Practice Exam: Activities E, D and I Are Concluding Activities
Practice Exam: Activities E, D and I Are Concluding Activities
Practice Exam: Activities E, D and I Are Concluding Activities
INDEX NUMBER
A project network analysis is to be carried out using the data provided below.
A 2 Start activity
B 5 C
C 1 A
D 3 C
E 7 B, F, G
F 2 C
G 9 A
H 5 F
I 7 H
1
Question (1): Develop the Network Diagram for the project in the space below
2
Question (2)
(2a) Compute the Earliest Start Time, Latest Start Time, Earliest Finish Time, Latest Finish Time,
and Total Float for each activity and record your answers in the spaces provided below.
Question (2c): Which activities can the project manager not afford to delay?