Study of Tehri Dam Civil Structures & Estimation of R/Wall Under Planning and Monitoring Department, Thdcil
Study of Tehri Dam Civil Structures & Estimation of R/Wall Under Planning and Monitoring Department, Thdcil
Study of Tehri Dam Civil Structures & Estimation of R/Wall Under Planning and Monitoring Department, Thdcil
REPORT
ON
SUBMITTED BY:
Aayushi Negi,
140970107001
Civil Engineering, THDC-IHET
Page | 1
ABSTRACT
Period of training:
Page | 2
ACKNOWLEDGEMENT
Page | 3
CONTENTS
INTRODUCTION
SPILLWAYS
CHUTE SPILLWAY
SHAFT SPILLWAY
ILO
POWER HOUSE
HRT
PENSTOCK
BUTTERFLY VALVE
TURBINE
GENERATOR
TRT
Page | 4
INTRODUCTION
HISTORICAL BACKGROUND
Page | 5
purpose. Construction on the Tehri Dam was complete in 2006 while
the second part of the project, the Koteshwar Dam, remains ongoing.
TECHNICAL DESCRIPTION
The dam is a 260 meters (850 ft) high rock and earth- fill
embankment dam. Its length is 575 meters (1886 ft), crest width 20
meters (66 ft), and base width 1128 meters (3701 ft). The dam
creates a reservoir of 2.6 cubic kilometres (2,100,000 acre.ft) with a
surface area of 52 square kilometres (20 sq mi.). The installed hydro
capacity is 1000 MW along with an additional 1000 MW of Pumped
Storage hydroelectricity.
Page | 6
which also includes the 400 MW Koteshwar Dam downstream. The
Complex will afford irrigation to an area of 270,000 hectares( 670,000
acres), irrigation stabilization to an area of 600,000
hectares( 1,500,000 acres) and a supply of 270 million gallons of
drinking water per day to the industrialized areas of Delhi, Uttar
Pradesh and Uttarakhand.
SPECIFICATIONS
A.RESERVOIR
B. DAM
Page | 7
D. GALLERIES (Underground)
PROJECT COST:
PROJECT BENEFITS
1. IGNEOUS ROCKS:
2. SEDIMENTARY ROCKS:
3. METAMORPHIC ROCKS:
Page | 11
TEHRI HYDRO DEVELOPMENT CORPORATION LIMITED
RIP-RAP
RIP-RAP INSPECTION
U/S GALLERY
FINE
D/S
FILTER
COARSE
SHELL FILTER
SHELL EL. 632.0 M
COFFER DAM
Page | 12
SPILLWAYS
1. CHUTE SPILLWAY:
Page | 13
The Chute spillway has been provided to negotiate gross head of
about 220m and the velocities generated are of the order of 55m/s at
the end of glacis. Aerators have been conferred to provide an air
cushion under the water flowing over the concrete surface of chute
so as to save the surface from cavitations’ damage.
Specification:
Page | 14
2. SHAFT SPILLWAY:
Apart from the chute spillway four vertical shaft spillways have been
provided. Negotiating a head of about 220m through vertical shaft
spillway has been done for the first time for such a big head.
The right bank vertical shaft spillway have been joined with existing
diversion tunnels T-3 and T-4 eccentrically through a narrow section
including swirling motion to the flow for energy dissipation in shaft to
avoid extensive erosion damage from the water fall.
In the left bank shaft spillway the junction of vertical shafts with the
horizontal tunnel, the air accompanied the flow in vertical shaft, is
forced to be located in a central core by way of centrifugal force. This
air core is the pressurised air zone from where air is taken out to the
atmosphere through de-aeration tunnel.
Specification:
Crest Level : EL 830.2m
Type : Ungated
No. of Shafts :2
Diameter of the Shaft : 12m
Height of Shaft : 225m
Design Discharge : 1900 cumecs each
Specification:
Crest Level : EL 815m
Type : Radial Gate and Stop-log Gate
No. of Shafts :2
Diameter of the Shaft : 12m
Height of Shaft : 203m
Type of hoist- Radial : Rope drum hoist
Specification:
Crest Level : EL 700m
Type : Radial Gated and Emergency Gate
Size : 4.5m×6m
Length : 276m
Weight :100 MT
Type of hoist- Radial : Hydraulic hoist
Emergency : Hydraulic hoist
Design Discharge : For regulation
Page | 16
Power House
Penstock:
Page | 17
There are 04 Numbers of penstocks attached with butterfly valve.
Water enters through the different penstocks to the different
generating units. Each penstock comprises upper horizontal, vertical
& lower horizontal reach including upper & lower bend. The diameter
of penstock is 5.75 m.
Butterfly Valve:
One Butterfly Valve installed at mouth of the each penstock. The
valve remains
close in case of Unit Shutdown. When the unit is started then after
sensing the
starting command, valve opens first to build-up pressure in spiral
casing and supply the water to the penstock.
Turbine:
It is vertical Francis type turbine having net head of 188 m and rated
output of 255 MW at a discharge of 150cum/ sec at a rated speed of
214.3 rpm. Water from the spiral casing enters through the 28 guide
vanes and strikes the 14 blades of therunner, which is coupled to the
main shaft. The shaft is coupled to the rotor of the generator at the
other end. The opening of guide vanes depends upon the generation
requirement. Water after striking the blades of the runner, fall axially
in the draft tube. For keeping shaft vertically, Turbine guide bearing is
installed which is of rotating sump self cooled type. Runner removal
from the bottom of the unit is possible through the runner removal
gallery.
Page | 18
This figure illustrates the specification of Installed turbines and diagram of
francis turbine.
Generator:
It is 278 MVA, 0.9 pf, 50HZ, 3 Phase generator which generates
power at a voltage of 15.75 KV. A generator has two parts, Stator and
Rotor. Power generated is transmitted through isolated phase bus
duct to transformer gallery from where it is stepped up to 400 KV by
GSU transformers. Two bearings named as Thrust bearing and upper
guide bear ing are installed for sustaining the outward thrust of rotor
and keeping shaft verticality. Both the bearings are of water cooled
type. It has 10% overload capacity for short duration. Carbon dust
collection system has been installed which works during application
of brakes.
.
Transformer Gallery :
Page | 19
4 in numbers, 306 MVA, 15.75/ 400KV GSU 3 Phase transformers are
installed in transformer gallery (TG) for the four units. 15.75 KV is
generated from the each unit and this power is stepped up to 400 KV
here and sent to switchyard through oil filled cables. These
generating transformers are provided with makeup valve which is
filled with water that cools the oil that is being used to cool the
transformer. These transformers are also equipped with micro wave
detector which detects the microwave that generated incase of some
spark and raises the alarm.
There are TRT-1, TRT-2 for the 4 Units. The dia. of the TRT is 9.0 m
and the lengths of TRTs are 748 m & 862 m. Tail race tunnels basically
carry the water from the draft of Hydro Power plant (HPP) to the
main stream river.
Page | 20
This figure illustrates the general layout of the Tehri Hydro project and Pump
storage plant.
Page | 21
This figure shows the cross section of PSP through water way.
Planning
Planning is the process of thinking about and organizing the activities
required to achieve a desired goal. It involves the creation and
maintenance of a plan, such as psychological aspects that require
Page | 22
conceptual skills. There are even a couple of tests to measure
someone’s capability of planning well. As such, planning is a
fundamental property of intelligent behaviour.
Also, planning has a specific process and is necessary for multiple
occupations (particularly in fields such as management, business,
etc.). In each field there are different types of plans that help
companies achieve efficiency and effectiveness. An important, albeit
often ignored aspect of planning, is the relationship it holds
to forecasting. Forecasting can be described as predicting what the
future will look like, whereas planning predicts what the future
should look like for multiple scenarios. Planning combines forecasting
with preparation of scenarios and how to react to them. Planning is
one of the most important project management and time
management techniques. Planning is preparing a sequence of action
steps to achieve some specific goal. If a person does it effectively, he
can reduce much the necessary time and effort of achieving the goal.
A plan is like a map. When following a plan, he can always see how
much he has progressed towards his project goal and how far he is
from his destination.
Planning process
Three-step result-oriented process for planning:
3. Arranges or creates the means required.
4. Implements, directs, and monitors all steps in their proper
sequence.
In organizations, planning is a management process, concerned with
defining goals for company's future direction and determining on the
missions and resources to achieve those targets. To meet the goals,
managers may develop plans such as a business plan or a marketing
plan. Planning always has a purpose. The purpose may be
achievement of certain goals or targets.
Main characteristics of planning in organizations are:
Page | 23
Planning increases the efficiency of an organization. It reduces the
risks involved in modern business activities. It utilizes with maximum
efficiency the available time and resources. The concept of planning
is to identify what the organization wants to do by using the four
questions which are : -
1. Where are we today in terms of our business or strategy
planning?
2. Where are we going?
3. Where do we want to go?
4. How are we going to get there?
Monitoring
Monitoring is the regular observation and recording of activities
taking place in a project or programme. It is a process of routinely
gathering information on all aspects of the project.
To monitor is to check on how project activities are progressing. It is
observation; ─ systematic and purposeful observation.
Monitoring also involves giving feedback about the progress of the
project to the donors, implementers and beneficiaries of the project.
Page | 24
Reporting enables the gathered information to be used in making
decisions for improving project performance.
Purpose of Monitoring:
Monitoring is very important in project planning and implementation.
It is like watching where you are going while riding a bicycle; you can
adjust as you go along and ensure that you are on the right track.
Monitoring provides information that will be useful in:
Analysing the situation in the community and its project;
Determining whether the inputs in the project are well utilized;
Identifying problems facing the community or project and finding
solutions;
Ensuring all activities are carried out properly by the right people and
in time;
Using lessons from one project experience on to another; and
Determining whether the way the project was planned is the most
appropriate way of solving the problem at hand.
ESTIMATE FOR
CONSTRUCTION 0F
RETAINING WALL
(At Bpuram Township)
Page | 25
TOTAL AMOUNT OF WORK=Rs. 311085
PREPARED BY:
Aayushi Negi
Page | 26