MANUAL OF PROCUREMENT
OF
GOODS/EQUIPMENT
in BW UNIT
1. PREAMBLE
1.1. Introduction
1.1.1. BSNL's aim is to procure the material of the specified quality, at the most
competitive rates, in a fair, just and transparent manner. Procurement is an
important activity in BSNL as about 50% of its budget is used for
procurement of materials. Consequent upon corporatization of Department
of Telecom Services & Department of Telecom Operations into a Corporate
Entity i.e. BSNL, a need has been felt to modify the existing procurement
procedure being followed by BSNL Corporate Office as well as by Telecom
Circles so as to cut down the procurement time in the present liberalized
telecom market. This is all the more necessary as BSNL is facing increasing
competition in all types of services and has to respond quickly for
procurement of materials as well as its utilization so as not only to keep its
market share in the emerging telecom scenario but also to expand and
acquire new market segments.
1.1.2. For Building Works/ Procurement of Services, BSNL BW unit has been
following CPWD Manual and other related documents/guidelines as issued
by BSNL from time to time. However the provisions of this Procurement
Manual are meant for procurement of goods only as outlined in Para 1.1.5
below.
1.1.3. In addition to above, there are items which are procured by BW Unit of BSNL
in course of execution of Building Works for BSNL and works (called external
works) of other government organizations/departments/entities. These items
are furniture and furnishing items, modular furniture/work
stations,Curtains,signage/name plates/logo, horticulture items like plants,
turf etc, tower material and part thereof, foundation stone /inauguration stone,
flower/bouquet, festoons, construction chemicals, anti-termite chemicals,
building materials for completion of balance work, computer & computer
peripherals, site equipment / tools etc..
1.1.4. This manual contains the detailed procedures, guidelines to be followed by
BSNL BW unit to ensure smoother and faster decision making. While the
Manual aims at providing broad procedures for procurement of goods, the
decision regarding the competent authority should be taken on the basis of
Schedule of Delegation of Administrative and Financial Powers issued by
Corporate Office. For purchase of goods by a purchase committee, wherever
applicable, the procedure shall be as defined in defined below.
1.1.5. With the formation of BSNL as a corporate entity in a Liberalized Telecom
Market where BSNL has to compete with a large number of competitors, it is
imperative for BSNL to serve in the competitive environment. For such a
scenario, it is essential not only to see the cost of materials being procured
but also the time required for its procurement as well as successful
1.8. E-Procurement
Procurement through e-procurement and e-tendering should be encouraged.
E-Tendering is the carrying out of the tendering process through the Internet,
using e-tendering software applications. This promotes competition for the
tender, and provides a process that is efficient for both the buyer and
suppliers and a selection process that is transparent to bidders. The process
results in a host of tangible and intangible benefits to both parties. The ERP
project is being implemented and this would provide a platform for e-
procurement in BSNL. Meanwhile a set of instructions in this regard has been
brought out in Section-4 part C under Chapter 4 of the Manual. It has been
decided to process the Procurement cases of amount of Rs Two lakhs and
above through e-tendering method.
***
BSNL Procurement Manual for BW Unit Page 7
CHAPTER – 2
(signature)
AGM ( )/ DGM ( )
User Section
2.8.2. Incomplete requisitions not containing above data will be returned forthwith.
2.8.3. This checklist duly filled in and approved by the concerned
PGM/GM/concerned head of User Unit should be signed by an officer not
lower than AGM and submitted along with the Requisition by concerned
User Section.
3. BID DOCUMENTS
3.2.2. A reading of the sections of the tender enquiry document, in the above order
will make it amply clear about the purpose and instructions behind the same.
However, some broad guidelines for using this document (viz. Standard
Tender Enquiry Document) are provided in the subsequent paragraphs.
3.3.2. The Detailed Notice Inviting Tender (DNIT) shall be put in the format at Para
3.3.1 above on the Website of BSNL i.e. website of respective Circle and
provide a link to e-tendering portal.
3.3.3. After issue of NIT, eligibility conditions should not be changed.
3.7.2 The approval of the competent authority must be taken for the text of the
Special Instructions to Bidders and Eligibility Conditions.
3.7.3 The guidelines for preparing section-4-B (SIB) along with corresponding
cross-reference with Section-4 A (GIB) provision is available in this section.
It is also indicated therein that the provisions in the Special Instructions to
Bidders and Eligibility Conditions (SIB) shall supersede the corresponding
provisions in the General Instructions to Bidders (GIB) in case of conflict.
3.7.4 Section-4-B (SIB) shall essentially have suitable clauses on the following:
3.9.4 Section-5-B may have clauses on the following items/ topics which may
complement/ supersede the corresponding clauses of Section-5 Part A
(GCC).The list is not exhaustive and actual clauses have to be framed on
case-to-case basis.
3.9.4.1 Delivery and Documents (refer GCC clause 6):
The delivery period will be decided on case-to-case basis considering
requirements of BSNL in the competitive environment. Early
BSNL Procurement Manual for BW Unit Page 16
deliveries may be accepted as per requirement of BSNL on case-to-
case basis.
In turnkey projects where Installation and Commissioning is to be
carried out by the supplier, the time-lines for such activities should
also be defined.
3.9.4.2 Incidental Services (refer GCC clause 8):
Requirement of such services will depend on the nature of the goods,
cost thereof etc. Some of the services will be needed along with the
goods and some may be needed separately (like maintenance service).
All such aspects are to be kept in view while formulating the requirement
of the incidental services.
3.9.4.3 Warranty(refer GCC clause 10):
For turnkey projects or high value procurements, the Warranty terms
may have to be elaborated keeping in view the actual project
requirements the date of commencement of the Warranty should be
clearly specified in the SCC.
Suitable Clause may be incorporated in the Special (Commercial)
Conditions of Contract, fixing reasonable timeframe to start warranty
of the goods/equipment after it has been put to use. This will be
treated as date of commissioning for the purpose of release of
payment and calculation of liquidated damages.
Note 2: The Tender document shall not be available for download on its submission
/ closing date.
4.1 The bidders shall submit necessary documentary proof showing that they
meet the eligibility criteria along with their tender bid. All documents submitted
will also be self-attested by the bidder.
5. Bid Security/EMD:
5.1 The bidder shall furnish the bid security/EMD in one of the following ways:-
(a) Demand Draft/ Banker’s cheque drawn in favour of ……………….…
(State Designation of concerned Accounts Officer) e.g. “AO (Cash),
BSNL, C.O. N. Delhi” and payable at ……………. (State the name of
the concerned payable City) e.g. “New Delhi” either separately for
each package or total for all no. of packages participated.
b) Bank Guarantee from a scheduled bank drawn in favour
of………………. (State Designation of concerned officer ) e.g. ‘DGM
(MMT), Bharat Sanchar Nigam Limited, Corporate Office, New Delhi
which should be valid for ……… days (i.e. one month beyondthe offer
validity period subject to maximum of 210 days) from the tender
opening date, separately for each package participated.
BSNL Procurement Manual for BW Unit Page 22
5.2 The MSE units shall be exempted from submission of Bid Security deposit on
production of requisite proof in respect of valid certification from MSME for the
tendered item.
Note 4: All documents submitted in the bid offer should be preferably in English. In
case the certificate viz. experience, registration etc. is issued in any other
language other than English, the bidder shall attach an English translation of
the same duly attested by the bidder & the translator to be true copy in
addition to the relevant certificate.
Note 5: All computer generated documents should be duly signed/ attested by the
bidder/ vendor organization.
5. Payment terms
6. Delivery Schedule
Note 7:-The period of delivery schedule to be specified by tender inviting
authority.
SECTION- 3 Part A
SCOPE OF WORK
A. General :
B. Scope of Work:
A. General :
1.0 DEFINITIONS
(a) "The Purchaser" means the Bharat Sanchar Nigam Ltd. (BSNL), New Delhi
(b) "The Bidder" means the individual or firm who participates in this tender
and submits its bid.
(c) "The Supplier" or “The Vendor” means the individual or firm supplying the
goods under the contract.
(d) "The Goods" means all the equipment, machinery, and/or other materials
which the Supplier is required to supply to the Purchaser under the contract.
(e) "The Advance Purchase Order" or “Letter of Intent” means the intention
of Purchaser to place the Purchase Order on the bidder.
(f) "The Purchase Order" means the order placed by the Purchaser on the
Supplier signed by the Purchaser including all attachments and appendices
thereto and all documents incorporated by reference therein. The purchase
order shall be deemed as "Contract" appearing in the document.
(g) "The Contract Price" means the price payable to the Supplier under the
purchase order for the full and proper performance of its contractual
obligations.
(j) “Successful Bidder(s)” means the bidder(s) to whom work in this tender is
awarded.
(k) “Item Rate Tender” is one wherein the bidder is required to quote rate of
each item of schedule of quantities (SOQ).
(l) “Percentage Rate Tender” is one wherein the bidder is required to quote a
percentage above/below the total estimated cost of work.
Note 1: Documents at S. No 10.1(e) and (i), are applicable in case of tenders with
estimated cost more than Rs 1 Crore.
Note:-The bidder shall mean individual company/ firm or the front bidder and its
technology partner, as applicable.
b) The envelope shall bear the name of the tender, the tender number and the
words 'DO NOT OPEN BEFORE' (due date & time).
c) The inner and outer envelopes shall indicate the name and complete postal
address of the bidder to enable the purchaser to return the bid unopened in
case it is declared to be received 'late'.
d) Tender should be deposited in the tender box provided by tendering authority
or sent by registered post or delivered in person on above mentioned
address (address is given in Clause 15.2 (a) above). The responsibility for
ensuring that the tenders are delivered in time would vest with the bidder.
e) Bids delivered in person on the day of tender opening shall be delivered upto
specified time & date as stated in NIT to Authority inviting the tenders at the
venue {address is given in clause 15.2 (a) above)}. The purchaser shall not
be responsible if the bids are delivered elsewhere.
f) Venue of Tender Opening:
The venue of tender opening is as under:
(Address of Venue)
15.3 If both the envelopes are not sealed and marked as required at para 15.1
and 15.2, the bid shall be rejected.
19.4 The date fixed for opening of bids, if subsequently declared as holiday by the
BSNL, the revised date of schedule will be notified. However, in absence of
such notification, the bids will be opened on next working day, time and
venue remaining unaltered.
21.4Prior to the detailed evaluation pursuant to clause 22, the Purchaser will
determine the substantial responsiveness of each bid to the Bid Document.
For purposes of these clauses, a substantially responsive bid is one which
confirms to all the terms and conditions of the Bid Documents without
material deviations. The purchaser's determination of bid's responsiveness
shall be based on the contents of the bid itself without recourse to extrinsic
evidence.
21.5 A bid, determined as substantially non-responsive will be rejected by the
purchaser and shall not, subsequent to the bid opening, be allowed to be
made responsive by the bidder by correction of the non-conformity.
21.6 The Purchaser may waive any minor infirmity or non-conformity or
irregularity in a bid which doesn't constitute a material deviation, provided
such waiver doesn't prejudice or affect the relative ranking of any bidder.
22.1 The Purchaser shall evaluate in detail and compare the bids previously
determined to be substantially responsive pursuant to clause 21.
22.2 The evaluation and comparison of responsive bids shall be done on the basis
of Net cost to BSNL. The net cost to BSNL will be determined on case to
case basis taking into account applicability of Input Tax Credit or otherwise.
23.2 Any effort by a bidder to modify its bid or influence the purchaser in the
purchaser's bid evaluation, bid comparison or contract award decision shall
result in the rejection of the bid.
24.1. The Purchaser shall consider placement of orders for commercial supplies
only on those eligible bidders whose offers have been found technically,
commercially and financially acceptable and whose goods have been type
approved/ validated by the purchaser.
27.2 The bidder shall within 14 days of issue of the advance purchase order, give
its acceptance along with performance security in conformity with the
proforma provided with the bid document at Section-7B.
30.3 Bid opening Authority will not return the bids submitted by the bidders on the
date of tender opening even if it is liable for rejection and will preserve the
bids in sealed cover as submitted by taking the signatures of some of the
desirous representatives of the participating bidder/companies present on
the occasion.
Note – This clause shall be deleted if not applicable for the tender.
1. Eligibility Conditions
Eligibility conditions for each tender shall be framed on case-to-case basis
and shall be got approved from the tender approving authority.
Some hints on framing of eligibility conditions are given below:
They should have successfully executed satisfactorily completed works of
any central / state government department, PSU or any other government
organization of following magnitude as under.
1. (Details to be inserted)”
The proof of having completed such works shall form part of the bid.
2. Bid Security
The bank guarantee/DD for bid security or Micro & Small Enterprise (MSE)
registration certificate for claiming exemption from submission of bid security,
as prescribed in clauses 12.1 & 12.2 of Section-4 A of the bid document
should be submitted by the bidder in a separate cover. The bank
guarantee/DD so submitted shall be as per the format given in Section-7 A
on prescribed judicial paper with stamps of proper value and should contain
full address of the issuing branch of the bank with its telephone number and
FAX number.
2. Eligible Bidders
(a) The bidder should have experience of undertaking similar contracts with
Govt. / Semi Govt./PSUs/Corporates/Autonomous bodies/Big reputed
company registered under companies Act,1956.
(b) The bidder should produce copy of valid Registration of establishment/firm
with Labor Act.
(c) The bidder shall furnish Annual Report/a current solvency certificate from its
bankers as evidence that he has financial capability to perform the contract.
(d) The bidder shall produce valid GST (Goods & Services Tax) Registration
certificate.
(e) The bidder should have PAN allotted to him by IT Department (Copy to be
enclosed).
(f) EPF registration no. if applicable/declaration regarding payment of minimum
wages to manpower engaged as per labour law.
3. Cost of bidding:
The bidder shall bear all costs associated with the preparation and
submission of the bid. BSNL, in no case shall be responsible for these costs
regardless of the conduct or outcome of the bidding process.
4.7 Then the Digital Signature Certificate ( Class III Certificates with signing key
usage) issued by e Mudra or any Certifying Authority recognized by CCA India on
eToken / Smart Card, should be registered.
4.8 The DSC that is registered only should be used by the bidder and should ensure
safety of the same.
4.9 Bidder may go through the tenders published on the site and download the
required tender documents for the tenders he/she is interested in.
4.14 Bidder, in advance, should get ready the bid documents to be submitted as
indicated in the tender document and generally, they can be in
PDF/xls/rar/zip/dwf formats. If there is more than one document, they can be
clubbed together and can be provided in the requested format. Each
document to be uploaded through online for the tenders should be less than
2 MB. If any document is more than 2MB, it can be reduced through zip/rar
and the same can be uploaded, if permitted. Bidders Bid documents may be
scanned with 100 dpi with black and white option. However, if the file size is
less than 1 MB the transaction uploading time will be very fast.
4.15 If there are any clarifications, this may be obtained through the site, or during the
pre-bid meeting, if any. Bidder should take into account the corrigendum published
from time to time before submitting the online bids.
4.16 The Bidders can update well in advance, the documents such as certificates,
annual report details etc., under “Document Library” option and these can be
selected as per tender requirements and then send along with bid documents
during bid submission. This will facilitate the bid submission process faster by
reducing upload time of bids.
4.17 Cost of Bid Document (non-refundable) and EMD:
(a) Bidder should submit the cost of bid documents in the form of a Crossed
Demand Draft of Rs --- (Rs. ----) (non refundable) drawn on any Scheduled
Bank in {name of city) in favour of ………………..………(state designation of
concerned Accounts Officer) e.g. “AO(Cash), BSNL, C.O. N. Delhi” and
payable at ………….………….…. (state the name of the concerned payable
City/ Station) e.g. “New Delhi”.
(b) The EMD for an amount of Rs.……………………. should be in the form of a
Crossed Demand draft drawn in favour of ………………..………(state
designation of concerned Accounts Officer) e.g. “AO(Cash), BSNL, C.O. N.
Delhi” and payable at ………….………….…. (state the name of the concerned
payable City/ Station) e.g. “New Delhi”./ Bank Guarantee valid for 180 days
from the date of tender opening as per format of “Bid Security Form” at Section
VII.
(c) The cost of bid document and the EMD in original in the form of DD/Bank
Guarantee along with all eligibility documents mentioned in Clause 10 of Section 4
Part – A should be posted/couriered/given in person to “EE, , BSNL , ---- .”. The
envelope with due mention of Name of work, due date & time of opening of bids,
name of the bidder should be submitted within the bid submission due date & time
BSNL Procurement Manual for BW Unit Page 48
for the tender. Scanned self attested copies of the same should also be uploaded
online as part of the offer as per the NIT conditions. The bidder should ensure that
all the above reach before the last date and time of submission of bid as mentioned
in the NIT. BSNL will not be responsible for any late delivery by courier/postal
services and the bid will be summarily rejected, if they are not received before due
date and time of opening of the tender.
4.20 The details of the Cash Receipt/ DD/BC, physically sent, should tally with the
details available in the scanned copy and the data entered during bid
submission time.
5. Bid Document:
5.1 Bid Document includes: a. Notice Inviting e-Tender
b. Instructions to bidders
c. General condition (Commercial) of the contract
d. Special condition of contract, if any
e. Schedule of quantities
f. Bid form and price schedule.
g. Performance Security bond Form
h. Letter of authorization to attend Bid opening
5.2 The Bidder is requested to examine all instructions, forms, terms and
specification in bid documents. Failure to furnish all the information required as
per bid documents and submission of the bids not substantially responsive to the
Bid documents in every respect, will be at the bidder’s risk and may result in
rejection of the bid.
5.3 A prospective bidder, requiring any clarification of the Bid Documents shall
notify the Purchaser online. The Purchaser shall respond online to any request for
clarification of the Bid Documents in given specific Date & Time and clarification
by the Purchaser shall be sent to the prospective bidder online.
8. Bid Price:
8.1 The bidder shall give the total composite rate inclusive of all levies & taxes
including GST in the Price Schedule. Rate should be quoted for all the items
otherwise the bid will be rejected summarily
8.2 The rate quoted by the bidder shall remain fixed during the entire period of
contract and shall not be subject to variation on any account. A bid submitted
with an adjustable price quotation will be treated as non- responsive and rejected.
9.1 Bidder should submit the EMD in offline. The Demand draft/Bank Guarantee
should be prepared as per the amount mentioned in NIT in favour of
…………..………(state designation of concerned Accounts Officer) e.g. “AO(Cash),
BSNL, C.O. N. Delhi” and payable at ………….………….…. (state the name of the
concerned payable City/ Station) e.g. “New Delhi”.. The original should be
posted/couriered/given in person to “EE, BSNL, ”, within the bid submission due
date & time for the tender. Scanned copy should be uploaded as part of the offer.
The bidder should ensure that the demand draft/bank Guarantee reach before the
last date and time of submission as mentioned in the NIT. BSNL will not be
responsible for any late delivery by courier/postal services and the bid will be
summarily rejected, if the cost of bid document and EMD are not received before
due date and time of opening of the tender.
9.2 The successful bidder’s bid security will be discharged upon the bidders
acceptance of the award of contract satisfactorily and furnishing the performance
security.
a. If bidder withdraws his bid during the period of bid validity specified by the
bidder in the bid form.
Bidders shall note that the very act of using DSC for downloading the tender
document and uploading the same along with their offers is deemed to be a
confirmation that they have read all sections and pages of the tender document
without any exception and have understood the complete tender document and are
clear about the requirements of the tender document
11. Submission of Bid:
11.1 Bidder should log into the site www.tenderwizard.com well in advance for bid
submission so that he/she upload the bid in time i.e. on or before the bid submission
date and time.
11.2 Bidder should prepare and submit the cost of bid documents and EMD as per
the instructions given in bid document. The details of the relevant instrument
physically sent, should tally with the details available in the scanned copy and the
BSNL Procurement Manual for BW Unit Page 51
data entered during bid submission time, otherwise the uploaded bid will be
rejected.
11.3 While submitting the bids online, the bidder shall read the terms & conditions
and accepts the same in order to proceed further to submit their bid.
11.4 Bidder shall select the payment option as offline to pay the cost of bid
document and EMD and enter details of the relevant instrument.
11.5 Bidder shall digitally sign and upload the required bid documents one by one
as indicated in the tender document.
11.6 Bidders shall note that the very act of using DSC for downloading the tender
document and uploading their offers is deemed to be a confirmation that they have
read all sections and pages of the tender document without any exception and have
understood the complete tender document and are clear about the requirements of
the tender document.
11.7 Bidders shall submit their bids through online e-tendering system well before
the bid submission end date &time (as per Server System Clock). BSNL will not be
held responsible for any sort of delay or the difficulties faced during the submission
of bids online by the bidders at the last moment.
11.8 After the final bid submission in the e-tender portal, the bidders shall take print
out of system generated acknowledgement number, and keep it as a record of
evidence for online submission of bid, which will also act as an entry pass to
participate in the bid opening.
11.9 Bidder should follow the server time being displayed on bidder’s dash board
at the top of the tender site, which shall be considered valid for all actions of
requesting, bid submission, bid opening etc., in the e-tender system.
12.1Bid opening committee will open the bids online in the presence of bidders or
their authorized representatives who chose to attend on opening date and time.
12.2The bidder’s representatives, who are present, shall sign in an attendance
register. Authority letter to this effect shall be submitted by the bidders before they
are allowed to participate in bid opening (format is given in section IX).
12.3The date fixed for opening of bids, if subsequently declared as holiday by the
Govt., the revised date of schedule will be notified. However, in absence of such
notification, the bids will be opened in the next working day, time and venue
remaining unaltered.
14.1Bid Evaluation will be done in two stages i.e. Technical Bid Evaluation and
Financial Bid Evaluation.
14.2The “Technical bid” of only those bidders shall be opened who have submitted
the cost of bid document and the EMD within stipulated date and time as per NIT
conditions. The “Technical Bid” will be evaluated first. Those bidders who are found
to be technically qualified, their financial bid only will be opened at later date. The
date & time of opening of "Financial bid" shall be conveyed to all the bidders who
have qualified in technical bid and their representative shall be allowed to attend
the financial bid opening.
14.3BSNL shall evaluate the bids to determine whether they are complete, whether
any computational errors have been made whether documents have been properly
signed and whether bids are generally in order.
14.4 If there is a discrepancy between words and figures the amount in words shall
prevail. Prior to detailed evaluation, BSNL will determine the substantial
responsiveness of each bid to the bid document. A substantially responsive bid is
one, which conforms to all the terms and conditions of bid documents without
material deviation. A bid determined as substantially non responsive will be rejected
by BSNL.
14.5BSNL shall evaluate in detail and compare the substantially responsive bids
and comparison of bids shall be on the price offered inclusive of all levies and
charges as indicated in the price schedule. The lowest bidder will be decided on the
value of “Grand Total” as mentioned in the Price Schedule.
14.6The accepting authority may cross verify the documents submitted by bidder
with the issuing authority, in case of any need.
15.3The BSNL may award the tender to more than one supplier at the rates quoted
by the lowest tenderer for each of the category.
16.1 BSNL reserves the right at the time of award of contract to increase or
decrease up to 25% of the required quantity of items specified in the schedule
of requirements without any change in unit price of the ordered quantity or
other terms and conditions.
The Purchaser reserves the right to accept or reject any bid and to annul the bidding
process and reject all bids, at any time prior to award of contract without assigning
any reason whatsoever and without thereby incurring any liability to the affected
bidder or bidders on the grounds for the Purchaser’s action.
18. Signing of Contract
18.1 Signing of Agreement shall constitute the award of contract on the bidder.
18.2 Upon the successful bidder furnishing the performance security, the BSNL
shall discharge its bid security.
19. Annulment of Award
Failure of the successful bidder to comply with the requirement of clause 17 shall
constitute sufficient ground for the annulment of the award and forfeiture of the bid
security in which event BSNL may make the award to any other bidder at the
discretion of BSNL or call for new bids.
(ii) A bidder accepting the request of BSNL for an extension to the period of bid
validity, in exceptional circumstances, will not be permitted to modify his bid.
Otherwise submitted bid will not be acceptable and summarily rejected.
4.21 The bidder has to digitally sign and upload the required eligibility & tender
documents one by one as indicated. Bidders should note that the very act of using
DSC for downloading the bids and uploading their offers shall be deemed to be a
confirmation that they have read all sections and pages of the bid document
including General conditions of contract without any exception and have understood
the entire document and are clear about the requirements of the tender
requirements.
4.22 The following Form of bid document should be filled up, signed with seal,
scanned and uploaded in the e- tender website by bidder: i. Bid Form (Section-IX
Part-A)
ii. Certificate of non-participation by family members of BSNL employees (Section-
VI)
4.23 If the price bid format is provided in a excel file, the rates offered should be
entered in the allotted space only and uploaded after filling the relevant columns.
The Price Bid template must not be modified/replaced by the bidder, else the bid
submitted is liable to be rejected for this tender.
4.24 The bidders are requested to submit the bids through online e-tendering
system well before the bid submission end date & time (as per Server System
Clock). BSNL will not be held responsible for any sort of delay or the difficulties
faced during the submission of bids online by the bidders at the eleventh hour.
4.27 The bidder should logout of the tendering system using the normal logout
option and not by selecting the (X) exit option in the browser.
4.28 For any queries regarding e-tendering process, the bidders are requested to
contact / email as provided in the tender document.
1. APPLICATION
The general condition shall apply in contracts made by the purchaser for the
procurement of goods/equipment.
2. STANDARDS
The goods/equipment supplied under this contract shall conform to the
standards prescribed in the Technical Specifications mentioned in section -
3.
3. PATENT RIGHTS
The supplier shall indemnify the purchaser against all third-party claims of
infringement of patent, trademark or industrial design rights arising from use
of the goods or any part thereof.
4. PERFORMANCE SECURITY
4.1 All suppliers (including MSEs who are registered with the designated MSME
bodies, like National Small Scale Industries Corporation etc. Shall furnish
performance security to the purchaser for an amount equal to 5% of the value
of Advance purchase order within 14 days from the date of issue of Advance
Purchase Order by the Purchaser.
4.2 The proceeds of the performance security shall be payable to the Purchaser
as compensation for any loss resulting from the supplier's failure to complete
its obligations under the contract.
4.3 The performance security Bond shall be in the form of Bank Guarantee
issued by a scheduled Bank and in the proforma provided in Section 7 B of
this Bid Document.
4.4 The performance security Bond will be discharged by the Purchaser after
completion of the supplier's performance obligations including any warranty
obligations under the contract.
8. INCIDENTAL SERVICES
The supplier may be required to provide any or all of the following services:
(a) Performance or supervision of on-site assembly and/or start-up of the
supplied Goods;
(b) Furnishing of tools required for assembly and/or maintenance of
supplied Goods;
(c ) Performance of supervision or maintenance and/or repair of the
supplied Goods, for a period of time agreed by the parties provided
that this service shall not relieve the supplier of any warranty
obligations under this contract.
9. WARRANTY
9.1 The supplier shall warrant that the stores to be supplied shall be new and
free from all defects and faults in materials used, workmanship and
manufacture and shall be of the highest grade and consistent with the
established and generally accepted standards for materials of the type
ordered and shall perform in full conformity with the specifications and
BSNL Procurement Manual for BW Unit Page 57
drawings. The supplier shall be responsible for any defect that may develop
under the conditions provided by the contract and under proper use, arising
from faulty material, design or workmanship such as corrosion of the
equipment, inadequate quantity of material to meet equipment requirements,
inadequate contact protection, etc and shall remedy such defects at its own
cost when called upon to do so by the Purchaser who shall state in writing
in what respect the stores are faulty. This warranty shall survive inspection
or payment for/ and acceptance of goods, but shall expire (except in respect
of complaints notified prior to such date) twelve months after the stores have
been taken over under clause 5.5 above.
9.2 If it becomes necessary for the Supplier to replace or renew any defective
portion(s) of the equipment under this clause, the provisions of the clause
10.1 shall apply to the portion(s) of the equipment so replaced or renewed
or until the end of the above mentioned period of twelve months, whichever
may be later. If any defect is not remedied by the supplier within a reasonable
time, the Purchaser may proceed to get the defects remedied from other
supplier etc., at the supplier's risk and expenses, but without prejudice to any
other rights which the purchaser may have against the supplier in respect of
such defects.
9.3 Replacement under warranty clause shall be made by the supplier free of all
charges at site including freight, insurance and other incidental charges.
10.2The balance payment, if any, shall be released as per specified timelines from
the date of supply of the equipment/goods in case there are no
damage/shortages. In those cases where such shortages/damages are
intimated to the supplier in writing, the balance payment shall be released
only after the cases are settled in accordance with the provision of the P.O.
Note: The actual payment conditions for new products or procurements having
installation and AMC services may be decided on case to case basis and
incorporated in special conditions of the contract.”
10.3. A certificate stating that the tendered items (stores) are meant for the use of
11. PRICES
11.1 Prices charged by the supplier for goods delivered and services performed
under the contract shall not be higher than the prices quoted by the Supplier
in its Bid except for variation caused by change in taxes/ duties as specified
in Clause-11.2 mentioned below.
11.2 For changes in taxes/ duties during the scheduled delivery period, the unit
price shall be regulated as under:
(a) Prices will be fixed at the time of issue of purchase order as per taxes
and statutory taxes/duties applicable at that time
(b) In case of reduction of statutory taxes and other duties during the
scheduled delivery period, purchaser shall take the benefit of
decrease in these taxes/ duties for the supplies made from the date
of enactment of revised duties/taxes.
(c) In case of increase in statutory duties/taxes during the scheduled
delivery period, the purchaser shall revise the prices as per new
duties/ taxes for the supplies, to be made during the remaining
delivery period as per terms and conditions of the purchase order.
11.3 Any increase in taxes and other statutory duties/ levies, after the expiry of
the delivery date shall be to the supplier's account. However, benefit of any
decrease in these taxes/duties shall be passed on to the Purchaser by the
supplier. The total price is to be adjusted (by reducing the basic price) with
increased duties and taxes as per price mentioned in PO
12.3.1The time for completion of the work shall, in the event of any deviations
resulting in additional cost over the tendered value, be extended if requested
by the contractor, as follows:
ii) 25% of the time calculated in (i) above or such further additional time as
may be considered reasonable by the competent authority.
12.4 In the case of extra items(s) (items that are completely new, and are in
addition to the items contained in the contract), the contractor may, within
15days of receipt of the order or occurrence of the item(s) claim
rates ,supported by proper analysis, for the work and the Engineer-In-Charge
shall within one month of the receipt of the claim supported by analysis,after
giving consideration to the analysis of the rates submitted by the contractor,
determine the rate on the basis of market rate(s). In the event of the
contractor failing to inform, the Engineer-In-Charge within stipulated period
of time, the rate, which he proposes to claim, the rate for such items shall be
determined by the Engineer-In-charge on the basis of market
rate(s)prevailing during that period. In case of substituted items (items that
12.4.1 If the market rate for the substitution item so determined is more than
the market rate of the agreement item (to be substituted) the rate payable to
the contractor for the substituted item shall be the rate for the agreement
item (to be substituted) so increased to the extent of the difference between
the market rate of the substituted item and the agreement item (to be
substituted).
12.4.2If the market rate for the substituted item so determined is less than
the market rate of the agreement item (to be substituted), the rate payable
to the contractor for the substituted item shall be the rate for the agreement
item (to be substituted) so decreased to the extent of the difference between
the market rates of the substituted item and the agreement item (to be
substituted).
(2) The number of the arbitrators and the appointing authority will be as under:
5. Parties agree that neither party shall be entitled for any pre-reference or
pendente-lite interest on its claims. Parties agree that any claim for such interest
made by any party shall be void.
(2) The parties to the arbitration agreement, while agreeing for resolution of dispute
by fast track procedure, may agree that the arbitral tribunal shall consist of a sole
arbitrator who shall be chosen by the parties.
(3) The arbitral tribunal shall follow the following procedure while conducting
arbitration proceedings under sub-section (1):-
(a) The arbitral tribunal shall decide the dispute on the basis of
written pleadings, documents and submissions filed by the
parties without oral hearing;
(b) The arbitral tribunal shall have power to call for any further
information or clarification from the parties in addition to the
pleadings and documents filed by them;
(c) An oral hearing may be held only, if, all the parties make a
request or if the arbitral tribunal considers it necessary to have
oral hearing for clarifying certain issues;
(d) The arbitral tribunal may dispense with any technical
formalities, if an oral hearing is held, and adopt such procedure
as deemed appropriate for expeditious disposal of the case.
(4) The award under this section shall be made within a period of six months from
the date the arbitral tribunal enters upon the reference.
(5) If the award is not made within the period specified in sub-section (4), the
provisions of sub- sections (3) to (9) of Section 29 A shall apply to the
proceedings.
7. The arbitral tribunal shall make and publish the award within time stipulated as
under:
Amount of Claims and Counter Claims Period for making and publishing of the
award (counted from the date the
arbitral tribunal enters upon the
reference)
Up to Rs. 5 crores Within 6 months (Fast Track procedure)
However, the above time limit can be extended by the Arbitrator for reasons to be
recorded in writing with the consent of parties and in terms of provisions of the Act.
In case of sole arbitrator, BSNL shall make all necessary arrangements for his
travel/stay and the expenses incurred shall be shared equally by the parties.
22. FALL CLAUSE (This clause shall be applicable for works with stipulated
period of completion exceeding 12 months)
22.1 The prices once fixed will remain valid during the scheduled delivery period
except for the provisions in clause 12.1 of Section-5A. Further, if at any time
during the contract
(a) It comes to the notice of purchaser regarding reduction of price for the
same or similar equipment/ service;
And / or
(b) The prices received in a new tender for the same or similar
equipment/service are less than the prices chargeable under the contract.
22.2 The purchaser, for the purpose of delivery period extension, if any, will
determine and intimate the new price, taking into account various related
aspects such as quantity, geographical location etc., and the date of its effect
for the balance quantity/ service to the vendor. In case the vendor does not
accept the new price to be made applicable during the extended delivery
period and the date of its effect, the purchaser shall have the right to
terminate the contract without accepting any further supplies. This
termination of the contract shall be at the risk and responsibility of the
supplier and the purchaser reserves the right to purchase the balance
unsupplied quantity/ service at the risk and cost of the defaulting vendor
besides considering the forfeiture of its performance security.
22.3 The vendor while applying for extension of time for delivery of
equipment/services, if any, shall have to provide an undertaking as "We have
not reduced the sale price, and/ or offered to sell the same or similar
equipment/ service to any person/ organization including Department of
central/state Government or any central/ state PSU at a price lower than the
price chargeable under the contract for scheduled delivery period."
22.4 In case under taking as in Clause 22.3 is not applicable, the vendor will give
the details of prices, the name(s) of purchaser, quantity etc. to the purchaser,
while applying extension of delivery period.
Note: The clauses mentioned below are for reference only. Exact clauses should
be framed as per requirement on case-to-case basis.
***
6(A) - For understanding the terms & condition of Tender & Spec. of work
a) Certified that:
2. If I/ We fail to enter into the agreement & commence the work in time,
the EMD/ SD deposited by us will stand forfeited to the BSNL.
Date:
Signature of Tenderer
PROFORMAS
5. We the Bank further agree with the EE that the EE shall have the fullest liberty
without our consent and without affecting in any manner our obligations
hereunder to vary any of the terms and conditions of the said Agreement or to
extend time of performance by the said bidder(s) from time to time or to
postpone for any time or from time to time any of the powers exercisable by
the EE against the said bidder(s) and to forbear or enforce any of the terms
and conditions relating to the said agreement and we shall not be relieved
from our liability by reason of any such variation, or extension being granted
to the said Bidder(s) or for any forbearance, act or omission on the part of the
EE or any indulgence by the EE to the said bidder(s) or by any such matter or
thing whatsoever which under the law relating to sureties would, but for this
provision, have effect of so relieving us.
7. In case EE demands for any money under this bank guarantee, the same
shall be paid through banker’s Cheque in favour of “…………(insert details
of appropriate authority)
8. The Bank guarantees that the below mentioned officer who have signed it
on behalf of the Bank have authority to give this guarantee under its
delegated power.
Place: ……………………………
2. We, “the Bank” do hereby undertake and assure to the EE that if in the
opinion of the EE, the Bidder has in any way failed to observe or perform the
terms and conditions of the said agreement or has committed any breach of
its obligations there-under, the Bank shall on demand and without any
objection or demur pay to the EE the said sum limited to P.G. Amount or
such lesser amount as EE may demand without requiring EE to have
recourse to any legal remedy that may be available to it to compel the Bank
to pay the same.
3. Any such demand from the EE shall be conclusive as regards the liability of
Bidder to pay to EE or as regards the amount payable by the Bank under
this guarantee. The Bank shall not be entitled to withhold payment on the
ground that the Bidder had disputed its liability to pay or has disputed the
quantum of the amount or that any arbitration proceeding or legal proceeding
is pending between Bidder and EE regarding the claim.
4. We, the Bank further agree that the guarantee shall come into force from the
date of its issue and shall remain in full force and effect up to its Validity date.
Place: ……………………………
Note 1: Only one representative will be permitted to attend the Bid opening
2. Permission for entry to the hall where bids are opened may be refused in
case authorization as prescribed above is not received.
Sub: This office contract no………….. dated …………. placed on you for supply
of …………………………………………………………………….
Yours faithfully,
(………………………)
For and on behalf of………..
Note: The entries which are not applicable for the case under consideration are to
be deleted.
Sub :This office contract no………….. dated …………. placed on you for supply
of ………………
Ref : 1. Your letter no……………………………… dated ……………….
requesting DP extension
2. This office letter no. ……………… dated ……… intimating conditions for
DP extension
3. Your letter no………………….. dated …………. accepting the conditions
for DP extension
In your above letter under reference (1), you have asked for extension/ further
extension of time for delivery/ execution/ installation/ commissioning. The terms and
conditions for extension of delivery period were conveyed to you vide this office
letter under reference (2).
In view of the circumstances stated in your above referred letter, and upon your
unconditional acceptance of the terms and conditions of this extension vide your
letter under reference (3), the time of delivery is hereby extended from _______
(last delivery period) to ____________ (presently agreed delivery period) on the
terms and conditions in letter under reference (2) above and agreed by you vide
letter under reference (3) i.e.:
(a) Liquidated damages maybe levied in accordance with agreed checked ok
clause 15.2 & 15.3 Section-5 Part A of terms and conditions of the tender/
PO.
(b) Notwithstanding any stipulation in the contract for increase in price on any
The letters under reference above and this letter shall form part and parcel of
agreement/ contract/ APO/ PO and all other terms & conditions of the contract
remain unaltered.
Yours faithfully,
(………………………)
for and on behalf of………..
Copy to :
…………………..
…………………..
…………………..
(All concerned)
Note:- The entries which are not applicable for the case under consideration are to
be deleted.
BID FORM
To From,
…………………………………………. ……………………………………….
<Complete address of the purchaser><complete address of the Bidder>
…………………………………………. …………………………………………
……………………………………… …………………………………………
Signature ………………………….
Witness Name ……………………………..
Signature…………………………. In the capacity of ………………………….
Name …………………………….. Duly authorized to sign the bid for and on
Address ...................................... behalf of ..............................................
S.No Item description Total Rate inclusive of GST Rate exclusive of GST Total amount Total amount
Quantity & all taxes & all taxes inclusive of GST & exclusive of GST
(A) (B)
all taxes & all taxes
(C) (D) (E)
(C X D) (C X E)
Declaration
1.“We hereby declare that in quoting the above prices, we have taken into account all charges and all applicable taxes.
5.1 Purpose
The Bid Bond Guarantee also known as Earnest Money Deposit (EMD) or
Earnest Money Bank Guarantee (EMBG).The purpose of EMD is to get a
commitment by the Bidder to honour its bid during the bid validity period.
5.2 Value
The value of EMD will be @ 2% of the total estimated cost of the equipment/
stores including services proposed to be procured in the tender subject to a
maximum of Rupees Two Crore.
Encashme
Extension
Extended
Returned
asked for
Resorted
Bidder
to the
Number
Of
***
BSNL Procurement Manual for BW Unit Page 90
CHAPTER - 6
6 OPENING OF BIDS
6.3 Venue
The Bid Opening would preferablybe conducted in office of Executive
Engineer/Sub Divisional Engineer concerned, which can accommodate
***
SCRUTINY OF TENDERS
(signature)
EE (C)/ SDE (C)
9.1 Purpose
Performance Bank Guarantees are obtained from suppliers to ensure
performance of the contract as specified in the purchase order including
warranty for satisfactory working of the equipment and stores during the
warranty period. This also serves to cover the risk of the BSNL during the
performance of the contract.
9.6.2 It should be ensured that the Bank Guarantee is not allowed to expire
in any circumstances.
10.1 Purpose
The purpose of the Advance Purchase Order (APO) is to formally intimate
the successful bidder/bidders of the intention of the BSNL to procure the
equipment.
10.2 Contents
The APO shall contain the following information:
a) File number, date and reference of Tender Enquiry No. and submitted
bid reference No.,etc.
b) Equipment / goods to be procured with quantities/price.
c) Technical Specifications
d) Commercial conditions governing the contract.
e) Finance aspects such as advance payable (if any), amount of
Performance Bank Guarantee along with format of the Bank
Guarantee.
f) Delivery Schedule.
g) Period within which the Bidder has to confirm acceptance to the APO
along with the performance bank guarantee.
h) Annexures comprising Sections-3 Part B , 5 Part A, 5 Part B of the bid
document, AMC draft, scope of work, detailed bill of material, make-
model list, etc
10.3 Format
Format of an APO is given below for ready reference.
Dear Sir,
2 Quantity
………..
3. Prices
The supply shall be governed at unit prices on all inclusive basis i.e. Excise
Duty, Sales Tax, packing, freight, forwarding, insurance etc but excluding
octroi/entry tax which shall be paid extra as per actuals, wherever applicable.
The price shall further be governed in accordance with clause No.12 and 24
of Section-III of Bid-document. The detailed prices are given below:
4. Delivery Period
4.1 ………………….
(The detailed month wise-supply schedule shall be mentioned)
(installation commissioning period, if any shall be mentioned).
4. 2 The equipment / goods supplied will be strictly in accordance with the
specifications laid down by the BSNL. The supply shall be made only after
Engineer-in-charge has carried out necessary inspection/testing and
approved the equipment/goods for supply to BSNL.
5. Payment terms
5.1 The payment schedule will be as under (The payment schedule shall be
mentioned):
5.2 The payment shall be made in Indian Rupees
6. Warranty
The warranty of the equipment / goods will be for 12 months period starting
from the date of the completion of supply/works. The supplier will provide
support service during this warranty through its factory facilities or its
8. Fall Clause:
13. BSNL reserves the right to cancel Purchase Order if the agreed delivery
schedule is not adhered to by the supplier. Any loss arising out of such
delays in the supply of the equipment shall be on the supplier account.
15. This APO & PO/Contract is subject to jurisdiction of Court at …….. only.
Yours faithfully
Enclosures:-
Copy to :
1. PCE (C) / CE (C)
2. SE (C)
3. SDE (Civil) concerned
4. Office copy.
***
PURCHASE ORDER
11.1Conditions for issue
The issue of Purchase Order in any procurement is subsequent to the
following conditions being met:
a) The Tender is approved by the competent authority.
b) The purchase proposal being approved and concurred by the
competent administrative authority and finance advice.
c) The successful bidder/bidders accepting the Letter of Intent/Advance
Purchase order containing all the commercial clauses and prices
unconditionally.
d) The successful bidders providing the required Bank Guarantee from
the Nationalized/ Scheduled Bank.
e) The Purchase Order shall be issued on firm prices only.
f) Any other condition required to be met.
File No.__________________
Dated__________
PO NO……………………………………..
______________________________________________________________
1 Name & :
Address of
Contractor
3 Purchaser’s I T.E.No……………………………………………
reference
Ii BSNL APO No…………………………………..
4 Contractor’s i Your acceptance to above APO vide your letter
reference ii No. …………..
iii
5 Scope of the :
PO
6 Consignee :
Details,
Paying
Authority etc.
7 Delivery 7.1 The total delivery period for supply of …………… equipment
Schedule shall be …………..from the date of placement of Advance
Purchase Order. The first …………..months shall be for
validation and lead time for preparation. The supplies shall be
BSNL Procurement Manual for BW Unit Page 107
evenly distributed month-wise and circle-wise as given
below:- (The delivery schedule will be mentioned)
7.2 If the supplier fails to complete the supply during the original
delivery period, the purchaser reserves the right to cancel the
Purchase Order & take action according to the terms &
conditions of the tender.
8 Performance : M/s……….has accepted the APO unconditionally/
Bank unequivocally & has furnished performance bank guarantee
Guarantee for an amount of Rs………….. vide BG
No. ……….dated ……… by………….. and this PBG is valid
upto …………...
19 Quantity and
Price
The detailed prices are given below:
13 Installation :
&Commissioning
14 Repair Center : If mandated as per contract provisions, the supplier shall have
to establish nodal repair centers in India for undertaking repair
of faulty goods/equipment.The turnaround time for such
repairs shall be maximum 21 days The supplier shall clearly
intimate the site for such repairs in advance.
15
15 Training :
16 Documentation :
18 Warranty :
19.2 The entire supply shall also be governed as per all terms &
conditions as laid down in the bid document of the tender
enquiry and as modified from time to time. Any
amendment/clarification/modification issued /to be issued
shall also be applicable for this supply. However, wherever
there is a conflict, special conditions as given in section IV of
bid document and conditions given in this Purchase Order will
prevail over the general conditions given in section 4 part A
in the bid document.
***
***
***
Yours faithfully,
(P.K. Kanchan)
Technical Examiner
Yours faithfully,
(P.K. Kanchan)
Technical Examiner
For Chief Technical Examiner
SatarktaBhawan, Block-A,
GPO Complex, INA
New Delhi- 110023
Dated the 3rd March, 2007
Circular No. 4/3/07
Sub:- Tendering process - negotiations with L-1.
Reference is invited to the Commission’s circulars of even number, dated
25.10.2005 and 3.10.2006. on the above cited subject. In supersession of
the instructions contained therein, the following consolidated instructions
are issued with immediate effect:—
(i) As post tender negotiations could often be a source of corruption, it is
directed that there should be no post-tender negotiations with L-1,
except in certain exceptional situations. Such exceptional situations
would include, procurement of proprietary items, items with limited
sources of supply and items where there is suspicion of a cartel
formation. The justification and details of such negotiations should be
duly recorded and documented without any loss of time.
(ii) In cases where a decision is taken to go for re-tendering due to the
unreasonableness of the quoted rates, but the requirements are
urgent and a re-tender for the entire requirement would delay the
availability of the item thus jeopardizing the essential operations,
maintenance and safety, negotiations would be permitted with L-1
bidder(s) for the supply of a bare minimum quantity. The balance
quantity should, however, be procured expeditiously through a re-
tender, following the normal tendering process.
(iii) Negotiations should not be allowed to be misused as a tool for
bargaining with L-1 with dubious intentions or lead to delays in
decision-making. Convincing reasons must be recorded by the
authority recommending negotiations. Competent authority should
exercise due diligence while accepting a tender or ordering
negotiations or calling for a re-tender and a definite time frame should
be indicated so that the time taken for according requisite approvals
for the entire process of award of tenders does not exceed one month
from the date of submission of recommendations. In cases where the
proposal is to be approved at higher levels, a maximum of 15 days
should be assigned for clearance at each level. In no case should the
(VineetMathur)
Deputy Secretary
All Chief Vigilance Officers
13.12 Staggering of tenders
(Letter No. 3-1/2003-MMT Dated 25.06.2003)
In pursuance of the efforts being made to bring total transparency in
tendering/procurement activity at all levels. I have been directed to
communicate the decision of the BSNL Corporate office that tenders for the
same item should be staggered in such a manner that next tender is opened
after the expiry of the scheduled delivery period of the first tender.
13.13 Evaluation Criteria in tenders
(Letter No. 3-2/2007-MMT Dated 16.11.2010)
A letter has been received from Central Vigilance Commission (CVC), New
Delhi regarding the evaluation criteria of the tender. The case has been
examined and I am directed to state that the tender process should be open
and transparent. The evaluation criteria for all future tenders should be
15.1 As all concerned are aware that the BSNL being an artificial juristic
person/ legal entity, does its business through the Directors/ below Board
level Executives/ Officers, who exercise the powers vested in the company
through appropriate delegation of powers made by the Board of Directors, in
accordance with Company’s Memorandum of Association and Articles of
Association and the Indian Companies Act and other applicable Government
instructions/ guidelines issued from time to time.
15.2 . While strict adherence to the stipulations of each such contract is a pre-
requisite, there are occasions, where deviations also take place. The
respective Officer-in-charge of the Contract working under branch head
(Nodal Officer), in whose jurisdiction a particular Agreement/ Understanding
etc. falls, is expected to monitor the progress of implementation of the
particular Agreement/ Understanding etc. to avoid a situation where BSNL
stands to lose its strength in getting the best performance from any such
contract.
15.9.0 If a banning order has been issued then the appeal against banning order
shall lie with the next higher authority
15.10. Maintenance of Up-to-date List:
Database in respect of all banned vendors, either banned by tender inviting /
approving authority (TIA) in the SSA, Circle or pan India basis, shall be
available on BSNL intranet portal.
15.10.1Tender inviting authority while issuing orders for banning of business (and/
or its revocation) shall endorse a copy to BW Unit BSNL C.O. which will be
responsible for updating/ maintaining the upto date list of banned vendors
along-with the period and area of banning on BSNL intranet portal.
*****
5. In the case the vendor does not reply/ respond to the notice, then the tender
approving authority will take necessary action to issue Business banning /
barring order. [Business banning/ barring order may be drafted using sample
draft enclosed at Draft at Annexure-1C (ii).
Note 1:- In case of other defaults listed in Appendix-1, Section 4A Chapter 4,
tender approving authority will take action in similar way as per above listed
procedure.
Note 2:- The above penalties will be imposed provided it does not clash with the
To,
M/s………………….
………………………
………………………
No……………………………………………………………. Dated…………………….
Yours sincerely,
Signature ……………
Name …………………….
Designation: SDE (C) / EE
(C)…………
Copy to: - 2) O/c.
No……………………………………………………………. Dated…………………….
NOTICE
We are in receipt of your above referred letter explaining the reasons for deficiency
noted in DD submitted by you towards EMD and/ or tender fee against our tender
No………………………………………opened on……………..
We find that the reasons furnished by you in your reply for submission of fake /
forged DD are not acceptable.
It will be relevant to mention that submission of fake / forged DD indicates that you
are not a trustable firm & invites penalty of banning of business dealing with your
firm.
You are hereby given a notice to submit your written reply indicating any further
reason/ justification for submission of fake/ forged DD.
Your reply should reach the undersigned within 7 days of receipt of this letter or 15
days from the date of issue of this letter, failing which we will be constrained to
initiate action for banning of business dealing with your firm.
Yours sincerely,
Signature ……………
Name …………………….
Designation: SDE (C) / EE
(C) …………
Copy to: - 2) O/c.
No……………………………………………………………. Dated…………………….
NOTICE
Kindly refer to our above mentioned letter wherein we had asked you to
explain your conduct on the deficiency noted by us in you offer/ bid.
We have not received any reply from you which implies that you accept the
error intimated to you and you have nothing to submit /say on the matter.
Submission of fake /forged DD as EMD and or tender fee is a grave default
from a responsible firm and invites serious penalties like banning of business
dealing.
You are hereby given a notice to submit your written reply indicating any
further reason/ justification for submission of fake /forged DD.
Your reply should reach the undersigned within 7 days of receipt of this
letter or 15 days from the issue of this letter, failing which we will be constrained to
initiate action for banning of business dealing with your firm.
Yours sincerely,
Signature ……………
Name …………………….
Designation: SDE (C) / EE
(C) …………
Copy to: - 2) O/c.
No…………………………………………………………. Dated…………………….
We are in receipt of your reply vide above mentioned letter in response to our
Notice intimating deficiency in EMD and/ or tender fee received from you.
We find that the reasons/ justifications furnished by you in your reply for
submission of fake / forged DD are not acceptable and warrant necessary action
as per policy of BSNL.
I am directed to intimate that the competent authority has found the deficiency
to be serious and thereby decided to ban business dealings with your firm for a
period of three years which will be effective from……………….(date) which may
please be noted.
Yours sincerely,
Signature ……………
Name ……………………
Designation: SDE (C) / EE
(C) ………..
Copy to: - 2) O/c.
3) PCE (C) / CE (C).
To,
M/s………………….
No……………………………………………………………. Dated…………………….
Kindly refer to our above mentioned Notice wherein we had asked you to
submit your written reply indicating reason/ justification on the deficiency intimated
to you in your offer/ bid.
We have not received any reply from you against our notice under reference
which implies that you accept the default committed by you and you have nothing
to say/ submit further.
I am directed to intimate that the competent authority has found the deficiency
to be serious and thereby decided to ban business dealings with your firm for a
period of three years which will be effective from……………….(date) which may
please be noted.
Yours sincerely,
Signature ……………
Name ……………………
Designation: SDE (C) / EE
(C) …………
Copy to: - 2) O/c.
3) PCE (C) / CE (C)
Note 1:- However, in this case the performance guarantee if alright will not
be forfeited.
Note 2:- Payment for already received supplies/ completed work shall be
made as per terms & conditions of PO/ WO.
5.1 The supplied equipment /goods i) If the material is not at all acceptable,
do not perform satisfactory in the then return the non-acceptable
field in accordance with the material (or its part) & recover its cost,
specifications mentioned in the if paid, from the o/s bills/ PG/ SD.
PO/ WO/Contract. OR
ii) If the material is acceptable with
degraded performance, the purchaser
may determine the price for degraded
equipment/goods (Financial penalty =
Price – price determined for degraded
equipment / goods) himself and/ or
through a committee.
Undertake recovery of financial penalty
from outstanding dues of vendor
including PG/ SD.
Note 8:-In case of clash between these guidelines & provision of invited tender,
the provision in the respective tender shall prevail over these guidelines.
Note 9:Banning of Business dealing order shall not have any effect on the
existing/ ongoing works which will continue along with settlement of Bills.
*****