Design and Construction of Offshore Concrete Structures: February 2017
Design and Construction of Offshore Concrete Structures: February 2017
Design and Construction of Offshore Concrete Structures: February 2017
February 2017
Guidance Note
NI 594 DT R00 E
NI 594
Design and Construction of
Offshore Concrete Structures
SECTION 1 GENERAL
February 2017
Section 1 General
1 General 3
1.1 Application
1.2 Referenced documents
2 Definitions 4
2.1 Offshore concrete structure
2.2 Concrete terms
3 Documents to be submitted 4
3.1 General
3.2 Documents and drawings
3.3 Material certificates
4 Design 5
4.1 General
SECTION 1 GENERAL
Standard Comments
ISO 19900 Petroleum and natural gas industries - General requirements General requirements applicable for offshore floaters
for offshore structures
ISO 19903 Petroleum and natural gas industries - Concrete offshore A large part of requirements are adopted for the pur-
structures pose of the present Guidance Note: materials, loads,
concrete works
EN 1992-1-1 Eurocode 2: Design of concrete structures - Part 1-1: General Structural checks and materials
rules and rules for buildings
American Concrete Institute (ACI) set of publications In particular:
ACI 357.2R - Report on barge-like concrete structures
ACI 546.2R - Guide to underwater repair of concrete
American Society for Testing Materials (ASTM) set of publications In particulars, standards on concrete material and
components testing methods
ISO 6934 Steel for prestressing of concrete Requirements for prestressing steel and associated
equipment
ISO 6935 Steel for the reinforcement of concrete Requirements for reinforcing steel
ISO 1920 Testing of concrete In particular:
• making and curing test specimens
• strength of hardened concrete
ISO 4463-1 Measurement methods for building - Setting-out and mea- Measuring procedures and acceptance criteria
surement - Part 1: Planning and organization, measuring
procedures, acceptance criteria
Concrete is the material formed by mixing cements, coarse 3.2.4 Layout and structure
and fine aggregate and water, with or without the incorpo- • Structural arrangement
ration of admixtures and additions, which develops its prop-
• Structural details including structural modelling
erties by hydration of the cement.
• Structure orientation
2.2.6 Reinforcing steel • Details of connections between concrete structure and
equipment
Reinforcing steel are all steel elements incorporated in • Details of concrete structure discontinuities
structural concrete in order to provide additional strength,
and in particular tensile strength, and which give the ductile • Inspection and survey plans
characteristics of concrete. • Storage/containment systems
• Corrosive characteristics of storage compartments
2.2.7 Prestressing steel (hydrocarbon, chemical products, sea water, etc)
• Corrosion protection measures and equipment
Prestressing steel defines all steel elements and their related
equipment used to apply a prestress (compression) on struc- • Protective equipment against collisions
tural components, in order to avoid or to reduce regions of • Mooring systems, including lines, anchors and relating
the structure loaded in tension. devices on the unit
1.2.1 The project specifications are to include drawings, 2 Inspection, testing and correcting
technical descriptions and specifications that describe how actions
the structure is to be constructed.
2.2.4 Inspection of falsework and formwork • removal of detritus and remains from the formwork
Inspections before casting, according to relevant classes, • treatment of construction joints
are to include the followings: • wetting of formwork
• geometry of formwork • preparation of formwork surface
• stability of formwork and falsework and their founda- • openings and blockouts
tions
After formwork removal, it is to be checked that temporary
• tightness of formwork and its parts inserts are removed.
2.2.5 Inspection of reinforcing steel 3.1.2 Material specifications are to be established for all
Before casting, inspections according to relevant classes are materials that are used in the production of concrete.
to confirm that:
3.1.3 Material can be rejected at any stage of execution if it
• the reinforcing steel is positioned at the specified spac- is established that the conditions upon which the approval
ing, in accordance with design drawings was based where not fulfilled.
• the concrete cover is in accordance with the specifica-
tions 3.2 Concrete components
• the reinforcing steel is not contaminated with oil, grease
or paint 3.2.1 General
• the reinforcement is tied and secured against displace- Concrete components are to be sound, durable and suitable
ment during concreting for making concrete that will attain and retain the required
properties.
• the space between bars is sufficient to place and com-
pact the concrete. Concrete components are not to contain harmful ingredi-
ents in quantities that can cause corrosion of reinforcing
2.2.6 Inspection of prestressing works steel or be detrimental to the durability of concrete.
Before casting operations, inspections will confirm that:
3.2.2 Cement - Certificates
• the position of tendons, sheaths, vents, drains, couplers,
Cement is to be delivered with works certificates, giving at
anchorages, etc, is in accordance with design drawings,
least the chemical and mineralogical composition of the
including the cover of tendons and spacing of tendons
product and the test values for all required properties.
• the tendons and sheaths are fixedly secured and their
supports are stables Works certificates are also to state the type/grade of the
cement, the batch identification and the tonnage, and are to
• the sheaths, vents, drains, anchorages, couplers and demonstrate compliance with other specified requirements,
their sealing are not damaged when relevant.
• the tendons, anchorages and couplers are not corroded Note 1: Works certificates may not requested when the cement is
• the sheaths, anchorages and couplers are clean. produced and tested under a national or international certification
scheme, and all required properties are documented based on sta-
Prior to tensioning or prior to releasing the pretension force, tistical data from the producer.
the actual concrete strength is to checked against the
requested strength. The calibration of jacks is to be 3.2.3 Cement - Testing
checked. Cement is to be tested in accordance with an approved
Before the start of grouting operations, the inspections are method as defined in recognized standards such as ASTM
to ensure that: ones.
• the qualification of grout is done, as required The following type of test may be required:
• the results of trial grouting are as required a) Physical properties
• ducts are clean and opened for grout through their • Strength in mortar
length • Soundness
• vents are prepared and identified • Fineness
• materials are batched and sufficient for overflow. • Initial settling time
During grouting, the inspections are to include: • Normal consistency
• check of the conformity of fresh grout tests for fluidity • Volumetric stability.
and segregation b) Chemical composition
• check of the characteristics of equipment and grout. • Oxide composition
• Sulphate content
2.2.7 Inspection of concreting operations
• Chlorite content
The inspection of concreting operations is to be performed
and documented in accordance with the requirements of • Loss of ignition
the present Guidance Note, according to the allocated • Pozzolanity
class. • Insoluble residue.
3.2.5 Types of cement for marine environment Aggregates from sea bed are normally not to be used,
The cement used for offshore concrete structures is to have except when they are properly washed to remove chlorites.
an established suitability for use in marine environment.
3.2.8 Aggregate - Documentation
The following types of cement are considered as suitable for Aggregate is to be delivered with a test report, as defined in
offshore concrete structure operating in marine environ- Sec 1, including at least the following information:
ment, if unmixed with other types of cement:
• description of the source
• Portland cements
• description of the production system
• Portland composite cements, with silica, fly ash or slag
and minimum 80% clinker. • particle size distribution/grading including silt content
• particle shape, flakiness
Provided that the suitability is demonstrated, the following
• porosity and water absorption
types of cement may also be considered:
• content of organic matter
• other Portland composite cements, with other pozzola-
nas or clinker below 80% • density and specific gravity
• Blast-furnance cements (less than 64% clinker) • potential reactivity with alkalis in cement
• Pozzolanic cements with less than 64% clinker • petrographical composition and properties than can
affect concrete durability.
• Composite cements with less than 64% clinker.
The sources of aggregate are to be investigated and
Cements are to be specified in grades based on the 28 days approved for their suitability and dependability for supply.
strength in mortar and are normally categorized as normal Aggregates of different grading will be stockpiled and trans-
hardening, rapid hardening and slow hardening cements. ported separately.
3.5.6 Mechanical splices and end-anchorages Survey reports carried out by certified parties recognized by
Mechanical splices and end-anchorages are to be delivered the Society or relevant authorities may be accepted by the
with a Works Certificate. Society.
Fatigue properties are to be tested and documented for the 4.1.3 The present Article adopts the requirements given in
actual combination of rebars, couplers and anchorages. ISO 19903.
Couplers giving a permanent slip on unloaded specimen of
more than 0,1 mm after 10 cycles of loading to 75% of the 4.2 Falsework and formwork
nominal yield strength are not to be used.
Friction welded end-anchorages on rebars are to be quali- 4.2.1 General
fied by testing in advance and during production. Testing Falsework and formwork including their supporting ele-
programme for qualification is to include a tension test and ments and foundations are to be designed and constructed
a bending test, documenting the strength and ductility of based on the following principles:
the connection. The friction weld is not to fail before the • to be compatible with the execution procedure speci-
rebar. fied for the intended project
• to sustain actions and loading expected during con-
3.6 Prestressing steel and equipment struction
• to have a stiffness compatible with the tolerances speci-
3.6.1 General
fied for the structural element under construction.
Prestressing steel and components are to be delivered with
a Works Certificate. 4.2.2 Falsework
Prestressing steel is to comply with relevant standards rec- A method statement for falsework is to be submitted and
ognized by the Society, as defined in Sec 1, and in particu- approved by the Society. Generally, it is to include:
lar with ISO 6934. • requirements specified for handling and adjusting, and
Prestressing equipment is to comply with the requirements chosen methods
of work specification and are to be approved by the Society. • requirements specified for intentional precambering and
Previous approval by a national authority or a recognized methods
institution may be accepted on a case-by-case basis. • requirements specified for unkeying, striking and dis-
3.6.2 Components mantling and methods.
Prestressing system is generally composed by: A particular attention is to be given to falsework deforma-
• tendons (wire, strands, bars) tions in order to prevent cracking of young concrete.
• anchorage devices 4.2.3 Formwork
• couplers Formwork is to keep the concrete in the shape until its hard-
• ducts or sheaths. ening.
All components are to be compatible each other and clearly The boards of panels are to be sufficiently tight to avoid loss
identifiable. of water or fine materials. When materials used for form-
works are expected to absorb or facilitate evaporation of
Sheaths for post-tensioning tendons are, generally, of a
water, they are to be wetted in order to minimize these
semi-rigid or rigid type. They are to be watertight and with
effects.
adequate stiffness to prevent damages and deformations.
Slipform systems and jumpform systems, when used, are to
comply with the requirements of ISO 19903.
4 Execution
4.4.2 Fabrication When fresh concrete cannot be cast in due time after ten-
Identification documents and certification of tests on mate- sioning, appropriate protective measures are to be taken to
rials and tendons is to be available on the site of execution. avoid damage of the bond or detrimental effect of steel or
Each component is to be clearly identified and traceable. concrete.
During stressing, the calculated elongation is to be
Prestressing steel is not to be subjected to welding and oxy-
achieved within a range of 3% for a group of tendons or 5%
gen cutting. Exceptions may be accepted based on the pro-
for a single tendon within the group for the specified ten-
visions of ISO 19903.
sioning force. Otherwise, relevant actions are to be taken
regarding the tensioning programme or the design.
4.4.3 Positioning
Prestressing system assemblies are to be positioned in 4.4.7 Post-tensioning
accordance with the supplier specifications and in accor- Tensioning is not to be carried out when air temperature is
dance with the construction drawings. below −10°C, or in other conditions where there is a risk of
Relevant requirements of the present Guidance Note relat- grout freezing.
ing to positioning tolerances are to be complied with. Ten- During stressing, the calculated elongation is to be
dons are not to sag or have a kink of any kind. achieved within a range of 5% for a group of tendons or
10% for a single tendon within the group for the specified
4.4.4 Tendons tensioning tensioning force. Otherwise, relevant actions are to be
A method statement for tendons tensioning is to be submit- taken regarding the tensioning programme or the design.
ted and approved. The jacking force/pressure and elonga- When planned performance of tensioning is not achieved,
tion at each step of the stressing operation until full force is further work (including grouting of tendon cut-off) is to be
obtained are to be recorded in a log and compared with postponed until the tendon is approved or corrective
pre-calculated values. All problems and/or non-conformi- actions established. Additional tests may be requested by
ties during tensioning are also to be recorded for the the Society to confirm friction factors or elastic modulus of
approval of the Society. tendon assembly.
The calibration of force-measuring devices is to be done on The period from threading to prestressing of tendons in nor-
the site of execution, before the start of tensioning opera- mally not to exceed 4 weeks. During this period, tendons
tions. are to be protected against corrosion.
The prestressing forces are to be transferred to a concrete Grouting/injection is to be done as soon as possible after
structural element only at a concrete strength fully compli- tensioning, normally within 2 weeks.
ant with the requirements specified by the design, and in no
4.4.8 Protective measures
case less than the minimum compressive strength specified
Tendons placed in sheaths, couplers and anchoring devices
by the approval document of the prestressing system. A par-
are to be protected against corrosion by filling all voids with
ticular attention is to be given to the anchorage areas.
a grouting /injection material such as:
• cement grout
4.4.5 Post-tensioned tendons
• grease
The following parameters are to be checked for compliance
• wax.
with supplier specification and other relevant approval doc-
uments: These materials are to comply with the requirements of
• straight entry into anchorages and couplers [3.4].
• coaxiality of tendons and anchorages. Anchorage areas and end caps are also to be filled and pro-
tected. Inlets and outlets are to be sealed.
Vents and drains on the sheaths are to be provided at both
ends and at all points where air or water can accumulate. 4.4.9 Grouting
For sheaths of considerable length, intermediate vents and A method statement is to be provided for the preparation
drains are to be provided. and execution of grouting/injection operations. All impor-
tant data and observations relating to grouting are to be
Alternative means of draining may be accepted on a case- recorded in a log.
by-case basis.
Grouting operations using cement-based grout are to be
Vents and drains are to be marked such as to identify the done within temperature conditions as given in Tab 7.
cable. Grouting at temperatures other than specified in Tab 7 may
The sheaths are to be checked after pouring of concrete to be accepted by the Society on a case-by-case basis, taking
ensure sufficient passage for the tendons, and are to be into account the specificities of grouting method and mate-
cleared of any water immediately prior to tendon threading. rials.
Grouting at temperatures lower than +5°C may be allowed
4.4.6 Pre-tensioning only when frost resistant grout material is used.
The release of prestressing force is to be done such that the Grouting is to be carried out at a continuous and steady rate
bond in the anchorage zone of the tendon will not be dam- from the lowest inlet until the emerging grout through
aged. anchor heads and outlets.
As a rule, grout pressure in ducts is not to exceed 2 MPa, 4.5.4 Pre-concreting operations
unless when allowed by the design. A particular attention is All preparation works are to be completed, inspected and
to be given to vertical ducts. documented, as requested by the present Guidance Note,
Non-retarded grout and grout without an expanding admix- before the casting is initiated.
ture is to be used within 30 minutes after mixing. When fresh concrete is pumped, an adequate back-up or
emergency procedure in case of blockage of piping is to be
In vertical or inclined ducts, or ducts with large diameter,
prepared and submitted.
post-injections before grout stiffening may be required in
order to remove voids or water. When voids are detected Construction joints are to present a roughened surface,
after grout stiffening, post-injection by vacuum grouting is which can be obtained by the application of a surface
to be carried out. Vacuum grouting is also required in case retarder on the fresh concrete and later cleaned by water
of duct blockage. jet. Concrete joints are to be clean and free of laitance.
Vacuum injections are to be pre-qualified by trials, particu- A particular attention is to be given to the protection of con-
larly for vertical ducts. When vacuum injection are used, crete against freezing, when the temperature is forecasted to
the free volume of ducts is to be measured and compared be below 0°C at the time of casting or in the curing period.
with the volume of injected grout. Where the ambient temperature is forecasted to be above
30°C at the time of casting or in the curing period, precau-
After completion of grouting, the ducts are to be sealed
tions are to be planned to protect the concrete against dam-
under a pressure of at least 0,5 MPa during at least 1 min-
aging effects of high temperatures.
ute.
When the grouting of a duct is interrupted, the fresh mate- 4.5.5 Placing and compaction
rial inside the duct is to be washed. No duct is to be left The concrete is to be placed and compacted in order to
with incomplete filling of grout. ensure that all reinforcement and cast-in items are properly
embedded in compacted concrete and that the concrete
Table 7 : Temperature ranges for achieves its intended strength and durability.
cement-based grouting Appropriate procedures are to be used where cross-sections
are changed, in narrow locations, at box-outs, at dense rein-
Temperature ranges (°C)
forcement arrangements and at construction joints. Settle-
Minimum Maximum
ment cracking over reinforcement in the top surface is to be
Structure temperature +5 +35
avoided by re-vibration.
Cement-based grout temperature +10 +25
The rate of placing and compaction is to be high enough to
4.4.10 Greasing avoid cold joints and low enough to prevent excessive set-
tlements or overloading of the formwork and falsework. The
Greasing is to be carried out at a continuous and steady
rate. After completion of greasing, the ducts are to be sealed concrete is to be placed in layers of a thickness that is com-
under pressure. patible with the capacity of the vibrators used. The concrete
of the new layer is to be vibrated systematically and include
The volume of the injected grease is to be checked against
the theoretical free volume in the duct. The change of re-vibration of the top of the previous layer in order to avoid
grease volume with the change of temperature is to be weak or inhomogeneous zones in the concrete. The vibra-
taken into account. tion is to be applied until the expulsion of entrapped air has
practically ceased, but not so as to cause segregation or a
4.5 Concreting weak surface layer.
Concrete is to be placed in such a manner as to avoid segre-
4.5.1 General gation. Free fall of concrete from a height of more than 2 m
Reference is made to the requirements of ISO 19903. is not occur unless the mix is demonstrated to allow this
without segregation.
4.5.2 Concrete testing
Concrete is to be compacted by means of high-frequency
Concrete is to be inspected at the point of placing. In the vibrators or by alternative methods that can be demon-
case of ready-mixed concrete, inspections are also to be strated to give adequate compaction. Contact between
done at the point of delivery. Samples are to be taken at the internal vibrators and reinforcement or formwork will be
point of placing. avoided as much as possible. Vibrators are not be used for
horizontal spreading of concrete.
4.5.3 Identity testing
Alternative methods to the use of vibrators in order to
Identity testing is to be carried out in order to verify that the
obtain an adequately compacted concrete are permitted,
concrete comes from a conforming population.
provided they are able to be documented for the relevant
Identity testing are requested at the point of delivery for type of conditions by trial casting. During placing and com-
ready-mixed concrete produced according to a recognized paction, the concrete is to be protected against adverse
certification scheme which certifies that all project require- solar radiation and wind, freezing, water, rain and snow.
ments are complied with. Identity testing may replace the Surface water is to be removed during concreting if the
requirements of [4.5.2]. planned protection fails.
4.5.6 Curing and protection of hardened concrete Curing compounds are not permitted on construction joints,
on surfaces where bonding of other materials is required,
Relevant requirements given in ISO 19903 are to be com- unless they are fully removed prior to the subsequent opera-
plied with. Reference is also made to the requirements of tion, or they are proven to have no detrimental effects on
ISO 1920-3 and ISO 1920-4. bonding.
The surface is to be protected from damage due to heavy
Concreting procedures are to ensure adequate curing in
rain, flowing water or other mechanical influences.
order to obtain maximum durability, minimize plastic
shrinkage, losses in strength and durability and to avoid 4.5.7 Post-concreting
cracking. The curing period is not to be less than two After removal of formwork, all surfaces are to be inspected
weeks. The duration of curing may be further estimated for conformity to the requirements of the design. The sur-
based on testing of strength or alternatively by the maturity face are to be protected from damages during construction.
of the concrete on the basis of the surface temperature of
the concrete or the ambient temperature. The maturity cal- 4.6 Embedded components
culation is to be based on an appropriate maturity function
proven for the type of cement or combination of cement 4.6.1 General reference
and addition used. The requirements of ISO 19903 are to be complied with.