Protection Automation Application Guide v1 - Compressed (401 500)
Protection Automation Application Guide v1 - Compressed (401 500)
• unit testing
• integration testing
• functional qualification testing
21-12
Chapter 21 ⋅ Relay Testing and Commissioning
correct for those inputs. ‘White box’ testing is concerned with using the target environment. In ideal circumstances, someone
testing the internal structure of the unit(s) and measuring the independent of the software development performs the tests.
test coverage, i.e. how much of the code within the unit(s) has In the case of high-integrity and/or safety critical software, this
been executed during the tests. The objective of the unit testing independence is vital. Validation Testing is ‘black box’ in
may, for example, be to achieve 100% statement coverage, in nature, i.e. it does not take into account the internal structure
which every line of the code is executed at least once, or to of the software. For relays, the non-protection functions
execute every possible path through the unit(s) at least once. included in the software are considered to be as important as
the protection functions, and hence tested in the same
21.6.3 Unit Testing Environment manner.
Both Dynamic and Static Unit Testing are performed in the
Each validation test should have predefined evaluation criteria,
host environment rather than the target environment.
to be used to decide if the test has passed or failed. The
Dynamic Unit Testing uses a test harness to execute the
evaluation criteria should be explicit with no room for
unit(s) concerned. The test harness is designed such that it
interpretation or ambiguity.
simulates the interfaces of the unit(s) being tested - both
software-software interfaces and software-hardware interfaces 21.6.7 Traceability of Validation Tests
- using what are known as stubs. The test harness provides
Traceability of validation tests to software requirements is vital.
the test data to those units being tested and outputs the test
Each software requirement documented in the software
results in a form understandable to a developer. There are
requirements specification should have at least one validation
many commercially available testing tools to automate test
test, and it is important to be able to prove this.
harness production and the execution of tests.
21.6.8 Software Modifications - Regression Testing
21.6.4 Software/Software Integration Testing
Regression Testing is not a type test in its’ own right. It is the
Software/Software Integration Testing is performed in the host
overall name given to the testing performed when an existing
environment. It uses a test harness to simulate inputs and
software product is changed. The purpose of Regression
outputs, hardware calls and system calls (e.g. the target
Testing is to show that unintended changes to the functionality
environment operating system).
(i.e. errors and defects) have not been introduced.
21.6.5 Software/Hardware Integration Testing Each change to an existing software product must be
Software/Hardware Integration Testing is performed in the considered in its’ own right. It is impossible to specify a
target environment, i.e. it uses the actual target hardware, standard set of regression tests that can be applied as a
operating system, drivers etc. It is usually performed after ‘catch-all’ for introduced errors and defects. Each change to
Software/Software Integration Testing. Testing the interfaces the software must be analysed to determine what risk there
to the hardware is an important feature of Software/Hardware might be of unintentional changes to the functionality being
Integration Testing. introduced. Those areas of highest risk will need to be
regression tested. The ultimate regression test is to perform the
Test cases for Integration Testing are typically based on those
complete Validation Testing programme again, updated to take
defined for Validation Testing. However the emphasis should
account of the changes made.
be on finding errors and problems. Performing a dry run of the
validation testing often completes Integration Testing. Regression Testing is extremely important. If it is not
performed, there is a high risk of errors being found in the field.
21.6.6 Validation Testing Performing it will not reduce to zero the chance of an error or
The purpose of Validation Testing (also known as Software defect remaining in the software, but it will reduce it.
Acceptance Testing) is to verify that the software meets its Determining the Regression Testing that is required is made
specified functional requirements. Validation Testing is much easier if there is traceability from properly documented
performed against the software requirements specification, software requirements through design (again properly
21-13
Protection & Automation Application Guide
documented and up to date), coding and testing. equipment can be used either for type testing of individual
relay designs or of a complete protection scheme designed for
21.7 DYNAMIC VALIDATION TYPE TESTING a specific application. In recognition of this, a new generation
There are two possible methods of dynamically proving the of power system simulators has been developed, which is
satisfactory performance of protection relays or schemes; the capable of providing a far more accurate simulation of power
first method is by actually applying faults on the power system system conditions than has been possible in the past. The
and the second is to carry out comprehensive testing on a simulator enables relays to be tested under a wide range of
power system simulator. system conditions, representing the equivalent of many years
The former method is extremely unlikely to be used – lead of site experience.
times are lengthy and the risk of damage occurring makes the
21.7.2.1 Simulation hardware
tests very expensive. It is therefore only used on a very limited
basis and the faults applied are restricted in number and type. Equipment is now available to provide high-speed, highly
Because of this, a proving period for new protection equipment accurate modelling of a power system. The equipment is based
under service conditions has usually been required. As faults on distributed digital hardware under the control of real-time
may occur on the power system at infrequent intervals, it can software models, and is shown in Figure 21.12. The modules
take a number of years before any possible shortcomings are have outputs linked to current and voltage sources that have a
discovered, during which time further installations may have similar transient capability and have suitable output levels for
occurred. direct connection to the inputs of relays –i.e. 110V for voltage
and 1A/5A for current. Inputs are also provided to monitor the
Power system simulators can be divided into two types: response of relays under test (contact closures for tripping,
• those which use analogue models of a power system etc.) and these inputs can be used as part of the model of the
• those which model the power system mathematically power system. The software is also capable of modelling the
using digital simulation techniques dynamic response of CTs and VTs accurately.
21-14
Chapter 21 ⋅ Relay Testing and Commissioning
• the power system model is capable of reproducing high can be any combination of phase to phase or phase to earth,
frequency transients such as travelling waves resistive, or non-linear phase to earth arcing faults. For series
• tests involving very long time constants can be carried compensated lines, flashover across a series capacitor
out following a short circuit fault can be simulated.
• it is not affected by the harmonic content, noise and
The frequency domain model is not suitable for developing
frequency variations in the a.c. supply
faults and switching sequences, therefore the widely used
• it is capable of representing the variation in the current
Electromagnetic Transient Program (EMTP), working in the
associated with generator faults and power swings
time domain, is employed in such cases.
• saturation effects in CTs and VTs can be modelled
• a set of test routines can be specified in software and In addition to these two programs, a simulation program
then left to run unattended (or with only occasional based on lumped resistance and inductance parameters is
monitoring) to completion, with a detailed record of test used. This simulation is used to represent systems with long
results being available on completion time constants and slow system changes due, for example, to
• the IEC61850 interface capabilities allow relays power swings.
intended for applications in digital substations to be
tested.
The fault can be applied at any one point in the system and
21-15
Protection & Automation Application Guide
IA
IB Linear
D/A CT Current
interpolation
conversion model amplifier
circuits
IC
VDU VA
Equipment
under
I/O test
Computer VB Linear
Keyboard Sub- D/A CVT Voltage
interpolation
system conversion model amplifier
circuits
VDU VC
Contact
status
monitor
Keyboard
Storage Key :
CT - Current transformer
CVT - Capacitor voltage transformer Signalling
VDU - Visual display unit Channel
Simulation
21-16
Chapter 21 ⋅ Relay Testing and Commissioning
N produced if required.
~ 3G L
4G Infinite bus
~ CB3 CT3 F3 F4 CT4 CB4 ~
Line 2
~ 8G
~ 9G LR3 LR4
21-17
Protection & Automation Application Guide
• to ensure that the equipment has not been damaged 21.10. Section 21.11 details the secondary injection that may
during transit or installation be carried out. Section 21.12 covers primary injection testing
• to ensure that the installation work has been carried and Section 21.13 details the checks required on any logic
out correctly involved in the protection scheme. Finally section 21.14 details
• to prove the correct functioning of the protection the tests required on alarm/tripping circuits tripping/alarm
scheme as a whole circuits.
21-18
Chapter 21 ⋅ Relay Testing and Commissioning
communications link to be tested from one end. voltage. This indicates the approximate knee-point or
saturation flux level of the current transformer. The
After completion of these tests, it is usual to enter the relay
magnetising current should then be recorded at similar voltage
settings required. This can be done manually via the relay front
intervals as it is reduced to zero.
panel controls, or using a portable PC and suitable software.
Whichever, method is used, a check by a second person that Care must be taken that the test equipment is suitably rated.
the correct settings have been used is desirable, and the The short-time current rating must be in excess of the CT
settings recorded. Programmable scheme logic that is required secondary current rating, to allow for measurement of the
is also entered at this stage. saturation current. This will be in excess of the CT secondary
current rating. As the magnetising current will not be
21.9.3 Current Transformer Tests sinusoidal, a moving iron or dynamometer type ammeter
The following tests are normally carried out prior to should be used.
energisation of the main circuits.
It is often found that current transformers with secondary
ratings of 1A or less have a knee-point voltage higher than the
21.9.3.1 Polarity check
local mains supply. In these cases, a step-up interposing
Each current transformer should be individually tested to verify
transformer must be used to obtain the necessary voltage to
that the primary and secondary polarity markings are correct;
check the magnetisation curve.
see Figure 21.16. The ammeter connected to the secondary of
the current transformer should be a robust moving coil, Test plug isolating
current transformers Variable transformer
from relay coils 250V 8A
permanent magnet, centre-zero type. A low voltage battery is A B C
P2 P1 Step-up transformer
P2 S2
_ S2 S1 + if required
Main circuit
breaker open
21-19
Protection & Automation Application Guide
21-20
Chapter 21 ⋅ Relay Testing and Commissioning
relay. Otherwise, a check may required subsequent to data scheme is not in service, and may also disconnect any d.c.
entry by inspection and recording of the relay settings, or it auxiliary supplies used for powering relay tripping outputs.
may be considered adequate to do this at the time of data
Withdrawing the test plug immediately restores the
entry. The recorded settings form an essential part of the
connections to the main current transformers and voltage
commissioning documentation provided to the client.
transformers and removes the test connections. Replacement
of the test block cover then removes the short circuits that had
21.10 SECONDARY INJECTION TEST
been applied to the main CT secondary circuits. Where several
EQUIPMENT
relays are used in a protection scheme, one or more test blocks
Secondary injection tests are always done prior to primary
may be fitted on the relay panel enabling the whole scheme to
injection tests. The purpose of secondary injection testing is to
be tested, rather than just one relay at a time.
prove the correct operation of the protection scheme that is
downstream from the inputs to the protection relay(s). Test blocks usually offer facilities for the monitoring and
Secondary injection tests are always done prior to primary secondary injection testing of any power system protection
injection tests. This is because the risks during initial testing to scheme. The test block may be used either with a multi-
the LV side of the equipment under test are minimised. The fingered test plug to allow isolation and monitoring of all the
primary (HV) side of the equipment is disconnected, so that no selected conductor paths, or with a single finger test plug that
damage can occur. These tests and the equipment necessary allows the currents on individual conductors to be monitored.
to perform them are generally described in the manufacturer's A modern test block and test plugs are illustrated in Figure
manuals for the relays, but brief details are given below for the 21.19.
main types of protection relays.
21-21
Protection & Automation Application Guide
both voltage and current outputs. The former are high-voltage, Relay with saturation
of CDG magnetic circuit
(phase shift from CDG
low current outputs for use with relay elements that require inductive load shown).
between the output of the test set and the relay current coil
during relay operation will give rise to a variation in current Typical VOLTAGE waveform
appearing across relay current
from that desired and possible error in the test results. The coils with sinusoidal I above
the relay setting (10 x shown).
relay operation time may be greater than expected (never less b) Undistorted relay current coil current distorted due to use of current source
than expected) or relay ‘chatter’ may occur. It is quite common Figure 21.20: Relay current coil waveforms
for such errors to only be found much later, after a fault has Modern test sets are computer based. They comprise a PC
caused major damage to equipment through failure of the (usually a standard laptop PC with suitable software) and a
primary protection to operate. Failure investigation then shows power amplifier that takes the low-level outputs from the PC
that the reason for the primary protection to operate is an and amplifies them into voltage and current signals suitable for
incorrectly set relay, due in turn to use of a test set with a application to the VT and CT inputs of the relay. The phase
current output consisting of a voltage-source when the relay angle between voltage and current outputs will be adjustable,
was last tested. Figure 21.20 shows typical waveforms as also will the phase angles between the individual voltages
resulting from use of test set current output that is a voltage or currents making up a 3-phase output set. Much greater
source – the distorted relay coil current waveform gives rise to precision in the setting of the magnitudes and phase angles is
an extended operation time compared to the expected value. possible, compared to traditional test sets. Digital signals to
exercise the internal logic elements of the relays may also be
provided. The alarm and trip outputs of the relay are connected
to digital inputs on the PC so that correct operation of the
relay, including accuracy of the relay tripping characteristic can
be monitored and displayed on-screen, saved for inclusion in
reports generated later, or printed for an immediate record to
present to the client. Optional features may include GPS time
synchronising equipment and remote-located amplifiers to
facilitate testing of unit protection schemes, and digital I/O for
exercising the programmable scheme logic of modern relays.
Some test sets offer a digital interface for IEC61850 GOOSE
I/O monitoring, and for virtual "injection" of IEC 61850-9-2
sampled values.
21-22
Chapter 21 ⋅ Relay Testing and Commissioning
The software for modern test sets is capable of testing the 440V
Supply switch 3 phase
functionality of a wide variety of relays, and conducting a set of A
4 wire supply
Variable
particular point on the characteristic to complete transformer
Relay
for current I>
determination of the tripping characteristic automatically. This control current element
feature can be helpful if there is any reason to doubt that the Range
adjusting CT
relay is operating correctly with the tripping characteristic 440/110V
phase shifting
A PA
specified. Figure 21.21 illustrates a modern PC-based test set. transformer
Relay
PA V V>
voltage element
Variable
transformer
for current
control
21-23
Protection & Automation Application Guide
some cases, manufacturers recommend, and clients accept, • the minimum current that gives operation at each
that if a digital or numerical relay passes its’ self-test, it can be current setting
relied upon to operate at the settings used and that testing can • the maximum current at which resetting takes place
therefore be confined to those parts of the scheme external to • the operating time at suitable values of current
the relay. In such cases, secondary injection testing is not • the time/current curve at two or three points with the
required at all. More often, it is required that one element of time multiplier setting TMS at 1
each relay (usually the simplest) is exercised, using a • the resetting time at zero current with the TMS at 1
secondary injection test set, to check that relay operation
Similar considerations apply to distance and unit protection
occurs at the conditions expected, based on the setting of the
relays of these technologies.
relay element concerned. Another alternative is for the
complete functionality of each relay to be exercised. This is
21.11.3 Test Circuits for Secondary Injection Testing
rarely required with a digital or numerical relay, probably only
The test circuits used will depend on the type of relay and test
being carried out in the event of a suspected relay malfunction.
set being used. Unless the test circuits are simple and obvious,
To illustrate the results that can be obtained, Figure 21.23 the relay commissioning manual will give details of the circuits
shows the results obtained by a modern test set when to be used. When using the circuits in this reference, suitable
determining the reach settings of a distance relay using a simplifications can easily be made if digital or numerical relays
search technique. are being tested, to allow for their built-in measurement
Fault A-N capabilities – external ammeters and voltmeters may not be
X(Ω)
required.
22.5
20.0 All results should be carefully noted and filed for record
17.5
purposes. Departures from the expected results must be
15.0
thoroughly investigated and the cause determined. After
12.5
10.0
rectification of errors, all tests whose results may have been
7.5 affected (even those that may have given correct results)
5.0 should be repeated to ensure that the protection scheme has
2.5
been implemented according to specification.
0.0
-2.5
-5.0
21.12 PRIMARY INJECTION TESTS
-7.5 This type of test involves the entire circuit; current transformer
-10.0 primary and secondary windings, relay coils, trip and alarm
-15.0 -10.0 -5.0 0.0 5.0 10.0 15.0 R(Ω)
circuits, and all intervening wiring are checked. There is no
Figure 21.23: Distance relay zone checking using search technique and
tolerance bands need to disturb wiring, which obviates the hazard of open-
circuiting current transformers, and there is generally no need
21.11.2 Schemes using Electromechanical/Static Relay for any switching in the current transformer or relay circuits.
Technology The drawback of such tests is that they are time consuming
Schemes using single function electromechanical or static and expensive to organise. Increasingly, reliance is placed on
relays will usually require each relay to be exercised. Thus a all wiring and installation diagrams being correct and the
scheme with distance and back-up overcurrent elements will installation being carried out as per drawings, and secondary
require a test on each of these functions, thereby taking up injection testing being completed satisfactorily. Under these
more time than if a digital or numerical relay is used. Similarly, circumstances, the primary injection tests may be omitted.
it may be important to check the relay characteristic over a However, wiring errors between VTs/CTs and relays, or
range of input currents to confirm parameters for an incorrect polarity of VTs/CTs may not then be discovered until
overcurrent relay such as: either spurious tripping occurs in service, or more seriously,
21-24
Chapter 21 ⋅ Relay Testing and Commissioning
failure to trip on a fault. This hazard is much reduced where If the main current transformers are fitted with test windings,
digital/numerical relays are used, since the current and voltage these can be used for primary injection instead of the primary
measurement/display facilities that exist in such relays enable winding. The current required for primary injection is then
checking of relay input values against those from other proven greatly reduced and can usually be obtained using secondary
sources. Many connection/wiring errors can be found in this injection test equipment. Unfortunately, test windings are not
way, and by isolating temporarily the relay trip outputs, often provided, because of space limitations in the main
unwanted trips can be avoided. current transformer housings or the cost of the windings.
connected to the alternator and circuit under test. Therefore, Optional ammeter
S1
the local mains supply and having several low voltage, heavy
current windings. These can be connected in series or parallel
according to the current required and the resistance of the
primary circuit. Outputs of 10V and 1000A can be obtained.
S2
Alternatively, modern PC-controlled test sets have power P2
amplifiers capable of injecting currents up to about 200A for a Relay or test block
single unit, with higher current ratings being possible by using contact fingers
Primary injection
test set
A
Variable transformer Injection transformer If the equipment includes directional, differential or earth fault
40A 250/10 + 10 + 10 + 10V relays, the polarity of the main current transformers must be
10kVA
checked. It is not necessary to conduct the test if only
Figure 21.24: Traditional primary injection test set
overcurrent relays are used.
21-25
Protection & Automation Application Guide
The circuit for checking the polarity with a single-phase test set digital and numerical relays normally include programmable
is shown in Figure 21.26. A short circuit is placed across the logic as part of the software within the relay, together with
phases of the primary circuit on one side of the current associated digital I/O. This facility (commonly referred to as
transformers while single-phase injection is carried out on the Programmable Scheme Logic, or PSL) offers important
other side. The ammeter connected in the residual circuit, or advantages to the user, by saving space and permitting
relay display, will give a reading of a few milliamperes with modifications to the protection scheme logic through software
rated current injected if the current transformers are of correct if the protection scheme requirements change with time.
polarity. A reading proportional to twice the primary current Changes to the logic are carried out using software hosted on
will be obtained if they are of wrong polarity. Because of this, a a PC (or similar computer) and downloaded to the relay. Use
high-range ammeter should be used initially, for example one of languages defined in IEC 61131, such as ladder logic or
giving full-scale deflection for twice the rated secondary Boolean algebra is common for such software, and is readily
current. If an electromechanical earth-fault relay with a low understood by Protection Engineers. Further, there are several
setting is also connected in the residual circuit, it is advisable commonly encountered protection functions that
to temporarily short-circuit its operating coil during the test, to manufacturers may supply with relays as one or more ‘default’
prevent possible overheating. The single-phase injection should logic schemes.
be carried out for each pair of phases.
Because software is used, it is essential to carefully test the
Temporary logic during commissioning to ensure correct operation. The
three-phase
short circuit only exception to this may be if the relevant ‘default’ scheme is
used. Such logic schemes will have been proven during relay
A
250V a.c. Primary injection
type testing, and so there is no need for proving tests during
supply test set commissioning. However, where a customer generates the
B
scheme logic, it is necessary to ensure that the commissioning
Relay
C tests conducted are adequate to prove the functionality of the
scheme in all respects. A specific test procedure should be
A
prepared, and this procedure should include:
Figure 21.26: Polarity check on main current transformers • checking of the scheme logic specification and
diagrams to ensure that the objectives of the logic are
21.12.4 Primary Injection Testing of Relay Elements achieved
As with secondary injection testing, the tests to be carried out • testing of the logic to ensure that the functionality of
will be those specified by the client, and/or those detailed in the scheme is proven
the relay commissioning manual. Digital and numerical relays • testing of the logic, as required, to ensure that no
usually require far fewer tests to prove correct operation, and output occurs for the relevant input signal combinations
these may be restricted to observations of current and voltage
The degree of testing of the logic will largely depend on the
on the relay display under normal load conditions.
criticality of the application and complexity of the logic. The
responsibility for ensuring that a suitable test procedure is
21.13 TESTING OF PROTECTION SCHEME
produced for logic schemes other than the ‘default’ one(s)
LOGIC
supplied lies with the specifier of the logic. Relay
Protection schemes often involve the use of logic to determine
manufacturers cannot be expected to take responsibility for the
the conditions under which designated circuit breakers should
correct operation of logic schemes that they have not designed
be tripped. Simple examples of such logic can be found in
and supplied.
Chapters 9-14. Traditionally, this logic was implemented by
means of discrete relays, separate from the relays used for
protection. Such implementations would occur where
electromechanical or static relay technology is used. However,
21-26
Chapter 21 ⋅ Relay Testing and Commissioning
21-27
Protection & Automation Application Guide
whose main protection is temporarily out of service. • each group of circuits which is electrically separate from
other circuits should be earthed through an
Maintenance is assisted by the displays of measured quantities
independent earth link
provided on digital and numerical relays. Incorrect display of a
• where a common voltage transformer or d.c. supply is
quantity is a clear indication that something is wrong, either in
used for feeding several circuits, each circuit should be
the relay itself or the input circuits. fed through separate links or fuses. Withdrawal of these
should completely isolate the circuit concerned
21.15.2 Maintenance Tests
• power supplies to protection schemes should be
Primary injection tests are normally only conducted out during segregated from those supplying other equipment and
initial commissioning. If scheme maloperation has occurred provided with fully discriminative circuit protection
and the protection relays involved are suspect, or alterations • a single auxiliary switch should not be used for
have been made involving the wiring to the relays from the interrupting or closing more than one circuit
VTs/CTs, the primary injection tests may have to be repeated. • terminations in relay panels require good access, as
these may have to be altered if extensions are made.
Secondary injection tests may be carried out at suitable
Modern panels are provided with special test facilities,
intervals to check relay performance, and, if possible, the relay so that no connections need be disturbed during routine
should be allowed to trip the circuit breakers involved. The testing
interval between tests will depend upon the criticality of the • junction boxes should be of adequate size and, if
circuit involved, the availability of the circuit for testing and the outdoors, must be made waterproof
technology of the relays used. Secondary injection testing is • all wiring should be ferruled for identification
only necessary on the selected relay setting and the results • electromechanical relays should have high operating
should be checked against those obtained during the initial and restraint torques and high contact pressures; jewel
commissioning of the equipment. bearings should be shrouded to exclude dust and the
use of very thin wire for coils and connections should be
It is better not to interfere with relay contacts at all unless they
avoided. Dust-tight cases with an efficient breather are
are obviously corroded. The performance of the contacts is fully essential on these types of electromechanical element
checked when the relay is actuated. • static, digital and numerical relays should have test
Insulation tests should also be carried out on the relay wiring facilities to assist in fault finding. The relay manual
to earth and between circuits, using a 1000V tester. These should clearly detail the expected results at each test
tests are necessary to detect any deterioration in the insulation point when healthy
resistance.
21-28
Chapter 21 ⋅ Relay Testing and Commissioning
21-29
POWER SYSTEM
MEASUREMENTS
Chapter 22
POWER SYSTEM MEASUREMENTS
LOCAL INFORMATION
.. Instruments or meters (may be directly connected, or
via a transducer)
.. Measurement centres
TRANSMITTED DATA
.. Transducers
REMOTE SYSTEMS
.. Measurement centres
.. Disturbance recorders
.. Power quality recorders (see chapter 23)
GEGridSolutions.com 22-1
Protection & Automation Application Guide
• ability to use multiple display elements per transducer against the possibility of their internal circuitry becoming open
• the burden on CTs/VTs is considerably less circuit. This ensures that a faulty device in the loop does not
cause complete failure of the output loop. The constant-
Outputs from transducers may be used in many ways – from current nature of the transducer output simply raises the
simple presentation of measured values for an operator, to voltage and continues to force the correct output signal round
being utilised by a network automation scheme to determine the loop.
the control strategy.
Transducers may have single or multiple inputs and/or 22.2.3 Transducer Accuracy
outputs. The inputs, outputs and any auxiliary circuits will all Accuracy is usually of prime importance, but in making
be isolated from each other. There may be more than one comparisons, it should be noted that accuracy can be defined
input quantity and the measurand may be a function of one or in several ways and may only apply under very closely defined
more of them. conditions of use. The following attempts to clarify some of the
Whatever measurement transducer is being used, there will more common terms and relate them to practical situations,
usually be a choice between discrete and modular types, the using the terminology given in IEC 60688.
latter being plug-in units to a standard rack. The location and The accuracy of a transducer will be affected, to a greater or
user-preferences will dictate the choice of transducer type. lesser extent, by many factors, known as influence quantities,
over which the user has little, or no, control.
22.2.1 Transducer Inputs
Table 22.1 provides a complete list of influence quantities. The
The input of a transducer is often taken from transformers and accuracy is checked under an agreed set of conditions known
these may be of many different types. Ideally, to obtain the as reference conditions. The reference conditions for each of
best overall accuracy, metering-class instrument transformers the influence quantities can be quoted as a single value (e.g.
should be used since the transformer errors will be added, 20oC) or a range (e.g. 10-40oC).
albeit algebraically, to the transducer errors. However, it is
common to apply transducers to protection-class instrument Input current Input voltage
transformers and that is why transducers are usually Input quantity distortion Input quantity frequency
characterised to be able to withstand significant short-term Power factor Unbalanced currents
overloads on their current inputs. A typical specification for the Continuous operation Output load
current input circuits of a transducer suitable for connection to Interaction between measuring elements Ambient temperature
protection-class instrument transformers is to withstand: Auxiliary supply voltage Auxiliary supply frequency
22-2
Chapter 22 ⋅ Power System Measurements
operating range of the transducer as specified by the Under changing conditions of the measurand, the output
manufacturer. The nominal range of use will naturally be wider signal does not follow the changes instantaneously but is time-
than the reference value or range. Within the nominal range of delayed. This is due to the filtering required to reduce ripple or,
use of a transducer, additional errors accumulate resulting in in transducers using numerical technology, prevent aliasing.
an additional error. This additional error is limited for any The amount of such a delay is called the response time. To a
individual influence quantity to, at most, the value of the class certain extent, ripple and response time are interrelated. The
index. response time can usually be shortened at the expense of
increased ripple, and vice-versa. Transducers having shorter
Table 22.2 gives performance details of a typical range of
response times than normal can be supplied for those
transducers (accuracy class 0.5) according to the standard.
instances where the power system suffers swings, dips, and
Max. Error- Nominal Max. Error- low frequency oscillations that must be monitored.
Influence Reference
Reference Working Nominal
Quantity Range Transducers having a current output have a maximum output
Range % Range Range
voltage, known as the compliance voltage. If the load
In=1A, 5A
Input current,In 0.5% 0-120% 0.5% resistance is too high and hence the compliance voltage is
20…120%
exceeded, the output of the transducer is no longer accurate.
Vn=50…500V
Input voltage,Vn 0.25% 0-120% 0.5%
80…120% Certain transducers are characterised by the manufacturer for
Input frequency 45…65Hz 0.5% - - use on systems where the waveform is not a pure sinusoid.
Power factor Cos ϕ=0.5…1 0.25% Cos ϕ=0…1 0.5% They are commonly referred to as ‘true r.m.s. sensing’ types.
Unbalanced current 0…100% 0.5% - - For these types, the distortion factor of the waveform is an
Current input
influence quantity. Other transducers are referred to as ‘mean-
Interaction between
measuring elements 0…360°
0.25%° - - sensing’ and are adjusted to respond to the r.m.s. value of a
pure sine wave. If the input waveform becomes distorted,
Continuous
Continuous operation
> 6h
0.5% - - errors will result. For example, the error due to third harmonic
distortion can amount to 1% for every 3% of harmonic.
Self Heating 1…30min 0.5% - -
Output load 10…100% 0.25% - - Once installed, the user expects the accuracy of a transducer
Waveform 1.41 to remain stable over time. The use of high quality components
- 1.2…1.8 0.5%
crest factor (sine wave) and conservative power ratings will help to ensure long-term
Ambient temperature 0°-50° C 0.5% -10°–60° C 1.0% stability, but adverse site conditions can cause performance
Aux. supply d.c. changes which may need to be compensated for during the
24…250V DC 0.25% 19V-300V 0.25%
voltage lifetime of the equipment.
A.C. Aux. Supply
90…110% fn 0.25% - -
frequency, fn 22.3 DIGITAL TRANSDUCER TECHNOLOGY
External magnetic
0…0.4kA/m 0.5% - - Digital power system transducers make use of the same
fields
technology as that described for digital and numerical relays in
Output series mode 1V 50Hz r.m.s. in
interference series with output
0.5% - - Chapter 7. The analogue signals acquired from VTs and CTs
are filtered to avoid aliasing, converted to digital form using
Output common 100V 50Hz r.m.s.
0.5% - - A/D conversion, and then signal processing is carried out to
mode interference output to earth
Table 22.2: Typical transducer performance extract the information required. Basic details are given in
Chapter 7. Sample rates of 64 samples/cycle or greater may be
Confusion also arises in specifying the performance under real
used, and the accuracy class is normally 0.2 or 0.5.
operating conditions. The output signal is often a d.c. analogue
of the measurand, but is obtained from alternating input Outputs may be both digital and analogue. The analogue
quantities and will, inevitably, contain a certain amount of outputs will be affected by the factors influencing accuracy as
alternating component, or ripple. Ripple is defined as the peak- described above. Digital outputs are typically in the form of a
to-peak value of the alternating component of the output communications link, with RS232 or RS485 serial, and RJ45
signal although some manufacturers quote ‘mean-to-peak’ or Ethernet connections commonly available. The response time
‘r.m.s.’ values. To be meaningful, the conditions under which may suffer compared to analogue transducers, depending on
the value of the ripple has been measured must be stated, e.g. the rate at which values are transferred to the communications
0.35% r.m.s. = 1.0% peak-to-peak ripple. link and the delay in processing data at the receiving end. In
fact, all of the influence quantities that affect a traditional
22-3
Protection & Automation Application Guide
analogue transducer also are present in a digital transducer in • a parallel output impedance, Zo. This represents the
some form, but the errors resulting may be much less than in actual output impedance of the current source and
an analogue transducer and it may be more stable over a long shunts a small fraction, I2, of the ideal output
period of time.
• an output current, Io, equal to (I1 - I2)
The advantages of a transducer using numerical technology
These features are shown diagrammatically in Figure 22.1.
are:
• improved long-term stability I1
• more accurate r.m.s measurements
• improved communications facilities I2
• programmability of scaling
Qin Zin Zo Io
• wider range of functions
• reduced size
The improved long term stability reduces costs by extending
the intervals between re-calibration. More accurate r.m.s
measurements provide the user with data of improved Figure 22.1: Schematic of an analogue transducer
accuracy, especially on supplies with significant harmonic
content. The improved communications facilities permit many Output ranges of 0-10mA, 0-20mA, and 4-20mA are
transducers to share the same communications link, and each common. Live zero (e.g. 4-20mA), suppressed zero (e.g. 0-
transducer to provide several measurements. This leads to 10mA for 300-500kV) and linear inverse range (e.g. 10-0mA
economy in interconnecting wiring and number of transducers for 0-15kV) transducers normally require an auxiliary supply.
used. Remote or local programmable scaling of the transducer The dual-slope type has two linear sections to its output
permits scaling of the transducer in the field. The scaling can characteristic, for example, an output of 0-2mA for the first
be changed to reflect changes in the network, or to be re-used part of the input range, 0-8kV, and 2-10mA for the second
elsewhere. Changes can be downloaded via the part, 8-15kV.
communications link, thus removing the need for a site visit. It
also minimises the risk of the user specifying an incorrect 22.5 TRANSDUCER SELECTION
scaling factor and having to return the transducer to the The selection of the correct transducer to perform a
manufacturer for adjustment. Suppliers can keep a wider measurement function depends on many factors. These are
range of transducers suitable for a wide range of applications detailed below.
and inputs in stock, thus reducing delivery times. Transducers
are available with a much wider range of functions in one 22.5.1 Current Transducers
package, thus reducing space requirements in a switchboard. Current transducers are usually connected to the secondary of
Functions available include harmonics up to the 31st, energy, an instrument current transformer with a rated output of 1 or
and maximum demand information. The latter are useful for 5 amps. Mean-sensing and true r.m.s. types are available. If
tariff negotiations. the waveform contains significant amounts of harmonics, a
true r.m.s sensing type must be used for accurate
22.4 ANALOGUE TRANSDUCER TECHNOLOGY measurement of the input. They can be self-powered, except
All analogue transducers have the following essential features: for the true r.m.s. types, or when a live zero output (for
example 4-20mA) is required. They are not directional and,
• an input circuit having impedance Zin
therefore, are unable to distinguish between ‘export’ and
• isolation (no electrical connection) between input and ‘import’ current. To obtain a directional signal, a voltage input
output is also required.
• an ideal current source generating an output current, I1,
which is an accurate and linear function of Qin, the 22.5.2 Voltage Transducers
input quantity Connection is usually to the secondary of an instrument
voltage transformer but may be direct if the measured quantity
is of sufficiently low voltage. The suppressed zero type is
commonly used to provide an output for a specific range of
22-4
Chapter 22 ⋅ Power System Measurements
input voltage where measurement of zero on the input effective range. Figure 22.2 illustrates the connections to be
quantity is not required. The linear inverse type is often used as used for the various types of measurement.
an aid to synchronising.
Transducer Transducer
22.5.3 Frequency Van Vab
Vca
Accurate measurement of frequency is of vital importance to Ia Ia
transmission system operators but not quite so important, S1 S2 S1 S2
perhaps, for the operator of a diesel generator set. Accuracy A
P1 P2
A
P1 P2
To load
that a device quoted as 0.1% and having a centre scale value of To load
50Hz will have a maximum error of +/- 50mHz under 3 phase, 4 wire balanced load 3 phase, 3 wire balanced load
reference conditions.
Va
Transducer Transducer
Vb
Vab
22.5.4 Phase Angle Ic
Vc Ic
Vca
Ia Ia Ib
Transducers for the measurement of phase angle are
S1 S2
frequently used for the display of power factor. This is achieved A
S1 S2
A
P1 P2 P1 P2
by scaling the indicating instrument in a non-linear fashion, S1 S2
B B
following the cosine law. For digital indicators and SCADA S1 S2
P1 P2
S1 S2
Vab
equipment, it is necessary for the receiving equipment to C
Vca P1 P2
C
P1 P2
N
provide appropriate conversions to achieve the correct display To load
To load
of power factor. Phase angle transducers are available with 3 phase, 3 wire unbalanced load
3 phase, 4 wire unbalanced load
various input ranges. When the scaling is -180o…0o…180°, there
is an ambiguous region, of about +/-2º at the extremes of the Transducer
range. In this region, where the output is expected to be, for Van
Ic
example, –10mA or +10mA, the output may jump sporadically Vcn
Ia Ib
from one of the full-scale values to the other. Transducers are S1 S2
also available for the measurement of the angle between two A
P1 P2
S1 S2
input voltages. Some types of phase angle transducer use the B
P1 P2
zero crossing point of the input waveform to obtain the phase S1 S2
C
information and are thus prone to error if the input contains N
P1 P2
22-5
Protection & Automation Application Guide
is required to be 12mA. This is within the capability of most 0- separate supply, the majority have a biased, or live zero output,
10mA transducers, the majority of which can accommodate such as 4-20mA. This is because a non-zero output cannot be
an over-range of 25%, but it does mean any associated obtained for zero input unless a separate supply is available.
analogue indicating instrument must have a sensitivity of Transducers that require an auxiliary supply are generally
12mA. However, the scale required on this instrument is now provided with a separate pair of terminals for the auxiliary
0-13.2kV, which may lead to difficulty in drawing the scale in circuit so that the user has the flexibility of connecting the
such a way as to make it readable (and conforms to the auxiliary supply input to the measured voltage, or to a separate
relevant standard). In this example, it would be more supply. However, some manufacturers have standardised their
straightforward to establish the full-scale indication as 15kV designs such that they appear to be of the self-powered type,
and to make this equivalent to 10mA, thus making the but the auxiliary supply connection is actually internal. For a.c.
specification of the display instrument much easier. The measuring transducers, the use of a d.c. auxiliary supply
transducer will have to be specified such that an input of 0- enables the transducer to be operated over a wider range of
150V gives an output of 0-10mA. In the case of transducers input.
with a 4-20mA output, great care is required in the output
The range of auxiliary supply voltage over which a transducer
scaling, as there is no over-range capability. The 20mA output
can be operated is specified by the manufacturer. If the
limit is a fixed one from a measurement point of view. Such
auxiliary voltage is derived from an input quantity, the range of
outputs are typically used as inputs to SCADA systems, and the
measurement will be restricted to about +/-20% of the nominal
SCADA system is normally programmed to assume that a
auxiliary supply voltage. This can give rise to problems when
current magnitude in excess of 20mA represents a transducer
attempting to measure low values of the input quantity.
failure. In addition, a reading below 4mA also indicates a
failure, usually an open circuit in the input connection. Thus,
using the above example, the output might be scaled so that
20mA represents 132V and hence the nominal 110V input 22.6 MEASUREMENT CENTRES
results in an output of 16.67mA. A more convenient scaling A Measurement Centre is different from a transducer in three
might be to use 16mA as representing 110V, with 20mA ways.
output being equal to 137.5V (i.e. 25% over-range instead of
• It can measure a large number of instantaneous
the 20% required). It would be incorrect to scale the transducer
parameters, and with an internal clock, calculate time-
so that 110V input was represented by 20mA output, as the
based parameters such as maximum demand
over-range capability required would not be available.
• It has many different forms of communication to
Similar considerations apply to current transducers and, with
transmit the data ranging from simple pulsed contacts
added complexity, to watt transducers, where the ratios of
to multiple digital communication ports
both the voltage and the current transformers must be taken
into account. In this instance, the output will be related to the • It has a local display so that information, system status
primary power of the system. It should be noted that the input and alarms can be displayed to the operator.
current corresponding to full-scale output may not be exactly This is largely impractical if analogue technology for signal
equal to the secondary rating of the current transformer but processing is used, but no such limitation exists if digital or
this does not matter - the manufacturer will take this into numerical technology is adopted. Therefore, Measurement
account. Centres are generally only found implemented using these
Some of these difficulties do not need to be considered if the technologies. As has been already noted in Chapter 7, a
transducer is only feeding, for example, a SCADA outstation. numerical relay can provide many measurements of power
Any receiving equipment that can be programmed to apply a system quantities. Therefore, an alternative way of looking at a
scaling factor to each individual input can accommodate most Measurement Centre that uses numerical technology is that it
input signal ranges. The main consideration will be to ensure is a numerical relay, stripped of its protection functions and
that the transducer is capable of providing a signal right up to incorporating a wide range of power system parameter
the full-scale value of the input, that is, it does not saturate at measurements.
the highest expected value of the measurand. This is rather an oversimplification of the true situation, as
there are some important differences. A protection relay has to
22.5.7 Auxiliary Supplies provide the primary function of protection over a very large
Some transducers do not require any auxiliary supply. These range of input values; from perhaps 5% to 500% or greater of
are termed ‘self-powered’ transducers. Of those that do need a rated values. The accuracy of measurement, whilst important,
22-6
Chapter 22 ⋅ Power System Measurements
22-7
Protection & Automation Application Guide
For primary tariff metering, security of information is a major and enables CB close circuits when the differences are within
design factor. Meters will also have tamper-proof physical pre-set limits. While CB closure at the instant of perfect
indication. synchronism is the ideal, this is very difficult to obtain in
practice and some mismatch in one or more of the monitored
22.8 SYNCHRONISERS quantities can be tolerated without leading to excessive
Synchronisers are required at points on a power system where current/voltage transients on CB closure. The check
two supplies (either generator and grid, or two grid supplies) synchroniser has programmable error limits to define the limits
may need to be paralleled. They are more than just a of acceptability when making the comparison.
measuring device, as they will provide contact closures to The conditions under which a check synchroniser is required to
permit circuit breaker closing when conditions for paralleling provide an output are varied. Consider the situation of a check
(synchronising) are within limits. However, they are not synchroniser being used as a permissive device in the closing
regarded as protection relays, and so are included in this control circuit of a CB that couples two networks together at a
Chapter for convenience. There are two types of synchronisers substation. It is not sufficient to assume that both networks
- auto-synchronisers and check synchronisers. will be live, situations where either Line A or Busbar B may be
dead may have to be considered, leading to the functionality
22.8.1 Check Synchronisers shown in Table 22.4(a).
The function of a check synchroniser is to determine if two
(a) Check synchroniser functionality
voltages are in synchronism, or nearly so, and provide outputs
Live bus/live line synchronising Live bus/dead line synchronising
under these conditions. The outputs are normally in the form
Network supply voltage #1 deviation from
of volt-free contacts, so that they may be used in CB control Dead bus/live line synchronising
nominal
circuits to permit or block CB closing. When applied to a
Network supply voltage #2 deviation from
power system, the check synchroniser is used to check that it nominal
Voltage difference within limits
is safe to close a CB to connect two independent networks
Frequency difference within limits Phase angle difference within limits
together, or a generator to a network, as in Figure 22.4. In this
CB closing advance time CB closing pulse time
way, the check synchroniser performs a vital function in
Maximum number of synchronising attempts
blocking CB closure when required.
(b) Additional functions for auto-synchroniser
CB Check
close synchroniser Incoming supply frequency deviation from
Incoming supply voltage raise/lower signal
controls nominal
Incoming supply voltage raise/lower mode Incoming supply frequency raise/lower mode
Close (pulse/continuous) (pulse/continuous)
Generator Incoming supply voltage setpoint Incoming supply frequency setpoint
∼ Network
Voltage raise/lower pulse time
Table 22.4: Synchroniser function set
Frequency raise/lower pulse time
Busbar
When the close signal is permitted, it may be given only for a
(a) Application to generator limited period of time, to minimise the chances of a CB close
signal remaining after the conditions have moved outside of
CB close
controls Check limits. Similarly, circuits may also be provided to block closure
synchroniser
if the CB close signal from the CB close controls is present
prior to satisfactory conditions being present – this ensures
Close
that an operator must be monitoring the synchronising
displays and only initiating closure when synchronising
Network Network conditions are correct, and also detects synchronising switch
#2 #1
Line A CB 1
contacts that have become welded together.
Busbar B
A check synchroniser does not initiate any adjustments if
(b) Application to two networks synchronising conditions are not correct, and therefore acts
Figure 22.4: Check synchroniser applications only as a permissive control in the overall CB closing circuit to
Synchronism occurs when two a.c. voltages are of the same provide a check that conditions are satisfactory. In a
frequency and magnitude, and have zero phase difference. The substation, check-synchronisers may be applied individually to
check synchroniser, when active, monitors these quantities all required CBs. Alternatively, a reduced number may be
22-8
Chapter 22 ⋅ Power System Measurements
installed, together with suitable switching arrangements in the power factor to the network by the generator after CB closure.
signal input/output circuits so that a single device may be The possibility of tripping due to reverse/low forward power
selected to cover several CBs. conditions and/or field failure/under-excitation is avoided. Use
of an auto-synchroniser also helps avoid human error if
22.8.2 Auto-synchroniser manual synchronising were employed – there is potential for
An auto-synchroniser contains additional functionality damage to equipment, primarily the generator, if synchronising
compared to a check synchroniser. When an auto- outside of permitted limits occurs.
synchroniser is placed in service, it measures the frequency To ensure that the CB is closed at the correct instant, the CB
and magnitude of the voltages on both sides of the circuit close time is normally a required data item. The auto-
breaker, and automatically adjusts one of the voltages if synchroniser calculates from a knowledge of this and the slip
conditions are not correct. Application of auto-synchronisers is frequency the correct time in advance of phase co-incidence to
normally restricted to generators – i.e. the situation shown in issue the CB close command. This ensures that the CB closes
Figure 22.4(a), replacing the check synchroniser with an auto- as close to the instant of phase co-incidence as possible. Upon
synchroniser. This is because it is generally not possible to receipt of the signal indicating ‘CB closed’ a further signal to
adjust either of the network voltages by changing the settings raise frequency may be sent to the governor to ensure stable
of one or a very few equipments in a network. When applied to export of power is achieved. Conversely, failure of the CB to
a generator, it is relatively easy to adjust the frequency and close within a set time period will reset the auto-synchroniser,
magnitude of the generated voltage by transmitting signals to ready for another attempt, and if further attempts are still
the Governor and AVR respectively. unsuccessful, the auto-synchroniser will lock out and raise an
The auto-synchroniser will check the voltage of the incoming alarm.
generator against the network voltage for compliance with the Practice in respect of fitting of auto-synchronisers varies widely
following: between Utilities. Where policy is flexible, it is most common
a. slip frequency within limits (i.e. difference in when the time to synchronise is important – i.e. emergency
frequency between the generator and network) standby and peak lopping sets. Many Utilities still relay on
manual synchronising procedures. It is also possible for both
b. phase difference between the voltages within limits
an auto-synchroniser and check-synchroniser to be fitted in
c. voltage magnitude difference within limits series. This provides protection against internal failure of the
auto-synchroniser leading to a CB close command being given
The CB close command is issued automatically when all three incorrectly.
conditions are satisfied. Checks may also be made that the
network frequency and voltage is within pre-set limits, and if 22.9 DISTURBANCE RECORDERS
not the synchronising sequence is locked out. This prevents Power systems suffer from various types of disturbances. In
synchronising under unusual network conditions, when it may post-fault analysis, it is beneficial to have a detailed record of a
not be desirable. This facility should be used with caution, disturbance to enable the initiating event to be distinguished
since under some emergency conditions, it could block the from the subsequent effects. Especially where the disturbance
synchronising of a generator that was urgently required in causes further problems (e.g. single-phase fault develops into
service to help assist in overcoming the condition. 3-phase), a detailed recording of the fault may be required to
distinguish between cause and effect. If the effects of a fault
If (a) above is not within limits, signals are sent automatically
are spread over a wide area, records of the disturbance from a
to the governor of the generating set to adjust the speed
number of locations can assist in determining the location of
setpoint appropriately. In the case of (c) not in limits, similar
the disturbance. The equipment used for this purpose is known
signals are sent to the Automatic Voltage Regulator to raise or
as a disturbance, or fault, recorder.
lower the setpoint. The signals are commonly in the form of
pulses to raise or lower the setpoint, but could be continuous
22.9.1 Disturbance Recorder Features
signals if that is what the particular equipment requires. It is
normal for the speed and voltage of the generator to be slightly A disturbance recorder will normally have the following
higher than that of the network, and this can be capabilities:
accommodated either by initial settings on the Governor/AVR • multi-channel analogue input waveform recording
or by providing setpoint values in the synchroniser. This
• multi-channel digital input recording
ensures stable synchronising and export of power at lagging
22-9
Protection & Automation Application Guide
• storage of several fault records, ready for same event from a different recorder to obtain a complete
download/analysis picture of events.
• recording time of several seconds per disturbance Since most disturbance recorders are fitted in substations that
• triggering from any analogue or digital input channel, are normally unmanned, the provision to download captured
or quantity derived from a combination of inputs, or information is essential. Each fault recording will contain a
manually large amount of data, and it is vital that the data is uniquely
identified in respect of recorder, fault event, channel, etc.
• distance to fault location for one or more feeders
Standards exist in field to facilitate the interchange of data, of
• variable pre/post trigger recording length which perhaps the best known is the IEEE COMTRADE
• time synchronisation (IRIG-B, GPS, etc.) format, now also an international standard (IEC 60255-24).
• programmable sampling rates Once downloaded, the data from a disturbance recorder can
be analysed by various PC software packages. The software
• standard data transfer formats (IEEE COMTRADE (IEC
will often have the ability to perform harmonic and other
60255-24), etc.
analysis.
• communication links to control centre (Ethernet,
modem, etc.)
• self-monitoring/diagnostics
Analogue channels are provided to record the important
currents and voltages at the fault recorder location. High
resolution is required to ensure accurate capture of the
waveforms, with 16 bit A/D conversion being typical. Digital
inputs are provided to capture signals such as CB opening,
protection relay operation, intertrip signals, etc. so that a
complete picture of the sequence of events can be built up. The
information can then be used to check that the sequence of
operations post-fault is correct, or assist in determining the
Figure 22.5a: Distributed digital fault recorder (Reason RPV 311 Digital
cause of an unexpected sequence of operations. To avoid loss Fault Recorder with PMU and TWFL)
of the disturbance data, sufficient memory is provided to
capture and store the data from several faults prior to transfer
of the data for analysis. Flexibility in the triggering
arrangements is extremely important, as it is pointless to
install a disturbance recorder, only for it to miss recording
events due to lack of appropriate triggering facilities. It is
normal for triggering to be available if the relevant threshold is
crossed on any analogue or digital channel, or a quantity
derived from a combination of the inputs.
Power system disturbances may last from periods of a few
seconds to several minutes. To ensure that maximum benefit is
obtained from the investment, a disturbance recorder must be
able to capture events over a wide range of timescales. This
leads to the provision of programmable sampling rates, to
ensure that short-term transients are captured with sufficient Figure 22.5b: Digital Fault Recorder (DFR) peripheral units – standard
resolution while also ensuring that longer-term ones have CT/VT with traveling wave fault location and process bus (Reason
RA333 Remote Acquisition Module)
sufficient of the transient captured to enable a meaningful
analysis to be undertaken. The record for each disturbance is
divided into sections covering pre-fault, fault, and post–fault
periods, and each of these periods may have different sampling
rates. Time synchronisation is also a vital feature, to enable a
recording from one recorder to be aligned with another of the
22-10
Chapter 22 ⋅ Power System Measurements
22-11
POWER QUALITY
Chapter 23
POWER QUALITY
GEGridSolutions.com 23-1
Protection & Automation Application Guide
this Chapter describe the causes in more detail, along with Limits Other
Type of Voltage Measurement Typical
methods of measurement and possible remedial measures. disturbance Level
from
period duration
applicable
EN50160 standards
Category Causes Impacts
Rapid voltage +/-5% to Short
Local and remote faults Tripping of sensitive equipment 230V Several per day
changes +/-10% duration
Voltage dips Inductive loading Resetting of control systems
Rapid voltage Short
Switch on of large loads Motor stalling/tripping 1kV-35kV <6% Per day IEEE 1159
changes duration
Tripping of sensitive equipment Short
Capacitor switching 230V >99% 20-200 per year Up to 3 mins EN61000-4-11
Damage to insulation and Interruptions
Voltage surges Switch off of large loads windings
Long
Phase faults Damage to power supplies for 230V >99% 10-50 per year >3 mins IEEE 1159
Interruptions
electronic equipment
Transient
Load switching Problems with equipment that 230V Generally <6kV Not specified <1ms IEEE 1159
Overvoltage
Overvoltage Capacitor switching requires constant steady-state
Voltage
System voltage regulation voltage 230V
unbalance
Mal-operation of sensitive Undervoltage 230V <-10% Not specified >1 min IEEE 1159
Industrial furnaces
equipment and relays
Non-linear loads <150% of
Harmonics Capacitor fuse or capacitor
Transformers/generators Voltage surge 230V nominal Not specified >200ms IEEE 1159
failures
Rectifier equipment voltage
Telephone interference
Voltage
Negligible most of time 230V 3% 10 min <200ms IEC 60827
Loss of generation fluctuations
Power frequency variation Motors run slower
Extreme loading conditions Frequency Measured over
De-tuning of harmonic filters +/- 1% 95% of 1 week Not specified
variation 10s
AC motor drives Flicker in:
Frequency Measured over
Voltage fluctuation Inter-harmonic current components Fluorescent lamps +4%, -6% 100% of 1 week Not specified
variation 10s
Welding and arc furnaces Incandescent lamps
THD<8% up to
Harmonics 95% of 1 week Not specified
Motor starting Light flicker 40th
Rapid voltage change
Transformer tap changing Tripping of equipment Table 23.2: Power system disturbance classification to EN 50160
Overheating in
Unbalanced loads motors/generators
For computer equipment, a common standard that
Voltage imbalance manufacturers use is the ITI (Information Technology Industry)
Unbalanced impedances Interruption of 3-phase
operation curve, illustrated in Figure 23.1. Voltage disturbances that lie
Power system faults Loss of supply to customer in the area indicated as ‘safe’ should not cause a malfunction
Short and long voltage Equipment failures equipment in any way. However, some disturbances at LV levels that lie
interruptions Control malfunctions Computer shutdowns within the boundaries defined by EN50160 might cause a
CB tripping Motor tripping malfunction because they do not lie in the safe area of the ITI
Heavy network loading curve. It may be necessary to check carefully which standards
Undervoltage
Loss of generation All equipment without backup are applicable when considering equipment susceptibility.
Poor power factor supply facilities
500
Lack of var support
450
Lightning Control system resetting
Percentage of nominal voltage (RMS)
400
Capacitive switching Damage to sensitive electronic
Transients 350
Non –linear switching loads components
System voltage regulation Damage to insulation 300
Affected by disturbance
250
Table 23.1: Power quality issues
200 Withstand disturbance
Table 23.2 lists the limits given in Standard EN 50160 and 150
notes where other standards have similar limits. 100
Limits Other 50
Affected by disturbance
Type of Voltage Measurement Typical
from applicable 0
disturbance Level period duration 0.001 0.01 0.1 1 10 100 1000 10000 100000
EN50160 standards Duration of disturbance (ms)
Voltage Variation 230V +/- 10% 95% of 1 week - Figure 23.1: ITI curve for equipment susceptibility
Voltage Dips 230V <10%<90% 10-1000/year 10ms –1sec IEEE 1159
23-2
Chapter 23 ⋅ Power Quality
supply system is a fault on the system, that is sufficiently Figure 23.3: Multiple voltage dip
remote electrically that a voltage interruption does not occur. The impact on consumers may range from the annoying (non-
Other sources are the starting of large loads (especially periodic light flicker) to the serious (tripping of sensitive loads
common in industrial systems), and, occasionally, the supply and stalling of motors). Where repeated dips occur over a
of large inductive loads. period of several hours, the repeated shutdowns of equipment
can give rise to serious production problems. Figure 23.4
Vrms
shows an actual voltage dip, as captured by a Power Quality
Nom. High
recorder.
Nom. Low 100
Dip magnitude: x% of declared PQ Standards
80
x % below nominal
Dip duration 60
User defined setpoints
Voltage (% of nominal)
40
20
Retained Voltage
0
Interruption Time
-20
Time
-40
-80
Voltage dips due to the latter are usually due to poor design of -100
the network feeding the consumer. A voltage dip is the most Figure 23.4: Recording of a voltage dip
common supply disturbance causing interruption of production
Typical data for undervoltage disturbances on power systems
in an industrial plant. Faults on a supply network will always
during evolving faults are shown in Figure 23.5. Disturbances that
occur, and in industrial systems, it is often practice to specify
lie in the front right-hand portion of the histogram are the ones
equipment to ride-through voltage dips of up to 0.2s. The most
that cause most problems, but fortunately these are quite rare.
common exception is contactors, which may well drop out if
the voltage dips below 80% of rated voltage for more than 50- Number of undervoltage disturbances recorded
31-40%
0.5-1ms
Retained voltage
1-5ms
5-10ms
10-50ms
11-20%
50-100ms
100-500ms
0.5-1s
1-5s
5-10s
>10s
Duration of disturbance
23-3
Protection & Automation Application Guide
150
23-4
Chapter 23 ⋅ Power Quality
23-5
THE DIGITAL SUBSTATION
Chapter 24
THE DIGITAL SUBSTATION
GEGridSolutions.com 24-1
Protection & Automation Application Guide
Along a similar time line, innovative approaches for The model shows that for the information to transfer from the
instrumentation transformers were being developed, with so- source to the destination, a transmitter (encoder) and a
called merging units converting indicative signals of power receiver (decoder), both connected by a channel are required.
system quantities into data streams for communication to IEDs. It also demonstrates that sources of noise can interfere with
the process. Considering communication between two people,
The technology was now available to communicate current
the source is the brain of the person who wants to get the
and voltage information to the different IEDs within the
message across, the transmitter could be that person’s voice
substation on a so called 'process bus', whilst the IEDs
and the channel is the atmosphere. At the receiving end, the
communicated information between themselves and the
receiver would be the other person’s ears and the destination
control centre on a so called 'station bus'. The digital
that person’s brain. Audible noise could drown out the
substation was close to becoming a reality, but despite
message causing it not to be received and this is a possible
attempts at standardisation, proprietary solutions hampered
cause of communication breakdown, but it is not the only one.
the end goal of "plug-and-play".
If the source is speaking but the destination is not listening (i.e.
The breakthrough came with the introduction and adoption of
they are not synchronised), communication won’t be
IEC61850, an open standard for electrical substation
successful. Similarly, if the two people talking don’t share a
automation. This standard provides detailed modelling of
common language, and/or if certain protocols are not observed
substation protection, control and monitoring functions, and
(e.g. not both speaking at the same time), failure is inevitable.
details communication services for exchanges between the
Successful communication requires common understanding
different products and substatems that make up a substation
between source and destination.
automation system.
The digital substation brings major benefits in terms of design 24.2.1 The OSI Model for Computer Communications
and engineering, installation, and operation. Off-the-shelf In the context of substation automation, communication is the
solutions can be offered, modifications can be easily transfer of information from one computing device to another
accommodated, cabling (and hence costs), are reduced, and but, as with the example above, problems with
embedded diagnostics assure system integrity. synchronisation, language, and protocol can all cause
This chapter takes a tour through the enablers of the digital communication failure.
substation, looking at communications (and how to ensure The substation communication might be in the form of a
that they are sufficiently secure, reliable, and dependable), dedicated link between two devices, or it may be over some
current and voltage transformation coupled with merging form of communications network.
units, and concluding with an introduction to the standard
The International Standards Organisation (ISO) recognised the
IEC61850.
need for a framework for inter-device data communications,
24.2 COMMUNICATIONS and in 1984 introduced the Open Systems Interconnection
Communication is the conveyance of information from a (OSI) model.
source to a destination. In 1949 C E Shannon and W Weaver The OSI model divides the data communication process into
[24.1] produced a mathematical model for communications as seven distinct layers. Each of the seven layers defines how the
shown in Figure 24.1. data is handled during the different stages of transmission.
Each layer provides a service for the layer immediately above
Information Transmitter Receiver
source (Encoder)
Channel
(Decoder)
Destination it.
Message Signal Received Message A model representing the seven layers is shown in Figure 24.2
Signal
with the purpose of the different layers being described below.
Noise
Source
24-2
Chapter 24 ⋅ The Digital Substation
Layer
Data Unit Layer Function 1
Type Start 0 0 1 0 1 1 0 Stop
7
Communication application
Application layer
6
Data Encryption and data representation
Host Presentation layer Start b0 b1 b2 b3 b4 b5 b6 b7 Stop
Layers 5
Inter-host communication
Session layer
4
Segment End-to-end connections and reliability
Transport layer
Idle Idle
3
Packet Logical addressing
Network layer
Media 2
Frame Physical addressing Time
Layers Link layer
Bit
1
Media, signal and binary transmission Figure 24.3: Example of a data frame
Physical layer
Figure 24.2: The OSI seven layer model A commonly used Data Link protocol is Ethernet. Examples of
equipment that work at this layer are Ethernet switches and
24.2.1.1 OSI Layer 1 – The Physical Layer bridges.
Every data message is transmitted on some medium. This
medium usually takes the form of cables, wires, or optical 24.2.1.3 OSI Layer 3 – The Network Layer
fibres, but it could just as well be wireless, with the data being The network layer is concerned with packet delivery. Logical
carried on electromagnetic waves. The physical layer specifies paths are established between the sending and receiving
the type of medium to be used between one end of the data equipment by adding information onto the data frame which
exchange and the other, the type of connectors to be used and defines where the packet has come from, and where the
the voltage and current levels, and if applicable, optical packet is going to. This takes the form of a logical source and
characteristics defining the state of the data bits. A very destination address for each packet of information. A
common medium, particularly in Ethernet systems started commonly used Network protocol is IP (Internet Protocol).
with the CAT 5 UTP cable (Category 5 Unshielded Twisted
An example of equipment that operates at the network layer is
Pair), which consists of four colour-coded twisted pairs of
a router.
wires terminated with RJ45 connectors. As the name implies,
this type of cable is not shielded against electromagnetic 24.2.1.4 OSI Layer 4 – The Transport Layer
interference. There is also a version of this cable called CAT 5
The transport layer is the first layer that is not concerned with
STP (Category 5 Shielded Twisted Pair) that has a metallic
the mechanics of the data transfer. It is concerned with
outer sheath, providing electromagnetic shielding. This type of
managing and sequencing the packets once they have arrived.
cable is often used in noisy environments like the substation.
There is an array of transport layer protocols ranging from the
CAT 5, has more recently evolved into new standards such as
very simple, which simply accepts the data as it comes in, not
CAT 6 and CAT 7, which offer even more robust shielding, fire
caring about whether the packets have errors nor even if they
protection etc.
are in the right order, through to quite complex protocols
24.2.1.2 OSI Layer 2 – The Data Link Layer which check the data for errors, send out an acknowledgement
to the sending equipment, order the packets into the correct
The physical layer provides the Data Link layer with bits. The
sequence and present the data to the next layer guaranteed
Data Link layer now provides some intelligence to this
error-free and correctly sequenced.
sequence of bits by defining Data Frames. These Data Frames
are packets of data containing the data to be transmitted and An example of a simple protocol is UDP (User Datagram
some control information governing the transmission. The Protocol). A more sophisticated widely used transport layer
control information comprises flags to indicate the start and protocol used is TCP (Transmission Control Protocol).
end of the message. The standards used at this layer must Layer 4 functionality is achieved by the devices at either end of
ensure that the control flags are not mistaken for data and that the transmission path, which is usually a computer. In the
the data frames are checked for errors. An example is given in context of substation protection, this would be the IED.
Figure 24.3.
24-3
Protection & Automation Application Guide
24.2.2 Communications Between IEDs EIA 232 was designed to allow computers to connect using
Modems and is suitable only for point-to-point connection. It
The OSI model outlines the need for compatibility between all
uses switched single-sided 12V (nominal) signals for data
communication layers between computers (which are
transmission as well as handshake signals to control the
generally in the form of IEDs in the substation). This section
communication. Due to Modem limitations, it is not generally
explores the lowest two layers; the physical and data link
used at speeds in excess of 9,600 bits per second. No isolation is
layers.
specified and so it is only suitable for connection over very short
24.2.2.1 Physical Connection to IEDs for Substation distances. For permanent connection in a substation
Control and Automation environment, the use of optical isolating units should be
considered to avoid damage caused by induced transients. If
In substation control and automation systems, connection to
transmission over longer distances is required, some form of EIA
IED communications ports at the physical layer (OSI layer 1) is
232 to fibre-optic converter and a fibre-optic communications
generally to one of three standards:
link should be used. Since EIA 232 provides only point to point
24-4
Chapter 24 ⋅ The Digital Substation
connectivity it is not used in automation systems, rather it is making it the ideal communication medium for the substation.
limited to relaying information to a SCADA system. Ethernet is discussed in detail, later in the chapter.
EIA 485
24.2.2.2 Network Topologies
EIA 485 is an electrical connection characterised by Table
24.2. When linking multiple products together to form a computer
network, in addition to the physical connection of the device, it
Item Details is also necessary to consider the network topology as well as
Max. number of transmitters 32
the protocol or language by which information is exchanged.
Max. number of receivers 32
Connection type Shielded Twisted Pair For automation systems to be effective, information must be
Mode of operation Differential communicated reliably between different devices in the
Maximum distance of transmission 1200m system. In early centralised systems, a hierarchical series of
Maximum data rate 10Mbits/s connections is required for devices at the acquisition and
Transmitter voltage 1.5V min process levels to communicate data upwards and to receive
Receiver intensity 300mV commands in return. This tree-type structure typifies the kind
Table 24.2: EIA(RS)485 characteristics of connection that the point-to-point EIA 232 communications
EIA 485 provides a two-wire half-duplex connection designed can bring.
for multi-drop connections as shown in Figure 24.4 which
The multi-drop capabilities of EIA 485 do more to encourage
makes it more suitable than EIA 232 for use in automation
distribution of control since the EIA 485 network will have
schemes.
devices connected on the same multi-drop bus, with a master
Terminating resistor connected to many slaves.
Master
Station Systems based on Ethernet technology provide more scope for
different topologies by virtue of equipment such as switches,
IED IED IED IED
hubs, bridges and routers.
Figure 24.4: Multi-drop connection of RS485 devices
24.2.3 Serial Communications
EIA 485 uses differential signalling on twisted pairs and can be
This is a form of communication whereby bits of data are
isolated. The multi-drop connection (sometimes called daisy-
exchanged serially through the signalling channel. With
chaining) generally has a limit of 1km, and although in theory
parallel communications multiple bits of data are exchanged in
the number of devices connected (nodes) is not limited, a
parallel. An example of parallel communication is the LPT
practical limit is normally 32 per bus, with repeaters being
printer port that used to feature on computers, printers, and
used if further expansion is required. Communication speeds of
office equipment before the widespread deployment of
64kbits per second (kbps) can be reliably achieved. EIA 485
Ethernet in the working environment.
allows relatively simple networks to be constructed very
efficiently and cost effectively. EIA 232, EIA 485, and Ethernet are all forms of serial
communication. The much higher speed of Ethernet sets it
Ethernet
Ethernet is a standard, which defines the connection of apart from the others. As a consequence, in the domain of
computing devices to local area networks (LANs). As per IEEE substation automation, communications based on EIA 232
802.3, standard signalling speeds are 10Mbps, 100Mbps or and EIA 485 tend to be referred to as “serial” communications,
1Gbps. It is the most widespread LAN technology. The with Ethernet being singled out for separate attention. This
specification allows connection to be made either electrically chapter adheres to that convention and continues with a
using an RJ45 connector, or by direct fibre-optic connection. discussion on “serial” communications based on EIA 232 and
Ethernet over fibre-optic cables provide a mechanism for EIA 485, later followed by Ethernet communication.
extremely high speed and noise resistant communication,
24-5
Protection & Automation Application Guide
24.2.3.1 Serial Communications Protocols Efforts were made to develop a standard solution and from the
A communications protocol is a set of standard rules for data protocols available, three open standards for IED serial
representation, signalling, authentication and error detection, communications emerged:
which defines the transfer of information over a • MODBUS
communication channel. Put another way, for devices to be • IEC 60870-5-103
able to speak to each other, they need to share a common
• DNP3
language and rules of engagement.
Modbus
When digital communication facilities were first added to Modbus was published in 1979 by Modicon. Originally
computer based protection devices, no standard protocol designed for programmable logic controllers of the
existed for this communication; manufacturers developed their time, it is a master-slave protocol that allows a master
own proprietary solutions to exploit the benefits of the to read or write bits in registers of the slave devices. It
communication interfaces. An example of a proprietary can be implemented on simple serial connections (EIA
485), but has also been migrated to Ethernet.
protocol is the Courier protocol that was developed by the
former GEC Measurements (now Alstom). IEC 60870-5-103
IEC 60870-5-103 was developed by Technical
A substation control system is required to communicate with Committee 57 of the International Electro-technical
all the distributed functionality in the system. If devices from Committee (IEC TC57). It is based on, and is a superset
different vendors are to be included in the system, then the of, the German VDEW communications standard.
different protocols will need to be supported. This increases the Primarily serving European clients, it defines the
system engineering work and consequently the cost. standards for communication between protection
equipment and the devices of the control system. As
Consider a relatively simple system, with a bay controller well as simple electrical connection, the standard also
connected to IEDs from different manufacturers A, B, and C as defines a direct communication interface implemented
depicted in Figure 24.5. over optical fibre.
DNP3
DNP3 was developed by Harris in the 1990s. It drew
on early work of TC57 on the IEC 60870-5 (before it
was standardised) to develop something with a specific
focus on the North American market that could be
Protocol A Protocol C
quickly implemented. Like Modbus, it is also supported
Protocol B
on Ethernet as well as simple serial connection.
Although originally targeted at the North American
market, it has been deployed elsewhere.
IED IED IED
A B C
24-6
Chapter 24 ⋅ The Digital Substation
24-7
Protection & Automation Application Guide
are not appropriate for use in mission critical applications such Device Device
destination on the LAN when the channel is free. Full duplex Star topology Ring topology
operation provides for consistent, reliable operation. Figure Figure 24.7: Simple star and ring network topologies
24.6 shows a typical Ethernet switch outline. In the star topology, a physical connection runs from each
device on the network to a central location, usually an
Message processor
Ethernet switch.
Input and output message queues on each port
In the ring topology, a physical connection is daisy-chained
In Out In Out In Out In Out
around the devices in the form of a ring.
Port 1 Port 2 Port 3 Port 4
Rx Tx Rx Tx Rx Tx Rx Tx
Full duplex Ethernet is inherently a star-based network topology. Initially it
message did not allow ring topology connection due to the risk of traffic
exchange
getting stuck in an endless loop around a ring and the
IED A IED B IED C IED D consequent paralysis of the network as the amount of stuck
Figure 24.6: Ethernet Switch outline (4-port) traffic increased. IEEE 802.1D introduced the Spanning Tree
Protocol (STP) which was developed to overcome this
Ethernet routers are used as gateways between the LAN and
limitation, and allow Ethernet to be used in rings as shown in
wide-area networks (WANs). They are similar to switches, but
Figure 24.8.
they have fewer ports and act at the network layer. The
information is presented to the router in the form of a Root switch
sequence of IP packets. Each packet has a logical source configured with
STP
address and destination address associated with it, and the
Device
router passes the packet on to the next step of the destination.
Packets with the same destination address do not necessarily
follow the same route. If one route gets congested, for
example, the router may decide to send the packet onwards Device Device
24-8
Chapter 24 ⋅ The Digital Substation
24-9
Protection & Automation Application Guide
Switchover delays and grace time are critical to the substation attached nodes DANP 1 and DANP 2 have full node
automation system. The switchover delay is dictated by the redundancy, whilst the singly attached nodes SAN 1 and SAN
grace time and is the most constraining factor in fault-tolerant 4 do not have any redundancy. Singly attached nodes can,
systems. The grace time is the time that the plant allows for however, be connected to both LANs, via a device that
recovery before taking emergency actions. converts a singly attached node into a doubly attached node.
These devices are referred to as redundancy boxes or
Some examples of grace times for automation systems are
RedBoxes. Devices with single network cards such as PCs,
given in IEC62439-3 and are shown in Table 24.3.
printers, etc., are singly attached nodes that may be connected
Applications Typical grace time into the PRP network via a RedBox as shown in figure Figure
Uncritical automation applications, e.g. enterprise systems 20s 24.11.
Automation management, e.g. manufacturing 2s
General automation, e.g. process automation, power plants 0.2s LAN A Switch LAN B Switch
Time-critical automation, e.g. synchronised drives 0.02s
Table 24.3: Examples of grace time
24-10
Chapter 24 ⋅ The Digital Substation
port, removes the HSR tag of the first frame received and Figure 24.13: HSR for unicast traffic
passes this to its upper layers. This now becomes the D frame. The use of PRP and HSR delivers network reliability, but the
The duplicate frame is discarded. networks also need to be secure. Security within network
The nodes forward frames from one port to another unless the communications comes under the banner 'Cyber Security',
particular node is the node that originally injected it into the ring. which will be discussed in the next section.
Source
C frame
When communications were first introduced into the
D frame D frame
A frame B frame substation environment for control and automation, they were
fully contained within the substation and based on proprietary
Singly Attached
Nodes protocols. As a consequence they enjoyed inherent security.
They were “secure by isolation” (if the substation network is
not connected to the outside world, it can’t be accessed from
the outside world), and “secure by obscurity” (if the formats
D frame D frame D frame and protocols are proprietary, it can be very difficult, to
DANH DANH DANH interpret and hack into them).
Figure 24.12: HSR for multicast traffic The increasing sophistication of substation protection, control
With unicast frames (frames that are intended for a single and automation schemes coupled with the advancement of
destination), there is just one destination and the frames are technology and the desire for vendor interoperability has
sent to that destination alone. All non-recipient devices simply resulted in standardisation of networks and data interchange
pass the frames on. They do not process them in any way. In within substations. In wide-area applications, substations can
other words, D frames are produced only for the receiving be interconnected with open networks such as corporate
DANH. This is illustrated in Figure 24.13 networks or the internet, which use open protocols for
communication. Open protocols mean that the security that
obscurity brought cannot be assumed, and interconnection via
open networks means that the security that isolation brought
them cannot be assumed either. This leaves the networks
vulnerable to so-called cyber-attacks.
24-11
Protection & Automation Application Guide
• Bad practice (users do not change default passwords, SOA is based on web services that are message oriented.
or everyone uses the same password to access all Secure messages can be sent between any of the devices in
substation equipment). the network and are not limited to point-to-point
• Inadequate technology (e.g. substation is not communication. SOA solutions are not prescribed to any
firewalled). specific profile, but the Device Profile for Web Services
Examples of availability issues are: (DPWS) protocol provides an appropriate level of security for
• Equipment overload, resulting in reduced or no substation automation. Figure 24.14 depicts layer 4 (TLS) and
performance. layer 7 (DPWS) security application.
• Expiry of a certificate prevents access to equipment.
24-12
Chapter 24 ⋅ The Digital Substation
IED A IED B
Transactions are controlled through RBAC, so that access is
granted only to what, where, and when, and to whom it
SSL SSL
should be granted.
SOA SOA
Computer
Operator Interface, Authentication Authorisation
IED D IED C IED, or EWS Server Server
IED
Discovery Messages
SOA SOA
DPWS Approach
Discovery Message response
Connection attempt
Figure 24.14: TLS vs DPWS
Authentication required
DPWS enables secure web services on devices with limited Authentication request
resources. This means that DPWS is very applicable to IEDs. Authentication response
Authorisation request
DPWS is widely deployed having been embedded in the
Get authorisation
Windows 7 operating system and the DotNet framework for Authorized
Secure exchanges
previous Windows versions.
Figure 24.16: Message Flow
24.3.1 Role Based Access Control
Note: Authorisation and Authentication functionality is
In order to have a complete cyber-security solution, other
usually contained in one server. This figure shows two servers
criteria must be taken into consideration, such as to illustrate the detailed interactions.
Authentication, Authorisation and Accounting (AAA). Once a device is attached to the network, an automatic device
In Role Based Access Control (RBAC), different classes of user discovery process may be performed. Following that, the user
can be granted different rights of access to different selects the device he/she would like to interact with. The
information in devices on the network. chosen device requests a token from the user to prove that
he/she has been authenticated by the security server. The user
A typical RBAC model is shown in Figure 24.15.
transfers this token to the end device (in this case, the IED).
User Permission The IED then requests the user roles and credentials from the
Assignment Assignment
authorisation server. If the roles and credentials are certified, a
secure exchange of data can occur between the devices'
Users Roles Operations Objects
applications. This secure data exchange includes for example
Permissions log events, messages stored at the IED level, etc., for which
the user has been granted access.
Figure 24.15: RBAC Model
The RBAC model has five basic elements: users, roles, 24.3.2 Cyber Security Standards
permissions, objects and operations.
There are several standards which apply to substation cyber-
• Objects are entities that contain or receive information security some of which are outlined in Table 24.5.
(e.g. files, directories, printers, etc.).
Standard Country Outline
• Operations are executable functions (read, write, insert,
NERC CIP (North American Electric Framework for the protection of the grid
delete, etc.) Reliability Corporation)
USA
critical Cyber Assets
• Permissions can contain objects and operations. BDEW (German Association of Requirements for Secure Control and
Germany
Energy and Water Industries) Telecommunication Systems
• Users acquire permissions through roles.
24-13
Protection & Automation Application Guide
24-14
Chapter 24 ⋅ The Digital Substation
CIP-009-1 Recovery Plans iron cores introduce measurement errors. Due to the wide
CIP 009 requires that a disaster recovery plan should be created dynamic range of current signals on power systems, current
and implemented. It should be tested with annual drills. transformers for protection need large cores to avoid
24.3.2.2 IEEE 1686 saturation under fault conditions. Due to the nature of the
IEEE 1686 is an IEEE Standard for substation IEDs' cyber- magnetic core material, however, these large cores produce
security capabilities. Used in conjunction with the NERC CIP significant errors at nominal current, which renders them
standards, it proposes practical and achievable mechanisms to impractical for metering purposes. Therefore metering-class
achieve secure operations as outlined below: transformers need to be introduced resulting in increasing
costs.
• Passwords are 8 characters long and can contain
upper-case, lower-case, numeric and special The iron core is a source of inaccuracy due to the need to
characters. magentise the core, as well as the effect of flux remanence,
• Passwords are never displayed or transmitted to a user. flux leakage, eddy current heating, etc. Conventional wired
• IED functions and features are assigned to different 1A/5A current transformers (CT) circuits have thermal
password levels. The assignment is fixed. overload constraints, and pose increasing burdens on the core
• Record of an audit trail listing events in the order in as cross-site wire run lengths increase. This can degrade
which they occur, held in a circular buffer. protection performance, potentially leading to the need to
• Records contain all defined fields from the standard and duplicate CTs. Conventional voltage transformer (VT) circuits
record all defined function event types where the may experience ferro-resonance phenomena, with thermal
function is supported. overstress resulting. Capacitor voltage transformers (CVT) can
• No password defeat mechanism exists. Instead a produce high frequency interference signals.
secure recovery password scheme is implemented.
As introduced in chapter 6, techniques that do not require the
• Unused ports (physical and logical) may be disabled.
iron core of conventional transducers can overcome the
Whilst the potential threats from cyber-attack are grave, limitations. The solutions use different sensor technologies
methods for assuring security in the real and cyber worlds are such as optical and Rogowski coils. In practical
constantly evolving and, correctly applied, should help keep the implementations, the techniques require sophisticated
lights on. solutions employing digital signal processors and micro-
processors in numerical products. Since such solutions are
24.4 CURRENT AND VOLTAGE – DIGITAL eminently able to support digital communications, it is a logical
TRANSFORMATION progression to present numerical representations of the
Developments in communication have done much to realise measured quantities to other substation devices via
the digital substation, but to realise a full digital substation it is communication links, rather than reproducing scaled analogue
necessary to have everything in digital form. Whilst much waveforms. This presentation of analogue power system
substation protection, control, and automation technology has quantities in the form of standardised digital communication
always been digital (trip signals, interlocking signals, etc.), the signals is the final element in realising the digital substation.
principal power system inputs of voltage and current have
Solutions providing signal transformation based on technology
traditionally been presented in analogue form.
other than wound transformers are often referred to as non-
It has been traditional to present scaled versions of power conventional instrument transformers (NCIT), and the devices
system currents and voltages to measuring devices, protective that provide the standardised digital communication
relays etc. Scaled versions can easily be produced using equivalents of the power system signals are referred to as
conventional electrical transformers, although capacitor merging units.
dividers may be additionally employed for transforming very
As described in the earlier chapter on transformers, NCIT
high voltages.
technologies may be based on optical techniques, or Rogowski
As is shown in chapter 6, conventional transformers based on coils, and overcome the limitation of iron-cored transformers
24-15
Protection & Automation Application Guide
IEDs
Communications
Merging Unit
network
Key
1A/5A CT and 110V VT wired analogue circuits and hard wired binary data
IEC61850 Ethernet communication
Merging units present signals such as power system voltages Key features of merging units are:
and currents to IEDs within the substation, in the form of • They can support signal processing for all transformer
numerical values adhering to standardised definitions. The use types including conventional and NCIT.
of NCIT sensors has made it possible for raw measurement • They provide current and voltage samples synchronised
information to be fed into so-called Merging Units for further to a time sync input such as 1PPS or IEEE 1588
distribution. It is these merging units that are one of the main • They deliver Ethernet multicast transmission of sampled
contributors to the digital substation, and these will be analogue values via process bus.
discussed in the next section. • They can support Ethernet connection to the station
bus; this however, is not a mandatory feature.
24.4.1 Merging Unit
• They feature watchdog self monitoring of the NCIT
The merging unit (MU) is the interface device which takes as
sensors as well as the MU itself.
its inputs connections from the instrument transformer
sensors, and performs signal processing to generate and The connections to the process bus and station bus are in
distribute output sampled value streams. The merging unit is accordance with the IEC61850 standard that is introduced
thus the gateway to the data from the instrument transformer, later in this chapter and is shown in Figure 24.19.
as it has the intelligence to interpret the effects of the specialist
physical characteristics of the instrument transformer sensor,
24-16
Chapter 24 ⋅ The Digital Substation
Suffix
IEC61850-8.1 Suffix description Suffix Specification
Station Bus
position
Sampled Values A 1000 PPS
Merging Unit IED B 100 PPS
D 1 PPM
First letter Format
E 10 PPS
Process Bus G 10000 PPS
IEC61850-9.2 H 1 PPS
GOOSE 0 DC Level Shift, width coded, no carrier
IED
First digit Modulation Frequency 1 Sine wave carrier, amplitude modulated
2 Manchester Modulated Code
Figure 24.19: Location of MU in the substation 0 No carrier/index count interval
1 100 Hz / 10 milliseconds
Each merging unit module offers signal processing to provide
2 1 kHz / 1 milliseconds
sampled values of phase currents (Ia, Ib, Ic), phase voltages Second digit Frequency/Resolution
3 10 kHz / 100 microseconds
(Va, Vb, Vc), plus residual current and residual voltage. The 4 100 kHz / 10 microseconds
5 1 MHz / 1 microsecond
sampled value frames are multicast via Ethernet, using a fibre
0 BCDTOY, CF, SBS
optic, or copper Ethernet connection.
1 BCDTOY, CF
The outputs of the merging units need to be accurately time 2 BCDTOY
3 BCDTOY, SBS
stamped. This requires the merging units to be accurately Third digit Coded expressions
4 BCDTOY, BCDYEAR, CF, SBS
time-synchronised, and this is discussed in the next section. 5 BCDTOY, BCDYEAR, CF
6 BCDTOY, BCDYEAR,
24.4.1.1 Merging Unit Time Synchronisation 7 BCDTOY, BCDYEAR, SBS
Table 24.6: Serial time code formats
The accurate time synchronisation needed by the merging
units is realised in the same way as for synchronising phasor Abbreviation Meaning
measurement units (PMUs) described in chapter 20. PPS Pulses Per Second
PPM Pulses Per Minute
Synchronisation can be achieved thanks to the global
DCLS DC Level Shift
positioning satellite system. Synchronising signals may either
BCD Binary Coded Decimal, coding of time (HH,MM,SS,DDD)
be delivered over fibre-optic links in the form of one-pulse-per- CF Control Functions depending on the user application
second (1pps) signals or over Ethernet according to IEEE1588. SBS Straight Binary Second of day (0....86400)
In 1956 the American Inter Range Instrumentation Group TOY Time Of Year
standardised the different time code formats. These were Table 24.7: Suffix Descriptions
published in the IRIG Document 104-60. This was revised in There are many subsets of the IRIG-B format. IRIG-B is the
1970 to IRIG Document 104-70, and published later as IRIG standard for time synchronisation using 100 PPS. It was this
Standard 200-70. flavour that was embraced by the utility industry to provide
real-time information exchange between substations. For IED
The name of an IRIG code format consists of a single letter
time synchronisation, IRIG-B12x is typically used for
plus 3 subsequent digits. Each letter or digit reflects an
modulated signals and IRIG-B00x for demodulated signals.
attribute of the corresponding IRIG code. The following tables
contain the meanings of the suffixes and descriptions of the The IRIG-B time code signal is a sequence of one second time
abbreviations used. frames. Each frame is split up into ten 100ms slots as follows:
• Time-slot 1: Seconds
• Time-slot 2: Minutes
• Time-slot 3: Hours
• Time-slot 4: Days
• Time-slot 5 and 6: Control functions
24-17
Protection & Automation Application Guide
• Time-slots 7 to 10: Straight binary time of day need for a common understanding between source and
destination has already been highlighted. The introduction of
The first four time-slots define the time in binary-coded
standard protocols such as Modbus, DNP3 and IEC60870-5-
decimal (BCD). Time-slots 5 and 6 are used for control
103 go some way to opening the doors to common
functions, which control deletion commands and allow
understanding, but it was the introduction of IEC61850 that
different data groupings within the synchronisation strings.
brought true possibilities for interoperability and ‘plug-and-
Time-slots 7-10 define the time in SBS (Straight Binary
play’ opportunities for substation automation.
Second of day).
Each frame starts with a position reference and a position 24.5 IEC61850
identifier. Each time-slot is further separated by an 8mS In the early 1990s the Electric Power Research Institute
position identifier. (EPRI) in the US started work on a Utility Communications
A typical 1 second time frame is illustrated in Figure 24.20. If Architecture (UCA). The goal was to produce industry
the control function or SBS time-slots are not used, the bits consensus regarding substation integrated control, protection,
defined within those fields are set as a string of zeroes. and data acquisition, to allow interoperability of substation
devices from different manufacturers. The work developed to
1 second
100 mS 200 mS 300 mS 400 mS 500 mS 600 mS 700 mS 800 mS 900 mS produce UCA2 which showed that true interoperability was
P0
Seconds
P1
Minutes
P2
Hours
P3
Days
P4
Days
P5
Years
P6
Control
P7
Functions
P8
SBS
P9
SBS
P0
possible. UCA2 was taken forward by IEC TC57 to produce the
standard IEC61850 that revolutionises substation automation.
= 8 mS position identification pulses = 8 mS position reference pulse
24-18
Chapter 24 ⋅ The Digital Substation
system context, which allows the engineer to • Lower integration costs. IEC 61850 networks are
immediately identify the meaning of the data. capable of delivering data without separate
• Devices are self-describing: Client applications can communication front-ends or reconfiguring devices.
download the description of all the data, without any This means that the cost associated with integrating
manual configuration of data objects or names. substation data is substantially reduced.
• High-Level Services: IEC61850’s abstract • Implement new capabilities: IEC61850 enables new
communications service interface supports a wide and innovative applications that would be too costly to
variety of services, such as generic object-oriented produce otherwise. This is because all data associated
substation events (GOOSE), sampled measured values with a substation is available on its LAN in a standard
(SMV), logs, etc. format and accessible using standard protocols.
• Standardised substation configuration language (SCL):
24.5.2 Structure of the IEC 61850 standard
SCL enables the configuration of a device and its role in
The IEC 61850 standard consists of ten parts, as summarised
the power system to be precisely defined using
in Table 24.8.
extensible mark-up language (XML) files.
Part Title
The major benefits of the standard are as follows:
Part 1 Introduction and overview
• Eliminates procurement ambiguity: The user Part 2 Glossary
requirements related to the substation automation Part 3 General requirements
system may be precisely defined using SCL. Part 4 System and project management
• Lower installation cost: IEC 61850 enables devices to Part 5 Communication requirements for functions and device models
exchange data - primarily digital, but also analogue if Configuration description language for communication in electrical
Part 6
necessary - using GOOSE over the station LAN without substations related to IEDs
having to wire separate links for each IED. By using the Part 7 Basic communication structure for substation and feeder equipment
station LAN to exchange these signals, this reduces Part 7.1 - Principles and models
infrastructure costs associated with wiring, trenching Part 7.2 - Abstract communication service interface (ACSI)
and ducting.
Part 7.3 - Common data classes
• Lower instrument transformer / sensor costs: A single Part 7.4 - Compatible logical node classes and data classes
merging unit can deliver measurement signals to many Part 8 Specific Communication Service Mapping (SCSM)
IEDs from a single instrument transformer / sensor.
- Mappings to MMS (ISO 9506-1 and ISO 9506-2) and to ISO/IEC
This reduces costs associated with primary equipment, Part 8.1
8802-3
wiring, calibration and maintenance. Part 9 Specific Communication Service Mapping (SCSM)
• Lower commissioning costs: IEC 61850-compatible Part 9.1 - Sampled values over serial unidirectional multidrop point to point link
devices do not require much manual configuration. Part 9.2 - Sampled values over ISO/IEC 8802-3
Also, client applications do not need to be manually Part 10 Part 10: Conformance testing
configured for each point they need to access, because Table 24.8: Structure of IEC 61850 standard
they can retrieve this information directly from the
device or import it via an SCL file. Many applications Parts 1 and 2 introduce the standard, provide a summary and
require nothing more than the setting up of a network a glossary of all terms used throughout the standard. Parts 3,
address. Most manual configuration is therefore 4, and 5 of the standard start by identifying the general and
eliminated, drastically reducing errors, rework, and specific functional requirements for communication in a
therefore costs. substation (key requirements stated above). These
• Lower equipment migration costs: The cost associated requirements are then used as forcing functions to aid in the
with equipment migrations is reduced due to the identification of the services and data models needed,
standardised naming conventions and device
application protocol required, and the underlying transport,
behaviour.
network, data link, and physical layers that will meet the
• Lower extension costs: Adding devices and applications
overall requirements.
into an existing IEC 61850-based network can be done
with little impact on existing equipment. Part 6 of the standard defines an XML-based Substation
24-19
Protection & Automation Application Guide
Configuration Language (SCL). SCL allows formal description The data model of any IEC 61850 IED can be viewed as a
of the relations between the substation automation system hierarchy of information, whose nomenclature and
and the substation switchyard. Each device must provide an categorisation is defined and standardised in the IEC 61850
SCL file that describes its own configuration. specification. The IEC61850 data model is represented
conveniently by Figure 24.21.
Part 7 specifies the communication structure for substations. It
consists of 4 sub-sections. IEC 61850 abstracts the definition
Data Attributes
of the data items and the services from the underlying stVal q t PhA PhB PhC
protocols. These abstract definitions allow data objects and
services to be mapped to any protocol that can meet the data Data Objects
Pos A
and service requirements. The definition of the abstract
services is found in part 7.2 of the standard and the Logical Nodes: 1 to n
abstraction of the data objects (referred to as Logical Nodes) is LN1: XCBR LN2: MMXU
24-20
Chapter 24 ⋅ The Digital Substation
The names of these logical nodes have been standardised in Each CDC has a set of attributes each with a defined name,
IEC61850 and cannot be changed. The naming convention is defined type, and specific purpose. A set of functional
as follows: constraints (FC) groups these attributes into categories. For
example, there is a CDC called SPS (Single Point Status).
<Single letter group designator><three-letter mnemonic
abbreviation of function><instance ID> In the Single Point Status (SPS) CDC there are functional
constraints for status (ST) attributes, substituted value (SV)
For example: PDIR1 belongs to the group “Protection
attributes, description (DC) attributes, and extended definition
functions” and is the “Directional element” for the first stage
(EX) attributes. In this example the status attributes of the SPS
(of overcurrent protection, typically). A complete list of logical
class consist of a status value (stVal), a quality flag (q), and a
node names is provided in the standard, and a selection of
time stamp (t).
those most pertinent to readers is given in appendix C.
Example:
Each logical node contains one or more elements of data.
Suppose that a logical device called Breaker1 consists of a
There are several hundred data elements, which can be
single circuit breaker logical node XCBR1. To determine if the
broadly categorized into seven groups:
breaker is in the remote or local mode of operation, the
• System information following expression would be used:
• Physical device information
• Breaker1/XCBR1$ST$Loc$stVal.
• Measurands
The returned value would indicate the mode of operation.
• Metered values
• Controllable data 24.5.4 Mapping IEC 61850 to a protocol stack
• Status information
The IEC 61850 abstract model needs to work over a real set of
• Settings protocols, which are convenient and practical to implement,
Each data element has a unique purposeful name determined and which can operate within the computing environments
by the standard, along with a set of attributes. These data commonly found in the power industry. The IEC61850
names provide a mnemonic description of its function. For standard takes advantage of existing protocols to achieve each
example, a circuit breaker is modelled as an XCBR logical necessary layer of communication.
node. This contains a variety of data including: Figure 24.22 shows a simplified version of the IEC61850
• Loc for determining if operation is remote or local protocol stack, and how it fits in with the OSI model.
• OpCnt for an operations count 7
MMS (core ACSI services) SV GOOSE SNTP
Application layer
• Pos for the position 6
Presentation layer
Connection-oriented
• BlkOpn block breaker open commands 5
Session layer
• BlkCls block breaker close commands 4
Transport layer
TCP
UDP
TCP
ISO
• CBOpCap for the circuit breaker operating capability 3
Network layer
IP IP
structure of the data within the logical node. There are CDCs for:
Figure 24.22: IEC 61850 protocol stack
• Status information
IEC 61850 part 8.1 maps the abstract objects and services to
• Measured information the Manufacturing Message Specification (MMS) protocols
• Controllable status information specified in ISO9506. MMS is the only public ISO-compliant
• Controllable analogue set point information protocol that can easily support the complex naming and
• Status settings service models specified by IEC 61850. MMS is used because
• Analogue settings it supports complex named objects and a rich set of flexible
24-21
Protection & Automation Application Guide
services that supports the mapping to IEC 61850 in a IED capabilities System specification
(LN, DO, …) (Single line, LNs, …)
System
straightforward manner. IED
configurator
Database
ICD Associations,
Part 8.1 also defines profiles for the lower layers of the relation to single line,
SCD preconfigured
communication stack. MMS operates over connection- reports, ...
Engineering IED
oriented ISO, or TCP/IP. SNTP operates over TCP/IP or workplace configurator
Project
UDP/IP. Sampled Values and GOOSE data map directly into engineering
File transfer
environment
Remote
the Ethernet data frame thereby eliminating processing of any CID
Substation
middle layers and providing very fast response. Automation File transfer Substation File transfers and parameterisation
system Local gateway with IEC61850 services
24-22
Chapter 24 ⋅ The Digital Substation
24-23
SUBSTATION CONTROL
AND AUTOMATION
Chapter 25
SUBSTATION CONTROL AND
AUTOMATION
GEGridSolutions.com 25-1
Protection & Automation Application Guide
25-2
Chapter 25 Substation Control and Automation
most elementary application. However, the selection of the because of a resulting limit to the number of IEDs that can be
complete set of functions required for a particular application is connected. The other important issue is one of reliability and
essentially the responsibility of the end-user Utility. Due to a availability – there is only one computer that can control the
modular, ‘building block’ approach to software design, it is substation and therefore only local manual control will be
normally relatively easy to add functionality at a later stage. possible if the computer fails for any reason. Such a topology is
This often occurs through changing operators’ needs and/or therefore only suited to small MV substations where the
electrical network development. Compatibility of the underlying consequences of computer failure (requiring a visit from a
database of network data must be addressed to ensure repair crew to remedy) are acceptable. Bay Modules are not
historical data can still be accessed. used, the software for control and interlocking of each
substation bay runs as part of the HMI computer software.
25.3 HARDWARE IMPLEMENTATION
To form a digital substation control system (DCS), the various 25.3.2 RTU-based Topology
elements described above must be assembled into some form This topology is an enhancement of the HMI topology and is
of topology. Three major hardware topologies can be identified shown in Figure 25.3. A digital RTU is used to host the
as being commonly used, as follows: automation software, freeing the HMI computer for operator
interface duties only. The HMI computer can therefore be less
25.3.1 HMI-based Topology powerful and usually takes the form of a standard PC, or for
This takes the form of Figure 25.2. The software to implement unmanned substations, visiting personnel can use a laptop PC.
the control/automation functions resides in the HMI computer Remote
and this has direct links to IEDs using one or more HMI
communications protocols. The link to a remote SCADA
SCADA
system is normally also provided in the HMI computer, though interface
a separate interface unit may be provided to offload some of HMI Internet
or PSTN
the processor requirements from the HMI computer, especially
if a proprietary communications protocol to the SCADA system
is used. Telecontrol or
Bus interface
HMI
Internet
or PSTN Legacy bus
Master clock
Telecontrol or (GPS, radio)
Station bus Bus interface I/O, devices CT, VT
IEDs
Computer
Legacy bus IEDs Legacy bus I/O, devices
The RTU, telecontrol interface
CT, VT
and the bus interface could be
separate equipment or
integrated into the same device
Computer IEDs
25-3 D
Protection & Automation Application Guide
HMI
Internet (b) Ring connection of bay modules
or PSTN
Telecontrol Computer
interface Station bus
Of course, it is possible to overcome the first problem by
Bay Module duplicating links and running the links in physically separate
Bus interface routes.
Bay Module
IED's An alternative is to connect the Bay Controllers, HMI computer
The bay module and bus
and SCADA gateway in a ring, as shown in Figure 25.5(b). By
IED's interface could be separate using a communications architecture such as found in a LAN
equipment or integrated into the
same device network, each device is able to talk to any other device on the
ring without any message conflicts. A single break in the ring
Legacy bus I/O, devices
CT, VT
does not result in loss of any facilities. The detection of ring
breakage and re-configuration required can be made
automatically. Thus, the availability and fault tolerance of the
The connection between the various Bay Controllers and the HMI network is improved. Multiple rings emanating from the HMI
computer is of some interest. Simplest is the star arrangement of computer can be used if the number of devices exceeds the
Figure 25.5(a). This is the least-cost solution but suffers from two limit for a single ring. It can be easier to install on a step-by-
disadvantages. Firstly, a break in the link will result in loss of step basis for retrofit applications, but of course, all these
remote control of the bay affected; only local control via a local advantages have a downside. The cost of such a topology is
HMI computer connected to the bay is then possible. Secondly, higher than that of the other solutions, so this topology is
the number of communications ports available on the HMI reserved for situations where the highest reliability and
computer will limit the number of Bay Modules. availability are required.
It is usual to have more than one operators’ HMI, either for
operational reasons or for fault-tolerance. The system
computer may be duplicated on a ‘hot-standby’ or ‘dual-
redundant’ basis, or tasks may be normally shared between
two or more system computers with each of them having the
capability of taking over the functions of one of the others in
the event of a failure.
The total I/O count in a major substation will become large
25-4
Chapter 25 Substation Control and Automation
and it must be ensured that the computer hardware and normally be done offline on the Engineers’ workstation, if
communications links have sufficient performance to ensure available, or as a background task on the control computer if
prompt processing of incoming data. Overload in this area can not. Careful and extensive checking of the data is required,
lead to one or more of the following: both before and after entry into the database, to ensure that no
errors have been made. Full testing on the new configuration
undue delay in updating the system status
using a simulator is recommended prior to use of the new
diagrams/events log/alarm log in response to an
database on the main control computer to ensure that there is
incident
minimal possibility of errors.
corruption of system database, so that the information
presented to the operator is not an accurate The software is written as a set of well-proven, standard
representation of the state of the actual electrical modules, so there is little or no need for new modules to be
system written and tested for a particular substation. The required
data for the calculations performed by the software is held in
system lockup
the network database. This means that adding functionality
As I/O at the bay level, both digital and analogue will typically later is not difficult, so long as the database design has
be handled by intelligent relays or specialised IEDs, it is considered this possibility. There may be problems if the
therefore important to ensure that these devices have sufficient electrical system configuration is altered or additional
I/O capacity. If additional IEDs have to be provided solely for functionality added, in reading historical data prior to the
ensuring adequate I/O capacity, cost and space requirements change. Training of operations personnel will inevitably be
will increase. There will also be an increase in the number of required in operation of the system, configuration
communications links required. management and automation system maintenance.
Automation system suppliers will be able to provide
25.4 SUBSTATION AUTOMATION configuration management and system maintenance services
FUNCTIONALITY under contract if required, often with defined cost schedules
The hardware implementation provides the physical means to and response times so financial management of the
implement the functionality of the substation automation automation scheme once installed is well-defined.
scheme. The software provided in the various devices is used The issuing of commands to switching devices in the system
to implement the functionality required. The software may be has to be carefully structured, in order to prevent commands
quite simple or extremely complex – Table 25.1 illustrates the that would cause a hazard being issued. A hierarchical
functionality that may be provided in a large scheme. structure is commonly used as shown in Figure 25.6,
The description of the electrical network and the characteristics beginning with the requirement for an operator wishing to
of the various devices associated with the network are held issue a command to switching devices to log-in to the system
within the computer as a database or set of databases. Within using a password, or other means of authentication.
each database, data is organised into tables, usually on a ‘per
device’ basis that reflects the important characteristics of the
device and its interrelationship with other devices on the
network. Electrical system configuration changes require
modification of the database using an appropriate software
tool. The tool is normally a high level, user-friendly interface,
so that modifications to the one-line can be drawn directly on-
screen, with ‘pick-and–place’ facilities. This work would
25-5 D
Protection & Automation Application Guide
25-6
Chapter 25 Substation Control and Automation
functions at least cost, and the data required for 25.5.3 Test Strategy
implementation of the automation scheme. The strategy adopted for the testing of the automation system
must naturally satisfy client requirements, and generally
25.5.2 System Testing follows on of two approaches:
The degree of testing to be carried will be defined by the
a single test is carried out when all equipment for the
customer and encapsulated in a specification for system
scheme has been assembled
testing. It is normal for testing of the complete functionality of
the scheme to be required prior to despatch from the incremental tests are carried out as the automation
manufacturer – termed a ‘factory acceptance test’ (FAT). The system is built up, with simulators used to represent
larger and more complex the automation scheme, the more missing equipment
important for all parties that such FAT testing is carried out. It The former solution is quickest and cheapest, but can give rise
is accepted wisdom that the earlier problems are discovered, to problems where it is not easy to locate problems down to
the cheaper and quicker it is to fix them. Remediation of the device level. It is therefore used principally when an
problems on-site during commissioning is the most expensive upgrade to an existing system is being carried out.
and time-consuming activity. Manual testing of a network
automation scheme is only practical for small networks, due to It is usual for all of the functionality to be tested, including that
the cost of testing. Simulation tools are necessary for all other specified for normal conditions and specified levels of
automation schemes. These tools fall into two categories: degradation within the automation system. This leads to a
large number of tests being required.
simulator tools that re-create the network to be
controlled by the automation system. 25.5.4 Management of System Tests
test management tools The large number of tests required to demonstrate the
compliance of an automation system with specification makes
25.5.2.1 Simulator tools manual techniques for management of the tests cumbersome
Simulator tools are dedicated to the network being tested. and time consuming. The end result is increased cost and
They will normally be provided with a simulation language that timescale. Moreover, each test may result in a large amount of
the test team can use to play scenarios, and hence determine data to be analysed. The results of the analysis need to be
how the automation system will react to various stimuli. presented in an easily understood form and stored as quality
Process simulator tools may be hardware and/or software records, for traceability. If changes are made to software for
based and emulate the response of the various devices to be any reason over the lifetime of the equipment, the different
controlled or measured (breakers, isolators, instrument versions must be stored, together with a record of what the
transformers or protection relays). They must be capable of changes between versions were, and why they were made.
closely following the dynamic response of such devices under The management of this becomes very complex, and software
multiple and cascade simulation scenarios. Specific tools and tools are normally used to address the issues of test schedules,
libraries are developed as required, which simulate the test result presentation, software version control, and
response of equipment within the control span of the configuration management.
automation equipment, or that of equipment outside of the
span of control, in order that the response of the automation
system can be tested.
Communications simulator tools are used both to load the
internal communications network within the automation
system to ensure that all devices are communicating correctly
and that performance of the overall automation system is
within specification during periods of high communications
traffic loading. These simulators are standardised and a single
simulator may be able to emulate several items of equipment.
External communications simulators test the communications
with an external system, such as a remote control centre.
25-7 D
APPENDIX
Appendix A
Terminology
ACCURACY
The accuracy of a transducer is defined by the limits of intrinsic
error and by the limits of variations.
ACCURACY CLASS
ADC
Analogue to Digital Converter
A/D CONVERSION
The process of converting an analogue signal into an
equivalent digital one, involving the use of an analogue to
digital converter
ADJUSTMENT
The operation intended to bring a transducer into a state of
performance suitable for its use
AI
Analogue Input
AIS
Air Insulated Switchgear
ALARM
An alarm is any event (see below) tagged as an alarm during
the configuration phase
GEGridSolutions.com A-1
Protection & Automation Application Guide
A-2
Appendix A ⋅ Terminology
A-3
Protection & Automation Application Guide
A-4
Appendix A ⋅ Terminology
A method of motor starting, in which full line voltage is applied EARTH FAULT PROTECTION SYSTEM
to a stationary motor
A protection system which is designed to respond only to faults
to earth
DIRECTIONAL RELAY
A protection relay in which the tripping decision is dependent EARTHING TRANSFORMER
in part upon the direction in which the measured quantity is
A three-phase transformer intended essentially to provide a
flowing
neutral point to a power system for the purpose of earthing
DISCRIMINATION
EFFECTIVE RANGE
The ability of a protection system to distinguish between power
The range of values of the characteristic quantity or quantities,
system conditions for which it is intended to operate and those
or of the energising quantities to which the relay will respond
for which it is not intended to operate
and satisfy the requirements concerning it, in particular those
DISTORTION FACTOR concerning precision
The ratio of the r.m.s. value of the harmonic content to the EFFECTIVE SETTING
r.m.s. value of the non-sinusoidal quantity
The ‘setting’ of a protection system including the effects of
current transformers. The effective setting can be expressed in
DLR
terms of primary current or secondary current from the current
Dynamic Line Rating. This is a technique to adapt thermal transformers and is so designated as appropriate
protection to include additional line heating and cooling
factors, in addition to the traditional inputs of current and ELECTRICAL RELAY
ambient temperature. Wind speed, wind direction and solar
A device designed to produce sudden predetermined changes in
radiation sensors may be added to the scheme in order to
one or more electrical circuits after the appearance of certain
more accurately simulate the thermal state and allow greater
conditions in the electrical circuit or circuits controlling it
line loadability.
NOTE: The term ‘relay’ includes all the ancillary equipment
DNP calibrated with the device
Distributed Network Protocol. A communication protocol used
on secondary networks between HMI, substation computers or ELECTROMECHANICAL RELAY
Bay Computers and protective devices An electrical relay in which the designed response is developed
by the relative movement of mechanical elements under the
DO action of a current in the input circuit
Digital Output
EMC
DROP-OUT (OR DROP-OFF) Electro-Magnetic Compatibility
A relay drops out when it moves from the energised position to
the un-energised position EMBEDDED GENERATION
Generation that is connected to a distribution system (possibly
DROP-OUT/PICK-UP RATIO at LV instead of HV) and hence poses particular problems in
The ratio of the limiting values of the characteristic quantity at respect of electrical protection
which the relay resets and operates. This value is sometimes
called the differential of the relay E.M.F.
Electro-motive Force ( or voltage)
A-5
Protection & Automation Application Guide
Full Load Current (full nominal rated load current for the
A-6
Appendix A ⋅ Terminology
Inter-Control Centre Communications Protocol (IEC 60870-6) INSULATED GATE BIPOLAR TRANSISTOR
A special design of transistor that is suitable for handling high
ICT
voltages and currents (relative to an ordinary transistor).
Interposing Current Transformer Frequently used in static power control equipment (inverters,
controlled rectifiers, etc) due to the flexibility of control of the
output
A-7
Protection & Automation Application Guide
LCD MCB
Liquid Crystal Display Miniature Circuit Breaker
LD MCCB
Ladder Diagram. One of the IEC 61131-3 programming Moulded Case Circuit Breaker
languages. This can also mean an IEC61850 Logical Device.
MEAN-SENSING TRANSDUCER
LDC A transducer which actually measures the mean (average)
Line drop compensation value of the input waveform but which is adjusted to give an
A-8
Appendix A ⋅ Terminology
output corresponding to the r.m.s. value of the input when MULTI-ELEMENT TRANSDUCER
that input is sinusoidal A transducer having two or more measuring elements. The
signals from the individual elements are combined to produce
MEASURAND an output signal corresponding to the measurand
A quantity subjected to measurement
MULTI-SECTION TRANSDUCER
MEASUREMENT CENTRE A transducer having two or more independent measuring
A non-protection IED capable of measuring a large number of circuits for one or more functions
electrical system parameters
MULTI-SHOT RECLOSING
MEASURING ELEMENT A reclosing scheme that permits more than one reclosing
A unit or module of a transducer which converts the operation of a CB after a fault occurs before lock-out occurs
measurand, or part of the measurand, into a corresponding
signal MV
Medium Voltage
MEASURING RANGE
That part of the span where the performance complies with N
the accuracy requirements Neutral
A-9
Protection & Automation Application Guide
NV OPGW
Non-volatile. Typically used to describe a secure memory Optical Ground Wire – a ground wire that includes optical
facility in numerical relays. fibres to provide a communications link
NVD OPTO
Neutral Voltage Displacement An optically coupled logic input (also referred to as a binary
input)
OCB
Oil Circuit Breaker OSI 7-LAYER MODEL
The Open Systems Interconnection 7-layer model is a model
OFF-LOAD TAP CHANGER developed by ISO for modelling of a communications network.
A tap changer that is not designed for operation while the
transformer is supplying load OUTPUT COMMON MODE INTERFERENCE
VOLTAGE
OHL An unwanted alternating voltage which exists between each of
Overhead line the output terminals and a reference point
A-10
Appendix A ⋅ Terminology
A conjunctive test that ascertains the range of values of each POINT OF COMMON COUPLING
parameter for which the test meets specific performance
The interface between an in-plant network containing
requirements
embedded generation and the utility distribution network to
PCB which the in-plant network is connected
A-11
Protection & Automation Application Guide
A-12
Appendix A ⋅ Terminology
ROCOF SEF
Rate Of Change Of Frequency (protection relay) Sensitive Earth Fault
A-13
Protection & Automation Application Guide
S.I.R. STATCOM
System Impedance Ratio A particular type of Static Var Compensator, in which Power
Electronic Devices are used to generate the reactive power
SINGLE ELEMENT TRANSDUCER required, rather than capacitors and inductors
A transducer having one measuring element
STATIC RELAY
SIPS An electrical relay in which the designed response is developed
System Integrity Protection Schemes by electronic, magnetic, optical or other components without
mechanical motion. Excludes relays using digital/numeric
SNTP technology
Simple Network Time Protocol
STC
SOE Short Time Current (rating of a CT)
Sequence Of Events
STORAGE CONDITIONS
SOTF The conditions, defined by means of ranges of the influence
quantities, such as temperature, or any special conditions,
Switch On To Fault (protection)
within which the transducer or relay may be stored (non-
operating) without damage
SPECIFIC CONJUNCTIVE TEST
A conjunctive test using specific values of each of the SVC
parameters
Static Var Compensator
SPRING WINDING TIME
SYNCHROPHASOR
For spring-closed CB’s, the time for the spring to be fully
A voltage or current vector synchronised to real time,
charged after a closing operation
accurately defining the magnitude and phase of a power
system quantity. Typically IEEE C37.118 applies
ST
Structured Text: One of the IEC 61131-3 programming
languages
A-14
Appendix A ⋅ Terminology
A-15
Protection & Automation Application Guide
UPS ZONE
Uninterruptible Power Supply The boundary limits, typically for a protected unit in the power
system, within which protection is expected to operate
USB
Universal Serial Bus
UTC
Universal Time Coordinated. The precise internationally
recognised time reference, equivalent to GMT.
V
Voltage
VCB
Vacuum Circuit Breaker
VDEW
Term used for IEC 60870-5-103 protocol. The VDEW protocol
is a subset of the IEC 60870-5-103 protocol
VOLTAGE TRANSDUCER
A transducer used for the measurement of a.c. voltage
VT
Voltage Transformer
WAMPAC
Wide-Area Monitoring/Measurement, Protection and Control
WAN
Wide Area Network
X
Reactance
Y
Admittance
Z
Impedance
A-16
Appendix B
ANSI/IEC Symbols FUNCTIONS ANSI IEC 61850
Other Common
Designations
Arc flash Detector AFD SARC
The most common methods for indicating protection device Automatic Tap Change Control ATCC AVR
functions are defined by the IEEE (ANSI) C37-2 and IEC Autoreclose 79 RREC DAR
61850, which both use alphanumeric codes. There are also Blocking (eg. Power Swing
68 RPSB PSB, OST, OOS
other common designations, some of which originate from IEC Blocking) or “out-of-step”
60617. A list of common ANSI device numbers and their Breaker Failure 50BF RBRF BFP
equivalents are given in this appendix. Broken Conductor 46BC PTOC I2/I1>
Busbar Differential 87BB PDIF Idiff>
Circuit Breaker 52 XCBR CB
Circuit Breaker Closed Auxiliary
52a XCBR
Contacts
Circuit Breaker Open Auxiliary
52b XCBR
Contacts
Circuit Switch 89 XSWI
Clock or Timing Source CLK
Closing Coil CC
Cold Load Pick-Up 51CLP CLP
Current Transformer Supervision RVCS CTS
Data Communications Device 16
Digital Fault Recorder DFR RDRE, RADR, RBDR
Delta Directional Comparison ∆I / ∆V
Directional Earth Fault
67N PTOC IN>, t>, DEF
Overcurrent
Directional Over Power 32O PDOP P>
Directional Overcurrent 67P PTOC I>
Directional Under Power 32U PDUP P<
Distance 21 PDIS Z
Distance Aided Schemes 21/85 PSCH
Disturbance Recorder DDR RDRE, RADR, RBDR DR
Dynamic Line Rating 49DLR PTTR DLR
Earth Fault Overcurrent 51N PTOC IN>
Ethernet Switch 16ES
Fault Locator 21FL RFLO DTF
Fuse Fail Overcurrent 51FF PTOC
Generator Differential 87G PDIF Idiff>
High Impedance Earth Fault
HIZ PHIZ Hi-Z
Detection
Human Machine Interface HMI IHMI
Instantaneous Overcurrent 50 PTOC I>
Interlocked Overcurrent Busbar
51BB PTOC
Protection Scheme
Interlocking 3 CILO
Interturn Fault 50 PDIF
Line Differential 87L PDIF Idiff>
Load Restoration 81R PTOF
GEGridSolutions.com B-1
Protection & Automation Application Guide
B-2
Appendix C There are many different institutions, both international and
national, which issue standards used by manufacturers of
Typical Standards Applicable to protection and control devices. The standards shown here can
Protection and Control Numerical be supplemented by the electrical power system operators'
Devices own particular standards. The most used standards bodies in
the field of power systems engineering are:
C.13 Power Frequency Magnetic Field Immunity 2kV rms. for 1 minute between all terminals connected
together and case earth.
C.14 Pulsed Magnetic field Immunity Dielectric withstand, EN 60255- 2kV rms. for 1 minute between all terminals of independent
C.15 Damped Oscillatory Magnetic Field Immunity 27:2013 circuits with terminals on each independent circuit connected
together.
C.16 Damped Oscillatory Tests
1kV rms. for 1 minute across watchdog contacts.
C.17 Power Frequency Test 1kV rms. for 1 minute across open contacts of the watchdog
C.18 ANSI/IEEE Surge Withstand Capability contacts.
ANSI dielectric withstand, ANSI/IEEE
C.19 Operating and Storage Temperature C37.90. (2005)
1kV rms. for 1 minute across open contacts of changeover
output contacts.
C.20 Six-Day Cyclic Temperature with Humidity 1.5kV rms. for 1 minute across normally open output contacts.
C.21 56-Day Humidity (IEC 60068-2-3) Insulation resistance, EN 60255-
100 MΩ minimum.
C.22 Mechanical Tests 27:2013
GEGridSolutions.com C-1
Protection & Automation Application Guide
C-2
Appendix C ⋅ Typical Standards Applicable to Protection and Control Numerical Devices
C-3
Protection & Automation Application Guide
Lower Temperature
High Temperature
IP10, EN 60529:2013 Protected against solid foreign objects of 50mm diameter and
Exposure Time
greater
Standard
C-4
delayed 14.9 14-9
INDEX high-speed 14.8 14-8
Application of unit protection systems to mesh corner 10.8.2 10-8 type of load 14.4.1.2 14-4
substations
Application of unit protection to breaker and a half 10.8.2 10-8 use with blocking schemes 14.8.1 14-9
substations
use with transfer trip protection schemes 14.8.1 14-9
Arc resistance formula 11.7.3 11-8
Armature reaction, of synchronous machines 5.3 5-2 use with zone 1 extension scheme 14.8.2 14-9
Arrangement of busbar protection schemes 15.7 15-7 Auto-reclosing: 14.1- 14-1,
Arrangement of CT connections: 14.12 14-12
Auto-synchroniser 22.8.2 22-9
in high impedance busbar protection 15.8.5 15-13
Auto-transformer:
in low impedance busbar protection 15.9.5 15-16
Asset management; transformers 16.19 16-22 equivalent circuits 5.16 5-13
Asymmetry of synchronous machine 5.7 5-6 positive sequence equivalent circuit 5.16.1 5-13
Attracted armature relays 7.2.1 7-2 special conditions of neutral earthing, zero 5.16.3 5-14
sequence reactance
Auto-close circuits 14.11 14-12
zero sequence equivalent circuit 5.16.2 5-13
Automatic changeover systems for 18.9 18-10
industrial/commercial networks
Auto-reclosing: B
anti-pumping devices 14.10.5 14-11 Back-up protection 2.9 2-8
application of 14.2 14-3 Balanced voltage system, unit protection 10.5 10-3
circuit breaker characteristics 14.4.1.3, 14-4, Balanced voltage unit protection scheme for tee’d 13.3.1 13-6
14.6.3 14-7 feeders
dead time 14.4.1, 14-3, Bar primary current transformers 6.4.5.2 6-9
14.6.4, 14-7, Basic circuit laws, theorems and network reduction 3.5 3-9
14.9 14-9
de-ionisation of fault path 14.4.1.4, 14-4, Bay controller, definition of 25.2.1 25-2
14.6.2 14-6
GEGridSolutions.com I-1
Protection & Automation Application Guide
differential 15.7- 15-7 CDC (Common Data Classes); IEC61850 24.5.2 24-19
15.11 15-20
faults 15.2 15-2 CE marking 21.4.5 21-10
high impedance 15.8 15-9 Characteristic time/current curves of IDMT relays 9.4 9-4
I-2
Index
Choice of dead time, use in auto-reclose schemes 14.6.4 14-7 Condition monitoring (transformers) 16.18, 16-19,
24.5.1 25-5
Choice of harmonic (transformer protection) 16.9.2 16-10 Conditions for direction comparison, unit protection 10.3 10-2
Choice of reclaim time 14.6.5 14-8 Conducted and radiated emissions tests 21.3.9 21-6
CIP (Critical Infrastructure Protection); cyber security 24.3.2.1 24-14 Conducted and radiated immunity tests 21.3.10 21-7
standards
Circuit breakers: 18.5.3 18-5 Configuration; functions within a substation control 25.5.1 25-6
system
air circuit breakers (ACBs) 18.5.3 18-5 Connections for directional relays 9.14, 9-12,
closing time 14.4.1.3 14-4 9.17.1 9-18
Considerations with numerical relays 7.7 7-9
dead time 14.6.4 14-7
Contact systems for relays 2.10.1 2-9
for auto-reclose schemes 14.4.1.3, 14-4,
14.6.3, 14-7 Convention of direction of current flow, unit protection 10.2 10-2
interrupting time 9.11.1, 9-9, Co-ordination of earth fault relays in three-phase four 18.7.2 18-8
14.4.1.3 14-4 wire systems
miniature circuit breakers (MCBs) 18.5.1 18-4 Co-ordination of relays with fuses 9.12.3 9-11
monitoring in numerical relays 7.6.3 7-8 Co-ordination problems in industrial and commercial 18.7 18-7
moulded case (MCCB) 18.5.2 18-5 networks
Co-ordination procedure for overcurrent protection 9.2 9-1
oil circuit breakers (OCBs) 18.5.4 18-6 relays
Core faults:
opening time 14.4.1.3 14-4
in generators 17.3 17-3
SF6 circuit breakers 18.5.6 18-6
in power transformers 16.2.6 16-3
Vacuum circuit breakers (VCBs) 18.5.5 18-6 Core-balance current transformers (CBCT) 6.4.5.3 6-10
Circuit laws 3.5.1 3-9 Cross country fault analysis 4.4.6 4-9
Circuit quantities and conventions 3.4 3-4 CT supervision in high impedance busbar schemes 15.8.4 15-12
Circuit theorems 3.5.2 3-9 CT supervision in low impedance busbar schemes 15.9.4 15-16
Circuit variables 3.4.1 3-6 Current differential protection scheme 10.8, 10-6,
Circulating current system, spill current 10.4 10-2 10.10 10-8
Current distribution due to a fault 4.5 4-10
Circulating current system, unit protection 10.4 10-2
Current distribution factors 4.5.1 4-11
Class PX (IEC 60044) current transformers 6.4.4 6-9
Current reversal on double circuit lines, distance 13.2.2.1 13-2
Class X (BS3938) current transformers 6.4.4 6-9 protection
Current setting of a relay 9.10 9-8
Classification of power system disturbances 23.2 23-1
Current transformers:
Closing impulse time 14.10.4 14-11
accuracy 6.4.1 6-7
Closing time of circuit breakers 14.4.1.3 14-4
accuracy class 6.4.2 6-8
Combined differential and restricted earth fault 16.10 16-10
protection of accuracy limit current 6.4.3 6-8
Combined I.D.M.T. and high set instantaneous 9.5 9-6
overcurrent relays air gap 6.4.5.5 6-10
Commissioning tests 21.9 21-1, all-optical transducer 6.5.1.3 6-17
21-15
Communication links 8.1, 8-1, anti-remanence 6.4.6.2 6-10
24.2 24-2
Communications: definition 24.2 24-2 bar primary 6.4.5.2 6-9
Comparison of transfer trip and blocking schemes 12.6 12-9 C Class 6.4.13 6-15
Complex transmission circuits, protection of 13.1- 13-1, class X (BS 3938) 6.4.4 6-9
13.7 13-12 construction 6.4.5 6-9
Complex variables 3.3.1 3-3
current or ratio error 6.4.1.1 6-8
Composite error of current transformers 6.4.2 6-8
I-3 D
Protection & Automation Application Guide
Hall-effect 6.5.2.1 6-19 Definitions of terms used in protection, control and Appendix A
automation
harmonics in 6.4.11 6-15 De-ionisation of fault path 14.4.1.4, 14-4,
hybrid 6.5.1.2 6-16 14.6.2 14-7
De-ionisation of fault path, auto-reclose schemes 14.4.1.4 14-4
IEEE standards 6.4.13 6-15
Delayed auto-reclose scheme 14.9 14-9
knee-point voltage 6.4.4 6-9
Delta/star transformer overcurrent protection 16.6 16-6
line current 6.4.6.3 6-10
Delta-connected winding of a transformer 16.3, 16-4,
linear 6.4.6.3 6-10 16.7 16-7
DeltaP; rate of change of power (SIPS) 20.4.2.1 20-13
magnetisation curve 6.4.4 6-9
Design for maintenance of protection schemes 21.16 21-28
non Conventional 6.5 6-15
Determination of sequence currents 4.4 4-6
open circuit secondary voltage 6.4 6-7
Device numbers, list of ANSI Appendix B
optical Instrument transducer 6.5.1 6-15,
24-13 Differential protection:
optical sensor concept 6.5.1.1 6-16
digital systems 10.8 10-6
phase error 6.4.1.2 6-8
electromechanical systems 10.7 10-5
polarity check 21.9.3.1 21-19
for sectionalised and duplicate busbars 15.7.1 15-8
rated short-time current 6.4.9 6-12
numerical systems 10.8 10-6
ratio check 21.12.2 21-25
of busbars 15.7- 15-7
saturation 6.4.10 6-12 15.11 15-20
of direct connected generators 17.5 17-4
secondary current rating 6.4.8 6-11
of generator-transformers 17.6 17-6
secondary winding impedance 6.4.7 6-11
of parallel feeders 13.2.1 13-2
summation 6.4.5.4 6-10
of transformer feeders 10.12.2 10-15
supervision in numerical relays 7.6.2 7-8
static systems 10.7 10-5
test windings 6.4.12 6-15
using analogue techniques 10.10 10-8
tests 21.9.3, 21-19
21.12 21-24 using high impedance relays 10.5 10-3
transient response 6.4.10 6-12
using low impedance relays 10.4 10-2
Cyber security; principles of 24.3 24-11
using optical fibre signalling 10.8.1 10-6
I-4
Index
IEC61850-9.2 process bus 24.5.6 24-22 example setting calculation 11.12 11-20
Direct and quadrature axis values of machines 5.8, 5-7, fully cross-polarised mho 11.7.5 11-10
5.11 5-9
Direct under-reach scheme 12.3.1 12-3 implementation 11.8 11-13
amplitude and phase comparison 11.7.1 11-6 percentage under-reach 11.10.3 11-17
apparent impedance seen by 13.4.1 13-8 permissive over-reach transfer tripping 12.3.4 12-5
application example 11.12 11-20 permissive under-reach transfer tripping 12.3.2 12-3
application of multi-ended feeders 13.5 13-11 permissive under-reaching acceleration 12.3.3 12-4
application problems 11.10, 11-17, phase fault impedance measurement 11.9.1 11-15
13.4, 13-8,
14.8 14-8 plain feeders 11.6 11-4
behaviour with earth faults 13.2.2.3 13-2
plain impedance 11.7.2 11-6
behaviour with earth faults on parallel 13.2.2.4 13-4
power swing blocking 11.10.6 11-19
feeders
behaviour with single circuit operation 13.2.2.5 13-4 principles of 11.2 11-2
comparison of transfer trip and blocking 12.6 12-9 Schemes: 12.1- 12-1,
schemes 12.6 12-9
current reversal on double circuit lines 13.2.2.1 13-2 self polarised mho 11.7.3 11-7
direct under-reach transfer tripping 12.3.1 12-3 starters for switched distance protection 11.8.1 11-14
scheme
static types 11.3.1 11-2
directional comparison unblocking 12.5 12-8
switched distance protection relays 11.8.1 11-14
earth fault impedance measurement 11.9.2 11-15
transfer trip 12.3 12-3
effect of earthing method 11.9 11-15
under-reach 11.10.3 11-18
effect of source impedance 11.9 11-15
under-reach on parallel lines 13.2.2.2 13-2
electromechanical types 11.3.1 11-2
I-5 D
Protection & Automation Application Guide
using zone 1 element 12.4.1.2 12-8 Earthing, system, effect of on zero sequence quantities 4.6 4-13
using zone 2 element 12.4.1.1 12-7 Effect of load current, unit protection schemes 10.11.3 10-12
Distribution transformer earthing of generators 17.2, 17-2, voltage factor 6.2.2 6-3
17.8.2.2, 17-10 Effective setting of earth fault relays 9.16.1 9-15
Disturbance recorder 22.9 22-10
Effective setting of electromechanical earth fault relays 9.16.1.2 9-15
Disturbance recorder function in numerical relays 7.6.4 7-8
EIA232, EIA485 standards 24.2.2.1 24-4
DNP3; history 24.2.3.1 24-5
Electrical faults in stator windings 17.3, 17-3,
Double busbar substation, application of auto-reclose 14.12.1 14-12 19.6 19-6
Double circuit lines, current reversal on 13.2.2.1 13-2 Electrical type tests 21.2 21-2
Double frequency or broad band trap 8.5.3 8-5 Electromagnetic compatibility type tests 21.3 21-4
Downed conducer protection, high impedance 9.21 9-31 Electromagnetic voltage transformers:
DPWS (Device Profile for Web Services; applied to 24.3 24-11 cascade type 6.2.8 6-5
OSI model construction 6.2.5 6-3
Dual fed substations, earth fault protection in 18.7.2 18-8
errors in 6.2.1 6-2
Dual homing star topology 24.2.4.3 24-9
protection of 6.2.4 6-3
Dynamic validation type testing 21.7 21-14
residual connection of 6.2.6 6-4
Earth fault impedance measurement using distance 11.9.2 11-15
relays transient performance 6.2.7 6-4
I-6
Index
overhead lines 5.22 5-22 Fault current contribution from induction motors 18.8 18-10
synchronous generator 5.2- 5-1, Fault detection and dtarting, unit protection schemes 10.11.5 10-13
5.10 5-8
transformer 5.14- 5-10, Fault detector operating quantities, unit protection 10.11.9 10-14
5.15 5-11 schemes
voltage transformer 6.2 6-2 Ferro-resonance 6.3.3 6-6
in voltage transformers 6.2.1 6-2 Forward reach limitations of distance relays 11.10.5 11-18
Ethernet standards; IEEE 802.1D ring topology 24.2.4.2 24-8 Four-switch mesh substation, auto-reclosing applied 14.12.3 14-13
to
Ethernet standards; IEEE 802.1W ring topology 24.2.4.2 24-8
Four-wire dual-fed substations 18.7.2 18-8
(replaces 802.1D)
Ethernet standards; IEEE 802.3 24.2.2.1 24-4 Frame-earth protection (Howard protection):
Ethernet; LAN (Local Area Network) 24.2.4 24-7 check system 15.6.4 15-6
Ethernet; MAC (Media Addressing Control) 24.2.4 24-7 scheme for double bus station 15.6.3 15-6
Event recorder 22.9 22-9 single busbar 15.6.1 15-4
Example relay setting calculations:
with sectioned busbars 15.6.2 15-5
complex transmission circuits 13.7 13-13
Frequency degradation (SIPS) 20.2 20-3
distance 11.12 11-20
Frequency shift keyed signals, protection signalling 8.6.3 8-9
earth fault, overcurrent 9.20.2 9-27 using
Frequency variations ) power quality) 23.3.5 23-4
generator 17.22 17-27
FSK (Frequency Shift Keying); signalling 10.10.1 10-8
induction motor 19.14 19-12
Fully cross-polarised mho relay 11.7.5 11-10
industrial systems 18.12 18-15
Fundamental theory 3.1-3.7 3-1,
overcurrent 9.20 9-22 3-14
Fundamentals of protection practice 2.1-2.12 2-1
parallel feeders – distance 13.7.1 13-13
Fuses for use with distribution transformers 16.6.1 16-6
parallel feeders - overcurrent 9.20.3 9-27
Fusing factor 18.4.3 18-4
phase fault 9.20.1 9-23
Fuzzy logic multi criteria algorithms 20.4.1 20-13,
ring main 9.20.4 9-29
20-15
transformer 16.19 16-22 Fuzzy logic; definition of 20.4.2.3 20-16
I-7 D
Protection & Automation Application Guide
embedded generation 17.21 17-25 GPS; satellite architecture and antenna (SIPS) 20.3.6 20-10
examples of protection calculations 17.22 17-27 Grading margins for overcurrent relays:
failure of prime mover 17.19.1 17-24 earth fault relays 9.16.1 9-15
loss of excitation 17.16 17-18 sensitive earth fault relays 9.16.2 9-16
loss of utility supply 17.21.1 17-26 Grading of ring mains 9.15, 9-13,
9.20.4 9-29
loss of vacuum 17.19.3 17-24
negative phase sequence 17.12 17-13 Hardware architecture of numerical relays 7.5.1 7-5
negative sequence 5.9 5-8 Harmonic content of inrush waveform, transformer 16.3.1 16-5
neutral voltage displacement 17.8.1.3, 17-9, Harmonics (power quality) 23.3.4 23-4
17.8.2.4 17-11
Harmonics in current transformers 6.4.11 6-15
overcurrent protection 17.7 17-6
Heating of induction motor windings 19.3, 19-2,
overfluxing 17.14.1 17-15
19.7 19-9
overfrequency 17.14.2 17-16 High frequency disturbance test 21.3.4 21-5
rotor earth faults 17.15.1 17-16 High resistance earthing of generators 17.2 17-2
rotor shorted turn protection 17.15.3 17-17 on EHV systems 14.6- 14-6,
14.8 14-8
stator earth fault 17.8 17-8 on lines using distance relays 14.8 14-8
stator winding protection 17.4 17-4 High voltage capacitor of line coupling equipment 8.5.3 8-5
unbalanced loading 17.12 17-13 Hi-Z high impedance downed conducer protection 9.21 9-31
underfrequency 17.14.2 17-16 HMI (Human Machine Interface), definition of 25.2 25-1
undervoltage 17.10 17-12 Howard protection (frame-earth protection) 15.6 15-4
voltage controlled overcurrent 17.7.2.1 17-7 HRC fuse applications 16.6.1, 16-6,
18.4 18-3
voltage restrained overcurrent 17.7.2.2 17-7
HRC fuses 18.4 18-3
zero sequence 5.10 5-8
HSR (High-availability Seamless Redundancy) 24.2.4.6 24-10
Generator-transformer protection 17.6 17-6
Hubs, switches and routers; definition of 24.2.4.1 24-7
GOOSE (Generic Object Oriented Substation Events; 24.5.1, 24-18,
Hybrid transducer 6.5.1.2 6-16
IEC61850) 15.4 15-3
I-8
Index
IEEE 1588 time synchronisation standard (SIPS) 20.3, 20-4, capacitor control 18.11.1 18-12
20.3.6 20-10
co-ordination problems 18.7 18-8
IEEE 1686; standard for substation IED cyber security 24.3.2.2 24-15
discrimination 18.4.2 18-4
IEEE standards, as used in current transformer 6.4.13 6-15
discrimination in 18.3 18-2
Impact of power quality problems 23.3 23-3
effect of ambient temperature 18.4.4 18-4
Impedance notation 3.6 3-14
examples of protection 18.12 18-15
Impedances:
fault current contribution from induction 18.8 18-10
direct-axis 5.11 5-9
motors
negative sequence 5.9, 5-8, fuse characteristics 18.4.1 18-3
19.7 19-9
fusing factor 18.4.3 18-4
positive sequence 5.8, 5-7,
5.14, 5-9, HRC fuses: 18.4 18-3
5.17, 5-14,
19.7 19-10 motor power factor correction 18.11.2 18-13
quadrature axis 5.5, 5-3,
5.11 5-9 power factor correction 18.11 18-12
transformer 16.2 16-2
protection against overvoltage 18.10 18-11
zero sequence 5.10, 5-8,
protection against reverse phase sequence 18.10 18-11
5.15, 5-11,
5.17 5-14 protection against undervoltage 18.10 18-11
Implementation of distance relays 11.8 11-13
protection of cables by 18.4.3 18-4
Incorrect relay operation, reasons for 2.4 2-5
protection of capacitors 18.11.3 18-13
Indicating LEDs in protection schemes 2.10.2 2-10
protection of motors by 18.4.5 18-4
Indication or flags 2.10.2 2-10
Industrial circuit breakers 18.5 18-4
Induction motor characteristics 19.3- 19-2,
19.7 19-10 Industrial consumers, auto-reclosing requirements 14.4.1.2 14-4
Induction motor equivalent circuit 19.7 19-9
Initial commissioning tests 21.9 21-17
Induction motor protection:
Injection test equipment, secondary 21.10 21.21
bearing failures 19.1 19-1
Injection tests, primary 21.12 21-24
earth fault 19.6 19-6
Injection tests, secondary 21.11 21-23
I-9 D