Qatar General Petroleum Corporation Ngl-1 Operating Manual: Vol: 1 Sec.: 8 1
Qatar General Petroleum Corporation Ngl-1 Operating Manual: Vol: 1 Sec.: 8 1
Qatar General Petroleum Corporation Ngl-1 Operating Manual: Vol: 1 Sec.: 8 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 1
1. GENERAL
3. START-UP
4. SHUTDOWN
5. EMERGENCY SHUTDOWN
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 2
Reference Drawing:
1. GENERAL
H.P fuel gas at 22.5 barg flows from the H.P. fuel gas system to the Adip Treating Unit
and into V-1323, feed gas knockout drum.
The vessel has a level gauge glass 13-LG-28 and a high level alarm 13-LIAH-29, which
will sound in the control room.
The gas passes upwards through an inlet pipe distributor and exits through a ‘YORK
MAT’ demister pad. The gas passes from V-1323 to C-1305 Adip Gas Absorber.
The facility exits to bypass the absorber and join the gas outlet line from V-1317 Adip
Gas Separator.
The gas flows from V-1323 into C-1305 below tray 1 and as the gas flows upwards it is
met by a flow of lean Adip coming down through C-1305. The Adip solution removes any
H2S from the gas.
The treated gas leaves the top of C-1305 and flows to V-1317. The gas enters V-1317
through a fluted inlet distributor.
Liquid (Adip and H2O) is drained from V-1317 via 13-LC-24 to Adip drain system. A level
glass 13-LG-25 indicates level locally and 13-LAH-33 alarms on a high level.
The gas from V-1317 then passes through on electrically traced line at 30C, 22.0 barg
pressure and at a flow of 12088 kg/hr. There is a 2" sweet gas off take line to the Merox
Unit.
The gas then flows into one of the adsorbers where it is dried through the bed of
activated alumina A2-5 before it is used for regeneration of the propane and butane
molecular sieve adsorbers C-1307A/B and C-1308A/B.
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 3
The gas-drying unit consists of two adsorption towers, which allow continuous automatic
drying of the gas stream. While one tower is used for drying the gas, the desiccant in the
other is being regenerated.
Gas flows downwards through the towers while being dried and upward through the bed
during the regeneration cycle Regeneration is achieved by passing a slip stream of hot
dry gas through the desiccant, the regeneration gas is heated in the regeneration gas/hot
oil exchanger E-1330 A/B.
After regeneration and before use for a new drying cycle, the desiccant bed must be
cooled; this is achieved using the same slipstream of dry gas but bypassing E-1330 A/B.
Automatic operation of the gas drying unit is controlled by sequencing timers which
initiate operation of control valves as shown in the table T-1470848.
Manual, hand wheel operation is available in the event of a total electrical or pneumatic
failure.
Adsorption tower
Diameter 2' 6"
Length tan/tan 14' 6"
Design code BS-1515 Part 1
Corrosion allowance 1/8"
Design pressure barg 27.0
Design temperature °C 246.1
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 4
General
Working : Automatic
Operation : Continuous
Location : Outdoors, in a dusty,
saliferous and corrosive atmosphere.
Process Design
Medium : Natural gas
Capacity : 12088 kg/hr
Operation pressure : 23.0 barg
Inlet temperature : + 43°C max.
Water content : Saturated
Outlet water content : 80 p.p.m. Vol.
Outlet temperature : 50°C
Regeneration gas capacity : 1350 kg/hr
Mechanical Design
Design pressure : 27.6 barg
Design temperature : 260 °C
Design code vessels : BS 1515 Part 1 (and DEP 31.22.10.31)
Design code piping : ANSI-B 31.3
Cycle
Cycle time : 16 hours
Drying time per vessel : 8 hours
Regeneration time : 4 1/2 - 5 hours
Cooling time : 2 1/2 - 3 hours
Depressurising : 15 min.
Pressurising : 15 min.
Other Data
Electric supply : 110V-DC
Instrument air : 3.5 - 10 bar g
Instr. air capacity : approx. 1 Nm3/8h
In- and Outlet connection : ANSI 6"-300 lbs RF
Regeneration gas to and
from heat-exchanger : ANSI 3"-300 lbs RF
Outlet regeneration gas : ANSI 4"-300 lbs RF
Outlet safety relief valves : ANSI 1"-150 lbs RF
Dimensions LxW1H : 7800x2450x4850 mm
Weight : approx. 32000 kg
Desiccant type : Activated Alumina A2-5
Quantity each tower : 4000 kg.
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 5
Instrument Air
Grease
Approx. 50 kg multi purpose Lithium Base Grease a year for lubrication of the
stem of orbit valves and actuators
a) Introduction
The GDPA is a dryer of the range of adsorption type compressed gas dryers
with regeneration by heated gas, to remove moisture from a compressed gas
flow.
The desiccant used is selected according to the required duty. Every gram of
desiccant is so porous that it can reach a surface area of hundreds of square
meters.
b) General Description
Each tower has been provided with inlet and outlet diffusing pipes, galvanized
steel supporting grid with stainless steel sieve plate, desiccant sampling tube,
a temperature gauge, a desiccant drain and fill port, a manhole with davit, a
vent and drain nozzle and a skirt. The inlet diffusing pipe prevents direct gas
impingement on the desiccant beds and distributes equally the inlet gas flow
over the desiccant bed.
The towers have been mounted on a steel skid, with all interconnecting pipes
with valves etc.
The regeneration unit consists of a hot-oil heat exchanger, flow controller and
piping with valves.
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 8
The heat exchanger and flow controller will be delivered by JGC Corporation,
Yokohama.
The two pneumatic valves 13-XV-911 and 13-XV-912 are mounted for
depressurising the tower which will come in the regeneration cycle. Valve
V-13 is for adjusting the depressurising time.
The operation of the pneumatic operated valves will be done by dual solenoid
5/2 way valves. The signals for these solenoids will come from the control
room.
The two safety relief valves 13-RV-251 and 13-RV-252 are designed for no
flow condition. They are only for e.g. fire relief. The set pressure is 27.0 barg.
The moisture probe QI will be mounted on the outlet of the dried gas. With
little sample valves, a very small part of the dried gas can be bled-off for dew
point measurements to the flare system.
a) Drying
The wet gas enters the dryer and flows via valve 13-XV-901 into adsorber 1.
The desiccant retains the moisture from the gas and the dried gas leaves the
unit via valve 13-XV-903.
b) Regeneration
2. Heating
Now a part of the dried gas flows via valve 13-XV-913 to the regeneration
heater E-1301A/B. The heated gas flows via flow controller 13-FIC-351
and valve 13-XV-910 into adsorber 2 and desorbs the moisture that has
been adsorbed by the adsorbent during the previous drying period. The
moisture laden regeneration gas leaves the unit via valve
13-XV-906,13-PIC-20 to acid gas flare or fuel gas.
After a certain time the adsorber will be regenerated.
3. Cooling
After the heating period, the regenerated adsorber has to be cooled down.
For cooling purpose the valves 13-XV-914, 13-XV-915 and 13-XV-908
open.
The cooling gas flows via valves 13-XV-914, 13-XV-915 and V-20 into
adsorber 2 to cool down the desiccant. After a pre-adjusted time the
cooling stops by closing the valves 13-XV-914, 13-XV-915 and
13-XV-908.
4. Pressurising
Note:
The moisture analyser is not on line and presently the moisture is being
analysed by portable moisture analyser (by laboratory).
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 10
Before putting the gas dryer into operation, reactivate one of the desiccant beds
e.g. adsorber 1 as follows
The adsorber 2 is now just drying the regeneration flow and adsorber 1 will be
regenerated.
When the outlet temperature of the regeneration gas reaches the value of
13-TE-351, switch-off the heater and open the valves : 13-XV-905
13-XV-904
13-XV-913
and close the valves: 13-XV-907
13-XV-914
13-XV-915
After adsorber 1 is cooled-down, the dryer is ready to put into operation. Drying
cycle will start with adsorber 1.
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 15
The continued sound operation of the dryer depends on proper maintenance from
the beginning. Although the dryer practically needs no maintenance, the best
results will only be obtained if the maintenance and service instructions
mentioned in the maintenance schedule below are faithfully followed.
Maintenance Schedule
1. Lubricate all orbit valves if necessary and check the stem packing.
2. Check the solenoid valves. Check if the vent ports are not clogged. Clean
filters if necessary.
1. Check for chafed or damaged wires and for poor or loose connections.
5. Check orbit valves e.g. for leakage on the diaphragm of the actuator.
9. Check the adjustment of the humidity alarm on the outlet of the dryer.
10. Check the adjustments of the valves V-13 and V-27 for the depressurising
and pressurising time.
12. Check all pressure and temperature gauges for their proper operation.
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 16
14. Check temperature and pressure from the inlet of instrument air.
c) Once a year
Warning:
We will advise you after examination of the sample if the desiccant has to be
renewed or not.
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 17
In the event of the gas dryer failing to operate normally, the most likely possible
faults with their remedies are given in the chart hereafter.
Before starting any repair work on the dryer, make sure that the voltage has been
switched-off at the disconnect switch and / or mains supply board and that a
safeguard has been placed to prevent unintentional “switch on”.
The old on-line moisture analyser is redundant and not in use. Presently
moisture is being analysed by portable analyser.
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 20
a) Stop programmer.
b) Close HP gas to system.
c) Very slowly depressurise dryers to LP fuel gas or acid gas flare via 13-PIC-20.
d) Isolate hot oil system.
e) Isolate 13-XV-903, 13-XV-904, 13-XV-916, 13-XV-914 and 13-XV-913.
QATAR GENERAL PETROLEUM CORPORATION VOL : 1
SEC. : 8
NGL-1 OPERATING MANUAL PAGE : 23
REFERENCE DRAWINGS
VOLUME 1 SECTION 8