120 Ton
4. LOADING SEQUENCE OF PILE STATIC LOAD TEST
The load shall be applied in increment of 25% of the working load up to 1.54 times working
load or failure. The procedure shall be carried out in two (2) cycles. The load increment and
time interval for holding of load is as follow:
(Pile Size: 200mm x 200mm RC Pile)
Particular Percentage Load (%) Load (Tons) Maintain (Hours)
0 0 0
25 19.5 1
( 1st Cycle ) 50 39 1
LOADING 75 58.5 1
100 78 8
75 58.5 1
50 39 1
UNLOADING 25 19.5 1
0 0 1
25 19.5 1
50 39 1
nd
( 2 Cycle ) 75 58.5 1
LOADING 100 78 1
125 97.5 1
150 117 1
154 120 24
150 117 1
125 97.5 1
100 78 1
UNLOADING 75 58.5 1
50 39 1
25 19.5 1
0 0 1
Total Hours 52 Hours
Notes:
i) Dial gauge reading to be taken every 15 minutes interval when maintained for one (1)
hour during loading and unloading. Reading at working load shall be taken at one (1)
hour interval except the reading for the first hour (to be taken every 15 minutes).
ii) Dial gauge reading to be taken 15 minutes interval. Reading at twice the working load
shall be taken at one (1) hour interval except the reading for the first hour (to be taken
every 15 minutes).
iii) If the rate of settlement exceeds 0.20mm/hr, the load shall be maintained for
additional 1 hour.
iv) Reading shall be recorded before and after applying load increment/decrement.
v) The result of the load test shall be recorded in three (3) plotting graph as follow:-
a) Load vs. Time
b) Settlement vs. Time
c) Settlement vs. Load
KSP TEST PILE (M) SDN. BHD. Method Statement
135 Ton
5. LOADING SEQUENCE OF PILE STATIC LOAD TEST
The load shall be applied in increment of 25% of the working load up to 1.5 times working
load or failure. The procedure shall be carried out in two (2) cycles. The load increment and
time interval for holding of load is as follow:
(Pile Size: 250mm x 250mm RC Pile)
Particular Percentage Load (%) Load (Tons) Maintain (Hours)
0 0 0
25 22.5 1
( 1st Cycle ) 50 45 1
LOADING 75 67.5 1
100 90 8
75 67.5 1
50 45 1
UNLOADING 25 22.5 1
0 0 1
25 22.5 1
50 27 1
nd
( 2 Cycle ) 75 54 1
LOADING 100 81 1
125 108 1
150 135 24
100 90 1
UNLOADING 50 45 1
0 0 1
Total Hours 48 Hours
Notes:
i) Dial gauge reading to be taken every 15 minutes interval when maintained
for one (1) hour during loading and unloading. Reading at working load
shall be taken at one (1) hour interval except the reading for the first hour
(to be taken every 15 minutes).
ii) Dial gauge reading to be taken 15 minutes interval. Reading at twice the
working load shall be taken at one (1) hour interval except the reading for
the first hour (to be taken every 15 minutes).
iii) If the rate of settlement exceeds 0.20mm/hr, the load shall be maintained
for additional 1 hour.
iv) Reading shall be recorded before and after applying load
increment/decrement.
v) The result of the load test shall be recorded in three (3) plotting graph as
follow:-
a) Load vs. Time
b) Settlement vs. Time
c) Settlement vs. Load
KSP TEST PILE (M) SDN. BHD. Method Statement
180 Ton
6. LOADING SEQUENCE OF PILE STATIC LOAD TEST
The load shall be applied in increment of 25% of the working load up to two (2) times
working load or failure. The procedure shall be carried out in two (2) cycles. The load
increment and time interval for holding of load is as follow:
(Pile Size: 250mm x 250mm RC Pile)
Particular Percentage Load (%) Load (Tons) Maintain (Hours)
0 0 0
25 22.5 1
( 1st Cycle ) 50 45 1
LOADING 75 67.5 1
100 90 8
75 67.5 1
50 45 1
UNLOADING 25 22.5 1
0 0 1
25 22.5 1
50 45 1
75 67.5 1
nd
( 2 Cycle ) 100 90 1
LOADING 125 112.5 1
150 135 1
175 157.5 1
200 180 24
150 135 1
100 90 1
UNLOADING 50 45 1
0 0 1
Total Hours 50 Hours
Notes:
i) Dial gauge reading to be taken every 15 minutes interval when maintained
for one (1) hour during loading and unloading. Reading at working load
shall be taken at one (1) hour interval except the reading for the first hour
(to be taken every 15 minutes).
ii) Dial gauge reading to be taken 15 minutes interval. Reading at twice the
working load shall be taken at one (1) hour interval except the reading for
the first hour (to be taken every 15 minutes).
iii) If the rate of settlement exceeds 0.20mm/hr, the load shall be maintained
for additional 1 hour.
iv) Reading shall be recorded before and after applying load
increment/decrement.
v) The result of the load test shall be recorded in three (3) plotting graph as
follow:-
a) Load vs. Time
b) Settlement vs. Time
c) Settlement vs. Load
KSP TEST PILE (M) SDN. BHD. Method Statement
300 Ton
7. LOADING SEQUENCE OF PILE STATIC LOAD TEST
The load shall be applied in increment of 25% of the working load up to two (2) times
working load or failure. The procedure shall be carried out in two (2) cycles. The load
increment and time interval for holding of load is as follow:
(Pile Size: 500mm Dia. Spun Pile)
Particular Percentage Load (%) Load (Tons) Maintain (Hours)
0 0 0
25 37.5 1
( 1st Cycle ) 50 75 1
LOADING 75 112.5 1
100 150 8
75 112.5 1
50 75 1
UNLOADING 25 37.5 1
0 0 1
25 37.5 1
50 75 1
75 112.5 1
nd
( 2 Cycle ) 100 150 1
LOADING 125 187.5 1
150 225 1
175 262.5 1
200 300 24
150 225 1
100 150 1
UNLOADING 50 75 1
0 0 1
Total Hours 50 Hours
Notes:
i) Dial gauge reading to be taken every 15 minutes interval when maintained
for one (1) hour during loading and unloading. Reading at working load
shall be taken at one (1) hour interval except the reading for the first hour
(to be taken every 15 minutes).
ii) Dial gauge reading to be taken 15 minutes interval. Reading at twice the
working load shall be taken at one (1) hour interval except the reading for
the first hour (to be taken every 15 minutes).
iii) If the rate of settlement exceeds 0.20mm/hr, the load shall be maintained
for additional 1 hour.
iv) Reading shall be recorded before and after applying load
increment/decrement.
v) The result of the load test shall be recorded in three (3) plotting graph as
follow:-
a) Load vs. Time
b) Settlement vs. Time
c) Settlement vs. Load
KSP TEST PILE (M) SDN. BHD. Method Statement
400 Ton
8. LOADING SEQUENCE OF PILE STATIC LOAD TEST
The load shall be applied in increment of 25% of the working load up to two (2) times
working load or failure. The procedure shall be carried out in two (2) cycles. The load
increment and time interval for holding of load is as follow:
(Pile Size: 600mm Dia. Spun Pile)
Particular Percentage Load (%) Load (Tons) Maintain (Hours)
0 0 0
st
( 1 Cycle ) 25 50 1
LOADING 50 100 1
75 150 1
100 200 8
75 150 1
50 100 1
UNLOADING 25 50 1
0 0 1
25 50 1
50 100 1
75 150 1
nd
( 2 Cycle ) 100 200 1
LOADING 125 250 1
150 300 1
175 350 1
200 400 24
150 300 1
100 200 1
UNLOADING 50 100 1
0 0 1
Total Hours 50 Hours
Notes:
i) Dial gauge reading to be taken every 15 minutes interval when maintained
for one (1) hour during loading and unloading. Reading at working load
shall be taken at one (1) hour interval except the reading for the first hour
(to be taken every 15 minutes).
ii) Dial gauge reading to be taken 15 minutes interval. Reading at twice the
working load shall be taken at one (1) hour interval except the reading for
the first hour (to be taken every 15 minutes).
iii) If the rate of settlement exceeds 0.20mm/hr, the load shall be maintained
for additional 1 hour.
iv) Reading shall be recorded before and after applying load
increment/decrement.
v) The result of the load test shall be recorded in three (3) plotting graph as
follow:-
a) Load vs. Time
b) Settlement vs. Time
c) Settlement vs. Load
KSP TEST PILE (M) SDN. BHD. Method Statement