(MCOF19M028) CF Assignment
(MCOF19M028) CF Assignment
Assignment of Corporate
Finance
Submitted
To
Submitted
By
Afsah Ibtasam
Electricity cost 800 units at the rate of 3 dollar per year and cost savings will decrease by
100 units per year.
425,000
Additional cash holding 8000
Additional investment inventory 4000
Concrete foundation of new machine 1000
Training of new machine operator 500
Shipping of new machine to plant site 300
13800
438800
Tax shield (11400* 40/100 )
4560
= 0.20+1.2(0.18-0.20)
= 0.176 or
= 17.6%
WACC = (0.30)(0.12)(1-0.40)+(0.30)(0.13)+(0.40)(0.176)
WACC = 0.131 or
= 13.1%
Securities w r wr
Debt 0,3 0,12 0,0216
Preferred stock 0,3 0,13 0,039
Common Stock 0,4 0,176 0,0704
Required Rate of Return 0,131
Cash Outflows =434240
NPV = 339006
1) Payback Period
IRR = lower rate + (difference in rate (+ve NPV/(+ve NPV + -ve NPV)
(1+0,13)^n (1+0.39)^n
Year CF at 13% Pv= CF/(1+r)^n at 39% Pv= CF/(1+r)^n
1 128198 1,130 113450 1,390 92229
2 161681 1,277 126620 1,932 83681
3 153827 1,443 106610 2,686 57278
4 157362 1,630 96513 3,733 42154
5 164158 1,842 89098 5,189 31636
6 166762 2,082 80099 7,213 23121
7 170859 2,353 72625 10,025 17043
8 242149 2,658 91087 13,935 17377
PV 776102 364519
= 341862
= -69721
IRR = lower rate + (difference in rate (+ve NPV/(+ve NPV + -ve NPV)
= 0.13 + (0.26 (341862 / (341862 + (-69721))
= 0.13 + (0.26(341862 / (411583)
= 0.13 + 0.21595
= 0.345
= 35%
3) Profitability index
This project is acceptable because of positive NPV and high internal rate of return.