Develop An AON Network For This Problem

This document contains information about the critical path and slack times for a project with activities A through G. The critical path is activities B and D with a total duration of 15 days. The total project completion time is 26 days. The slack times range from 0 days for activities on the critical path to 13 days for activity A.

Uploaded by

agus suar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
173 views2 pages

Develop An AON Network For This Problem

This document contains information about the critical path and slack times for a project with activities A through G. The critical path is activities B and D with a total duration of 15 days. The total project completion time is 26 days. The slack times range from 0 days for activities on the critical path to 13 days for activity A.

Uploaded by

agus suar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

1.

Develop an AON network for this problem


Answer:
2. What is the critical path?

Earliest Earliest Latest Latest On


Duratio Slack*
Activity Start Finish Start Finish Critical
n LS-ES
(ES) (EF)* (LS) (LF)* Path
A 2 0 2 13 15 13 NO
B 5 0 5 0 5 0 YES
C 1 0 1 11 12 11 NO
D 10 5 15 5 15 0 YES
E 3 15 18 15 18 0 YES
F 6 1 7 12 18 11 NO
G 8 18 26 18 26 0 YES

3. What is the total project completion time?


Answer:

IMMEDIATE TIME
Activity
PREDECESSOR (S) DAYS (S)
A -- 2
B -- 5
C -- 1
D B 10
E A, D 3
F C 6
G E, F 8
Total Project Completion Time 26

4. What is the slack time for each individual activity?

Earliest Earliest Latest Latest On


Duratio Slack*
Activity Start Finish Start Finish Critical
n LS-ES
(ES) (EF)* (LS) (LF)* Path
A 2 0 2 13 15 13 NO
B 5 0 5 0 5 0 YES
C 1 0 1 11 12 11 NO
D 10 5 15 5 15 0 YES
E 3 15 18 15 18 0 YES
F 6 1 7 12 18 11 NO
G 8 18 26 18 26 0 YES

*Note:
 EF = ES + Activity Time (Duration)
 LS = LF – Activity Time (Duration)
 Slack Time = LS -ES