Single Tap Double Block and Bleed Isolation Cuts Costs of Pipeline Piggability Expansion
Single Tap Double Block and Bleed Isolation Cuts Costs of Pipeline Piggability Expansion
What’s Inside:
» Common High Pressure PIPELINE OPERATORS PERFORM INLINE INSPECTION (ILI)
Isolation Challenges
to evaluate the integrity of natural gas and hazardous liquid
» Double Block and Bleed Defined pipelines. By providing an indirect measurement of pipeline
features and anomalies, including corrosion, dents, and
» Benefits of Single Tap gouges, ILI can help operators prioritize repairs, mitigate risk,
DB&B Isolation and maximize throughput.
T.D. Williamson | 1
C A S E S T U D Y : Single Tap Double Block and Bleed Isolation
To overcome these challenges, the operator employed provide a barrier against the pipeline pressure. Occupational Health and Safety code specifically
newer technology that enabled a safe, double block encourages the use of double block and bleed
and bleed isolation through a single tap, saving time In this case, however, that solution was not viable: the technology when conducting maintenance on
and money. work zone was too small to allow for multiple taps pipelines under pressure.
and fittings on each line.
The work site’s size and Space wasn’t the only constraint, however. Not only DOUBLE BLOCK AND
location, coupled with a did the operator require an alternative that could BLEED ISOLATION
tight timeline, meant that provide an effective isolation within the confined area,
the isolation techniques time was also an issue: the entire project, including definition:
typically executed by the launcher-receiver installation, had to be completed
“The isolation of a pipeline section
operator could not be used. under an aggressive nine-day schedule. And the site’s
location adjacent to a major highway further
utilizing two independent seals, both
capable of handling full pipeline
emphasized the priority placed around safety. To meet pressure, and a drain or vent of
CHALLENGE the timetable and safety requirements, first time sufficient size to manage any product
In 2015, the operator of a large Canadian natural gas isolation success was imperative. passing the primary seal.”
system launched two projects to make the last of the
Vancouver, BC, area transmission system piggable for SOLUTION
ILI. That included the installation of pig launching and To ensure a safe, efficient isolation within the confined Historically, pipeline operators have used a number of
receiving equipment on a 36-inch pipeline at a river work zone, the operator contracted global pipeline different methods to meet that criteria, including:
crossing, and moving a pig receiving barrel for a solutions provider T.D. Williamson (TDW) to execute » Two separate in-line valves with a bleed port
24-inch pipeline from one station to another. double block and bleed isolations using 24-inch and in between.
36-inch STOPPLE® Train technology. STOPPLE Train
» Combining an inline valve and a plugging head
Typically, the operator would isolate and bypass the technology has been used successfully in more than
with a bleed port in between.
work sites using three fittings at each end of the 2,300 insertions around the world.
isolation to prevent any product seepage from
» The tandem orientation of two plugging heads
Double block and bleed isolations are associated with with a bleed port between each block.
migrating to the work site. They would include a
reduced branch for bypass flow, a full-size branch for increased reliability, savings, and safety, making them TDW STOPPLE Train technology is unique because
the plugging head, and a reduced branch for a bag increasingly popular among oil and gas operators it consists of two plugging heads with independent
stop — an inflatable bag inserted into the line to worldwide. In fact, the province of Alberta’s seals connected in a train formation and inserted into
T.D. Williamson | 2
C A S E S T U D Y : Single Tap Double Block and Bleed Isolation
T.D. Williamson | 3
C A S E S T U D Y : Single Tap Double Block and Bleed Isolation
The STOPPLE Train system is field-proven to greatly increase the probability taps, excavations, possible leak paths, and amount of welding required. In
of achieving a workable seal during the initial set. As the time frame for addition, the highway remained open to traffic during the isolation, with its
this job was extremely tight, the importance of establishing a safe isolation safety uncompromised.
quickly was critical. The TDW team successfully executed each STOPPLE
By using the STOPPLE Train system, the operator maintained uninterrupted
Train isolation on the first attempt, enabling the installation of the
product flow while expanding the piggability and, ultimately, the integrity of
launcher-receiver to be completed ahead of schedule, in seven business
its transmission system.
days instead of the expected nine.
The STOPPLE Train system also promoted safety through Single Tap Open Smaller
first-time isolation success and by reducing the number of
T.D. Williamson | 4