F18 Module 8
F18 Module 8
MODULE
EIGHT
Draw a logical network diagram for making tea, using the following WBS:
Activity
Description Predecessor
ID
A Decide to make tea
B Put water in kettle A
C Put teabags in teapot A
D Put milk in cup A
E Boil water B
F Put boiled water in teapot C, E
G Put tea in cup F
H Drink tea D, G
MAKING TEA
Put
boiled
Put water Boil water in Pour tea Drink tea
Start
in kettle water teapot in cup
Put tea in
teapot
Put milk
in cup
Problem: you are restricted
by the number of hands you
have!
MAKING TEA
Put
boiled
Put water Boil water in Pour tea Drink tea
Start
in kettle water teapot in cup
Put tea in
teapot
The logic diagram and network assume that resources are unlimited – either in
total or some other constraint (e.g. skilled worker).
By adding in the resource view, we create the project schedule.
Time-phased resourcing also allow for the creation of a cost budget for the
project.
TECHNICAL VS RESOURCE CONSTRAINTS
TYPES OF SCHEDULING PROBLEMS
Time-constrained Resource-
constrained
Must be completed by
an imposed date. Must be completed
within an imposed
If project is late, add cost.
resources (cost).
If project is over cost,
Cost is flexible but add time.
should be minimized.
Time is flexible, but
should be minimized.
TWO TYPES OF SMOOTHING
Time-constrained
Although meeting the project timeline is the priority, we do not want to waste
resources.
Resource-constrained
Although meeting the project cost or other constrained resource requirements are
a priority, we still want to finish the project as soon as possible.
Disadvantages
Week
1 2 3 4
NETWORK NODE TO SCHEDULE CHART
NETWORK NODE TO SCHEDULE CHART
NETWORK NODE TO SCHEDULE CHART
2 2 2
RESOURCE-CONSTRAINED SMOOTHING
10 minutes
Licenced under CC
3.0
YOUR TURN – EXERCISE #6
Delays in one project can affect not just that project, but other ones as well.
There is always a chance that there will be idle resources or project delays due
to resource constraints – it is impossible for everything to be perfectly balanced.
This means that we want to optimize resource utilization as much as possible,
while planning for potential problems.
Organizationally, it will become evident over time where the problems tend to
occur (for example, it is consistent that resources are over-allocated) and this
can be planned for during the estimation process.
However – what might happen over time?
What are the potential root causes?
SCHEDULING IN THE PORTFOLIO
ENVIRONMENT
Recommendations:
1. Create project offices to oversee scheduling of resources across projects.
Question – does this actually mitigate conflicts?
2. Use a project priority queuing system: first come, first served for resources.
Question – is this the right way to manage prioritization?
3. Centralize project management (PMO) – treat all projects as part of one big
‘megaproject’. Question – how does this deal with complexity? How does it shift
organizational power relationships?
4. Outsource project to reduce the number of projects handled internally.
Question – if under-resourcing represents a risk, what risk option does this
recommendation use?
CREATING THE PROJECT COST BASELINE
WORKED EXAMPLE – EXERCISE #10
WORKED EXAMPLE – EXERCISE #10
WORKED EXAMPLE – EXERCISE #10
WORKED EXAMPLE – EXERCISE #10
TRY ON YOUR OWN – EXERCISE #9
Continue to work on the Risk Cases, and remember to submit prior to your due
date, with your team minutes!
Next week we will be talking about reducing project durations. Watch the video
posted on FOL to help prepare yourself.
READ Chapter 9, Reducing Project Duration, Project Management 7E – Larson
and Gray.