing Party shall only be granted by the
Receiving Party to its employees or authorized representatives, when their knowledge
of such information becomes necessary, provided that such persons have signed
confidentiality agreements or are otherwise bound by confidentiality obligations which
contain the minimum terms, restrictions and limitations provided herein.
220
Confidentiality Agreement Format Appendix 6
EQUITABLE REMEDIES
7. The Receiving Party acknowledges that any breach of this Agreement may cause
irreparable harm to the Disclosing Party for which the latter is entitled to seek, among
others, indemnification for damages, as well as injunctive or other equitable remedies
as may be allowed by law.
MISCELLANEOUS
8. The Receiving Party shall not transfer or assign this Agreement to any other person or
entity, whether by operation of law or otherwise, without the prior written consent of
the Disclosing Party. Any such attempted assignment shall be void and of no effect.
10. This Agreement is the complete and exclusive agreement regarding the disclosure of
Confidential Information between the parties, and replaces or supersedes any and all
prior oral or written communications and agreements between the parties regarding
Confidential Information without prejudice to the rules and regulations concerning
restrictions on disclosure of information such as on matters involving national
security, diplomatic or foreign relations, intelligence and other classified information.
[ACKNOWLEDGMENT]
221
Guidelines on the Grant of Honoraria to Government Personnel Appendix 7
Involved in Government Procurement
APPENDIX 7
GUIDELINES ON THE GRANT OF HONORARIA TO GOVERNMENT PERSONNEL
INVOLVED IN GOVERNMENT PROCUREMENT
1.0 Background
Budget Circular (BC) No. 2004-5A, dated March 23, 2004, provides the guidelines on
the grant of honoraria to government personnel involved in government procurement
consistent with Republic Act 9184 (Government Procurement Reform Act). Certain
provisions thereof need further clarification particularly on the entitlement to
honoraria when alternative modes of procurement are used, the definition of a
“successful procurement project”, and the funding source for payment of honoraria.
2.0 Purpose
To amend BC No. 2004-5 and reissue the guidelines on the grant of honoraria to
qualified personnel.
3.0 Coverage
This circular shall apply to all national government agencies (NGAs), and its
instrumentalities, including state universities and colleges (SUCs), government-
owned or -controlled corporations (GOCCs) and local government units (LGUs).
4.0 Rationale
5.0 Guidelines
5.1 The chairs and members of the Bids and Awards Committee (BAC) and the
Technical Working Group (TWG) may be paid honoraria only for successfully
completed procurement projects. In accordance with Section 7 of the
Implementing Rules and Regulations Part A (IRR-A) of RA No. 9184, a
procurement project refers to the entire project identified, described,
detailed, scheduled and budgeted for in the Project Procurement
Management Plan prepared by the agency.
195
Issued on 7 October 2005.
222
Guidelines on the Grant of Honoraria to Government Personnel Appendix 7
Involved in Government Procurement
• Direct contracting;
• Repeat order;
• Shopping;
• Negotiated procurement under Section 53 (b) of the IRR following the
procedures under Section 54.2 (d) thereof, whereby the procuring entity
directly negotiates with previous supplier, contractor or consultant, or
when the project is undertaken by administration or thru the AFP, in case
of infrastructure projects; and
• Negotiated procurement under Section 53 (c) to (g) of the IRR.
5.3 The honoraria of each person shall not exceed the rates indicated below per
completed procurement project:
5.4 The average amount of honoraria per month over one year shall not exceed
twenty five percent (25%) of the basic monthly salary. The honoraria,
however, shall be paid only upon the successful completion of each
procurement.
5.6 The members of the BAC Secretariat who are performing the attendant
functions in additions to their regular duties in other non-procurement units
of the agency may likewise be paid honoraria at the same rate as the TWG
Chair and Members, subject to the same regulations.
The members of the BAC Secretariat whose positions are in the Procurement
Unit of the agency shall not be entitled to honoraria. The payment of
overtime services may be allowed, subject to existing policy on the matter.
223
Guidelines on the Grant of Honoraria to Government Personnel Appendix 7
Involved in Government Procurement
5.9 In lieu of honoraria, the payment of overtime services may be allowed for the
administrative staff, such as clerks, messengers and drivers supporting the
BAC, the TWG and the Secretariat, for procurement activities rendered in
excess of official working hours. The payment of overtime services shall be in
accordance with the existing policy on the matter.
5.10 Those who are receiving honoraria for their participation in procurement
activities shall no longer be entitled to overtime pay for procurement-related
services rendered in excess of official working hours.
6.1 The amount necessary for the payment of the honoraria and overtime pay
authorized herein shall be sourced only from the following:
6.3 The total amount of honoraria and overtime pay to be paid for procurement-
related activities shall not exceed the said collections.
6.4 In cases of deficiency in collections from the sources identified in item 6.1
above, the amount of honoraria and overtime pay shall be adjusted
proportionately for all those entitled thereto.
Cases not covered by the provisions of this Circular shall be referred to the Secretary
of Budget and Management for Resolution.
196
Refer to DBM Budget Circular No. 2007-3 for amendments.
224
Guidelines on the Grant of Honoraria to Government Personnel Appendix 7
Involved in Government Procurement
9.0 Effectivity
1.0 Purpose
1.1 To amend item no. 6.1 of BC 2004-5A which provides the funding source for
payment of honoraria and overtime pay to government personnel involved in
government procurement as authorized under Republic Act No. 9184
(Government Procurement Reform Act), as follows:
• Honoraria – for Chairs and Members of the Bids and Awards Committee
(BAC) and the Technical Working Group (TWG); and,
• Overtime Pay – For administrative staff supporting the BAC and TWG.
1.2 To identify additional funding source for payment of honoraria and overtime
pay to the aforecited personnel; and
1.3 To revise other related provisions of BC No. 2004-5A (i.e., items 6.3 and 6.4)
in order to clarify the manner of payment of said benefits.
2.0 Coverage
This Circular shall apply to all national government agencies (NGAs) including state
universities and colleges (SUCs), government-owned or controlled corporations
(GOCCs) and local government units (LGUs).
3.0 Guidelines
3.1 The amount necessary for payment of honoraria and overtime pay authorized
under BC No. 2004-5A dated October 7, 2005 shall be sourced from the
following:
3.1.2 Savings realized from the current year specific budget of the agency
under the General Appropriations Act (GAA).
197
Issued on 29 November 2007.
225
Guidelines on the Grant of Honoraria to Government Personnel Appendix 7
Involved in Government Procurement
3.1.4 In the case of LGUs, savings from the local budgets approved by their
respective Sanggunian subject to the pertinent provisions of R.A. 7160
(Local Government Code of 1991).
3.3 In the use of savings, priority shall be given to augmentation of the amounts
set aside for mandatory expenditure items provided under the General
Provisions of the General Appropriations Act (GAA). It is understood that the
use of agency savings for payment of honoraria and overtime pay for
procurement activities shall be made only after satisfying said mandatory
expenditure items.
All other provisions of BC 2004-5A not consistent with this Circular shall remain in
force and effect.
5.0 Effectivity
226
Guidelines on the Sale of Bidding Documents Appendix 8
APPENDIX 8
GUIDELINES ON THE SALE OF BIDDING DOCUMENTS
2.0 PURPOSE
These guidelines are formulated to provide standard rates for the sale of bidding
documents to rationalize the fees primarily to regulate its price and to lessen the
exercise of discretion of procuring entities so as not to discourage market
participation and competition.
These guidelines shall apply to the national government, its branches, constitutional
offices, departments, bureaus, offices and agencies, including state universities and
colleges, government-owned and/or -controlled corporations, government financial
institutions, and local government units.
4.1. Procuring entities shall make the bidding documents available on the same
date the advertisement and/or posting of the Invitation to Bid was made
pursuant to Section 17.3 of the IRR of RA 9184.
4.2. As required in Section 21.1(g) 198 of the IRR of RA 9184, the price of the
bidding documents must be included in the Invitation to Bid/Request for
Expression of Interest in order to inform all prospective bidders of the cost of
its acquisition.
4.3. The BAC shall issue the bidding documents to any prospective bidder upon
payment of the standard rate of the bidding documents.
4.4. The standard rate for the sale of bidding documents shall be based on the
fixed rate on a fixed range approach and shall be applicable in the
procurement of goods, consulting services, and the contracting for
infrastructure projects by the procuring entity, whether procured by way of
public bidding or any of the alternative methods of procurement that utilize
processes and procedures in competitive bidding.
4.5. Procuring entities are proscribed to adopt any internal rule or practice that
establish fees that are inconsistent or beyond the standard rate for the sale of
bidding documents set forth in these guidelines.
198
As amended by the 2016 Revised IRR of R.A. No. 9184.
227
Guidelines on the Sale of Bidding Documents Appendix 8
4.6. The proceeds from the sale of the bidding documents shall continue to be
used for the payment of honoraria as provided for in Budget Circular No.
2004-5A, dated 7 October 2005, or to augment the funds for the procuring
entity’s legal assistance and indemnification package as provided in the
Guidelines for Legal Assistance and Indemnification of Bids and Awards
Committee Members and its Support Staff.
The cost of bidding documents shall correspond to the ABC range as indicated in the
table below. This shall be the maximum amount of fee that procuring entities can set
for the acquisition of bidding documents.
Any other guidelines, administrative order, office order, rule or regulation and/or
parts thereof contrary to or inconsistent with the provisions of these Guidelines is
hereby repealed, modified, or amended accordingly.
7.0 EFFECTIVITY
These guidelines shall take effect fifteen (15) days after publication in the Official
Gazette or in a newspaper of general nationwide circulation and upon filing with the
University of the Philippines Law Center of three (3) certified copies of these
guidelines. 199
199
Issued through GPPB Resolution 04-2012, dated 24 February 2012, and published in The Daily Tribune on 20 August 2012.
228
Guidelines in the Determination of Eligibility of Foreign Appendix 9
Suppliers, Contractors, and Consultants to Participate in
Government Procurement Projects
APPENDIX 9
GUIDELINES IN THE DETERMINATION OF ELIGIBLITY OF FOREIGN SUPPLIERS,
CONTRACTORS, AND CONSULTANTS TO PARTICIPATE IN GOVERNMENT
PROCUREMENT PROJECTS
In line with the economic policies enunciated in the Constitution, particularly on the
promotion of Filipino labor, domestic materials, and locally produced goods, Republic
Act No. 9184, in consonance with Republic Act No. 5183, adopts as general principle
the preference for Filipino nationals in the award of Government’s procurement
contracts.
However, in light of the principles of economic exchange and expansion of trade and
exports with other countries on the basis of equality and reciprocity, with due regard
to the government’s initiatives in the prohibition and/or regulation of monopolies and
other situations that restrain trade and fair competition, qualified foreign nationals
may be eligible to participate in the public procurement of goods, infrastructure
projects and consultancy services; provided, however, that provisions on domestic
preference, Most-Favored Nation (MFN) status and non-discrimination treatments
under applicable laws and treaties are complied with.
For purposes of these guidelines, the following terms or words and phrases
shall be defined as follows:
200
Apostille Handbook, A Handbook on the Practical Operation of the Apostille Convention, p. xviii. Netherlands: The Hague
Conference on Private International Permanent Bureau.
201
As amended by GPPB Resolution No. 13-2019, dated 23 May 2019, published in the Official Gazette on 26 August 2019.
229
Guidelines in the Determination of Eligibility of Foreign Appendix 9
Suppliers, Contractors, and Consultants to Participate in
Government Procurement Projects
3.2. Contracting Party refers to a State that has joined the Apostille Convention, 202
whether or not the Convention has entered into force for that State. 203 (n)
3.8. Local Supplier refers to any citizen of the Philippines, or any corporate body
or commercial company duly organized and registered under the laws of the
Philippines where Filipino ownership or interest is at least sixty percent
(60%), habitually established in business and engaged in the manufacture or
sale of the merchandise or performance of the general services covered by
his bid.
4.1.1. When the goods sought to be procured are not available from local
suppliers, subject to Item 5 herein; or
202
Apostille Handbook, A Handbook on the Practical Operation of the Apostille Convention, p. xviii. Netherlands: The Hague
Conference on Private International Permanent Bureau.
203
As amended by GPPB Resolution No. 13-2019, dated 23 May 2019, published in the Official Gazette on 26 August 2019.
204
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
205
Ibid.
230
Guidelines in the Determination of Eligibility of Foreign Appendix 9
Suppliers, Contractors, and Consultants to Participate in
Government Procurement Projects
5.1. In the procurement of goods not available from Local Suppliers, the procuring
entity may invite foreign suppliers, manufacturers and/or distributors to
participate in the procurement process.
5.2. For purposes of these guidelines, goods are not available from Local Suppliers
when, at any time before advertisement for their procurement, it is
determined that no Local Supplier is capable to supply the required goods to
the Government, in which case, foreign suppliers, manufacturers and/or
distributors may be invited to participate in the bidding. Therefore, the head
of the procuring entity or his duly authorized representative shall certify that,
after diligent market research conducted by the procuring entity, the goods
sought to be procured are not available from Local Suppliers. In addition,
when applicable, the procuring entity shall secure a certification from the
appropriate Government regulatory body, such as, but not limited to, the
Bureau of Product Standards of the Department of Trade and Industry (DTI)
for electrical products, mechanical/building & construction materials,
chemicals, foods and other consumer products, and the Bureau of Food and
Drugs of the Department of Health (DOH) for drugs, medicine, and other
206
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
207
As amended by the 2016 Revised IRR of R.A. No. 9184.
208
Ibid.
209
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
210
Ibid.
231
Guidelines in the Determination of Eligibility of Foreign Appendix 9
Suppliers, Contractors, and Consultants to Participate in
Government Procurement Projects
related medical devices, that based on its available records, the goods sought
to be procured are not available from Local Suppliers.
5.4. In the case mentioned in Item 5.3, for purposes of inviting foreign suppliers,
the bidding requirements and conditions, as advertised, shall not be modified
or changed. Otherwise, modifications and/or changes in the requirements
and conditions of the bidding shall disallow the procuring entity to resort to
invitation of foreign bidders.
6.1. In cases where the procuring entity intends to procure goods from an
exclusive local manufacturer, supplier, distributor, or dealer through direct
contracting under Section 50 (c) of the IRR, 212 when said method is
recommended by the BAC and approved by the Head of the Procuring Entity,
and reflected in the approved Annual Procurement Plan, it shall, before
commencing any negotiations with a local supplier, post through the website
of the procuring entity, if any, and in the Philippine Government Electronic
Procurement System (PhilGEPS), an invitation to foreign manufacturers to
submit a manifestation of its intention to participate. Should any foreign
manufacturer submit such manifestation within the period prescribed in the
invitation, the procuring entity shall commence the conduct of public bidding.
If no foreign manufacturer submits such manifestation within the said period,
the procuring entity may proceed with the intended procurement through
direct contracting with the said exclusive local manufacturer, supplier,
distributor, or dealer.
211
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
212
Ibid.
232
Guidelines in the Determination of Eligibility of Foreign Appendix 9
Suppliers, Contractors, and Consultants to Participate in
Government Procurement Projects
7.3. The said certification 214 shall be validated during post-qualification of bidders.
The TWG shall verify or validate the apostille through the Competent Authority's e-
register or by phone or electronic mail. The Contact information for the Competent
Authorities is available using the link below:
9.0 EFFECTIVITY
These Guidelines or any amendments hereto shall take effect fifteen (15) days after
publication in the Official Gazette or in a newspaper of general nationwide circulation
and upon filing with the University of the Philippines Law Center of three (3) certified
copies of these guidelines. 217
213
As amended by GPPB Resolution No. 34-2014, dated 16 December 2014, published in the Manila Times on 15 May 2015.
214
Ibid.
215
As of May 14, 2019: Austria, Finland, Germany and Greece.
216
As amended by GPPB Resolution No. 13-2019, dated 23 May 2019, published in the Official Gazette on 26 August 2019.
217
Issued through GPPB Resolution 018-2005, dated 12 September 2005, and published in the Official Gazette on 27 March
2006.
233
Guidelines on the Use of Bid Securing Declaration Appendix 10
APPENDIX 10
GUIDELINES ON THE USE OF BID SECURING DECLARATION
These Guidelines shall govern the use of Bid Securing Declaration as an additional
form of bid security under the Implementing Rules and Regulations (IRR) of Republic
Act No. 9184, otherwise known as “The Government Procurement Reform Act”.
These guidelines shall apply to all branches, constitutional commissions and offices,
agencies, departments, bureaus, offices, and instrumentalities of the Government,
including government-owned and/or -controlled corporations (“GOCCs”), government
financial institutions (“GFIs”), state universities and colleges (“SUCs”), and local
government units (“LGUs”).
The bidder shall have the option to use a Bid Securing Declaration or any other bid
security in the form and amount enumerated under Section 27.2 of the IRR.
3.0 DEFINITION
3.2. The Bid Securing Declaration shall comply with the standard format attached
hereto as Annex “A” and shall be submitted to the procuring entity in the
manner prescribed under Sections 25 and 27 of the IRR.
4.1. The Bid Securing Declaration shall be valid for a reasonable period determined
by the Head of the Procuring Entity concerned and indicated in the bidding
documents, which in no case shall exceed one hundred twenty (120) calendar
days from the date of the opening of bids, unless duly extended by the bidder
upon the request of the Head of the Procuring Entity.
4.2. The Bid Securing Declaration shall automatically expire in the following
instances:
234
Guidelines on the Use of Bid Securing Declaration Appendix 10
The Bid Securing Declaration shall be enforced when the bidder commits any act
resulting to the forfeiture of bid security under Sections 23.1(b), 34.2, 40.1 and 69.1,
except 69.1(f), of the IRR of RA 9184. 218
6.0 PENALTIES
Commission of any of the acts mentioned in Section 5 of these Guidelines shall merit
the following sanctions:
a) Penalty of automatic disqualification for two (2) years from bidding for any
procurement contract with any Procuring Entity, upon receipt of the Blacklisting
Order; 219
Two percent (2%) of the Approved Budget for the Contract (ABC) or the
difference between the evaluated bid prices of the bidder with the Lowest
Calculated/Highest Rated Bid and the bidder with the next Lowest
Calculated/Highest Rated Bid, and so on, whichever is higher. 220
As regards, the bidder with the Lowest Calculated/Highest Rated Bid, the
amount shall be two percent (2%) of the ABC or the difference between
the evaluated bid price and the ABC, whichever is higher. 221
Two percent (2%) of the ABC or the difference between the evaluated bid
price and the ABC, whichever is higher. 222
218
Issued through GPPB Resolution 015-2014, dated 20 June 2014, and published in the Manila Times on 27 November 2017.
219
As amended by GPPB Resolution 16-2020, dated 16 September 2020, published in the Philippine Star on 26 September 2020
220
Ibid.
221
Ibid.
222
Ibid.
223
Ibid.
224
Ibid.
235
Guidelines on the Use of Bid Securing Declaration Appendix 10
(iv) The bidder shall pay the above-mentioned fine within fifteen (15) days
from receipt of the written demand by the procuring entity as a result of
the violation of the conditions in the Bid Securing Declaration. 225
(v) The imposition of the foregoing fine is without prejudice to other legal
action the government may undertake against the erring bidder. 226
7.1. The procuring entity shall immediately issue the blacklisting order upon
determination of the grounds for enforcement of the Bid Securing Declaration
provided in Section 5 hereof.
7.2. Only in cases where the notice of award is not in conformity with the Bidding
Documents may the blacklisted bidder file a motion for reconsideration with the
Head of the Procuring Entity within three (3) calendar days from receipt of the
blacklisting order.
7.3. The blacklisted bidder shall only be delisted upon the expiration of the period of
penalty and payment of the fine.
8.0 EFFECTIVITY
These Guidelines shall take effect immediately after publication in the Official Gazette
or a newspaper of general nationwide circulation and upon filing with the University
of the Philippines Law Center of three (3) certified copies of these guidelines. 227
225
Ibid.
226
Ibid.
227
Issued through GPPB Resolution 03-2012, dated 27 January 2012, and published in The Daily Tribune on 20 August 2012.
236
Tie-Breaking Method Appendix 11
APPENDIX 11
GPPB CIRCULAR 06-2005
TIE-BREAKING METHOD
1.0 Purpose
This Circular 228 is issued to advise government agencies on how to resolve cases
where an occurrence of a tie among bidders takes place, i.e., two or more of the
bidders are determined and declared as the Lowest Calculated and Responsive
Bidder (LCRB), for the procurement of goods and infrastructure projects, or the
Highest Rated and Responsive Bidder (HRRB) for the procurement of consulting
services.
2.0 Coverage
3.2 Procuring entities are hereby required to identify at the onset of the bidding
process, and thereafter include in the bidding documents as instruction or a
matter of information to prospective bidders, a ready and clear measure to be
used in the event two or more of the bidders have been post-qualified as
LCRB or HRRB. In all cases, the measure determined by the procuring entity
shall be non-discretionary and non-discriminatory such that the same is based
on sheer luck or chance. The procuring entity may use “draw lots” or similar
methods of chance.
3.3 However, in lieu of the pre-determined criteria set and declared in the bidding
documents, the procuring entity may opt to bring the concerned bidders to
agree on a better selection criteria which should also be non-
discretionary/non-discriminatory and is similarly based on sheer luck or
chance.
228
Issued on 05 August 2005.
237
Guidelines on Pre-Selection Procedure in the Conduct of Appendix 12
Limited Source Bidding
APPENDIX 12
GUIDELINES AMENDING THE PRE-SELECTION PROCEDURE IN THE CONDUCT OF
LIMITED SOURCE BIDDING UNDER GPPB RESOLUTION 05-2011
2.0 PURPOSE
These guidelines are formulated to provide the procedure for the pre-selection of
suppliers or consultants in the use of Limited Source Bidding as an alternative
method of procurement of goods and consulting services pursuant to Section 49 of
R.A. 9184 and its IRR.
4.0 GUIDELINES
4.1. Upon determination that a procurement activity may be done through Limited
Source Bidding, the procuring entity, through the Bids and Awards Committee
229
Section 48 of the revised IRR of R.A. No. 9184.
230
Section 49.1 of the revised IRR of R.A. No. 9184.
238
Guidelines on Pre-Selection Procedure in the Conduct of Appendix 12
Limited Source Bidding
4.2 In the event that there is a relevant government authority, but no list exists,
the procuring entity shall request the identified relevant government authority
for the issuance of the list. The relevant government authority concerned
shall not unduly and unreasonably delay the issuance of such list. In case of
non-issuance by the relevant government authority of the list, the procuring
entity shall resort to open competitive bidding in its selection of supplier or
consultant.
4.3 In the event that no relevant government authority exists, and/or the
procuring entity represents that it is the relevant government authority, it
may prepare a self-generated list of suppliers or consultants, with known
experience and proven capability on the requirements of the particular
contract; Provided, that it establishes, attests to such fact, and confirms that
it has the expertise on the subject matter of procurement by virtue of its
mandate and nature of its functions and operations; Provided, further, that in
the event that the procuring entity cannot establish its expertise on the
subject matter of procurement within the purview of Section 49.2 of the IRR,
the procuring entity shall resort to open competitive bidding in its selection of
supplier or consultant.
4.4 In preparing the pre-selected list, the BAC, possibly with the assistance of the
Technical Working Group (TWG), shall adopt a set of criteria to be used as
basis in evaluating the capability of the entities. Said criteria shall take into
consideration the following characteristics of the supplier/consultant:
c) Financial position.
4.5 The BAC shall evaluate and submit the recommended pre-selected list to the
head of the procuring entity (HOPE) for approval. The pre-selected list shall
include (i) the technical specifications/terms of reference of the project, and
(ii) the specific criteria used by the procuring entity for the evaluation of the
preselected suppliers or consultants.
4.6 Upon approval, the HOPE shall transmit the pre-selected list to the GPPB in
compliance with Section 49.2 of the IRR of RA 9184. The list must be
accompanied with a certification from the HOPE: (i) justifying the recourse to
239
Guidelines on Pre-Selection Procedure in the Conduct of Appendix 12
Limited Source Bidding
Limited Source Bidding, (ii) verifying the compliance with the criteria
previously set; and (iii) certifying that the pre-selected list is a list of known
suppliers or consultants where resort to public bidding will not likely result in
any additional suppliers or consultants participating in the bidding.
4.7 The GPPB-TSO shall acknowledge receipt of the pre-selected list and shall
post the list in the GPPB or PhilGEPS website for the purpose of transparency.
4.8 Pursuant to Section 49.4, the procuring entity shall post the procurement
opportunity to be undertaken through Limited Source Bidding in the PhilGEPS
website, website of the procuring entity concerned, if available, and at any
conspicuous place reserved for this purpose in the premises of the procuring
entity concerned for seven (7) calendar days, upon receipt of said
acknowledgment letter.
Any other guidelines, administrative order, office order, rule or regulation and/or
parts thereof contrary to or inconsistent with the provisions of these Guidelines are
hereby repealed, modified or amended accordingly.
7.0 EFFECTIVITY
These Guidelines shall take effect fifteen (15) days after its publication in the Official
Gazette or in a newspaper of general nationwide circulation and upon filing with the
University of the Philippines Law Center of three (3) certified copies of these
guidelines. 232
231
As amended by the 2016 Revised IRR of R.A. No. 9184.
232
Issued through GPPB Resolution 06-2012, dated 30 March 2012, and published in The Daily Tribune on 20 August 2012.
240
Guidelines on Implementation of Infrastructure Projects Appendix 13
Undertaken by the AFP Corps of Engineers
APPENDIX 13
GUIDELINES ON IMPLEMENTATION OF INFRASTRUCTURE PROJECTS
UNDERTAKEN BY THE AFP CORPS OF ENGINEERS
The Armed Forces of the Philippines Corps of Engineers (AFPCOE), being an integral
part of the Government, has the capability to undertake infrastructure projects. As
such, it is the policy of the Government to engage the services of the AFPCOE in
directly implementing projects as provided in these guidelines.
These guidelines shall streamline and provide rules governing the implementation of
infrastructure projects undertaken by the AFPCOE.
3.1 End-User Agency – The agency that is the beneficiary of the project or
source of funds of the project to be implemented by the AFPCOE.
3.2 Implementing Unit – The AFPCOE unit tasked to undertake the project as
covered by a Construction Directive issued by the AFP Chief of Engineers or the
Chief Engineers of the major services, namely: Army, Navy, and Air Force.
3.3 Job Order – The hiring of laborers for piece work or intermittent job of short
duration not exceeding six (6) months and pay is on a daily or hourly basis.
The Implementing Unit may recruit workers from the locality and directly hire
them to provide the required labor for the project being undertaken, subject to
applicable laws, rules and regulations. The Implementing Unit prepares a
payroll that serves as the basis for the payment of wages to the workers.
3.4 “Pakyaw” system – The system of hiring laborers where the Implementing
Unit invites, through appropriate procurement procedures, “pakyaw” groups to
submit price quotations for the labor component required for a specified piece
of work. The “pakyaw” groups shall comprise a group of laborers residing
within the vicinity of the project site, and shall not be a regular licensed
contractor.
241
Guidelines on Implementation of Infrastructure Projects Appendix 13
Undertaken by the AFP Corps of Engineers
4.2. End-User Agency infrastructure projects in high security risk areas – Projects
funded by other government agencies and covered by a Memorandum of
Agreement between them and the DND-AFP, to be implemented by the
AFPCOE through funds transferred from the end-user agency to the DND-AFP.
These include, but are not limited to, the construction and rehabilitation of
roads, bridges, school buildings, housing and resettlement sites, irrigation and
electrification projects and other vital facilities and utilities. However, these
projects may only be undertaken by the AFPCOE in areas which are considered
as high security risk areas or in areas with potential conflict or peace and order
problem, as determined by the authorized officials of the DND/AFP.
4.3. Special projects - Projects categorized as listed below. The project funds shall
be transferred to the DND/AFP prior to the implementation of the project
subject to existing laws and regulations, and guidelines that shall be formulated
by the Secretary of National Defense (SND).
5.2 End-User Agency may only request AFPCOE to implement projects and
transfer funds to it if the End-User Agency has no proficiency to conduct the
procurement, or no technical capability to undertake the project on its own,
and only if the project is located in a high security risk area or in areas with
242
Guidelines on Implementation of Infrastructure Projects Appendix 13
Undertaken by the AFP Corps of Engineers
5.3 The SND or his duly authorized representative shall approve projects
undertaken by administration, in accordance with the provisions of Section
23.4 233 of the Implementing Rules and Regulations (IRR) 234 of Republic Act
9184 (R.A. 9184). If the end-user is another government entity, the Chief of
Engineers of the AFP or the Engineering Brigade Commander concerned and
the Head of the End-User Agency or his duly authorized representative shall
enter into a Memorandum of Agreement (MOA), subject to the approval of
the AFP Chief-of-Staff and the SND or his duly authorized representative.
6.1 The approved MOA or the Memorandum shall be the basis for the transfer of
funds from the End-User Agency to the GHQ-AFP. The funds shall be taken up
in the Trust Account for Inter-Agency Transferred Funds for Infrastructure,
which will be set up in the books of accounts of the GHQ-AFP. The GHQ-AFP
shall release the funds and corresponding Cash Cover to the Implementing Unit
subject to the conditions herein specified.
6.2 Liquidation for funds transferred shall be the responsibility of the Implementing
Unit, subject to existing COA rules and regulations.
The budget for the project may include a provision for Architectural and Engineering
(A&E), as well as Administration and Supervision (A&S) expenses, as necessary.
A&E expenses shall be used to support the preparation of plans, specifications,
estimates and other documents related to and necessary for the commencement of
the project. A&S expenses, on the other hand, shall be used to support the project
management requirements of the unit, including, but not limited to, material testing
and quality control, travel for project inspection, and overhead expenses. The SND
shall issue guidelines to determine the appropriate amount of A&E as well as A&S
expenses. For projects funded by other agencies, however, A&E expenses shall not
exceed three percent (3%) of the project cost, and A&S expenses shall not exceed
three percent (3%) of the project cost, to be supported by the approved program of
work in the MOA.
8.1 Subject to the agreement of the DND-AFP and the End-User Agency, either the
DND BAC or AFP BAC, or End-User Agency BAC shall handle all procurement of
equipment, labor, supplies, materials, consultancy services and other
requirements of the AFPCOE in the implementation of its mandate. In case the
End-User Agency is responsible for the procurement of construction supplies
233
As amended by the 2016 Revised IRR of R.A. No. 9184.
234
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
243
Guidelines on Implementation of Infrastructure Projects Appendix 13
Undertaken by the AFP Corps of Engineers
and materials, the Implementing Unit shall be responsible only for hiring of
labor, provision of equipment, and project management.
8.3 The Implementing Unit may hire additional labor to augment their organic
personnel, if necessary; Provided, however, that the civilian labor component
for the project shall not be more than sixty percent (60%), and, as far as
practicable, shall be sourced from the project locality. The AFPCOE shall
ensure that unskilled laborers hired are paid the minimum wage applicable to
the area, and that semi-skilled and skilled workers are paid wages not
exceeding the prevailing market rates in the area. In hiring the laborers and
workers, the Implementing Unit may adopt either the direct hiring system or
the “pakyaw” system. In the case of “pakyaw” system, Section 3 of the GPPB
Guidelines for the Implementation of Projects Undertaken “By Administration”
or Force Account shall be followed.
8.4 The Implementing Unit may likewise lease supplemental equipment and tools
as may be needed, chargeable against project funds, in accordance with
existing laws, rules and regulations on the lease of equipment. Furthermore,
the same should be provided for in the approved program of work. The
AFPCOE may also enter into lease contracts with option to purchase, if
warranted.
10.0 EFFECTIVITY
10.1 These Guidelines or any amendments thereto shall take effect fifteen (15)
days after publication in the Official Gazette or a newspaper of general
circulation and upon filing with the University of the Philippines Law Center of
three (3) certified copies of these guidelines. 236
235
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
236
Issued through GPPB Resolution 09-2005, dated 28 April 2005, and published in the Official Gazette on 13 June 2005.
244
Guidelines on NGO Participation in Public Procurement Appendix 14
APPENDIX 14
GUIDELINES ON NON-GOVERNMENTAL ORGANIZATION PARTICIPATION IN
PUBLIC PROCUREMENT
Section 23, Article II of the Philippine Constitution prescribes that the State shall
encourage the participation of Non-Governmental Organizations (NGOs), community-
based, or sectoral organizations in the promotion of the welfare of the nation.
As a general rule, all procurement shall be done through competitive public bidding.
However, when an appropriation law earmarks an amount for projects to be
specifically contracted out to NGOs, it is the intent of Congress to give due
preference to NGOs.
3.0 PURPOSE
3.1 If the procuring entity decides to conduct public bidding, to prescribe the
rules and procedures that shall govern public bidding limited to NGOs; and
3.2 If the procuring entity decides to enter into negotiated procurement under
Section 53.11 of the Implementing Rules and Regulations (IRR) 237 of Republic
Act No. 9184 (R.A. 9184), to provide the necessary steps and procedures in
the selection of the NGO.
245
Guidelines on NGO Participation in Public Procurement Appendix 14
4.3 The selected NGO shall keep and maintain separate savings account and
accounting records in accordance with generally accepted accounting rules
and principles, subject to visitorial audit and examination by the procuring
entity or the Commission on Audit.
4.4 Unless otherwise provided by law, technical specifications prescribed for the
School Building Program under the Department of Education shall be the
same as those prescribed by the Department of Public Works and Highways.
4.5 For the erasure of doubt, the NGO, whether selected through public bidding
or negotiated procurement, shall be required to post a performance security
in accordance with Section 39 of the IRR of R.A. 9184 and a warranty in
accordance with Section 62 of the IRR of R.A. 9184.
5.1 If the procuring entity decides to select the NGO through competitive public
bidding, it shall advertise and post Invitation to Bid/Request for Expression of
Interest in accordance with Section 21.2.1 of the IRR. 239
5.2 In addition to the information enumerated under Section 21.1 of the IRR, the
Invitation to Bid/Request for Expression of Interest 240 shall also include (i) the
legal basis or appropriation law or ordinance which earmarks a specific
amount or project to NGOs; and (ii) a statement that the project shall be
limited to NGOs.
239
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
240
Ibid.
241
Ibid.
242
Ibid. (As amended by the 2016 Revised IRR of R.A. No. 9184.)
246
Guidelines on NGO Participation in Public Procurement Appendix 14
5.4 Other stages of the bidding process shall be observed in accordance with the
relevant provisions of the IRR 244 of R.A. 9184.
6.2 After the required posting period, the procuring entity shall invite at least
three (3) prospective NGOs to submit sealed price quotations or password-
protected price quotations in compressed archive folders, in case of electronic
submission of price quotations. 246
6.3 The procuring entity shall likewise require submission of the complete project
proposal together with supporting feasibility studies, designs, plans,
blueprints, budgets and charts.
6.4 On the date specified in the notice, the procuring entity shall open the price
quotations and determine the Lowest Calculated Bid (LCB). For electronic
submission of price quotations, the passwords for accessing the same will be
disclosed on a specified date by the prospective NGOs to the Procuring Entity
either in person or face-to-face through videoconferencing, webcasting or
similar technology and the Procuring Entity shall determine the Lowest
Calculated Bid (LCB). 247 Consistent with the nature of an NGO, no profit
should be included in its bid. Thus, the procuring entity shall ensure that the
LCB does not include any profit margin or mark-up.
6.5 After determination that the proposal submitted by the NGO with the Lowest
Calculated Bid complies with the technical requirements of the project, the
procuring entity shall require submission of the following eligibility documents
to ensure that said NGO is technically, legally, and financially capable to
undertake the proposed project:
Legal Documents
243
Ibid. (As amended by the 2016 Revised IRR of R.A. No. 9184.)
244
Ibid.
245
Ibid.
246
As amended by GPPB Resolution No. 09-2020, dated 7 May 2020, published in the Philippine Daily Inquirer on 15 May 2020.
247
Ibid.
248
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
247
Guidelines on NGO Participation in Public Procurement Appendix 14
f) Latest tax returns and tax clearance pursuant to Executive Order No.
398, s. of 2005;
Technical Documents
h.3 Availability of equipment that it owns, has under lease, and/or has
under purchase agreements that may be used for construction
contracts, provided that ownership of equipment is not a requisite
for eligibility.
Financial Documents
i) Audited financial statements for the past three (3) years, stamped
“received” by the BIR or its duly accredited and authorized institutions,
showing, among others, its total and current assets and liabilities. 251
6.6 After submission of the eligibility documents, the procuring entity shall enter
into a Memorandum of Agreement (MOA) with the NGO which prescribes:
d) timelines, such as, but not limited to, date of completion, periodic
inspection or evaluation schedule, and reporting
249
Ibid.
250
Ibid. (As amended by the 2016 Revised IRR of R.A. No. 9184.)
251
Ibid.
248
Guidelines on NGO Participation in Public Procurement Appendix 14
6.7 To guarantee its faithful performance, the selected NGO shall post a
Performance Security upon the signing of the MOA in accordance with Section
39 of the IRR. 252
6.8 After performance of its obligations under the MOA, the selected NGO shall
likewise submit a warranty security in accordance with Section 62 of the IRR.
7.1 Payment to the NGO shall be made on a staggered basis. As a general rule,
the selected NGO shall not receive additional payment unless
reporting/liquidation requirements of the previous payment shall have been
complied with.
7.2 Release of funds to the NGO shall follow the payment schedule prescribed by
the MOA or contract.
7.4 The selected NGO shall return any amount not utilized upon completion of
the project.
8.0 EFFECTIVITY
These guidelines shall take effect fifteen (15) days after its publication in the Official
Gazette or in a newspaper of general nationwide circulation. 253
252
Ibid.
253
Issued through GPPB Resolution 012-2007, dated 29 June 2007, and published in the Manila Times on 26 October 2007.
249
Guidelines for Contract Price Escalation Appendix 15
APPENDIX 15
REVISED GUIDELINES FOR CONTRACT PRICE ESCALATION
1.1. These Guidelines shall govern requests for price escalation during
implementation of contracts for the procurement of goods and infrastructure
projects under extraordinary circumstances pursuant to and in accordance
with Section 61 of Republic Act No. 9184 (R.A. 9184), otherwise known as
“Government Procurement Reform Act” and its Implementing Rules and
Regulations (IRR). 254 No contract price escalation for consulting services shall
be allowed.
1.2. These Guidelines shall apply to all branches, constitutional commissions and
offices, agencies, departments, bureaus, offices and instrumentalities of the
Government, including government-owned and/or controlled corporations
(GOCCs), government financial institutions (GFIs), state universities and
colleges (SUCs), and local government units (LGUs).
2.0 PURPOSE
2.1. To prescribe the rules and procedures in the approval by the Government
Procurement Policy Board (GPPB) of requests for price escalation;
2.2. To ensure that the task mandated by Section 61 of R.A. 9184 shall be
undertaken competently, objectively and expeditiously by the GPPB and the
National Economic and Development Authority (NEDA); and
2.3. To establish the legal and technical parameters for an objective determination
of events that will result to extraordinary circumstances in accordance with
the Civil Code of the Philippines.
3.1. Price Escalation. Refers to an increase in the contract price during contract
implementation on the basis of the existence of “extraordinary circumstances”
as determined by the NEDA and upon prior approval of the GPPB.
254
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
250
Guidelines for Contract Price Escalation Appendix 15
these Guidelines, and such decrease or increase could not have been
reasonably foreseen or was manifestly beyond the contemplation of the
parties at the time of the establishment of the obligation.
3.5. W P I . Refers to the Wholesale Price Index, which measures the monthly
changes in the general price level of commodities, usually in large quantities,
that flow into the wholesale trading system.
3.6. CPI . Refers to the Consumer Price Index, which measures the monthly
changes in the average retail prices of goods and services commonly
purchased by a particular group of people in a particular area.
3.7. PP I . Refers to the Producer Price Index, which measures the average
change in the unit price of a commodity as it leaves the establishment of the
producer.
For purposes of these Guidelines, the term “extraordinary circumstances” shall refer
to the following articles of the Civil Code of the Philippines:
a. Typhoons;
b. Thunderstorms;
c. Flooding of lowly areas; and
d. Vehicular accidents;
(iii) The event must be such as to render it difficult but not impossible for
the supplier or contractor to fulfill his obligation in a normal manner or
within the contemplation of the parties;
251
Guidelines for Contract Price Escalation Appendix 15
(v) The allowance for price escalation should an ordinary fortuitous event
occur is stipulated by the parties or the nature of the obligation
requires the assumption of risk.
a. Fire;
b. War;
c. Pestilence;
d. Unusual flood;
e. Locusts; and
f. Earthquake;
Provided that the circumstances before, during and after the event shall be
taken into consideration.
In the review and approval of a request for price escalation, the requesting procuring
entity shall comply with the following conditions before the same can be acted upon:
5.1. Endorsement. The head of the procuring entity concerned shall endorse the
request for price escalation to the NEDA, through its Director-General,
accompanied by the following documents:
a. A certification from the head of the procuring entity stating that the
request for price escalation is justified in accordance with R.A. 9184, its
IRR, and these Guidelines;
252
Guidelines for Contract Price Escalation Appendix 15
g. Data on the price indices of the materials or goods, including the source
of data used in the detailed computation of the proposed price
escalation as referred to in item (d) above, covering a historical thirty
(30)-month period reckoned from the date of bid opening; and
5.2. Two-Stage Review Process. The review process shall commence only after
the NEDA has acknowledged the completeness of the request in accordance
with this Section. A request for price escalation shall only be granted if it
satisfies both the First and Second Stage reviews.
5.2.1. First Stage: Legal Parameters. This stage shall establish the legal
basis for extraordinary circumstances that will allow contract price
escalation. The determination shall strictly be in accordance with
any of the extraordinary circumstances mentioned in Section 4 of
these Guidelines.
253
Guidelines for Contract Price Escalation Appendix 15
In case there are no applicable price indices for the item, good, or
component, the applicable general wholesale price index shall be
used.
Where:
254
Guidelines for Contract Price Escalation Appendix 15
5.4. Period and Frequency of Requests for Price Escalation. Requests for price
escalation shall only be made for cost items already incurred by the
contractor/supplier, as supported by official receipts, sales invoices, or other
documentary evidence. No request for price escalation shall be made for
prospective application. Further, price escalation shall only be granted to
those items included in a specific request; Provided further, that requests for
price escalation shall be made not less than six (6) months reckoned from the
date of the effectivity of the contract, and not less than six (6)-month period
thereafter, except for price escalation being requested at the completion of
the contract.
255
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
255
Guidelines for Contract Price Escalation Appendix 15
recommendations to the GPPB for appropriate action. The GPPB shall then
approve/act upon the request for price escalation during one of its meetings,
to be attended by the head of the procuring entity concerned or his duly
authorized representative/s.
Upon completion of the contract, the procuring entity shall calculate the amount of
price escalation supposedly due the contractor/supplier/consultant to consider
likewise any downward movement in prices during the entire contract
implementation period. If the resulting amount of price escalation is lower than the
amount of price escalation already paid, the amount of overpayment shall be
deducted by the procuring entity from the retention money, in case of infrastructure
projects, or the warranty security, in case of goods, on or before its expiration.
7.1. The head of the procuring entity shall not pay any contract price escalation
until after the GPPB has approved the claim.
7.2. The approval by the GPPB of the request for contract price escalation shall in
no way be construed as an approval or validation of any irregularity
committed by the requesting entity during the procurement process.
8.1. In case the project is behind schedule based on the approved Project
Evaluation Review Technique/Critical Path Method (PERT/CPM) network or
schedule, price escalation on the portion of work that should have been, but
was not, actually accomplished within the period shall be based on the
applicable price index for the period in which it should have been
accomplished. Payment of the computed amount shall not be made until said
unaccomplished portion of the work is completed and upon prior approval of
the GPPB and the head of the procuring entity.
8.2. Where advance payment has been made, no price escalation shall be granted
for the following:
The GPPB may amend these Guidelines as may be necessary. Nevertheless, the
GPPB may formulate supplemental guidelines in the form of addenda or annexes for
the review process as stipulated in Section 5.2 hereof without need of amending
these Guidelines.
256
Guidelines for Contract Price Escalation Appendix 15
10.1. Claims for price escalation for contracts completed after the effectivity of
these Guidelines shall be filed within two (2) years from completion of the
contract concerned.
10.2. Claims for price escalation for contracts the Invitation to Apply for Eligibility
and to Bid (IAEB) for which were issued after the effectivity of R.A. 9184 and
completed before the effectivity of these Guidelines shall be filed not later
than two (2) years from the date of effectivity of these Guidelines.
10.3. The thirty (30) – month historical data prescribed in computing for two (2)
standard deviations as provided in Section 5.2.2.a shall apply to price
escalation claims for contracts the IAEB for which were issued after the
effectivity of these Guidelines.
These Guidelines or any amendments thereof shall take effect immediately after
publication in the Official Gazette or a newspaper of general nationwide circulation
and upon filing with the University of the Philippines Law Center of three (3) certified
copies of these Guidelines. 256
256
Published in the Manila Times on 22 October 2008.
257
Guidelines for Contract Price Escalation Appendix 15
The indices listed herein shall be used for the detailed computation and validation of price
escalation for goods
a.1 food;
a.2 beverages and tobacco;
a.3 crude materials except fuel;
a.4 mineral fuels, lubricants and related materials;
a.5 chemicals including animal and vegetable oils and fats;
a.6 manufactured goods classified chiefly by materials;
a.7 machinery and transport equipment; and
a.8 miscellaneous manufactured articles.
c.1 beverage;
c.2 tobacco;
c.3 textile;
c.4 leather products;
c.5 footwear and wearing apparel;
c.6 wood and wood products;
c.7 furniture and fixtures;
c.8 paper and paper products;
c.9 publishing and printing;
c.10 chemical products;
c.11 petroleum products;
c.12 rubber products;
c.13 plastic products;
c.14 non-metallic mineral products;
c.15 miscellaneous non-metallic mineral;
c.16 glass and glass products;
c.17 cement;
c.18 basic metals;
c.19 iron and steel;
c.20 non-ferrous metal;
c.21 fabricated metal products;
c.22 machinery;
c.23 electrical machinery;
c.24 transport equipment; and
c.25 other manufacturing industries.
258
Guidelines for Contract Price Escalation Appendix 15
The fluctuation factor and its application in the parametric formula shall include among
others, any or combination of the following:
K7= 0.15 + 0.02 (Li/Lo) + 0.62 (Bi/Bo) + 0.05 (Fi/Fo) + 0.16 (Ei/Eo)
K9 = 0.15 + 0.01 (Li/Lo) + 0.62 (Ai/Ao) + 0.12 (Bi/Bo) + 0.03 (Fi/Fo) + 0.07
(Ei/Eo)
K10 = 0.15 + 0.02 (Li/Lo) + 0.47 (Ci/Co) + 0.21 (Bi/Bo) + 0.02 (Di/Do) +
0.03 (Fi/Fo) + 0.10 (Ei/Eo)
259
Guidelines for Contract Price Escalation Appendix 15
K11 = 0.15 + 0.06 (Li/Lo) + 0.36 (Ci/Co) + 0.16 (Bi/Bo) + 0.03 (Di/Do) +
0.06 Fi/Fo) + 0.18 (Ei/Eo)
12. Reinforced concrete structures fluctuation factor for bridge, culvert, retaining wall,
bulkhead, piles, precast, parapet wall, railing, footing, columns, supporting slab
and beam
K12 = 0.15 + 0.03 (Li/Lo) + 0.28 (Ci/Co) + 0.13 (Bi/Bo) + 0.03 (Di/Do) +
0.25 (Ri/Ro) + 0.03 (Fi/Fo) + 0.10 (Ei/Eo)
13. Reinforced concrete structures fluctuation factor for headwall, catch basin,
manhole, drop inlet concrete post.
K13 = 0.15 + 0.21 (Li/Lo) + 0.25 (Ci/Co) + 0.03 (Di/Do) + 0.19 (Ri/Ro) +
0.09 (Bi/Bo) + 0.02 (Fi/Fo) + 0.06 (Ei/Eo)
14. Reinforced concrete pipe (RCP) or culvert pipe (RCCP) fluctuation factor
K14 = 0.15 + 0.05 (Li/Lo) + 0.61 (Qi/Qo) + 0.02 (Ci/Co) + 0.01 (Bi/Bo) +
0.04 (Fi/Fo) + 0.12 (Ei/Eo)
K15 = 0.15 + 0.13 (Li/Lo) + 0.69 (Qi/Qo) + 0.02 (Ci/Co) + 0.01 (Bi/Bo)
K16 = 0.15 + 0.03 (Li/Lo) + 0.41 (Ci/Co) + 0.19 (Bi/Bo) + 0.09 (Di/Do) +
0.04 (Fi/Fo) + 0.09 (Ei/Eo)
K17 = 0.15 + 0.18 (Li/Lo) + 0.27 (Ci/Co) + 0.13 (Bi/Bo) + 0.07 (Fi/Fo) +
0.20 (Ei/Eo)
K18 = 0.15 + 0.33 (Li/Lo) + 0.30 (Qi/Qo) + 0.13 (Ci/Co) + 0.04 (Bi/Bo) +
0.01 (Fi/Fo) + 0.04 (Ei/Eo)
K19 = 0.15 + 0.06 (Li/Lo) + 0.67 (Ri/Ro) + 0.04 (Fi/Fo) + 0.08 (Ei/Eo)
K20 = 0.15 + 0.03 (Li/Lo) + 0.71 (Si/So) + 0.03 (Fi/Fo) + 0.08 (Ei/Eo)
260
Guidelines for Contract Price Escalation Appendix 15
K24 = 0.15 + 0.28 (Li/Lo) + 0.48 (Ni/No) + 0.02 (Fi/Fo) + 0.07 (Ei/Eo)
26. Wood structure fluctuation factor for falsework, temporary wood bridge, wood
guardrail
K26 = 0.15 + 0.06 (Li/Lo) + 0.63 (Di/Do) + 0.04 (Fi/Fo) + 0.12 (Ei/Eo)
K27 = 0.15 + 0.15 (Li/Lo) + 0.62 (Di/Do) + 0.02 (Fi/Fo) + 0.06 (Ei/Eo)
K28 = 0.15 + 0.02 (Li/Lo) + 0.78 (Ii/Io) + 0.01 (Fi/Fo) + 0.04 (Ei/Eo)
K29 = 0.15 + 0.03 (Li/Lo) + 0 .69 (Ii/Io) + 0.03 (Fi/Fo) + 0.10 (Ei/Eo)
K30 = 0.15 + 0.02 (Li/Lo) + 0.77 (Ki/Ko) + 0.02 (Fi/Fo) + 0.04 (Ei/Eo)
K31 = 0.15 + 0.07 (Li/Lo) + 0.69 (Ji/Jo) + 0.02 (Fi/Fo) + 0.07 (Ei/Eo)
K32 = 0.15 + 0.04 (Li/Lo) + 0.77 (Ii/Io) + 0.01 (Fi/Fo) + 0.03 (Ei/Eo)
K33 = 0.15 + 0.03 (Li/Lo) + 0.79 (Pi/Po) + 0.01 (Fi/Fo) + 0.02 (Ei/Eo)
261
Guidelines for Contract Price Escalation Appendix 15
K38 = 0.15 + 0.07 (Li/Lo) + 0.03 (Ci/Co) + 0.01 (Bi/Bo) + 0.65 (Xi/Xo) +
0.03 (Fi/Fo) + 0.06 (Ei/Eo)
K39 = 0.15 + 0.12 (Li/Lo) + 0.66 (Xi/Xo) + 0.05 (Ci/Co) + 0.02 (Bi/Bo)
K40 = 0.15 + 0.09 (Li/Lo) + 0.53 (Si/So) + 0.06 (Fi/Fo) + 0.17 (Ei/Eo)
K45 = 0.15 + 0.01 (Li/Lo) + 0.73 (Di/Do) + 0.03 (Fi/Fo) + 0.08 (Ei/Eo)
262
Guidelines for Contract Price Escalation Appendix 15
K48 = 0.15 + 0.01 (Li/Lo) + 0.81 (Ti/To) + 0.01 (Fi/Fo) + 0.02 (Ei/Eo)
K49 = 0.15 + 0.04 (Li/Lo) + 0.79 (Ti/To) + 0.01 (Fi/Fo) + 0.01 (Ei/Eo)
K50 = 0.15 + 0.13 (Li/Lo) + 0.69 (Ti/To) + 0.01 (Fi/Fo) + 0.02 (Ei/Eo)
52. General construction fluctuation factor (for others not covered by any or
combination of the above 51 fluctuation factors)
Where:
263
Guidelines for Contract Price Escalation Appendix 15
For the preceding formula, the following Price Indices shall be used:
General construction price index as published by the National Statistics Office (NSO) or other
appropriate/authorized government agency.
Labor cost index as published by the Department of Labor and Employment. Equipment
index as published by the NSO or other appropriate/authorized government agency.
Asphaltic material price index as published by the NSO or other appropriate/authorized
264
Guidelines for Contract Price Escalation Appendix 15
government agency.
Glass and glazing material price index as published by the NSO or other
appropriate/authorized government agency.
Galvanized and/or cast-iron pipe (Plumbing) material price index as published by the NSO or
other appropriate/authorized government agency.
Polyvinyl chloride pipe (Plumbing) material price index as published by the NSO or other
appropriate/authorized government agency.
Asbestos cement (Plumbing) material price index as published by the NSO or other
appropriate/authorized government agency.
Structural steel material price index as published by the NSO or other appropriate/authorized
government agency.
Exterior electrical material price index as published by the NSO or other
appropriate/authorized government agency.
Electrical fixtures / devices material price index as published by the NSO or other
appropriate/authorized government agency.
Metal product material price index as published by the NSO or other appropriate/authorized
265
Guidelines for Contract Price Escalation Appendix 15
government agency.
Tile work material price index as published by the NSO or other appropriate/authorized
government agency.
In the absence of any price index for a specified adjustable item, the price index of the
nearest related item shall be used.
266
Guidelines for Contract Price Escalation Appendix 15
I. FACTS
1. There is legal basis to claim for price escalation in accordance with Section 4 of these
Guidelines.
2. The work item identified to have been affected by the extraordinary circumstance is
Reinforcing Steel Bars or K19 of Annex B of these Guidelines.
K19 = 0.15 + 0.06 (Li/Lo) + 0.67 (Ri/Ro) + 0.04 (Fi/Fo) + 0.08 (Ei/Eo)
3. The date of bid opening for the subject contract was December 2007 and the
contract was implemented starting January 2008.
4. The six (6) – month period under consideration for contract price escalation is from
January to June 2008.
5. The thirty (30) – month historical data for the components of K19 necessary for
testing compliance with the Technical Parameters under Section 5.2.2 of these
Guidelines is from July 2005 to December 2007 (Please refer to Table 1 of this Annex
for the relevant price indices provided under Annex B of these Guidelines).
The following steps illustrate how to determine whether request for price escalation may
be granted using the 2 Standard Deviation (STDEV) rule under Section 5.2.2.a:
1. Compute the Mean for each component of K19 using the data in Table 1 for the
entire thirty (30) month period (July 2005 to December 2007).
267
Guidelines for Contract Price Escalation Appendix 15
2. Compute the 2 STDEV above Mean (2σ+μ) of each K19 component by adding the
Mean computed under Step 1 to the 2 STDEV. The 2 STDEV is computed by getting
the STDEV of the thirty (30) – month historical data of each K19 component and
multiplying it by 2. 257
3. Establish the K19 Threshold by substituting the values of the 2 STDEV above Mean
computed in Step 2 into the K19 work item formula as follows:
= 447.13
4. Compute the Average Value of each price index for the six (6) – month period
(January to June 2008) under consideration for contract price escalation. (Please
refer to Table 1 of this Annex)
Table 3: Computation for Average Value of Price Index (Jan to Jun 2008)
K19 Component Average Value
Labor (L) 364.8
Reinforcing Steel (R) 625.1
Automotive Fuel (F) 542.1
Equipment (E) 328.7
5. Establish K19 Average by computing the six (6) – month Average Value of the work
item for the period under consideration for price escalation (January to June 2008)
as follows:
K19 Average = 0.15 + 0.06 (Ave. Value)L + 0.67 (Ave. Value)R + 0.04
(Ave. Value)F + 0.08 (Ave. Value)E
257
Computation of the STDEV is easily done using spreadsheet applications such as Apple Numbers, Microsoft Excel, and
OpenOffice.org Calc.
268
Guidelines for Contract Price Escalation Appendix 15
6. To determine whether request for price escalation may be granted, the K19 Average
should be compared to the K19 Threshold. If K19 Average is greater than K19
Threshold, price escalation may be granted; otherwise, the request for price
escalation should be denied.
7. In the above example, K19 Average is greater than K19 Threshold. Therefore, price
escalation may be granted for the period of January to June 2008.
After determining that price escalation may be granted for the period under
consideration, the computation for the amount to be granted is done for each month
of said period.
1. Compute the Monthly Rates of Increase for the period under consideration
(January to June 2008) in accordance with Section 5.2.4.a of these Guidelines as
follows:
K19 June = 0.15 + 0.06 (Li/Lo) + 0.67 (Ri/Ro) + 0.04 (Fi/Fo) + 0.08 (Ei/Eo)
= 0.15 + 0.06 (1.05) + 0.67 (1.31) + 0.04 (1.25) + 0.08 (1.12)
= 1.23
K19 May = 0.15 + 0.06 (Li/Lo) + 0.67 (Ri/Ro) + 0.04 (Fi/Fo) + 0.08 (Ei/Eo)
= 0.15 + 0.06 (1.00) + 0.67 (1.16) + 0.04 (1.11) + 0.08 (1.12)
= 1.12
K19 April = 0.15 + 0.06 (Li/Lo) + 0.67 (Ri/Ro) + 0.04 (Fi/Fo) + 0.08 (Ei/Eo)
= 0.15 + 0.06 (1.00) + 0.67 (1.10) + 0.04 (1.04) + 0.08 (1.12)
= 1.08
K19 Mar = 0.15 + 0.06 (Li/Lo) + 0.67 (Ri/Ro) + 0.04 (Fi/Fo) + 0.08 (Ei/Eo)
= 0.15 + 0.06 (1.00) + 0.67 (1.05) + 0.04 (1.01) + 0.08 (1.12)
= 1.04
K19 Feb = 0.15 + 0.06 (Li/Lo) + 0.67 (Ri/Ro) + 0.04 (Fi/Fo) + 0.08 (Ei/Eo)
= 0.15 + 0.06 (1.00) + 0.67 (1.03) + 0.04 (0.98) + 0.08 (1.12)
= 1.03
K19 Jan = 0.15 + 0.06 (Li/Lo) + 0.67 (Ri/Ro) + 0.04 (Fi/Fo) + 0.08 (Ei/Eo)
= 0.15 + 0.06 (1.00) + 0.67 (1.03) + 0.04 (1.00) + 0.08 (1.12)
= 1.03
2. Compute the Percentage Rate of Increase for the work item for each month of the
period under consideration in accordance with Section 5.3 as follows:
269
Guidelines for Contract Price Escalation Appendix 15
This shows that the Escalated Value of the work item for the months of June, May,
and April is 18%, 7%, and 3%, respectively, higher than the original value of the
work item.
3. Compute the Escalated Value to be granted for the work item by applying the
Percentage Rate of Increase for each month to the monthly billing, which should
be supported by official receipts, sales invoices, and other acceptable documentary
evidence, as follows:
270
Guidelines for Contract Price Escalation Appendix 15
Reinforcing Automotive
Labor Equipment
Period Steel Fuel
(L) (E)
(R) (F)
271
Guidelines on Procurements Involving Foreign-Denominated Appendix 16
Bids, Contract Prices and Payment Using Letters of Credit
APPENDIX 16
GUIDELINES ON PROCUREMENTS INVOLVING FOREIGN-DENOMINATED BIDS,
CONTRACT PRICES AND PAYMENT USING LETTERS OF CREDIT
Pursuant to Section 61 of Republic Act No. 9184 and its counterpart provision in the
Implementing Rules and Regulations (IRR), 258 for the given scope of work in
procurement contracts as awarded, all bid prices shall be considered as fixed prices
and, therefore, not subject to price escalation during contract implementation,
except under extraordinary circumstances. Thus, to ensure that this policy is carried
out, it is required, as a matter of general rule and procedure, that all contracts be
denominated and paid in Philippine currency; except when the procuring entity
agrees that obligations shall be settled in any other currency at the time of payment,
subject to conditions provided for under these guidelines.
3.0 PURPOSE
These guidelines are formulated: (1) to implement the policy on fixed-pricing under
Section 61 of Republic Act No. 9184 (R.A. 9184), otherwise known as “Government
Procurement Reform Act,” (2) to provide procedural details in the submission and
evaluation of bids when the bidders are all-foreign or mixed local and foreign; and
finally, (3) to address situations where, by the use of letters of credit as mode of
payment to manufacturers, suppliers and/or distributors, there is a resulting
increase/decrease of the actual amount of expenditure of the procuring entity
resulting from the appreciation/depreciation of the peso from the day of bid opening
through the time of the opening of LC until the time of its negotiation, including the
accrual of expenses by reason of the opening of letters of credit.
4.1. The procuring entity shall include in the Bidding Documents, as a separate
item in the Schedule of Requirements and in the Special Conditions of
Contract, a provisional sum to cover the possible increase of the actual
amount of expenditure of the procuring entity resulting from the
appreciation/depreciation of the peso from the day of bid opening through
the time of the opening of LC until the time of its negotiation, including the
accrual of expenses by reason of the opening of letters of credit.
258
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
272
Guidelines on Procurements Involving Foreign-Denominated Appendix 16
Bids, Contract Prices and Payment Using Letters of Credit
The same shall revert to the fund of the procuring entity as savings
in case of non-use.
4.2. The face value of the LC shall be determined in accordance with the following
procedures which shall be stated in the bidding documents:
4.2.2. If at the date of LC opening, the said peso equivalent is lower than
the peso amount stated in the contract, the face value of the LC
shall be the full amount of the foreign-denominated portion of the
bid stated in the contract.
4.2.3. If at the date of LC opening, the said peso equivalent is higher than
the peso amount stated in the contract, the face value of the LC
shall be the full amount of the foreign-denominated portion of the
bid stated in the contract, in which case, the provisional sum shall
be used to cover the difference.
4.3. All charges for the opening of the LC and/or incidental expenses thereto (i.e.,
bank commission, documentary stamp tax, cable, etc.) shall be for the
account of the supplier and shall be so stated in the bidding documents.
5.1. All bids may be denominated wholly in local currency or wholly in foreign currency,
which shall be accepted or tradeable by the Bangko Sentral ng Pilipinas, 259 or a
combination thereof; provided, however, that foreign component of bids shall cover
only imported goods as supported by import documents.
5.2. For purposes of bid evaluation and comparison, bids denominated, in whole
or in part, in foreign currency shall be converted to Philippine currency based
on the exchange rate prevailing on the day of the bid opening.
259
As amended by GPPB Resolution No. 15-2020, dated 28 July 2020, published in the Official Gazette on 21 September 2020.
273
Guidelines on Procurements Involving Foreign-Denominated Appendix 16
Bids, Contract Prices and Payment Using Letters of Credit
6.1.3. In case of repeat order under Section 51 of the IRR 262 of R.A. 9184,
the contract price, either in Philippine Peso or in foreign currency,
must be the same as or lower than that in the original contract;
Provided, however, that the price is still the most advantageous to
the Government, after price comparison and verification.
7.1. For procurement projects fully utilizing domestic or foreign 263 funds, where
the goods will be supplied by a foreign supplier, the procuring entity, may
open LCs or similar instruments in favor of such foreign supplier from a
Government Servicing Bank. Payment/s shall be made on the letter of credit
only after the delivery and acceptance of the goods as certified by the
Procuring Entity. 264
7.2. In cases where the procuring entity has to incur additional expenses resulting
from the opening of LC where it assumes the risk of foreign currency
fluctuation from time of LC opening with the issuing bank until it is eventually
negotiated with the foreign negotiating bank in the place of the foreign
supplier, said expenses shall be covered by the provisional sum.
8.0 EFFECTIVITY
These Guidelines or any amendments hereto shall take effect fifteen (15) days after
publication in the Official Gazette or in a newspaper of general nationwide circulation
and upon filing with the University of the Philippines Law Center of three (3) certified
copies of these guidelines. 265
260
Ibid.
261
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
262
Ibid.
263
As amended by GPPB Resolution No. 12-2019, dated 22 April 2019, published in the Official Gazette on 26 August 2019.
264
Ibid.
265
Issued through GPPB Resolution 020-2005, dated 07 October 2005, and published in the Official Gazette on 09 January
2006.
274
Uniform Guidelines for Blacklisting Appendix 17
APPENDIX 17
UNIFORM GUIDELINES FOR BLACKLISTING OF MANUFACTURERS, SUPPLIERS,
DISTRIBUTORS, CONTRACTORS AND CONSULTANTS
1.0 SCOPE
These guidelines shall apply to all branches, constitutional commissions and offices,
agencies, departments, bureaus, offices, and instrumentalities of the Government,
including government-owned and/or controlled corporations (“GOCCs”), government
financial institutions (“GFIs”), state universities and colleges (“SUCs”), and local
government units (“LGUs”).
b.) In case of partnerships, to the partnership itself and its partners; 269 (n)
266
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
267
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Philippine Daily Inquirer on 20
November 2017.
268
Ibid.
269
Ibid.
270
Ibid.
271
Ibid.
275
Uniform Guidelines for Blacklisting Appendix 17
3.2 Aw ard . A written notice from the procuring entity accepting a bid or
proposal.
272
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Philippine Daily Inquirer on 20
November 2017.
273
Ibid.
274
Ibid.
275
Ibid.
276
Ibid.
277
Ibid.
278
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
279
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Official Gazette on 20 November
2017.
276
Uniform Guidelines for Blacklisting Appendix 17
3.10 Offense . A violation under Section 69 of RA 9184 and its IRR in one
procurement project wherein the Procuring Entity has already issued a
Blacklisting Order. 280 (n)
c) Allowing the use of one’s name, 284 or using the name of the name of
another for purpose of public bidding.
h) All other acts that tend to defeat the purpose of the competitive
bidding, such as habitually withdrawing from bidding or submitting late
280
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Official Gazette on 20 November
2017.
281
Ibid.
282
Ibid.
283
Ibid.
284
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
277
Uniform Guidelines for Blacklisting Appendix 17
bids or patently insufficient bids, 285 for at least three (3) times within a
year, except for valid reasons.
iii. Stockpiling in proper places of all materials and removal from the
project site of waste and excess materials, including broken
pavement and excavated debris in accordance with approved
plans and specifications and contract provisions;
285
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
286
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Official Gazette on 20 August
2018.
287
Ibid.
288
Ibid.
278
Uniform Guidelines for Blacklisting Appendix 17
i. Negative slippage of 15% and above within the critical path of the
project due entirely to the fault or negligence of the contractor;
and
289
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Official Gazette on 20 August
2018.
290
Ibid.
279
Uniform Guidelines for Blacklisting Appendix 17
At the option of the procuring entities, a reasonable fee may be required for
initiating the blacklisting proceedings. (a)
5.2 Notification
Upon verification of the existence of grounds for blacklisting, the BAC shall
immediately notify the contractor concerned in writing, advising him that:
a) a complaint for blacklisting has been filed against him, or he has been
considered by the BAC for blacklisting, stating the grounds for such; (a)
c) a hearing shall be conducted before the BAC, upon his request, where
he may present documentary evidence, verbal testimony and cross-
examine the witnesses presented against him; and
Within five (5) calendar days from receipt of notification, the contractor shall
submit its written answer with documentary evidence to the BAC with a
manifestation for request of hearing to determine questions of fact, if he so
desires. No time extension shall be allowed.
Should the contractor fail to answer within the same period, the BAC shall
issue a resolution recommending to the Head of the Procuring Entity the
immediate suspension 295 of the contractor from participating in any bidding
process of the agency and the forfeiture of his bid security. (a)
291
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Official Gazette on 20 August
2018.
292
Ibid.
293
Ibid.
294
Ibid.
295
Ibid.
280
Uniform Guidelines for Blacklisting Appendix 17
5.3 Hearings
If a hearing is requested, the BAC shall immediately set the date and time for
hearing. The hearing shall be non-litigious and shall be terminated within five
(5) days.
The BAC may also invite a representative from a duly recognized private
group in a sector or discipline relevant to the procurement at hand as an
observer for each hearing.
If no request is made, the BAC shall make a determination of the case based
on the complaint, answer, documentary evidence submitted and facts
verified. If the BAC is convinced that the contractor is at fault, it shall issue a
resolution recommending to the head of the agency the suspension 296 of the
contractor from participating in any bidding process of the agency and the
forfeiture of his bid security. (a)
5.4 Decision
The Head of the Procuring Entity shall, within fifteen (15) days from receipt
of the resolution and the records of the BAC proceedings, determine whether
reasonable cause exists for the suspension 297 of the contractor and the
forfeiture of the latter’s bid security. If the Head of the Procuring Entity
determines that such reasonable cause exists, he shall issue a decision
suspending 298 the contractor from participating in any bidding process of the
agency, and further declaring that his bid security is forfeited. Otherwise, he
shall dismiss the case. (a)
The decision shall clearly and distinctly state the facts, evidence and the law
on which it is based, as well as the date of effectivity of the penalty, if any.
The Head of the Procuring Entity may delegate to the BAC the authority to
impose the corresponding sanction(s) provided for in these guidelines.
The Head of the Procuring Entity shall furnish the suspended 299 contractor a
copy of the decision immediately from its promulgation. (a)
296
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Official Gazette on 20 August
2018.
297
Ibid.
298
Ibid.
299
Ibid.
300
Ibid.
301
Ibid.
302
Ibid.
303
Ibid.
281
Uniform Guidelines for Blacklisting Appendix 17
The motion for reconsideration and/or appeal must first be resolved before
any Blacklisting Order may be issued. 306(n)
The Head of the Procuring Entity shall resolve with finality the motion for
reconsideration within seven (7) calendar days from the filing thereof and
furnish suspended contractor a copy of the resolution immediately from its
promulgation.
In the event that the motion for reconsideration is denied, the suspended bidder
may file an appeal, through a Notice of Appeal, with the appellate authority, if
any, within seven (7) calendar days from receipt of the decision denying the
motion for reconsideration, and upon payment of the appeal fee in the same
amount as prescribed for the filing of protest under Section 55.3 of the IRR of
R.A. 9184. The appellate authority shall decide on the appeal within seven (7)
calendar days upon perfection of appeal. 308 (n)
The decision of the agency shall become final and executory after the lapse of
seven (7) calendar days from the receipt of the notice of decision or resolution on
the motion for reconsideration. If an appeal 309 is filed, the affirmed, modified or
reversed decision shall become final and executory upon receipt thereof by the
agency and person/entity concerned. (a)
304
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Official Gazette on 20 August
2018.
305
Ibid.
306
Ibid.
307
Ibid.
308
Ibid.
309
Ibid.
282
Uniform Guidelines for Blacklisting Appendix 17
Upon finality of the decision blacklisting 310 the contractor, the Head of Procuring
Entity or appellate authority shall issue a Blacklisting Order disqualifying the erring
contractor from participating in the bidding of all government projects. (a)
6.4 Upon termination of contract due to default and/or unlawful acts 311 of the
contractor, the Head of the Procuring Entity shall issue within seven (7)
calendar days 312 a Blacklisting Order immediately 313 disqualifying the erring
contractor from participating in the bidding of all government projects. The
performance security of said contractor shall also be forfeited. (a)
If the contractor fails to show cause after the lapse of the seven (7)
day period, either by inaction or by default, the Head of the
310
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Official Gazette on 20 August
2018.
311
Ibid.
312
Ibid.
313
Ibid.
314
Ibid.
315
Ibid.
316
Ibid.
317
Ibid.
318
Ibid.
319
Ibid.
320
Ibid.
283
Uniform Guidelines for Blacklisting Appendix 17
Before the issuance of a Blacklisting Order, the erring contractor may participate in
the procurement of any government project except in the agency where he is
suspended. But if Blacklisting Order is issued prior to the date of the notice of award
(“NOA”), the blacklisted person/entity shall not be qualified for award and such
project/contract shall be awarded to another bidder pursuant to R.A. 9184 and its
IRR. 323
The effectivity period for the penalty of one (1) or two (2) years, as the case may be,
shall be clearly specified in the Blacklisting Order, the commencement of which, shall
be the same date as the issuance of the Blacklisting Order. 324(n)
In case the penalty of blacklisting for two (2) years is imposed during the pendency
of a previous blacklisting order, the latter shall be deemed terminated and subsumed
in the two (2)-year blacklisting. 325 (n)
If an offense is committed for the third time or oftener, the penalty applicable shall
still be blacklisting for two (2) years. 326 (n)
9.0 DELISTING
A blacklisted person/entity shall be automatically delisted after the period for the
penalty shall have elapsed. (a)
10.1. Blacklisting Orders duly approved by the Head of the Procuring Entity or
Appellate Authority, shall contain the following information: 327
321
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Official Gazette on 20 August
2018.
322
Ibid.
323
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
324
As amended by GPPB Resolution No. 40-2017, dated 21 December 2017, published in the Official Gazette on 20 August
2018.
325
Ibid.
326
Ibid.
327
As amended by GPPB Resolution No. 14-2020, dated 25 June 2020, published in the Philippine Star on
23 July 2020.
284
Uniform Guidelines for Blacklisting Appendix 17
10.2 The Procuring Entity through its official or alternate user shall post the
Blacklisting Order in the Online Blacklisting Portal within three(3)
calendar days from the date of its effectivity. 328
On the other hand, the Procuring Entity, through its official or alternate
user, shall immediately remove the name of Blacklisted Entity upon
receipt of a lawful order from a judicial or quasi-judicial body directing it
to temporarily or permanently lift the period of suspension or remove
the name of a Blacklisted Entity from the Consolidated Blacklisting
Report. 329
10.4 A Blacklisted Entity which was delisted from the Consolidated Blacklisting
Report or whose period of suspension was permanently lifted or which
has been permanently removed from the Consolidated Blacklisting
Report pursuant to a lawful order shall be qualified to participate in all
government procurement upon the lapse of the period of suspension or
effectivity of the order, as the case may be, without further clearance
from the Procuring Entity that issued the Blacklisting Order.
10.5 The Procuring Entity’s official or alternate user shall immediately repost
the name of a Blacklisted Entity in the Consolidated Blacklisting Report
upon the lapse of the order temporarily lifting the period of suspension
or removing the name of a Blacklisted Entity in the Consolidated
328
Ibid.
329
Ibid.
330
Ibid.
285
Uniform Guidelines for Blacklisting Appendix 17
Blacklisting Report.
The period of suspension imposed upon the Blacklisted Entity shall not
be diminished by an order temporarily lifting the period of suspension or
removing a Blacklisted Entity from the Consolidated Blacklisting Report.
Upon reposting, the PE’s official or alternate user shall adjust the period
of suspension by adding the number of days the suspension of the
Blacklisted Entity was temporarily lifted or its name was removed from
the Consolidated Blacklisting Report in order to fully serve the one (1)
year or two (2) years penalty, as the case may be. 331
10.7 The Online Blacklisting Portal shall automatically notify the Procuring
Entity through its BAC Chairperson, GPPB-TSO, and PhilGEPS of the
posting and updating made by the Procuring Entity’s official or alternate
user. The notice shall be the basis of the PhilGEPS in denying the
registration of, or excluding from the Government of the Philippines–
Online Merchant Registry (GoP-OMR) the account of the Blacklisted
Entity pursuant to Section 5.6 of Resolution No. 12-2012 or the
Guidelines for the Use of the GOP-OMR. 333
10.8 The ministerial authority of the GPPB and its TSO is limited to
maintenance and updating of the Online Blacklisting Portal. The
Blacklisting Order posted by the Procuring Entity carries with it the
presumption that the provisions of the Blacklisting Guidelines and the
Contract Termination Guidelines, as the case may be, were duly
complied with and that due process was afforded to the Blacklisted
Entity.
331
Ibid.
332
Ibid.
333
Ibid.
334
Ibid.
286
Uniform Guidelines for Blacklisting Appendix 17
11.0 AMENDMENTS
12.0 EFFECTIVITY
These Guidelines or any amendments thereof shall take effect immediately after
publication in the Official Gazette or a newspaper of general nationwide circulation
and upon filing with the University of the Philippines Law Center of three (3) certified
copies of these guidelines. 335
335
Issued through GPPB Resolution 09-2004, dated 20 August 2004, and published in the Official Gazette on 30 November
2004.
287
Guidelines for Legal Assistance of BAC Members and its Appendix 18
Supporting Staff
APPENDIX 18
GUIDELINES FOR LEGAL ASSISTANCE AND INDEMNIFICATION OF BIDS AND
AWARDS COMMITTEE (BAC) MEMBERS AND ITS SUPPORT STAFF
1.0 SCOPE
These guidelines shall govern the indemnification package for public officials
providing services in and for the Bids and Awards Committee (BAC) pursuant to and
in accordance with Section 73 of Republic Act No. 9184 (R.A. 9184), otherwise
known as “Government Procurement Reform Act” and its Implementing Rules and
Regulations (IRR). 336
These guidelines shall apply to all branches, agencies, departments, bureaus, offices
and instrumentalities of the Government, including Government-Owned and/or
Controlled Corporations (GOCCs), Government Financial Institutions (GFIs), State
Universities and Colleges (SUCs), and Local Government Units (LGUs).
2.0 PURPOSE
2.1. To prescribe the rules and procedures in granting legal assistance and
indemnification to the Bids and Awards Committee (BAC) members and BAC
Support Staff.
2.3. To establish the legal parameters for the effective implementation of the legal
assistance and indemnification provided for BAC members and BAC Support
Staff.
3.1. BAC. Refers to the Bids and Awards Committee as defined and established in
accordance with Rule V of the Implementing Rules and Regulations (IRR) 337
of RA 9184.
3.2. BAC m em bers. Refer to the regular and provisional members of the BAC
determined accordance with Rule V of the IRR. 338
336
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
337
Ibid.
338
Ibid.
288
Guidelines for Legal Assistance of BAC Members and its Appendix 18
Supporting Staff
3.6. M edical Assistance. The remuneration given by the procuring entity for any
injury or disability incurred by members of the BAC and/or the BAC Support
Staff in the lawful performance of their official functions and duties. For this
purpose, “injury” means any bodily impairment arising from and in the course
of procurement-related activities.
3.7. BAC Support Staff. Refers to the members of the BAC Secretariat and the
Technical Working Group duly designated by the procuring entity pursuant to
the provisions of Rule V of the IRR 339 of RA 9184.
2. The BAC member or BAC Support Staff concerned must have engaged
the services of a private lawyer or external counsel.
3. The BAC member or BAC Support Staff must have not been adjudged as
guilty of gross negligence, misconduct, or grave abuse of discretion.
4. The free legal assistance shall cover actual cost of suit and attorney’s
fees. The attorney representing the BAC member or BAC Support Staff
shall be entitled to a maximum of Five Thousand Pesos (₱ 5,000.00) per
appearance which shall be paid by the procuring entity.
339
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
289
Guidelines for Legal Assistance of BAC Members and its Appendix 18
Supporting Staff
6. The BAC member or BAC Support Staff shall be entitled to actual, moral,
and exemplary damages when awarded by the court. Likewise, the
attorney representing the BAC member or BAC Support Staff shall be
entitled to attorney’s fees awarded by the court.
2. The liability insurance policy shall cover only those liabilities asserted
against the public official and incurred by him in his capacity as such
BAC members or BAC Support Staff as the case may be.
3. The insurer shall pay for the loss arising from the claim or suit made
against the BAC members or BAC Support Staff during the policy period
wherein they serve in such capacity.
4. For purposes of this issuance, the term “loss” shall include judgments,
expenses for settlement or compromise, as well as all reasonable fees
and other expenses incurred by such persons in connection with any
administrative, civil, or criminal action, suit or proceeding to which they
may be or have been made a party by reason of the lawful performance
of their official functions and duties in such capacity.
5. Provided further, that, such BAC members or BAC Support Staff shall
not be adjudged in such action or proceeding to be guilty of gross
negligence, misconduct, or grave abuse of discretion or guilty of any
other complaint or charges.
290
Guidelines for Legal Assistance of BAC Members and its Appendix 18
Supporting Staff
3. The claimant or his/her relatives must notify the head of the procuring
entity within seven (7) calendar days from the occurrence of the injury
or disability.
5.1. The claimant(s) shall file their respective claim(s) for legal assistance, liability
insurance, or medical assistance as the case may be, with the head of the
procuring entity; and shall secure the approval of the latter on the terms and
conditions of the engagement of counsel.
5.2. The head of the procuring entity shall be given at least fifteen (15) to thirty
(30) calendar days to examine, review, verify and validate the authenticity of
the documents presented by the claimant.
5.3. Upon finding that all the requirements have been duly complied with and that
all the necessary documents submitted are genuine, it shall then order the
processing of the claims and the subsequent release of funds for the
approved claims.
5.4. Any expenses incurred in advance by the claimant arising from the
performance of his official functions in such capacity shall be subject to
reimbursement upon submission of the necessary documents and approval
thereof by the head of the procuring entity.
5.5. If the BAC member or its support staff is found to be not guilty for gross
negligence, misconduct, or grave abuse of discretion, he shall liquidate his
cash advances by presenting receipts of payment and other necessary
documents mentioned in Item 5.2. On the other hand, if the BAC member or
its support staff is found to be guilty for gross negligence, misconduct, or
grave abuse of discretion, he shall pay the cash advances made through
salary deductions or reimbursement.
The funds to be used for the grant of the free legal assistance, liability insurance or
medical assistance shall be taken from the agency’s annual appropriation.
291
Guidelines for Legal Assistance of BAC Members and its Appendix 18
Supporting Staff
Protest fees, proceeds from the sale of bidding documents, and any other additional
funds derived from other income-generating activities of the agency may be used to
augment the funding source provided in this section.
7.0 AMENDMENTS
8.0 EFFECTIVITY
These guidelines or any amendments thereof shall take effect within fifteen (15)
days after publication in the Official Gazette or a newspaper of general nationwide
circulation and upon filing with the University of the Philippines Law Center of three
(3) certified copies of these guidelines. 340
340
Issued through GPPB Resolution 021-2005, dated 07 October 2005, and published in the Official Gazette on 09 January
2006.
292
Revised Guidelines on Recognition of Umbrella Organization of Appendix 19
Consultants
APPENDIX 19
REVISED GUIDELINES ON RECOGNITION OF UMBRELLA ORGANIZATION OF
CONSULTANTS
Under Annex “B” of the Implementing Rules and Regulations (IRR) of Republic Act
9184 (RA 9184), the Government Procurement Policy Board (GPPB) is directed to
recognize an Umbrella Organization of Consultants composing of various
organizations of consultants and individual consultants in the Philippines that may be
engaged by the Government on matters relating to consulting services.
2.0 PURPOSE
3.1. The GPPB shall recognize the UOC that best represents consultants who
belong to a major sector of the consulting industry listed under Annex “A”
hereof, which shall be updated by the GPPB whenever necessary.
3.2. The criteria shall focus on the ability and capacity of a UOC to meet the
following:
f) Join the government in its advocacy against graft and corruption; and
293
Revised Guidelines on Recognition of Umbrella Organization of Appendix 19
Consultants
4.1. A recognized UOC shall have the following duties and responsibilities:
f) Immediately notify the GPPB whenever there are changes within the
organizational set-up of the UOC which includes, but not limited to,
amendments to articles of incorporation and by-laws, replacement of
UOC’s liaison officer;
294
Revised Guidelines on Recognition of Umbrella Organization of Appendix 19
Consultants
295
Revised Guidelines on Recognition of Umbrella Organization of Appendix 19
Consultants
5.1.2.4. For this criterion, the organization shall submit the following
documents:
5.1.4.2. The organization shall act as the regulatory body of all its
members, and as such, it should formulate mechanisms for
296
Revised Guidelines on Recognition of Umbrella Organization of Appendix 19
Consultants
Recognition of a UOC shall be done by the GPPB under the following procedure:
297
Revised Guidelines on Recognition of Umbrella Organization of Appendix 19
Consultants
6.5. If the GPPB finds the organization qualified to be a UOC, it will declare such
organization as the recognized UOC for the major sector listed in Annex “A”
hereof, and will issue a Certificate of Recognition.
6.6. Whenever the GPPB finds that the application of the applicant-organization is
insufficient to warrant recognition, the GPPB shall re-evaluate the application
upon compliance by the applicant-organization of its order to revise the
application and/or to submit additional documents.
7.1. The recognition of UOC shall be valid for two (2) years after the issuance of
the Certificate of Recognition, unless sooner revoked for a cause.
7.2. The GPPB shall conduct an annual review of the over-all performance of the
UOC. It may also conduct random inspection of the activities of the UOC, as
it deems necessary.
7.3. No challenge of the UOC’s recognition shall be entertained for the duration
of its validity.
7.4. After due process, the GPPB may, motu proprio or upon a valid complaint
filed by any interested party, suspend or revoke the recognition of a UOC
for failure to perform its duties and responsibilities as prescribed herein.
7.5. Any other sanctions the GPPB may deem to impose in the future shall be, at
all instances, proportionate to the offense committed by the UOC.
This shall take effect fifteen (15) days after publication in the Official Gazette or in a
newspaper of general nationwide circulation and upon filing with the University of
the Philippines Law Center of three (3) certified copies. 341
341
Issued through GPPB Resolution 02-2011, dated 28 January 2011 and published in The Daily Tribune on 21 March 2011.
298
Revised Guidelines on Recognition of Umbrella Organization of Appendix 19
Consultants
ANNEX A
List of Major Sectors of the Philippine Consulting Industry
a) Agricultural development
b) Agricultural production, agro processing and agro business
c) Agricultural sector development
d) Fishery and livestock
a) Disaster Management
b) Risk Reduction
c) Geophysical Hazards
a) Basic education
b) Education sector development
c) Non-formal education
d) Senior Secondary General Education
e) Technical education, vocational training, and skills development
f) Tertiary education
a) Banking system
b) Business and other services
c) Capital markets and funds
299
Revised Guidelines on Recognition of Umbrella Organization of Appendix 19
Consultants
7. Health and Social Welfare pertains, but is not limited, to the following
sectors/services:
a) Architecture
b) Construction supervision
c) Engineering
d) Irrigation and drainage
e) Transportation systems and facilities
f) Value engineering
g) Vertical structures
10. Labor and Employment pertains, but is not limited, to the following
sectors/services:
a) Manpower Development
b) Working Conditions
c) Occupational Safety and Hazards
d) Wage Classification
300
Revised Guidelines on Recognition of Umbrella Organization of Appendix 19
Consultants
e) Legislative liaison
a) Economic management
b) Government and civil society
c) National government administration
d) Sub-national government administration
e) Support to NGOs
a) Community Development
b) Community Resettlement
14. Other Sectors as may be recognized by the GPPB such as, but not limited to, the
following sectors/services:
a) Civil aviation
b) Military
c) Multimodal transport and sector development
d) Tourism
e) Transport and storage
301
Guidelines on the Procurement of Printing Services Appendix 20
APPENDIX 20
GUIDELINES ON THE PROCUREMENT OF PRINTING SERVICES
1.1. Pursuant to the relevant provisions of the General Appropriations Act 342,
procuring entities have the option to engage the services of private printers for
their printing and publication expenditures, subject to public bidding in
accordance with RA 9184 and pertinent accounting and auditing rules and
regulations.
2.1. These guidelines shall govern the procurement of printing services for
accountable forms by the national government, its branches, constitutional
offices, departments, bureaus, offices, agencies, and instrumentalities, including
state universities and colleges, government owned/controlled corporations,
government financial institutions, and local government units.
2.2. It shall not apply to official ballots and election paraphernalia, including
statement of votes, certificates of canvass, and paper seals, which is covered by
Section 184 of Batas Pambansa Blg. 881, otherwise known as the Omnibus
Election Code of the Philippines and Section 13 of RA 9369.
For the purpose of these guidelines, the following terms shall have the corresponding
meanings:
342
As amended by GPPB Resolution 04-2011, dated 25 February 2011, published in the Manila Times on 13 June 2011.
302
Guidelines on the Procurement of Printing Services Appendix 20
4.0 PROCEDURE
4.1. The procuring entity shall determine whether a printing expenditure is for an
Accountable Form or for a Sensitive High Quality/Volume document.
4.2. The procuring entity shall prepare the technical specifications for the Accountable
Forms or Sensitive High Quality/Volume printing requirement, which shall include,
among others, the prescribed security features, output quantity, and target
completion time.
4.3. It shall then conduct a market analysis to determine the Approved Budget for the
Contract (ABC) taking into consideration the prevailing standard cost for its
printing requirements.
4.3.1. The procuring entity may seek the assistance of the PCOO in
determining whether no RGP is capable of undertaking the printing
service.
4.3.2. Upon determination by the PCOO that no RGP can undertake the
printing service due to time constraints and equipment limitations, the
procuring entity may engage the services of private printers.
4.4. Thereafter, the procuring entity shall send a Request for Quotation (RFQ) to the
RGPs. The quotations received will be evaluated by the procuring entity to
determine which among the RGPs is most capable in performing the printing
service in the most advantageous terms for the procuring entity.
4.4.1. In case the offer submitted by an RGP exceeds the ABC set by the
procuring entity, it may request the Presidential Communications
Operations Office (PCOO) to determine (i) whether the offer of the RGP
is excessive; and (ii) set the appropriate rate for such transaction.
4.5. The procuring entity shall then engage the services of the appropriate RGP
through an Agency-to-Agency Agreement pursuant to Section 53.5 of the IRR of
RA 9184.
4.6. The appropriate RGP engaged by the procuring entity shall directly undertake the
printing services for the contracts entered into, and cannot engage, subcontract,
or assign any private printer to undertake the performance of the printing
service.
5.0 EFFECTIVITY
5.1. These guidelines shall take effect immediately upon publication in the Official
Gazette or in a newspaper of general circulation. 343
343
Issued through GPPB Resolution 05-2010, dated 29 October 2010, and published in the Philippine Star on 08 January 2011.
303
Guidelines on the Procurement of Printing Services Appendix 20
ANNEX A
304
Guidelines on the Procurement of Printing Services Appendix 20
305
Guidelines on the Procurement of Printing Services Appendix 20
306
Guidelines on the Procurement of Printing Services Appendix 20
307
Guidelines on the Procurement of Printing Services Appendix 20
308
Guidelines on the Procurement of Printing Services Appendix 20
309
Guidelines on the Procurement of Water, Electricity, Appendix 21
Telecommunications and Internet Service Providers
APPENDIX 21
GUIDELINES ON PROCUREMENT OF WATER, ELECTRICITY,
TELECOMMUNICATIONS AND INTERNET SERVICE PROVIDERS
Section 5 (h) of Republic Act No. (R.A.) 9184 defines goods as referring to all items,
supplies, materials, and general support services which may be needed in the
transaction of public business or in the pursuit of any government undertaking. Such
definition necessarily includes the procurement of internet service providers and
public utility services, such as water, electricity, and telecommunication services.
2.0 PURPOSE
2.1 Prescribe the appropriate method under R.A. 9184 that applies to the
procurement of water, electricity, telecommunications, and internet service
providers; and
Considering that water and electricity service providers are granted exclusive
franchises to operate within a specific territory, procurement of water and
electricity services shall be done through direct contracting under Section 50
(c) of the Implementing Rules and Regulations (IRR) 344 of R.A. 9184. This
provision does not apply to the purchase of bottled water or to the
procurement by any agency of the government, whether national or local, in
its operation as water or electric concessionaire (e.g. repair of pumping
stations).
344
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
310
Guidelines on the Procurement of Water, Electricity, Appendix 21
Telecommunications and Internet Service Providers
345
As amended by GPPB Resolution No. 41-2017 dated 21 December 2017, published in the Philippine Daily Inquirer on 24
April 2018.
346
Ibid.
347
Ibid.
348
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
311
Guidelines on the Procurement of Water, Electricity, Appendix 21
Telecommunications and Internet Service Providers
349
As amended by GPPB Resolution No. 41-2017 dated 21 December 2017, published in the Philippine Daily Inquirer on 24
April 2018.
350
Ibid.
351
Ibid.
352
Ibid.
353
Ibid.
312
Guidelines on the Procurement of Water, Electricity, Appendix 21
Telecommunications and Internet Service Providers
If the procuring entity does not presently engage an ISP or, after
conduct of a cost-benefit analysis as required in the preceding
subsection, is not satisfied with the performance of its existing ISP,
the following procurement methods are prescribed:
5.0 EFFECTIVITY
354
As amended by GPPB Resolution No. 41-2017 dated 21 December 2017, published in the Philippine Daily Inquirer on 24
April 2018.
355
Ibid.
356
Issued through GPPB Resolution 019-2006, dated 06 December 2006, and published in the Official Gazette on 09 April 2007.
313
Revised Guidelines on Index-Based Pricing for Procurement of Appendix 22
Petroleum, Oil, and Lubricant Products
APPENDIX 22
REVISED GUIDELINES ON THE PROCUREMENT OF PETROLEUM, OIL, AND
LUBRICANT PRODUCTS
These rules and procedures shall govern the procurement of POL by the national
government, its departments, bureaus, offices and agencies, including state
universities and colleges, government-owned and/or controlled corporations,
government financial institutions and local government units when POL is a major
operational requirement necessary for the pursuit 358 of their principal mandate. (a)
2.0 PURPOSE
2.1. To identify the conditions for the applicability of the index-based pricing
scheme in the procurement of POL products by a procuring entity.
2.2. To prescribe the rules and procedures on the use of index-based pricing
scheme for the procurement of POL in bulk. 359 (a)
3.1 Bid Price- refers to the bid of the prospective supplier, less discounts given,
plus delivery cost, regardless of the index used in the procurement of
petroleum, oil, and lubricant (POL) products. 360 (a)
3.2 Bulk Procurement – refers to any procurement which, by the totality of its
POL requirements and by their sheer volume, necessitates procurement from
suppliers for purpose of economies of scale. 361 (a)
3.3 Total Contract Price - refers to the aggregate of the amounts set by a
procuring entity, as the ceiling, to meet the volume requirement for each type
of POL product; the value of which shall not exceed the approved budget for
the contract (ABC).
3.4 Delivery Cost - refers to cost of freight incurred by the Supplier from the
source to the delivery point, i.e., refinery to delivery point for deliveries ex-
refinery, or oil terminal/depot to delivery point for deliveries ex-depot
357
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
358
As amended by GPPB Resolution No. 05-2018, dated 18 May 2018, published in the Official Gazette on 20 August 2018.
359
Ibid.
360
Ibid.
361
As amended by GPPB Resolution No. 26-2019 dated 30 October 2019, published in the Official Gazette on 30 December
2019.
314
Revised Guidelines on Index-Based Pricing for Procurement of Appendix 22
Petroleum, Oil, and Lubricant Products
3.6 Expanded Value Added Tax (E-VAT) - refers to a consumption tax on the
sale or importation of goods and services in the ordinary course of business.
3.9 Mean of Platts Singapore or MOPS - refers to the mean of the high and
low components of a Platts assessment for oil cargoes loading from
Singapore as officially released by S&P Global Platts, a provider of energy and
commodities information and a source of benchmark price assessments in the
physical commodity market based in Singapore.(a) 363
3.10 Petroleum, Oil, and Lubricant or POL Products - for purposes of these
guidelines, shall refer to those enumerated in Section 6 hereof. 364 (a)
3.11 Wholesale Posted Price or WPP- refers to the reference fuel prices
individually set by local refiners and traders subject to periodic changes based
on the movement in crude oil prices, foreign exchange, and all other costs
without hauling charge, dealer’s mark-up and dealer’s E-VAT.(a) 365
POL requirements shall be considered major if the use of the same is 367 necessary in
the primary operation of the procuring entity and in the pursuit 368 of its principal
mandate. The duration of the contract to cover the POL requirement of the
procuring entity may be one year or more. In the case of multi-year, the same shall
362
As amended by GPPB Resolution No. 26-2019 dated 30 October 2019, published in the Official Gazette on 30 December
2019.
363
Ibid.
364
Ibid.
365
Ibid.
366
As amended by GPPB Resolution No. 05-2018, dated 18 May 2018, published in the Official Gazette on 20 August 2018.
367
As amended by GPPB Resolution No. 05-2018, dated 18 May 2018, published in the Official Gazette on 20 August 2018.
368
Ibid.
315
Revised Guidelines on Index-Based Pricing for Procurement of Appendix 22
Petroleum, Oil, and Lubricant Products
5.1 The rules and regulations governing competitive bidding shall apply whenever
the rules in these Guidelines are silent.
5.2 Right to Inspect. The procuring entity shall allow the Department of Energy
(DOE) to inspect the procuring entity’s fuel facilities, if there is any, subject to
DOE’s guidelines to check compliance to Philippine National Standards (PNS)
on products and facilities, among others. The procuring entity may provide
the delivery schedule of the supplier to DOE. 370 (n)
6.1. The WPP index shall be used in the procurement of the following products:
6.2. The MOPS index shall be used in the procurement of the following products:
6.3. In the procurement of all types of lubricant products, the procuring entity
may adopt either a fixed or index-based pricing. If its assessment or cost-
benefit analysis indicates that index-based pricing is more advantageous,
then it shall adopt the ICIS-LOR index.
6.4. The foregoing list shall be subject to annual review, modification or re-
classification by the GPPB, or as often as it deems necessary.
7.1. The Procuring Entity shall indicate in its ITB among others the ABC per
product with indicative volume for bidding purposes only. Regardless of the
index used, the bid price shall be determined by the prospective supplier’s
bid, less discounts given plus delivery cost.
369
As amended by GPPB Resolution No. 26-2019, dated 30 October 2019, published in the Official Gazette on 30 December
2019.
370
Ibid.
371
Ibid.
372
Ibid.
373
Ibid.
374
As amended by GPPB Resolution No. 26-2019, dated 30 October 2019, published in the Official Gazette on 30 December
2019.
316
Revised Guidelines on Index-Based Pricing for Procurement of Appendix 22
Petroleum, Oil, and Lubricant Products
7.2. Cost for E-VAT and other governmental costs are presumed to be included in
the computation of the bid price by the prospective suppliers.
7.3. For purposes of bid evaluation and/or comparison of bids, regardless of the
index used, the Lowest Calculated Bid shall be determined by identifying the
bidder that offered the lowest bid price.
7.4. For purposes of payment, the bid price, discount and the delivery cost stated
in the contract shall be fixed from the time of the bidding through the term of
the contract. Delivery should be done at the end of the week. The amount to
be paid by the procuring entity for POL requirements actually delivered and
duly received by it shall be:
7.4.1. For the WP index, the bid price, less the discounts offered, if
any, plus or minus the weekly price adjustments duly posted by
the Oil Industry Management Bureau (OIMB) of the
Department of Energy (DOE) in its Price Watch / Price
Adjustments / Fuel page in the DOE’s website, and the delivery
cost stated in the contract, at the date of actual delivery
[Payment = (bid price – discounts) +/- (DOE) weekly price
adjustments for gasoline and diesel)+ (delivery cost or DC);
7.4.2. For the MOPS index, the bid price, less the discounts offered,
if any, plus or minus the MOPS week on week price
adjustments, the delivery cost stated in the contract, at the
date of actual delivery [Payment = (bid price – discounts) +/-
(MOPS week on week price adjustments) + (DC)]; or
7.4.3. For the ICIS-LOR Index, the bid price, less the discounts
offered, if any, plus or minus the ICIS-LOR pricing adjustment,
the delivery cost stated in the contract, at the date of actual
delivery [Payment =(bid price –discounts) +/- (ICIS pricing
adjustments) + (DC)].
7.5. The supplier will provide a detailed price adjustment for its POL products
actually delivered, as part of its billing (weekly price adjustments for WP
index, daily traded MOPS pricing, and ICIS pricing adjustment), together with
its certification under oath that:
7.5.1. The supplier’s price adjustments are those reported and duly
posted at DOE’s website for products using the WP index;
317
Revised Guidelines on Index-Based Pricing for Procurement of Appendix 22
Petroleum, Oil, and Lubricant Products
318
Revised Guidelines on Index-Based Pricing for Procurement of Appendix 22
Petroleum, Oil, and Lubricant Products
319
Revised Guidelines on Index-Based Pricing for Procurement of Appendix 22
Petroleum, Oil, and Lubricant Products
7.7. For staggered deliveries, the end- user or acceptance team shall make, after
every delivery, an accounting of the amount actually payable based on the
date of the delivery receipt to determine the allowable unit/volume that may
be ordered from the remaining amount allotted for each POL product. The
procuring entity shall be allowed to make adjustments in the units/volume to
be delivered per type of product to conform to the remaining amount in the
total contract price.
7.8. Illustrative Example of the Computation for Succeeding Deliveries for Diesel.
(n)
320
Revised Guidelines on Index-Based Pricing for Procurement of Appendix 22
Petroleum, Oil, and Lubricant Products
PE decides to adjust the volumes (upwards or downwards) for the next two
months, which may be based on usage and projected price adjustments, or
based on contractor’s monthly balance of the POL budget of the PE.
PE decides to adjust the volumes (upwards or downwards) for the next two
months which may be based on usage and projected price adjustments, or
based on contractor’s monthly balance of the POL budget of the PE.
321
Revised Guidelines on Index-Based Pricing for Procurement of Appendix 22
Petroleum, Oil, and Lubricant Products
7.9. If during contract implementation, the total contract price for the project
would have been consumed notwithstanding that the requirements were not
fully delivered in the units / volume contemplated, no further order and
payments shall be made. This provision shall form part of the bidding
documents.
322
Revised Guidelines on Index-Based Pricing for Procurement of Appendix 22
Petroleum, Oil, and Lubricant Products
8.0 EFFECTIVITY
These Guidelines amend GPPB Resolution No. 11-2007, dated 31 May 2007 and
GPPB Resolution No. 05-2018, dated 18 May 2018 and 375 shall take effect
immediately. 376 (a)
375
As amended by GPPB Resolution No. 26-2019, dated 30 October 2019, published in the Official Gazette on 30 December
2019.
323
Guidelines on Procurement of Security and Janitorial Services Appendix 23
APPENDIX 23
GUIDELINES ON THE PROCUREMENT OF SECURITY AND JANITORIAL SERVICES
Under Section 5 (h) of Republic Act No. 9184 (R.A. 9184), as reiterated in Section 5
(r) of its Implementing Rules and Regulations (IRR) 377, procurement of general
support services, including non-personal or contractual services, such as security and
janitorial services, falls under the definition of goods. Thus, in the procurement of
security or janitorial services, the winning bid is determined by the lowest calculated
and responsive bid.
It is recognized, however, that the proper and efficient procurement of security and
janitorial services should be based not solely on cost, but should also take into
consideration a range of other factors, such as, but not limited to, length of contract,
standards of internal governance, adequacy of resources, levels of training, and
adherence to labor and other social legislation.
These guidelines shall govern the procurement of security and janitorial services by
government agencies.
These guidelines shall not apply to the procurement of other general support
services, such as, repair and maintenance of equipment and furniture, trucking,
hauling, and other services.
3.0 PURPOSE
3.1. To provide conditions on the use of multi-year contracts for security and
janitorial services.
4.1 Procuring entities are highly encouraged to evaluate the technical proposal of
bidders using the additional set of parameters prescribed in Appendix A of
these guidelines. However, considering that procuring entities have different
needs and requirements, the minimum standard for each parameter shall be
determined by the procuring entity.
377
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
324
Guidelines on Procurement of Security and Janitorial Services Appendix 23
4.2 To determine compliance with these parameters, procuring entity may require
additional documents or materials as part of the bidder's technical proposal.
These additional documents or materials must be expressly stated in Section
VII: Technical Specifications of the PBDs for the Procurement of Goods
consistent with Section 25.2 (a) (vii) of the IRR of R.A. 9184. 378
4.3 The procuring entity shall check compliance with the technical parameters
using a non-discretionary "pass/fail" criteria
Procuring entities may enter into multi-year contracts, but not to exceed three (3)
years, in the procurement of security and janitorial services, subject to the following
conditions:
5.1. The Invitation to Apply for Eligibility and to Bid must expressly state the
following:
5.1.1. Duration of the contract to be bid, which should not exceed three
(3) years;
5.1.2. The Approved Budget for the Contract (ABC) for the first year only.
5.2. All bid prices for a duration of three (3) years shall be fixed and shall not be
adjusted during contract implementation, except for the following:
5.2.1. Increase in minimum daily wage pursuant to law or new wage order
issued after date of bidding,
5.2.3. If during the term of the contract the procuring entity sees the need
for an increase or decrease in the number of security guards or
janitorial attendants, the resulting cost of said increase or decrease,
provided that the ABC for the relevant year is not exceeded.
The procuring entity shall ensure that the foregoing allowable price
adjustments are specified under Section 8.1 of the Special Conditions of
Contract of the PBDs.
5.3. The Financial Proposal shall contain a breakdown of all costs, including cost
of supplies and equipment, necessary for the execution of the contract.
5.4. Procuring entities shall expressly provide, under Section Vll. Technical
Specifications, which shall form part of the contract under Section 13.1 of the
General Conditions of the Contract of the PBDs, that the service
provider/contractor shall maintain a satisfactory level of performance
throughout the term of the contract based on a prescribed set of
performance criteria.
378
Ibid. (As amended by the 2016 Revised IRR of R.A. No. 9184.)
325
Guidelines on Procurement of Security and Janitorial Services Appendix 23
5.5. Before end of each year, procuring entities shall conduct an assessment or
evaluation of the performance of the service provider/contractor based on the
set of performance criteria prescribed under Section VII. Technical
Specifications.
5.6. Based on its assessment, the procuring entity may pre-terminate the contract
for failure by the service provider/contractor to perform its obligations
thereon following the procedure prescribed under the Guidelines on
Termination of Contracts issued by the Government Procurement Policy Board
under Resolution No.018-2004 dated 22 December 2004.
6.0 EFFECTIVITY
These Guidelines shall take effect fifteen (15) days after its publication in the
Official Gazette or in a newspaper of general circulation and upon filing with
the University of the Philippines Law Center of three (3) certified copies of
these guidelines. 379
379
Issued through GPPB Resolution 024-2007, dated 28 September 2007, and published in the Manila Times on 26 October
2007.
326
Guidelines on Procurement of Security and Janitorial Services Appendix 23
APPENDIX A
ADDITIONAL SET OF TECHNICAL PARAMETERS
A. Security Services
1. Stability
2. Resources
3. Security Plan
4. Other Factors
B. Janitorial Services
1. Stability
2. Resources
3. Housekeeping Plan
4. Other Factors
327
Revised Guidelines on the Extension of Contracts for General Appendix 24
Support Services
APPENDIX 24
REVISED GUIDELINES ON THE EXTENSION OF CONTRACTS FOR GENERAL
SUPPORT SERVICES
2.0 PURPOSE
These guidelines are formulated to identify the conditions for the allowance of
contract extension and to prescribe the rules and procedures governing the same,
for the purpose of averting hiatus in support services essential, indispensable, or
necessary in the operations of a procuring entity.
These guidelines shall govern the extension of ongoing contracts of general support
services which are essential, indispensable, or necessary to support the operations of
any of the procuring entities or for the enhancement of the welfare of its personnel
to include, but shall not be limited to, non-personal or contractual services such as
maintenance of equipment and furniture, janitorial and security services.
However, these guidelines shall not apply to contracts with water, electricity,
telecommunications, and internet service providers, which shall be governed by the
Guidelines on Procurement of Water, Electricity, Telecommunications and Internet
Service Providers provided issued by the Government Procurement Policy Board
under Resolution No. 19-2006, dated 6 December 2006.
4.2 The original contract subject of the extension was awarded in accordance
with the provisions of Republic Act 9184 (R.A. 9184) and its Implementing
Rules and Regulations (IRR). 380
4.3 The procuring entity concerned has substantially undertaken the procurement
activities required prior to award of the new contract under R.A. 9184 and its
IRR. 381
380
As amended by GPPB Resolution 03-2011, dated 28 January 2011, published in the Manila Times on 6 April 2011.
381
Ibid.
328
Revised Guidelines on the Extension of Contracts for General Appendix 24
Support Services
4.6 The current service provider has not violated any of the provisions of the
original contract.
4.7 The terms and conditions of the original contract shall not be changed or
modified, except when changes or modifications will redound to the
advantage of the government at no additional cost to the Procuring Entity.
5.1 All contract extensions shall be subject to the prior approval of the Head of
the Procuring Entity or his/her duly authorized representative upon
recommendation of the Bids and Awards Committee.
5.2 In addition to the foregoing, if the proposed contract extension exceeds six
(6) months, the Head of the Procuring Entity or his/her duly authorized
representative shall immediately report to the Government Procurement
Policy Board in writing of its intent to extend beyond six months.
These Guidelines repeal GPPB Resolution 08-2005 and the amendments thereto per
GPPB Resolution 03-2006, dated 28 April 2005 and 11 March 2006, respectively.
7.0 EFFECTIVITY
7.1 These guidelines or any amendments hereto shall take effect fifteen (15)
days after publication in the Official Gazette or in a newspaper of general
nationwide circulation. 382
382
Issued through GPPB Resolution 023-2007, dated 28 September 2007, and published in the Manila Times on 26 October
2007.
329
Guidelines on Comparison of Bids Submitted by Cooperatives Appendix 25
APPENDIX 25
GPPB CIRCULAR 02-2010
GUIDELINES ON COMPARISON OF BIDS SUBMITTED BY COOPERATIVES
1.0 Purpose
This Circular 383 is being issued to clarify the procedure for comparison of bids
submitted by cooperatives in line with the principle that all bids shall be evaluated on
an equal footing to ensure fair and competitive bid comparison.
2.0 Coverage
3.1 Under Section 32.2.2 of the Implementing Rules and Regulations (IRR) of
Republic Act 9184, all bidders shall be required to include the cost of all
taxes, such as, but not limited to, value added tax, income tax, local taxes,
and other fiscal levies and duties which shall be itemized in the bid form and
reflected in the detailed estimates.
Such bids, including said taxes, shall be the basis for bid evaluation and
comparison.
3.2 Since cooperatives are granted tax exemptions by law, they enjoy a clear
advantage over non-cooperatives.
3.3 To ensure that all bids shall be evaluated on an equal footing, all taxes
itemized by non-cooperatives in their bids and which cooperatives are exempt
from shall be added to the bids of cooperatives strictly for purposes of
evaluation and comparison.
3.4 If, after evaluation and comparison, the bid submitted by a cooperative is still
determined to be the lowest bid, the taxes added during bid evaluation shall
be removed. Award of contract shall be based on the original bid price,
subject to Section 34.4 of the IRR.
383
Issued on 24 November 2010.
330
Honoraria of GPPB-TSO Recognized Trainers Appendix 26
APPENDIX 26
GPPB CIRCULAR 10-2015
HONORARIA OF GPPB-TSO RECOGNIZED TRAINERS
1.0 Purpose:
This Circular 384 is being issued to reiterate to all Government Agencies the mandate
of GPPB Resolution No. 16-2013 requiring adherence to the standard rates on the
payment of honoraria to GPPB-TSO Recognized Trainers as provided in DBM Circular
No. 2007-1, and to remind all GPPB-TSO Recognized Trainers to received honoraria
pursuant only to the rates prescribed under DBM Circular No. 2007-1.
2.0 Coverage:
2.1 All Departments, Bureaus, Offices and Agencies of the National Government
including State Universities and Colleges, Government Owned and/or
Controlled Corporations, Government Financial Institutions, and Local
Government Units; and
2.2 All GPPB-TSO Recognized Trainers, who serve as Lectures, Resource Persons
and Speakers in Seminars, Training Programs and other similar activities on
RA 9184 and its revised IRR.
3.1 Government Agencies shall adhere to the provisions of GPPB Resolution No.
16- 2013 confirming the imposition of standard rates of honoraria mandated
under DBM Circular No. 2007-1; and
384
Issued on 18 August 2015.
331
Guidelines for the Establishment of Negative List of Surety Appendix 27
and/or Insurance Companies
APPENDIX 27
GUIDELINES FOR THE ESTABLISHMENT OF NEGATIVE LIST OF SURETY AND/OR
INSURANCE COMPANIES
1. POLICY STATEMENT
1.1. Pursuant to Sections 27.2, 39.2 and 62.2.3.3 of Implementing Rules and
Regulations (IRR) of Republic Act (RA) No. 9184, surety bond is one of the
acceptable forms of bid, performance, and warranty securities, provided it is
callable upon demand and accompanied by an Insurance Commission
Certificate stating that the surety and/or insurance company is authorized to
issue such bond or security.
1.2. In view of the prevalence of instances when procuring entities are unable to
claim on surety bonds submitted by bidders, there exists pressing need to
protect procuring entities and ensure the reliability of surety bonds as an
acceptable form of bid security.
1.3. The GPPB shall prepare, maintain, and update a Negative List based on the
submitted names by different procuring entities, and shall be posted in the
GPPB website, which shall include the name/s of the erring surety and/or
insurance companies and the effectivity of their suspension.
2. PURPOSE
1.1. These Guidelines are formulated to provide the necessary steps and procedures
on the establishment of a list of surety and/or insurance companies that have
failed to honor their obligations on the surety bond they issued as bid,
performance, and/or warranty securities of bidders participating in public
procurement.
1.2. It may also serve as the first step and/or basis of government agencies in filing
of complaints against erring surety and/or insurance companies with the
Insurance Commission.
4. DEFINITION OF TERMS
332
Guidelines for the Establishment of Negative List of Surety Appendix 27
and/or Insurance Companies
4.3 Surety Bond refers to a bond issued by a surety company to guarantee the
performance by the bidder of an obligation or undertaking in favor of the
procuring entity, i.e., bid security, performance security, or warranty security.
4.4 Callable on Dem and refers to the surety company’s absolute, primary, and
direct responsibility and liability to the procuring entity for an obligation that is
accessory or collateral to the valid principal obligation contracted by a bidder by
virtue of the surety’s undertaking to be bound solidarily with the bidder.
4.5 Bid Security refers to the guaranty, in the form and amount prescribed, that
the successful bidder shall, within ten (10) calendar days or less, as indicated in
the Instructions to Bidders, from receipt of the notice of award, enter into
contract with the procuring entity and furnish the performance security
required in Section 39 of the IRR, except when Section 37.1 of the IRR allows a
longer period.
4.6 Perform ance Security refers to the guaranty posted prior to the signing of
the contract for the faithful performance by the winning bidder of its obligations
under the contract in accordance with the Bidding Documents in an amount
equal to the percentage of the total contract price in accordance with the
schedule provided in Section 39.2 of the IRR.
4.7 W arranty Security refers to the guaranty that the contractor shall perform
his responsibilities as prescribed in Section 62.2.3.1(a) of the IRR against
“Structural Defects” or “Structural Failures” for infrastructure projects.
The following are the grounds for the inclusion of a surety company in the Negative
List:
a) Refusal or failure of the surety company to honor the claim against the surety
bond upon written demand of the procuring entity for whom the same was
issued;
333
Guidelines for the Establishment of Negative List of Surety Appendix 27
and/or Insurance Companies
1.1. Initiation
1.1.1. Once a bidder has been duly determined to have defaulted in the
performance of its obligations as prescribed under Sections 27.1, 39.1
and 62.2.3.1 of the IRR, the head of the procuring entity (HOPE),
upon recommendation of the Bids and Awards Committee (BAC) or
the Implementing Unit (IU), shall forfeit the surety bond issued as bid,
performance, or warranty security.
1.1.2. The procuring entity shall notify the bidder and the concerned surety
company relative to the act/s committed by the bidder which would
result to the forfeiture of the surety bond, and shall make a claim on
the surety bond.
1.2. Verification
Upon denial of the claims on the surety bond or if the surety company
committed any of the grounds enumerated under Section 5 above, the BAC/IU,
shall, within a period of seven (7) calendar days, verify the existence of the
aforementioned grounds and shall prepare and submit a Verified Report to the
HOPE.
1.3.1. Upon receipt of the Verified Report and determination of the validity
of the action, the HOPE shall issue a Show Cause Order to the surety
company:
1.3.2. Within a period of seven (7) calendar days from receipt of the Show
Cause Order, the concerned surety company shall submit to the HOPE
a Verified Position Paper stating why the company should not be
included in the Negative List
334
Guidelines for the Establishment of Negative List of Surety Appendix 27
and/or Insurance Companies
1.4. Decision
1.4.1. Upon receipt of the Verified Position Paper, the HOPE shall assess,
review and decide the matter, based on the representations made and
evidence submitted, within a non-extendible period of ten (10)
calendar days.
1.4.3. If the HOPE determines that the surety company committed any of
the afore-stated grounds, it shall issue a decision to include surety
company in the Negative List. Otherwise, the HOPE shall dismiss the
case. In either case, the decision of the HOPE shall clearly and
distinctly state the facts, evidence and the law upon which it is based.
1.4.4. The HOPE may, at any time before receipt of the surety company’s
Verified Position Paper, withdraw the Show Cause Order if the claims
on the surety bond have been settled by the surety company
concerned.
The HOPE shall immediately serve a written notice of the Decision to the
surety/insurance company, and upon receipt by the surety/insurance company
thereof, furnish a copy of the Decision to the Insurance Commission and the
GPPB, through its Technical Support Office (TSO), indicating the following:
1.6.1. Upon receipt of a copy of the Decision, the GPPB, through its TSO,
shall include the name of the surety company in the Negative List and
shall post the same at the GPPB website for a period of two (2) years,
which may thereafter be extended to another period of two (2) years
upon notice from the procuring entity that the surety/insurance
company remains in default.
1.6.2. Upon inclusion in the Negative List, the GPPB, through its TSO, shall
immediately notify the surety company of such status.
335
Guidelines for the Establishment of Negative List of Surety Appendix 27
and/or Insurance Companies
7.1. The inclusion in the Negative List shall result in the rejection of the surety
bonds issued by the suspended surety/insurance company submitted as bid,
performance, or warranty security in the relevant procurement activities of
NGAs, GOCCs, GFIs, SUCs and LGUs during the period of inclusion and
suspension.
7.2. The BAC shall ensure that surety bonds issued as bid, performance, or
warranty security submitted are not issued by surety companies included in the
list. Any bidder who submits a surety bond issued by a surety company in the
Negative List shall be declared ineligible.
7.3. Considering that surety companies are subject to the jurisdiction and
supervision of the Insurance Commission, the list may serve as basis for the
pursuit of complaint/s filed before the Insurance Commission, if any.
8. DELISTING
The GPPB-TSO shall remove a surety company from the Negative List even before
the expiration of the period upon the advice of the PE or by the IC in cases where
the IC had amicably settled the matter or adjudicated the issue with finality, unless
the surety or insurance company remains in default, and/or the PE has duly elevated
the matter to a higher authority or court on appeal or certiorari.
9. AMENDMENTS
10. EFFECTIVITY
These Guidelines shall take effect immediately after its publication in the Official
Gazette or in a newspaper of general nationwide circulation and upon filing with the
University of the Philippines Law Center of three (3) certified copies of these
guidelines. 385
385
Issued through GPPB Resolution No. 15-2012, dated 29 June 2012, published in the Official Gazette on 1 April 2015.
336
Guidelines for the Procurement of Goods and Services, Appendix 28
Infrastructure Projects and Consulting Services to be Procured
and Performed Overseas
APPENDIX 28
GUIDELINES FOR THE PROCUREMENT OF GOODS AND SERVICES,
INFRASTRUCTURE PROJECTS AND CONSULTING SERVICES TO BE PROCURED
AND PERFORMED OVERSEAS 386
1. PURPOSE
The Guidelines are formulated to provide rules and procedures for the procurement of
Goods and Services, Infrastructure Projects, and Consulting Services to be procured
and performed overseas; and to ensure transparency, efficiency, competition, and
accountability in the procurement process.
The Guidelines shall apply to the national government, its branches, constitutional
offices, departments, bureaus, offices and agencies, including state universities and
colleges, government-owned and/or -controlled corporations, government financial
institutions, and local government units, in the procurement of Goods and Services,
Infrastructure Projects, and Consulting Services to be procured and performed
overseas. Consequently, if the project will be performed within the Philippines, the
relevant provisions of the 2016 Revised Implementing Rules and Regulations (IRR) of
Republic Act (RA) No. 9184 on Competitive Bidding or Alternative Modes of
Procurement shall apply.
3. GENERAL GUIDELINES
a. Annual Procurement Plan (APP). In accordance with Section 7.2 of the IRR,
no procurement shall be undertaken unless it is in accordance with the approved
APP of the Procuring Entity.
386
Issued through GPPB Resolution No. 28-2017, dated 31 July 2017, published in the Philippine Daily Inquirer on 22
December 2017.
337
Guidelines for the Procurement of Goods and Services, Appendix 28
Infrastructure Projects and Consulting Services to be Procured
and Performed Overseas
4. SPECIFIC GUIDELINES
b. The BAC or the authorized personnel or committee shall determine the technical,
legal, and financial eligibility requirements to be submitted by the prospective
bidders or any other means to verify the technical, legal and financial capability
of the supplier, contractor or consultant.
c. The BAC or the authorized personnel or committee shall prepare and send the
Request for Quotations (RFQ) or Request for Proposals (RFP) to at least three
(3) suppliers, contractors or consultants of known qualifications. This,
notwithstanding, those who responded through any of the required postings
shall be allowed to participate. Receipt of at least one (1) quotation on the
deadline for submission of quotations shall be sufficient to proceed with the
evaluation thereof. In no instance shall Procuring Entities be required to pay any
sum of money for the purpose of obtaining RFQs/RFPs.
d. The BAC or the authorized personnel or committee may meet with all
prospective bidders, depending on the nature and complexity of the project, in
order to clarify and/or explain any of the requirements, terms, conditions, and
specifications stipulated in the RFQ/RFP.
338
Guidelines for the Procurement of Goods and Services, Appendix 28
Infrastructure Projects and Consulting Services to be Procured
and Performed Overseas
5. EFFECTIVITY CLAUSE
This Guidelines shall take effect fifteen (15) calendar days after its publication in the
Official Gazette or in a newspaper of general nationwide circulation and upon filing
with the University of the Philippines Law Center.
339
Guidelines and Conditions in the Recognition of GPPB Appendix 29
Procurement Trainings or Capacity Development Activities
pursuant to Section 16 of Republic Act (RA) No. 9184 and its
2016 revised Implementing Rules and Regulations (IRR) and
the Recognition of the Existing Pool of Procurement Trainers
APPENDIX 29
GUIDELINES AND CONDITIONS IN THE RECOGNITION OF GPPB PROCUREMENT
TRAININGS OR CAPACITY DEVELOPMENT ACTIVITIES PURSUANT TO SECTION
16 OF REPUBLIC ACT (RA) NO. 9184 AND ITS 2016 REVISED IMPLEMENTING
RULES AND REGULATIONS (IRR) AND THE RECOGNITION OF THE EXISTING
POOL OF PROCUREMENT TRAINERS 387
1.0 PURPOSE
This Circular is issued to provide guidance on the conditions for the recognition of
procurement trainings or capacity development activities pursuant to Section 16 of
the 2016 revised IRR of RA 9184, and to confer authority to the existing pool of
trainers of the Government Procurement Policy Board – Technical Support Office
(GPPB-TSO) to conduct procurement trainings.
2.1 All Departments, Bureaus, Offices and Agencies of the National Government
including State Universities and Colleges, Government Owned and/or
Controlled Corporations, Government Financial Institutions, and Local
Government Units; and
3.1 Pursuant to Section 16 of the 2016 revised IRR of RA 9184, the GPPB shall
establish a sustained training program to develop the capability of the Bids
and Awards Committees (BACs), BAC Secretariats, Technical Working
Groups (TWGs), and the Procurement Units of Procuring Entities, and
professionalize the same.
3.2 The Head of the Procuring Entity (HoPE) shall ensure that the BAC, its
Secretariat and TWG members, including other relevant procurement
personnel are sent to attend procurement training or capacity development
program.
3.3 Within six (6) months upon designation, the BAC, its Secretariat and TWG
members should have satisfactorily completed such training or program
conducted, authorized or accredited by the GPPB through its TSO.
387
Issued through GPPB Resolution No. 12-2018, dated 04 September 2018, published in the Philippine Daily Inquirer on 20
March 2019.
340
Guidelines and Conditions in the Recognition of GPPB Appendix 29
Procurement Trainings or Capacity Development Activities
pursuant to Section 16 of Republic Act (RA) No. 9184 and its
2016 revised Implementing Rules and Regulations (IRR) and
the Recognition of the Existing Pool of Procurement Trainers
4.1 Provided that it shall meet the parameters set forth in this Circular, the
following are considered as training or capacity development activities by
GPPB:
341
Guidelines and Conditions in the Recognition of GPPB Appendix 29
Procurement Trainings or Capacity Development Activities
pursuant to Section 16 of Republic Act (RA) No. 9184 and its
2016 revised Implementing Rules and Regulations (IRR) and
the Recognition of the Existing Pool of Procurement Trainers
342
Guidelines and Conditions in the Recognition of GPPB Appendix 29
Procurement Trainings or Capacity Development Activities
pursuant to Section 16 of Republic Act (RA) No. 9184 and its
2016 revised Implementing Rules and Regulations (IRR) and
the Recognition of the Existing Pool of Procurement Trainers
343
Guidelines and Conditions in the Recognition of GPPB Appendix 29
Procurement Trainings or Capacity Development Activities
pursuant to Section 16 of Republic Act (RA) No. 9184 and its
2016 revised Implementing Rules and Regulations (IRR) and
the Recognition of the Existing Pool of Procurement Trainers
The Basic Level must be completed in two (2) days from the date
of registration. It includes eight (8) modules and an objective type
of examination where the user must be able to obtain a passing
score. A Certificate of Completion shall be issued to users who
shall successfully complete the level. Completion of this level will
provide access to the succeeding levels.
Modules include:
An exam shall be provided towards the end of the Basic Level for
which a Certificate of Completion shall be issued to successful
users.
Modules include:
344
Guidelines and Conditions in the Recognition of GPPB Appendix 29
Procurement Trainings or Capacity Development Activities
pursuant to Section 16 of Republic Act (RA) No. 9184 and its
2016 revised Implementing Rules and Regulations (IRR) and
the Recognition of the Existing Pool of Procurement Trainers
The Advanced Level must be completed in two (2) days from the
date of completion of the Intermediate Level. At the end of the
2nd day, the modules for this level shall no longer be accessed.
Modules include:
7.3.1 Upon completion of the Advanced Level, the user has the option
to take the final examinations, the coverage of which includes the
content of all three (3) levels. A passing score will entitle the user
a certificate of completion of the entire Procurement eLearning
Program.
8.1 The GPPB-TSO has an existing pool of recognized trainers who are tapped as
speakers/lecturers to conduct procurement trainings nationwide.
8.2 The GPPB-TSO trainers are recognized after having successfully completed
the Recruitment, Selection, Recognition and Retention Program of the GPPB-
TSO composed of the following stages:
345
Guidelines and Conditions in the Recognition of GPPB Appendix 29
Procurement Trainings or Capacity Development Activities
pursuant to Section 16 of Republic Act (RA) No. 9184 and its
2016 revised Implementing Rules and Regulations (IRR) and
the Recognition of the Existing Pool of Procurement Trainers
8.3 Due to the acquired expertise gained from years of experience, and the
extensive work and research on government procurement, the GPPBTSO
officials and staff, both past and present, shall be recognized trainers on
government procurement subject to compliance with the requirements of the
GPPB-TSO’s Recruitment, Selection, Recognition and Retention Program, or
such other requirements or compliance mechanism instituted by the GPPB-
TSO.
8.4 The GPPB shall recognize GPPB-TSO recognized trainers among the
authorized resource speakers/lecturers to be tapped and/or conduct
procurement trainings pursuant to Sections 4.1.2 and 4.1.3, upon satisfaction
of the following requirements:
8.5 The GPPB-TSO shall maintain an updated list of recognized GPPB Trainers in
its website.
9.0 This Circular shall take effect after fifteen (15) days following the publication in the
Official Gazette or a newspaper of general nationwide circulation and upon filing
with the University of the Philippines Law Center of three (3) certified true copies of
this Resolution.
346
Guidelines on the Use of the Virtual Store for the Procurement Appendix 30
of Common-Use Supply and Equipment
APPENDIX 30
GUIDELINES ON THE USE OF THE VIRTUAL STORE FOR THE PROCUREMENT OF
COMMON-USE SUPPLY AND EQUIPMENT 388
1. Policy Statement
1.1 It has been the policy of the government to promote transparency and
efficiency, and use of information and communications technology in the
conduct of procurement. Accordingly, Section 8 of Republic Act (RA) No. 9184
and Section 8.1.1 of the 2016 revised Implementing Rules and Regulations
(IRR), the Philippine Government Electronic Procurement System (PhilGEPS)
shall serve as the primary and definitive source of information on government
procurement.
1.2 Section 8.1.2 of the revised IRR further provides that in order to take
advantage of the significant built-in efficiencies of the PhilGEPS and the volume
discounts inherent in bulk purchasing, all Procuring Entities shall utilize the
PhilGEPS for the procurement of Common-Use Supplies and Equipment (CSE).
Moreover, Section 8.2.4.1 thereof authorizes the ordering of common-use and
non-common use items online through a virtual store feature of the PhilGEPS.
1.3 In furtherance of these objectives, the PhilGEPS was upgraded to adapt to the
developments in modern technology and to improve its responsiveness to the
needs of all procurement stakeholders through the introduction of the
Modernized PhilGEPS (mPhilGEPS) project.
2. Scope
2.1. This Guidelines shall apply to the procurement of CSEs from the Virtual Store
by all departments, bureaus, offices, and instrumentalities of all branches in
the government, including state universities and colleges (SUCs), government-
owned or controlled corporations (GOCCs), government financial institutions
(GFIs), and local government units (LGUs) in the procurement of CSEs included
in the Electronic Catalogue.
2.2. The GPPB shall promulgate separate guidelines for the procurement of Non-
Common Use Supplies and Equipment from the Virtual Store once the
mPhilGEPS functionality for this purpose has been developed.
3. Definition of Terms
For purposes of this Guidelines, the following terms words and phrases shall mean or
be understood as follows:
388
Issued through GPPB Resolution No. 20-2018, dated 18 October 2018, published in the Philippine Daily Inquirer on 4 May
2019.
347
Guidelines on the Use of the Virtual Store for the Procurement Appendix 30
of Common-Use Supply and Equipment
3.3 Allowable Area – within Metro Manila and provinces within a 35-kilometer
radius from the Procurement Service (PS) – Main Office.
3.8 Depot – refers to the warehouse facilities of the PS that physically receives,
stores, and distributes CSEs.
3.9 Electronic Catalogue – refers to the feature of the mPhilGEPS that shows an
online list of CSE items available in the PS.
3.10 Electronic Wallet (eWallet) – refers to the online service that allows
Agencies to pay for CSEs procured from the Virtual Store using a unique
number created in the Virtual Store System and assigned to an Agency upon
registration.
3.11 eWallet Balance – refers to the available cash remitted in advance by the
Agency to PS for the procurement of CSEs.
3.13 Notice of Cash Allocation (NCA) – refers to the Cash authority issued by
the DBM to central, regional and provincial offices and other operating units
through the authorized government servicing banks of the Modified
Disbursement Scheme, to cover the cash requirements of the Agencies.
3.14 Virtual Store – refers to the online service of the mPhilGEPS that allows
Agencies to view, search, select, and procure CSEs.
348
Guidelines on the Use of the Virtual Store for the Procurement Appendix 30
of Common-Use Supply and Equipment
All Agencies are mandated to fully use the mPhilGEPS for the procurement of CSEs
through its Virtual Store feature in accordance with Section 8 of the revised IRR of RA
No. 9184.
5.1. Agencies shall register with the Virtual Store by filling out the Virtual Store
Buyer Registration Form to be provided by the PS, which shall be signed by the
HOPE or his/her authorized representative.
5.2. Agencies shall upload their approved APP-CSE in the mPhilGEPS, which shall be
the basis of procurement from the Virtual Store. Once uploaded, the APP-CSE
shall be the basis of the PS in forecasting CSE demands for the applicable
budget year.
The authorized APP-CSE Uploader shall upload in the mPhilGEPS the approved
APP-CSE for the succeeding budget year not later than 31 August of the
current year in accordance with the format prescribed by the PS.
5.3. Any amendments to the uploaded APP-CSE may only be made by the APP-CSE
Uploader and shall be consistent with the Agency’s duly approved yearly
budget. The approval of the APP-CSE Approver is needed before the Agency
Buyer can procure based on the revised items and/or quantities.
5.4. The PS shall create an eWallet for the Agencies for the purpose of depositing
funds, which shall be used to pay for the CSEs procured from the Virtual Store.
5.4.1. Agencies shall initially deposit cash funds equivalent to three (3)
months of their APP-CSE, whether allocated for the Maintenance and
Other Operating Expenses or the Capital Outlay, to a single fund in
the PS against which payment for CSEs procured through the Virtual
Store will be charged.
Agencies shall remit to PS, within five (5) working days from receipt
of NCA, the amount equivalent to the eWallet Balance required
herein.
349
Guidelines on the Use of the Virtual Store for the Procurement Appendix 30
of Common-Use Supply and Equipment
5.4.4. Agencies shall be responsible for ensuring that the use of funds for
procurement through the Virtual Store are in accordance with
existing budgeting, accounting, and auditing rules and regulations.
6.1 Agencies can only procure CSEs in accordance with the items and quantities
indicated in their uploaded APP-CSE. Only the authorized Agency Buyer/s can
procure CSEs from the Virtual Store.
Upon confirmation of the order, the Virtual Store shall send an electronic mail
confirming the order to the Agency Buyer who placed the order.
6.2 CSEs that are not currently available from the assigned Depot will be listed in
the Certificate of Non-availability of Stocks (CNAS) appearing in the Virtual
Store of the assigned depot, and may then be procured from sources other
than the Virtual Store without the need of securing the Certificate of Non
availability of Stocks (CNAS), subject to the following: 389
a. The item is not available from the DBM-PS, as shown on its website; and
b. Procuring Entities shall keep a record of the proof of unavailability of the
CSE as shown in the PS website, such as a printed form of the webpage or a
screenshot of the same showing the date and time that it was accessed.
6.3 The PS shall have a user help desk which offers support through a hotline to
solve problems Agencies may face during their online order operations. The PS
shall likewise provide a kiosk for walk-in Agencies for the purpose of procuring
from the Virtual Store.
7. Payment
7.1. The Virtual Store will automatically draw down from the eWallet and update
the eWallet Balance upon order confirmation.
In the event that the eWallet Balance is insufficient to cover the amount of the
CSEs to be procured, the Virtual Store will automatically reject the order.
8.1. CSEs procured from the Virtual Store may be obtained within a specific number
of days as determined by PS through any of the following modes:
8.1.1. Pick-up from PS warehouse or Depots – the Agency arranges for its
own transportation to pick-up the procured CSEs from the PS
warehouse or Depot. Agencies identified by a Depot as located in a
389
As amended by GPPB Resolution No. 17-2020, dated 18 September 2020, published in the Philippine Star on 26 September
2020
350
Guidelines on the Use of the Virtual Store for the Procurement Appendix 30
of Common-Use Supply and Equipment
8.2. For all deliveries, the agency shall designate an official “Drop Point” located at
the ground floor of the office building or storage area where ordered goods will
be delivered and unloaded.
8.3. In case of pickup under Section 8.1.1, inspection shall be conducted by the
Agency’s authorized representative as to the correctness of the item ordered
and quantity prior to release.
8.4. In the case of deliveries under Sections 8.1.2 to 8.1.4, inspection shall be
conducted by the Agency’s authorized representative as to the correctness of
the item/s ordered and quantity upon delivery to the Agency’s registered
delivery location.
8.5. In all instances of delivery, the Agency’s authorized representative shall sign a
Delivery Receipt acknowledging that the item /s and quantity is the same as
that procured in the Virtual Store. In case of shortages, the agency shall notify
PS the discrepancy in the Delivery Receipt. Upon notification, the PS shall then
deliver to complete the order.
8.6. Return of CSEs procured, whether due to defects or error committed by the
Agency in selecting the item or such other acceptable reason, shall comply with
the PS return policies and procedure.
The interpretation of the provisions in this Guidelines, including cases not covered
herein, shall be submitted to the PS for resolution of the GPPB or its Technical Support
Office.
If, for any reason, any part or provision of this Guidelines is declared invalid or
unconstitutional, any part or provision not affected thereby shall remain in full force
and effect.
351
Guidelines on the Use of the Virtual Store for the Procurement Appendix 30
of Common-Use Supply and Equipment
All issuances that are inconsistent or contrary to the provisions of this Guidelines are
hereby repealed or modified accordingly.
12. Effectivity
This Guidelines shall take effect immediately upon publication in the Official Gazette or
in a newspaper of general nationwide circulation.
352
Guidelines on the Implementation of Early Procurement Appendix 31
Activities (EPA)
APPENDIX 31
GUIDELINES ON THE IMPLEMENTATION OF EARLY PROCUREMENT ACTIVITIES
(EPA) 390
1.2 This Guidelines shall cover all types of procurement for goods, infrastructure
projects and consulting services funded out of or by the General Appropriations
Act (GAA), appropriations ordinance, corporate budget, or loan agreement in
case of Foreign-Assisted Projects (FAPs).
2. PREPARATORY ACTIVITIES
2.1 The procuring entity (PE) shall complete all the appropriate preparatory
activities such as, but not limited to, cost-benefit analysis, feasibility studies,
market research, and detailed engineering designs, regulatory clearances and
right of way acquisitions for civil works projects prior to the approval of the
indicative APP.
390
Issued through GPPB Resolution No. 14-2019, dated 17 July 2019, published in the Official Gazette on 26 August 2019.
353
Guidelines on the Implementation of Early Procurement Appendix 31
Activities (EPA)
2.2 The indicative APP must be duly approved by the Head of the Procuring Entity
(HoPE) and submitted to:
2.3 The indicative APP shall be posted on the agency’s Transparency Seal pursuant
to DBM Circular Letter No. 2018- 8 dated 30 July 2018.
2.5 The PE shall expressly provide in the bidding documents and through PhilGEPS
posting that the Procurement Project is undertaken through EPA. The PE shall
likewise ensure that the prospective bidders are properly informed, through the
bidding documents and during the pre-bid conference, of all the implications of
a Procurement Project undertaken through EPA. This shall include, but not
limited to the:
3. IMPLEMENTING GUIDELINES
3.1 EPA shall refer to the conduct of procurement activities, from posting of the
procurement opportunity, if required, until recommendation of the Bids and
Awards Committee (BAC) to the HoPE as to the award of the contract, for
goods to be delivered, infrastructure projects to be implemented and
consulting services to be rendered in the following fiscal year, pending
approval of their respective funding sources.
3.2 The award of contract for Procurement Projects undertaken through EPA may
be made only upon:
354
Guidelines on the Implementation of Early Procurement Appendix 31
Activities (EPA)
3.3 PEs are encouraged to undertake EPA to ensure the timely delivery of goods,
implementation of infrastructure projects and rendition of consultancy services.
3.3.2 For Procurement Projects funded by corporate and local funds, the
EPA may be undertaken from the time the proposed corporate or
local budget has been submitted to the approving authority.
3.4 Rules for Procurement Projects to be funded from a Source Agency and
Implemented by a Recipient Agency.
355
Guidelines on the Implementation of Early Procurement Appendix 31
Activities (EPA)
For example:
3.5 The source and recipient agencies shall ensure that any and all conditions or
documents required to be met or submitted as a prerequisite for the release of
funds or sub-allotment thereof shall be timely prepared to enable the
implementing agency to award the contract within the prescribed period.
4. BID VALIDITY
The PE may request the bidders to extend the validity of their bid securities beyond
one hundred twenty (120) calendar days, prior to their expiration, if the funding
source for the Procurement Project has yet to be approved and made effective.
356
Guidelines on the Implementation of Early Procurement Appendix 31
Activities (EPA)
A change in the form of the bid security is allowed if this is made prior to the
expiration of the bid validity sought to be extended.
If the bidder refuses to extend the bid validity, the PE shall reject the bid submitted by
said bidder.
5. PROCUREMENT TIMELINES
The conduct of EPA from posting to recommendation of the BAC to the HoPE as to the
award of the contract shall observe the mandatory timelines set forth in the 2016
revised Implementing Rules and Regulations (IRR) of Republic Act No. (RA) No. 9184,
including the period for re-bidding which shall be within fifteen (15) days after each
declaration of failure of bidding, which may be extended up to thirty (30) days upon
approval of the HoPE.
6.1 As soon as the funding source for the Procurement Project has been approved,
regardless of the stage of the EPA, the indicative APP shall be revised and
approved in accordance with Section 7.2 of the 2016 revised IRR of RA No.
9184.
6.2 Upon approval of the APP and the commencement of the running of the period
to award the contract and complete the procurement process, the HoPE may
approve or disapprove the recommendation of the BAC.
In case of approval, the HoPE shall issue the Notice of Award to the Lowest
Calculated Responsive Bid or Highest Rated Responsive Bid, as the case may
be, and thereafter sign the contract.
In case of disapproval, the HoPE shall notify the BAC and the bidder in writing
of such decision and the grounds thereof which shall be any of the grounds
provided for under Section 41 of the 2016 revised IRR of RA No. 9184.
6.3 The final approved APP shall be submitted to the GPPB on or before the end of
January of the budget year, and shall be posted in accordance with Executive
Order No. 662, series of 2007, as amended (refer to Appendix 1 for the revised
APP form for the conduct of EPA).
7. AWARD OF CONTRACT
For example:
357
Guidelines on the Implementation of Early Procurement Appendix 31
Activities (EPA)
Agency A’s Approved Budget for the Contract (ABC)for its procurement of
heavy-duty shredders is 1 Million Pesos as authorized in the NEP and after
undertaking EPA the contract price to be awarded amounts to 1 Million Pesos,
Agency A may award the contract upon approval and effectivity of the GAA.
However, in the case of a reenacted budget, the PE may only award the
contract for Recurring Procurement Projects and not for new Procurement
Projects. Recurring Procurement Projects shall refer to Procurement Projects
included in the previous year’s budget which has been reenacted in or for the
current year.
7.2 If the amount authorized for a Procurement Project has been reduced, the PE
may still make an award if the contract price to be awarded is within the
amount authorized in the GAA, reenacted budget, appropriations ordinance,
corporate budget, or loan agreement regardless of the posted ABC.
For example:
Agency A’s ABC for its procurement of printers is 1.2 Million Pesos as
authorized in the NEP and after undertaking EPA the contract price to be
awarded is1 Million Pesos. If the budget is reduced to 1 Million Pesos, Agency
A may award the contract because the contract price to be awarded is within
the amount authorized.
7.3 The HoPE shall not award any Procurement Project if the amount therefor has
been withdrawn or in the event the amount authorized in the GAA, reenacted
budget, appropriations ordinance, corporate budget, or loan agreement is
lower than the amount of contract to be awarded.
For example:
a. Agency A’s ABC for its procurement of LED lighting system for its
auditorium is 1.5 Million Pesos as authorized in the NEP and after
undertaking EPA the contract price to be awarded is 1.3 Million Pesos. If
the budget is withdrawn, Agency A shall NOT award the contract
pursuant to Sec. 41(c) (iii) of the 2016 revised IRR of RA No. 9184.
7.4 In all instances, the HoPE has the authority to exercise the reservation clause
under Section 41 of RA No. 9184, which grants the HoPE the right not to award
the contract if, for any justifiable and reasonable ground, the award of the
contract will not redound to the benefit of the government.
7.5 Notwithstanding the approval and effectivity of the GAA, reenacted budget,
appropriations ordinance, corporate budget or loan agreement, as the case
may be, PEs shall not award contracts for Procurement Projects requiring
358
Guidelines on the Implementation of Early Procurement Appendix 31
Activities (EPA)
Special Allotment Release Order or Sub-Allotment Release Order until the same
has been issued, secured or released.
8.1. Pursuant to Section 85 of Presidential Decree No. 1445 or the State Audit Code,
no contract involving the expenditure of public funds shall be entered into
unless there is an appropriation. Accordingly, pending approval and effectivity
of the GAA, corporate budget or appropriations ordinance, or the loan
agreement in the case of FAPs, the following periods shall be tolled or
suspended:
8.1.1 the fifteen-day (15 day) period for the HoPE to approve the
Resolution of the BAC and to issue the Notice of Award provided
under Section 37; and
8.2. The period of time for the award of contract and termination of the
procurement process, as the case may be, shall begin to run again upon the
approval and effectivity of the GAA, reenacted budget, appropriations
ordinance, corporate budget or loan agreement, as the case may be.
It shall not commence anew but rather, grants the HoPE the balance of the
remaining period to award the contract or terminate the procurement process.
For example:
The BAC conducted the Bid Opening on 30 July and the BAC issued a
Resolution recommending award of the contract on 11 October.
The 3-month period to complete the procurement process and the 15-day
period for the HoPE to approve the contract are suspended beginning 12
October.
The HoPE has seventeen (17) days to complete the procurement process from
the approval and effectivity of the funding source. This is the period remaining
from the 3-month period to complete the procurement process, i.e., 90 days
less 73 days (or the period covering July 30 to October 11).
If the approval and effectivity of the GAA is 1 January, the 3month period to
complete the procurement process and the 15day period for the HoPE to
approve the contract shall run again and the HoPE has (i) 15 days or until 16
January to award; and (ii) 17 days or until 18 January to complete the
procurement process.
359
Guidelines on the Implementation of Early Procurement Appendix 31
Activities (EPA)
9. MONITORING
Projects undertaken through EPA shall be reported in the APP under a column
separate from the regular procurement activities (refer to Appendix 1 for the
revised APP form for the conduct of EPA).
10. EFFECTIVITY
360
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
APPENDIX 32
GUIDELINES ON THE USE OF FRAMEWORK AGREEMENT BY ALL PROCURING
ENTITIES 391
1. PURPOSE
This Guidelines shall prescribe the rules for the use of Framework Agreement,
including the procedure in the conduct of public bidding that will be subject of
Framework Agreement.
2.1 This Guidelines shall govern the use of Framework Agreement by all
departments, bureaus, offices, and agencies of the national government,
government owned or controlled corporations, government financial
institutions, state universities and colleges, and local government units.
2.2.1 for the procurement of goods and services which are repeatedly
required but by their nature, use, or characteristic, the quantity or
exact time of need cannot be accurately predetermined; and
2.2.2 for the procurement of goods which are not advisable to be carried
in stock.
3. DEFINITION OF TERMS
3.2 Call for Mini Competition. Refers to a written request from the procuring
entity inviting all parties to a multi-year Framework Agreement to submit their
best price proposal for items or services subject of Mini Competition.
391
Issued through GPPB Resolution No. 27-2019 dated 10 December 2019, published in the Official Gazette on 30 December
2019 and supersedes the Revised Guidelines on Ordering Agreement.
361
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
3.4 Framework Agreement List. Refers to the list of goods or services, and their
corresponding technical specifications, scope of work, projected quantities, and
estimated prices, subject of the Framework Agreement.
This shall be limited to repeatedly required goods or services that are identified
to be necessary and desirable, but, by its nature, use, or characteristic, the
quantity and/or exact time of need cannot be accurately pre-determined and
are not advisable to be carried in stock.
4. GENERAL CONDITIONS
4.1 Procuring entities may use Framework Agreement if the Bids and Awards
Committee (BAC) determines that entering in a Framework Agreement is more
practical, economical, and advantageous for the procuring entity, based on the
study or evaluation conducted by the end-user unit representative showing
that:
362
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
4.1.5 Procuring entity will benefit from the fixed price or lower price for
the duration of the Framework Agreement;
4.1.6 Call-Offs at the time of actual need will result in the optimum usage
of the ABC; or
4.2 The procurement of goods and services under a Framework Agreement shall
be conducted following the procedure for competitive bidding provided in RA
No. 9184 and its revised IRR, subject to Item 6 of this Guidelines.
6. PROCUREMENT PLANNING
6.1 The Framework Agreement List shall be prepared in the most practical and
efficient manner that will encourage participation and competition among
interested suppliers or service providers in the relevant industry. The
Framework Agreement List shall be prepared taking into consideration the
following:
363
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
6.1.4 The cost per item or service shall be determined and prepared after
careful consideration of variables and factors that may affect future
market prices using, whenever applicable, historical data, market
study, feasibility study, net present value of money, foreign
exchange rate, inflation rate, cost of money, assessment of Total
Cost of Ownership, Life Cycle Costing and Value for Money analysis
taking into consideration the timeframe and period for the
implementation of the Framework Agreement.
6.2 No procurement shall be undertaken under this Guidelines unless the same is
in accordance with the Annual Procurement Plan (APP) and the Project
Procurement Management Plan (PPMP) prepared by the procuring entity. The
procuring entity, in the preparation of its APP, shall include procurement
projects that will be subjected to Framework Agreements, and attach all
Framework Agreement Lists as part of the APP.
364
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
The issuance of MYCA shall be subject to existing budgeting and auditing rules
and regulations.
7. COMPETITIVE BIDDING
7.1 The procuring entity shall conduct competitive bidding using a single stage,
two-envelope procedure as prescribed in Sections 23 and 25 of RA No. 9184
and its revised IRR. For this purpose, the procuring entity, through its BAC,
shall prepare, separate technical specifications or scope of work for every item
to be bidded out and indicate, among others, total cost for each item, the
maximum quantity it may procure when needed, and the requested delivery or
performance lead time from issuance of the Call-Off or from any date
determined by the procuring entity.
7.2 The Invitation to Bid shall indicate that the procurement will be subject to a
Framework Agreement pursuant to this Guidelines, and shall state whether the
Framework Agreement is for a single or multi-year Framework Agreement.
7.3 For multi-year Framework Agreement, the ABC for the first year shall be the
basis in computing for the required amount of the single largest completed
contract, net financial contracting capacity, bid security, bidding documents fee
and protest fee.
7.4 The procedure and requirements for Competitive Bidding provided in RA No.
9184 and its revised IRR shall apply while the Lowest Calculated and
Responsive Bidder (LCRB) shall be determined as follows:
365
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
7.5 Prices quoted by the bidder must be within the total cost per item as provided
in the Framework Agreement List. Financial bid offer that provides price
quotations that exceeds the total cost per item shall be automatically
disqualified.
8. FRAMEWORK AGREEMENT
8.1 Within ten (10) calendar days from receipt by the participating bidder(s) of the
Notification to Execute a Framework Agreement with the procuring entity, the
bidder or its duly authorized representative shall formally enter into a
Framework Agreement with the procuring entity for an amount of One Peso
(Php 1.00) to be paid by the procuring entity as a consideration for the option
granted to the procuring entity to procure the items in the Framework
Agreement List when the need arises.
8.2 Framework Agreements shall include the following: (a) Framework Agreement
List; (b) a provision that the perfection of the actual procurement contract shall
be reckoned from the execution of the Call-Offs; and (c) statement that upon
the execution of the Call-Offs, all rules and guidelines governing
implementation of procurement contracts under RA No. 9184 and its revised
IRR shall be applicable.
8.4 Framework Agreements shall not state or imply any agreement by the
procuring entity to place future contracts or make orders with the supplier or
service provider.
366
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
8.6 Framework Agreements shall be valid only for the period stated in the bidding
documents which, shall not exceed three (3) years from the time the
Framework Agreement was entered into and executed by the parties, and shall
not be extended beyond its lifetime.
8.7 To guarantee the faithful performance by the supplier or service provider of its
obligations under the Framework Agreement, it shall submit a performance
security in accordance with Section 39 of the revised IRR of RA No. 9184 or a
Performance Securing Declaration as defined under this Guidelines prior to the
signing of the Framework Agreement.
8.8 The basis for the computation of the performance security shall be the total
contract price whether the procurement is for a single or multi-year framework
agreement.
8.9 Notwithstanding the eligibility of a bidder, the BAC reserves the right to review
the qualifications of the supplier or service provider. If there has been any
change in the capability of the supplier or service provider to undertake its
obligations under the framework agreement so that if it fails the eligibility
criteria set thereon, the procuring entity shall consider the said supplier or
service provider as ineligible and shall disqualify it from obtaining any award or
contract.
8.10 Bidders executing the Framework Agreement either for single or multi-year
shall ensure the continuing validity of their eligibility documents during the
implementation of the contract.
9. CALL OFF
9.1. When the procuring entity has determined that an item or service covered in
the Framework Agreement is needed, it shall require the delivery of the
item or rendition of the service identified in the Framework Agreement List in
such quantity or scope and at the price for which it was awarded by
executing a Call-Off.
9.2. For a single-year Framework Agreement, Call-off may be executed and issued
to the winning supplier or service provider immediately upon determination
that an item or service is needed.
9.3. For a multi-year Framework Agreement, Call-off shall be issued after conduct
of mini competition in favor of the supplier or service provider that provided
the lowest calculated and responsive bid.
9.4. The BAC may execute as many Call-Offs for the same item as may be needed
within the period of the Framework Agreement as long as the total quantity for
all Call-Offs do not exceed the maximum quantity in the Framework Agreement
List and the aggregate amount of all executed Call-Offs do not exceed the total
contract price specified in the Framework Agreement.
367
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
9.5. The succeeding Call-Offs shall have the same unit price based on the financial
bid offer in case of single-year Framework Agreement. For multi-year
Framework Agreement with multiple qualified bidders, the price depends on
the result of each Mini-Competition but not to exceed the price submitted
during the initial submission of the bidders’ financial bid as provided in Section
7.4.2 of this Guidelines.
9.6. The BAC may execute Call-Offs requiring delivery to multiple destinations or
performance at multiple locations.
9.7. For purposes of participation in other public bidding activities, the aggregate of
the Call-Offs for a particular item or similar items satisfactorily completed by
the supplier or service provider shall be considered as one (1) completed
contract with the cumulative amount thereof as the total contract amount. In
such case, the date appearing in the Certificate of Acceptance issued by the
procuring entity for the last delivery will be considered as the date of
completion of the contract. On the other hand, only those undelivered items in
the Call-Offs executed by the procuring entity shall be included in the
Statement of All Ongoing Government and Private Contracts for purposes of
participating in other bidding activities.
10.1 After receipt by the supplier or service provider of the Call-Off from the
procuring entity, it shall deliver or perform the items within the period specified
in the Framework Agreement, unless a different time is provided in the Call-Off.
10.2 Any extension of time for the delivery or performance shall be made in writing
and prior to the date of deliver or performance indicated in the Framework
Agreement or Call-Off and subject to prior approval by the procuring entity
after consideration of reasonable and justifiable causes.
10.3 If the supplier or service provider fails to deliver or perform within the agreed
period, including any time extension, it shall be liable to the procuring entity for
liquidated damages of at least equal to one-tenth of one percent (.001) of the
cost of the unperformed portion of the total amount of the items ordered per
Call-Off for every day of delay.
10.4 Once the cumulative amount of liquidated damages reaches ten percent (10%)
of the total amount of the items ordered per Call-Off, the procuring entity may
rescind the same, without prejudice to other courses of action and remedies
open to it.
10.5 The Warranty provision for goods under Section 62 of RA No. 9184 and its
revised IRR shall be observed under the Framework Agreement, and shall be
required for each Call-Off.
368
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
10.6 Without prejudice to the provisions of applicable laws, rules, and guidelines,
the Framework Agreement shall automatically terminate under any of the
following conditions:
10.7 All other rules governing contract implementation and termination under RA
No. 9184, its revised IRR, and relevant procurement policies shall be
applicable.
11.1 No Repeat Order for an item in the Framework Agreement List shall be allowed
until after the procuring entity has exhausted the maximum quantity for the
same item specified therein or after the Framework Agreement has expired,
whichever comes first and subject to the conditions provided in Section 51 of
RA No. 9184 and its revised IRR. For this purpose, the Repeat Order may only
be availed of within six (6) months from the date of the last or final Call-Off for
a specific item where the maximum quantity has been exhausted or from the
expiration of the Framework Agreement.
11.2 In case Repeat Order is allowed and resorted to, the twenty five percent (25%)
maximum allowable quantity shall be based on the aggregate quantity of actual
items ordered and delivered.
This Guidelines repeal GPPB Resolution Nos. 06-2005 and 01-2012, dated 01 April
2005 and 27 January 2012, respectively.
13. EFFECTIVITY
369
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
370
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
371
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
372
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
373
Guidelines on the Use of Framework Agreement by All Appendix 32
Procuring Entities
374
Transparency, Accountability, and Good Governance in the Appendix 33
Procurement Process
APPENDIX 33
TRANSPARENCY, ACCOUNTABILITY, AND GOOD GOVERNANCE IN THE
PROCUREMENT PROCESS 393
1.0 OBJECTIVE
This Circular is being issued to remind all Procuring Entities (PEs) to strictly
comply with the existing rules on transparency, accountability, and good
governance policies and measures in the procurement process.
This Circular shall apply to all PEs or any branch, agency, department, bureau,
office, or instrumentality of the Government of the Philippines, National
Government Agencies, including Government-Owned and/or Controlled
Corporations, Government Financial Institutions, State Universities and Colleges,
and Local Government Units.
TABLE 1
Philippine
Government
Conspicuous
Electronic
place reservedfor
Procurement PE’s Others
this purpose in
Legal Document or System website,if
thepremises of
Basis Information (PhilGEPS) any
the PE
Website
Competitive Bidding:
Sec. 8.4.2,
Invitation to Bid (Goods
IRR of RA ✓
and Infrastructure Projects) ✓ ✓
No. 9184
Sec. 8.4.2,
Request for Expressionof
IRR of RA ✓
Interest (ConsultingServices) ✓ ✓
No. 9184
Secs. 8.4.2
and 17.4,IRR Downloadable complete
✓
of RANo. BiddingDocuments ✓ ✓
9184
Send to all those
Sec. 8.4.3,
Supplemental BidBulletin, if who have properly
IRR of RA
applicable ✓ ✓ ✓ secured the Bidding
No. 9184
Documents
393
GPPB Circular No. 01-2021 issued through GPPB Resolution No. 04-2021 dated 4 March 2021, published in The Philippine
Star on 15 March 2021.
375
Transparency, Accountability, and Good Governance in the Appendix 33
Procurement Process
Sec. 37.1.6,
IRR of RANo. Notice of Award (NOA) ✓ ✓ ✓
9184
Sec. 37.4.2,
IRR of RANo. Notice to Proceed(NTP) ✓
✓
9184
Sec. 37.4.2,
IRR of RANo. Approved Contract ✓ ✓
9184
Item
V(C)(2)((b)
Extension of the deadline in
(v), Annex
Shopping ✓ ✓ ✓
“H”, IRR of
RA No. 9184
NOA, Contract or Purchase
Item Order (PO), including NTP if
IV(L)(2) necessary, except for
Annex “H”, contracts with Approved
✓ ✓ ✓
IRR of RA Budget for the Contract
No. 9184 (ABC) of PhP50,000
and below
GPPB
Notice of the lifting of the
Reso. No.09- ✓
suspension
2020
4.2. Official websites and social media platforms maintained and used by the
PEs shall serve as the secondary source of critical procurement
376
Transparency, Accountability, and Good Governance in the Appendix 33
Procurement Process
4.3 All agencies and instrumentalities under the Executive Department shall
post the following information on their official websites and social media
platforms in an organized manner and shall ensure its security and
integrity:
4.5 For PEs under the Executive Department whose projects have an ABC of
Fifty Million Pesos (PhP 50,000,000.00) and above, the post-award
information under Item 4.3(a) shall also be published once in a
newspaper of general circulation pursuant to Section 4 of AO No. 34.
5.1 The PhilGEPS shall provide a facility for observers, duly authorized by the
Bids and Awards Committee, to monitor the procurement proceedings
online, pursuant to Section 8.7 and Section 13 of the 2016 revised IRR of
394
Shall refer to the Invitation to Bid or Request for Expression of Interest pursuant to Section 8.4.2 of the 2016 revised IRR of
RA No. 9184, in relation to Section 21, and to Invitation or Request for submission of price quotations or proposals pursuant to
Section 54.2 of the 2016 revised IRR of RA No. 9184.
395
Shall refer to the Notice of Award pursuant to Section 37.1.6 and Section 37.4.2 of the 2016 revised IRR of RA No. 9184,
and to the Notice of Award, Contract or Purchase Order, including the Notice to Proceed, if necessary under Item IV(L)(2), Annex
“H”, of the 2016 revised IRR of RA No. 9184.
377
Transparency, Accountability, and Good Governance in the Appendix 33
Procurement Process
RA No. 9184.
5.2 PEs shall provide their duly-authorized observers online access to monitor
all stages of the procurement process through the modernized PhilGEPS.
Until such time that the modernized PhilGEPS becomes operational and is
able to provide said facility, PEs shall provide said observers online access
to monitor the conduct of procurement proceedings through their own
facilities.
5.2 PEs that are unable to provide the said online access shall inform the
GPPB- TSO in writing by emailing [email protected], together with
the reasons therefor, and shall be considered in the performance
evaluation of the PE through the Agency Procurement Compliance and
Performance Indicator System and the Procurement Monitoring Report.
6.1. All PEs must observe the rules and procedures provided under the
Uniform Guidelines for Blacklisting of Manufacturers, Suppliers,
Distributors, Contractors and Consultants as provided under GPPB
Resolution No. 40-2017 and GPPB Resolution No. 14-2020 on the
Prescribed Form of Blacklisting Order, Implementation of the Online
Blacklisting Portal (OBP) for Posting and Updating of Status of Blacklisted
Entities.
6.2 With the creation and mandatory use of the OBP which can be
accessed through
https://www.gppb.gov.ph/OnlineBlacklistingPortal/pages/1111d0b57dxx4f
dsd e96812839a349e18, the Consolidated Blacklisting Report (CBR) can
now be generated and updated real time, providing up-to-date
information that is readily accessible to all interested parties, including
the Commission on Audit. Likewise, the OBP provides automatic
notification to the PE, through its BAC Chairperson, and the PhilGEPS of
every posting and updating of the status of blacklisted entities made in the
OBP.
6.3 Pursuant to Section 5 of AO No. 34, the PhilGEPS shall post the CBR found
in this link [https://www.gppb.gov.ph/ConsolidatedBlacklistingReport.php]
on its website and all PEs under the Executive Department are directed to
post the said CBR on their official website and social media platforms.
Sgd.
WENDEL E. AVISADO
Chairperson
GPPB
378
GPPB ALTERNATE MEMBERS AND
INTER-AGENCY TECHNICAL WORKING GROUP MEMBERS
Resource Person
Assistant Commissioner Alexander B. Juliano
(Commission on Audit)
379
DEPARTMENT OF BUDGET AND MANAGEMENT
GOVERNMENT PROCUREMENT POLICY BOARD
TECHNICAL SUPPORT OFFICE
Unit 2504 Raffles Corporate Center, F. Ortigas Jr. Road, Ortigas Center, Pasig City
Tel. Nos. (02) 7-900-6741 to 44
www.gppb.gov.ph
380