Work Breakdown Structure
Work Breakdown Structure
Work Breakdown Structure
Structure
www.AssignmentPoint.com
www.AssignmentPoint.com
A work breakdown structure (WBS), in project management and systems
engineering, is a deliverable-oriented decomposition of a project into smaller
components. A work breakdown structure is a key project deliverable that
organizes the team's work into manageable sections. The Project Management
Body of Knowledge (PMBOK) defines the work breakdown structure as a
"deliverable oriented hierarchical decomposition of the work to be executed by
the project team."
Overview
The work breakdown structure provides a common framework for the natural
development of the overall planning and control of a contract and is the basis
for dividing work into definable increments from which the statement of work
www.AssignmentPoint.com
can be developed and technical, schedule, cost, and labor hour reporting can be
established.
The WBS is organized around the primary products of the project (or planned
outcomes) instead of the work needed to produce the products (planned
actions). Since the planned outcomes are the desired ends of the project, they
form a relatively stable set of categories in which the costs of the planned
actions needed to achieve them can be collected. A well-designed WBS makes
it easy to assign each project activity to one and only one terminal element of
the WBS. In addition to its function in cost accounting, the WBS also helps map
requirements from one level of system specification to another, for example a
requirements cross reference matrix mapping functional requirements to high
level or low level design documents.
The development of the WBS normally occurs at the start of a project and
precedes detailed project and task planning.
History
www.AssignmentPoint.com
The concept of work breakdown structure developed with the Program
Evaluation and Review Technique (PERT) by the United States Department of
Defense (DoD). PERT was introduced by the U.S. Navy in 1957 to support the
development of its Polaris missile program. While the term "work breakdown
structure" was not used, this first implementation of PERT did organize the
tasks into product-oriented categories.
By June 1962, DoD, NASA and the aerospace industry published a document
for the PERT/COST system which described the WBS approach. This guide
was endorsed by the Secretary of Defense for adoption by all services. In 1968,
the DoD issued "Work Breakdown Structures for Defense Materiel Items"
(MIL-STD-881), a military standard requiring the use of work breakdown
structures across the DoD.
The document has been revised several times, most recently in 2011. The
current version of this document can be found in "Work Breakdown Structures
for Defense Materiel Items" (MIL-STD-881C). It includes WBS definitions for
specific defense materiel commodity systems, and addresses WBS elements that
are common to all systems.
www.AssignmentPoint.com
Missile Systems WBS
www.AssignmentPoint.com
Design principles
100% rule
An important design principle for work breakdown structures is called the 100%
rule. It has been defined as follows:
The 100% rule states that the WBS includes 100% of the work defined by the
project scope and captures all deliverables – internal, external, interim – in
terms of the work to be completed, including project management. The 100%
rule is one of the most important principles guiding the development,
decomposition and evaluation of the WBS. The rule applies at all levels within
the hierarchy: the sum of the work at the “child” level must equal 100% of the
work represented by the “parent” and the WBS should not include any work
that falls outside the actual scope of the project, that is, it cannot include more
than 100% of the work… It is important to remember that the 100% rule also
applies to the activity level. The work represented by the activities in each work
package must add up to 100% of the work necessary to complete the work
package.
www.AssignmentPoint.com
WBS dictionary can help clarify the distinctions between WBS elements. The
WBS Dictionary describes each component of the WBS with milestones,
deliverables, activities, scope, and sometimes dates, resources, costs, quality.
Example
The figure on the left shows a work breakdown structure construction technique
that demonstrates the 100% rule and the "progressive elaboration" technique. At
www.AssignmentPoint.com
WBS Level 1 it shows 100 units of work as the total scope of a project to design
and build a custom bicycle. At WBS Level 2, the 100 units are divided into
seven elements. The number of units allocated to each element of work can be
based on effort or cost; it is not an estimate of task duration.
The three largest elements of WBS Level 2 are further subdivided at Level 3.
The two largest elements at Level 3 each represent only 17% of the total scope
of the project. These larger elements could be further subdivided using the
progressive elaboration technique described above.
Misconceptions
www.AssignmentPoint.com